3. What is BNBC?
BNBC stands for Bangladesh National Building Code.
First version published in 1993.
Huge Changes Made in 2017.
4. • What is civil plan ?
Civil plan means the civil engineering design.
• What is included in civil plans?
Information about site grading, erosion & sediment control etc.
Civil Plan
5. We draw the civil plan of the flat along with
stair, lift and lobby following some step:
1. Drawing should be clear, simple and clean
2. Need to access a particular function from the Draw menu.
3. Separate functions to draw text, dimensions, patterns, symbols
and other elements of a drawing.
4. Need to be specific about the no. Of lines, arcs or any other shapes
5. Must specify where each line and arc starts, where it ends,
the center point of the arc, the radius, etc.
6. Separate functions to draw text, dimensions, patterns, symbols
and other shapes.
6. Fittings & Fixture Layout
Demonstration of exact location for different fixtures.
The input information must be correct for all equipment of each
particular area.
civil layout (i.e. whether it’s a bedroom or a kitchen).
Sufficient amount of lighting, cooling and connectivity for external
loads (i.e. 2/3 pin sockets) need to be provided.
7. 1.Place all the Switchboards (SB) accordingly. Note carefully the direction of
door openings for this, ‘Toilets’, ‘Stores’, ‘Kitchens’ should be outside of the
room
2.Provide sufficient number of lights and fans for each room. If the room is
fairly large then we provide multiple fans, lights and even multiple SBs.
3.Provide sufficient number of switched socket outlets on both SBs and
distant from the SBs. Each SB around the living rooms should have at least
one socket outlet. Kitchens may have a distant socket for wall mounted fans,
toilets should have distant socket for electric razors, hair driers etc.
4.SDB and MDB positioning should be wise. MDB needs to be monitored by
the meter readers.So, it should be placed in an easily accessible place where
sufficient lighting arrangement is we should ensured.
10. Conduit Layout
• Demonstration & optimization of the electrical
connectivity between source of energy and loads.
• Line from Secondary distribution board to Switch Board
are usually Medium load line.
• Switch Board to Light and Fan are usually Light load line
11. Wire Size in (mm²)
For Light load-2.5(mm²)
For Medium load-4 (mm²)
For High load-6(mm²)