P3 AGREEMENTS
Stephanie W. Kam, Esq.
14 November 2016
Toronto
Typical P3 Structure
2
Government
Private Entity
Contractor Operator
Shareholders Lenders
Concession
Agreement
Shareholders
Agreement
Financing
Agreement
Constructions
Contract
Operations
Contract
Direct
Agreement
Typical P3 Agreements
Purpose
1. Specify the Relationship between the
government and the private entity
2. Define the Responsibilities of both parties
3. Identify the Requirements necessary to
efficiently and effectively perform tasks
The Concession Agreement
3
• Government’s perspective:
– Defines the service delivery by the private entity
– Fixes the budget for a public facility
– Ensures value for money
• Private entity’s perspective:
– Defines compensation for service delivery
– Enables long-term planning
– Minimizes political interference
– Provides clarity on expectations of the government
4
The Concession Agreement
• Scope
– Description of physical area and rights
• Duration
– Period for which concession is being granted
• Termination
– Material breach
– Insolvency
– Misrepresentations
– Assignment
– Payment default
– Failure to comply with arbitral award
5
Principal Contract Terms
• Government’s Obligations
– Granting right of access to site
– Providing licences, permits, approvals
– Procuring leases, easements, rights of way
– Passing legislation
– Availability payment and/or user fees
• Private Entity’s Obligations
– Financing, construction, operations, maintenance
– Compliance with applicable legislation
– Minimum number of national citizens (if applicable)
– Concession fees (if applicable)
6
Principal Contract Terms
• Force Majeure
– General description of events
– Risk shared between the parties
– Mitigation of force majeure events
– Extension of concession, cap?
• Change in Law
– Extension of concession
– Grace period
• Governing Law
• Dispute Resolution
7
Principal Contract Terms
Thank you
Stephanie Kam
skam@cpcs.ca
8

More Related Content

What's hot

Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Project Finance Session 01
Project Finance Session 01Project Finance Session 01
Project Finance Session 01Bodenbr
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Presentationon infrastructure project_finance
Presentationon infrastructure project_financePresentationon infrastructure project_finance
Presentationon infrastructure project_financesabinji
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7Bodenbr
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
 
Project Financing
Project FinancingProject Financing
Project Financingkcbradley
 
Adb procurement guidelines introduction2
Adb procurement guidelines   introduction2Adb procurement guidelines   introduction2
Adb procurement guidelines introduction2Joy Irman
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
Contractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsContractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsGary L. Henry
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 

What's hot (20)

Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Project Finance Session 01
Project Finance Session 01Project Finance Session 01
Project Finance Session 01
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Presentationon infrastructure project_finance
Presentationon infrastructure project_financePresentationon infrastructure project_finance
Presentationon infrastructure project_finance
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Project Financing
Project FinancingProject Financing
Project Financing
 
Adb procurement guidelines introduction2
Adb procurement guidelines   introduction2Adb procurement guidelines   introduction2
Adb procurement guidelines introduction2
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Contractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsContractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction Contracts
 
NEC Framework Contract webinar
NEC Framework Contract webinarNEC Framework Contract webinar
NEC Framework Contract webinar
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 

Similar to P3 Fundamentals Seminar - P3 Agreements

#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahiSN Panigrahi, PMP
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best2cd
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsAnatoly Darov, P.E.
 
Texas Promulgated Contract Forms
Texas Promulgated Contract FormsTexas Promulgated Contract Forms
Texas Promulgated Contract FormsPeggy Santmyer
 
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...Kullarat Phongsathaporn
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar
 
corporate legal environment (contract).docx
corporate legal environment (contract).docxcorporate legal environment (contract).docx
corporate legal environment (contract).docxDoon Business School
 
Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6KHogan62
 
Web program slides (2) (2)
Web program slides (2) (2)Web program slides (2) (2)
Web program slides (2) (2)Carol Buckmann
 
NCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleNCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleLeona Charles
 
Essential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsEssential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsezLandlordForms
 
Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015SDMinBC
 
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...SN Panigrahi, PMP
 
Breach of contract (1)
Breach of contract (1)Breach of contract (1)
Breach of contract (1)Dr.Aravind TS
 
Running Head ELEMENTS OF A CONTRACT 1 .docx
Running Head ELEMENTS OF A CONTRACT   1            .docxRunning Head ELEMENTS OF A CONTRACT   1            .docx
Running Head ELEMENTS OF A CONTRACT 1 .docxtodd271
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Dr. Zaid Mahayni
 

Similar to P3 Fundamentals Seminar - P3 Agreements (20)

#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and Towns
 
Texas Promulgated Contract Forms
Texas Promulgated Contract FormsTexas Promulgated Contract Forms
Texas Promulgated Contract Forms
 
Ac 11
Ac 11Ac 11
Ac 11
 
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
 
corporate legal environment (contract).docx
corporate legal environment (contract).docxcorporate legal environment (contract).docx
corporate legal environment (contract).docx
 
Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6
 
Web program slides (2) (2)
Web program slides (2) (2)Web program slides (2) (2)
Web program slides (2) (2)
 
Evergreen Clause Fundamentals
Evergreen Clause FundamentalsEvergreen Clause Fundamentals
Evergreen Clause Fundamentals
 
NCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleNCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations article
 
Essential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsEssential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key Inclusions
 
Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015
 
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
 
Ac 17
Ac 17Ac 17
Ac 17
 
Breach of contract (1)
Breach of contract (1)Breach of contract (1)
Breach of contract (1)
 
Running Head ELEMENTS OF A CONTRACT 1 .docx
Running Head ELEMENTS OF A CONTRACT   1            .docxRunning Head ELEMENTS OF A CONTRACT   1            .docx
Running Head ELEMENTS OF A CONTRACT 1 .docx
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
 
Nce603 mod unit4
Nce603 mod unit4Nce603 mod unit4
Nce603 mod unit4
 

P3 Fundamentals Seminar - P3 Agreements

  • 1. P3 AGREEMENTS Stephanie W. Kam, Esq. 14 November 2016 Toronto
  • 2. Typical P3 Structure 2 Government Private Entity Contractor Operator Shareholders Lenders Concession Agreement Shareholders Agreement Financing Agreement Constructions Contract Operations Contract Direct Agreement Typical P3 Agreements
  • 3. Purpose 1. Specify the Relationship between the government and the private entity 2. Define the Responsibilities of both parties 3. Identify the Requirements necessary to efficiently and effectively perform tasks The Concession Agreement 3
  • 4. • Government’s perspective: – Defines the service delivery by the private entity – Fixes the budget for a public facility – Ensures value for money • Private entity’s perspective: – Defines compensation for service delivery – Enables long-term planning – Minimizes political interference – Provides clarity on expectations of the government 4 The Concession Agreement
  • 5. • Scope – Description of physical area and rights • Duration – Period for which concession is being granted • Termination – Material breach – Insolvency – Misrepresentations – Assignment – Payment default – Failure to comply with arbitral award 5 Principal Contract Terms
  • 6. • Government’s Obligations – Granting right of access to site – Providing licences, permits, approvals – Procuring leases, easements, rights of way – Passing legislation – Availability payment and/or user fees • Private Entity’s Obligations – Financing, construction, operations, maintenance – Compliance with applicable legislation – Minimum number of national citizens (if applicable) – Concession fees (if applicable) 6 Principal Contract Terms