1. Organization: Walvoil
Training Guide
Create ECN
Production Planning
Reference: PP ECM01
CC01 – Create Engineering Change Number
Definition:-
Component that allows you to change objects with history (with date validity)
The different processing statuses of the object are saved. All changes are made with reference
to a change master record.
In the R/3 System, you can change object types with reference to a change number. For
example:
• Materials
• Documents
• Bills of material
Menu path
Logistics Central FunctionsEngineering Engineering Change Management Change
Number CC01 - Create
Double click Create
Enter Profile ‘PP000001’ and Enter
Prepared By: Page:
26/03/2007 M.P.R.Prasad Page 1 of 5
3. Organization: Walvoil
Training Guide
Create ECN
Production Planning
Reference: PP ECM01
The Object types Material BOM, document and Material are defaulted by Profile ‘PP00001’. If
required You can Uncheck Object types.
Prepared By: Page:
26/03/2007 M.P.R.Prasad Page 3 of 5
4. Organization: Walvoil
Training Guide
Create ECN
Production Planning
Reference: PP ECM01
Click on Objects:
Do not enter Document, Material/s and Material BOM. The entry will be done automatically by
the system when the above Objects are created with the change number
Save the ECN
Prepared By: Page:
26/03/2007 M.P.R.Prasad Page 4 of 5
5. Organization: Walvoil
Training Guide
Create ECN
Production Planning
Reference: PP ECM01
Change Number is automatically assigned by the system
Prepared By: Page:
26/03/2007 M.P.R.Prasad Page 5 of 5
6. Organization: Walvoil
Training Guide
Create ECN
Production Planning
Reference: PP ECM01
Change Number is automatically assigned by the system
Prepared By: Page:
26/03/2007 M.P.R.Prasad Page 5 of 5