2. AVAILIBILITY OF LINE PIPE
LINE PIPE DISPATCHED 1654 Nos./20074.99 Mtr. 195 Nos./ 2363.56 Mtr. 876 Nos./10575.205 Mtr Remarks
LINE PIPE RECEIVED 1618 Nos./ 19577.80 Mtr. 195 Nos./2363.56 Mtr. 860 Nos./10406.00 Mtr.
Progressively received
the Line Pipe at the end
of Oct’22
LINE PIPE WELDED 1295 Nos./15669.50 Mtr. 172 Nos./2083.56 Mtr. 760 Nos./9135.50 Mtr.
LINE PIPE AVAILABLE AT SITE 323 Nos./3968.80 Mtr. 23 Nos./280.00 Mtr. 180 Nos./2178.00 Mtr.
LINE PIPE BALACE TO
RECEIVE
36* Nos./ 497.19 Mtr. - 16 Nos./ 169.205 Mtr.
19.05 mm Thk 22.23 mm Thk 23.83 mm Thk
3. MAJOR CHALLANGES
Delay in continuous supply of Line Pipe.
Delay in payment for execution of agreement with authorities.
Payment Delay to contractor, not willing to mobilize the machinery and manpower.
Truck association issues to be resolve to start full functional work at Keonjhar.
Issue against ownership of IDCO/PWD Land.
Stiff resistance of Encroachers who have encroached into corridors of NHAI, IDCO, PWD & RD roads (e.g. Residence
buildings, hotels, petrol pumps, shop keepers etc). District administration wants the request for demolition to come from
respective agencies and not from JSW.
Unnecessary demand of villagers for CSR activities other than compensation.
In many places, authorities have undertaken plantation in approved ROU corridor.