This presentation explains the following:
- System Configurations
- Single & Multiple Generators
- Single & Multiple Utilities
- Generator & Utility Protection and Utility Approval
- Momentary Paralleling vs. Soft Load/Unload
- Operating Modes
- Base Load Control
- Import / Export Control
- Zero Power Transfer (ZPT) or Storm Anticipation
- Utility and Generator (Plant) Islanding
- Power Factor Control
2. System Configurations
Single & Multiple Generators
Single & Multiple Utilities
Generator & Utility Protection and Utility Approval
Momentary Paralleling vs. Soft Load/Unload
Operating Modes
Base Load Control
Import / Export Control
Zero Power Transfer (ZPT) or Storm Anticipation
Utility and Generator (Plant) Islanding
Power Factor Control
11. 27 – Under voltage
32 – Reverse power
32RV – Reverse VARS (loss of excitation)
46 – Negative phase sequence overcurrent (phase
unbalance or single phasing)
50/51 – Instantaneous / time overcurrent
51V – Time overcurrent with voltage restraint
51G – Ground overcurrent
59 – Over voltage
81O/U – Over / under frequency
86 – Lock out
87G – Generator differential overcurrent
GENERATOR PROTECTION
13. 27 – Under voltage
32 – Reverse power
47 – Phase sequence / under voltage
50/51 – Instantaneous / time overcurrent
51G – Ground overcurrent
51N – Zero sequence overcurrent
59 – Over voltage
59G – Ground overvoltage
81O/U – Over / under frequency
86 – Lock out
87T – Transformer differential overcurrent
UTILITY PROTECTION
15. UTILITY APPROVAL FOR PARALLELING
Utility Requirements
Interconnect agreement forms/documents.
One-line of proposed system.
Utility protective relaying chosen, utility usually gives their
requirements or choice of mfg.
Preliminary relay settings.
DC schematics showing tripping schemes.
Utility may require transfer trip.
Some utilities may require full protection even for
momentary paralleling.
Generator Protection
Not normally approved by utility.
Typically specified by consulting eng.
16. Extended parallel time
More components required
Generally more relaying
protection required
Extends breaker contact life
with normal operation
Little or no power surges
between utility and
generator
Generally less than 100 milli-sec.
Fewer components
Sometimes less relaying
requirements
More wear on breaker contacts
More power surges to utility and
generator
SOFT LOAD/UNLOADMOMENTARY PARALLELING
Extended parallel time
More components required
Generally more relaying
protection required
Extends breaker contact life
with normal operation
Little or no power surges
between utility and
generator
Generally less than 100 milli-sec.
Fewer components
Sometimes less relaying
requirements
More wear on breaker contacts
More power surges to utility and
generator
MOMENTARY vs SOFT LOAD/UNLOAD
17. Generator Kw output controlled by biasing Governor
Analog
Digital
Communications
Generator PF controlled by biasing voltage regulator.
Analog
Digital
Communications
GENERATOR LOAD CONTROL
18. UTILITY PARALLELING MODES OF OPERATION
Base Load
Constant generator kW output
Import Control
Constant kW input from utility
Export Control (rarely used mode)
Constant kW utility sell back to utility
Zero Power Transfer
Control rate of power flow (transfer) to/from utility/generator
19. Genset produces constant kW output regardless of
utility or load levels.
Used for generation at landfills.
If not contracted by utility, load should always be
greater than generator output or excess kW will be
“back fed” into utility grid.
Gas turbines operate well with base loading since some
or most are used with heat recovery.
BASE LOADING
21. OPERATING MODES – BASE LOAD
UTIL MW
8
LOAD MW
8
GEN MW
0
GEN
BREAKER
OPEN
BREAKER
CLOSED
BASE LOAD MODE INITIATED –
GENSET STARTED
22. OPERATING MODES – BASE LOAD
UTIL MW
8
LOAD MW
8
GEN MW
0
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET PARALLELED TO
UTILIITY – BASE LOAD SET
POINT = 6 MW.
23. OPERATING MODES – BASE LOAD
UTIL MW
7
LOAD MW
8
GEN MW
1
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET LOADING STARTED –
BASE LOAD SET POINT = 6 MW.
24. OPERATING MODES – BASE LOAD
UTIL MW
2
LOAD MW
8
GEN MW
6
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET OUTPUT AT BASE
LOAD SET POINT OF 6 MW.
25. OPERATING MODES – BASE LOAD
UTIL MW
-1
LOAD MW
5
GEN MW
6
GEN
BREAKER
CLOSED
BREAKER
CLOSED
LOAD DECREASES, GENSET
OUTPUT GREATER THAN LOAD,
EXCESS EXPORTED TO UTILITY
GRID.
26. OPERATING MODES – BASE LOAD
UTIL MW
3
LOAD MW
5
GEN MW
2
GEN
BREAKER
CLOSED
BREAKER
CLOSED
BASE LOAD TERMINATED,
GENSET UNLOADS
27. OPERATING MODES – BASE LOAD
UTIL MW
5
LOAD MW
5
GEN MW
0
GEN
BREAKER
OPEN
BREAKER
CLOSED
GENSET OUTPUT NEAR ZERO,
BREAKER OPENS, ENGINE RAN
FOR COOL DOWN PERIOD.
28. Also referred to as peak shaving or load following.
Used for utility load curtailment contracts.
Load dependant start/stop can be used with multiple
genset installations.
Export control not very commonly used.
IMPORT / EXPORT CONTROL
34. OPERATING MODES – IMPORT
UTIL MW
1
LOAD MW
8
GEN MW
7
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET OUTPUT INCREASED
UNTIL UTILITY IMPORT SET
POINT IS MET (I MW).
35. OPERATING MODES – IMPORT
UTIL MW
2
LOAD MW
9
GEN MW
7
GEN
BREAKER
CLOSED
BREAKER
CLOSED
LOAD INCREASES, UTILITY
IMPORT SET POINT NOT MET.
36. OPERATING MODES – IMPORT
UTIL MW
1
LOAD MW
9
GEN MW
8
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET OUTPUT FURTHER
INCRESED UNTIL UTILITY
IMPORT SET POINT MET.
37. OPERATING MODES – IMPORT
UTIL MW
-2
LOAD MW
6
GEN MW
8
GEN
BREAKER
CLOSED
BREAKER
CLOSED
LOAD DECREASES, GENSET
OUTPUT “BACK-FED” TO
UTILITY.
38. OPERATING MODES – IMPORT
UTIL MW
1
LOAD MW
6
GEN MW
5
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET OUTPUT DECRESED
UNTIL UTILITY IMPORT SET
POINT MET.
40. OPERATING MODES – IMPORT
UTIL MW
6
LOAD MW
6
GEN MW
0
GEN
BREAKER
OPEN
BREAKER
CLOSED
GENSET OUTPUT NEAR ZERO,
BREAKER OPENS AND ENGINE
RAN FOR COOL DOWN PERIOD.
41. Soft transfer of load to and from generator and utility.
Common mode of operation used at Data Centers or
other critical load networks.
Sometimes referred to as “storm anticipation” or
“storm avoidance”.
ZERO POWER TRANSFER
42. GENERATOR CONTRIBUTION
LOAD
UTILITY
TIME
0
A B C D
100
200
300
400
500
600
700
800
900
1000
K
I
L
O
W
A
T
T
S
ZERO POWER TRANSFER
A. THE GENERATOR BREAKER CLOSES AND THE GENERATOR STARTS TO LOAD
WHICH REDUCES THE UTILITY kW..
B. THE UTILITY kW.. IS REDUCED TO ZERO AND UTILITY BREAKER OPENS. SITE
POWERED BY GENERATOR.
C. AFTER THE GENERATOR IS RE-SYNCHRONIZED TO THE UTILITY, UTILITY
BREAKER IS CLOSED AND THE GENERATOR UNLOADING IS STARTED.
D. THE GENERATOR kW.. IS REDUCED TO ZERO AND GENERATOR BREAKER
OPENS. SITE NOW POWERED BY UTILITY.
LOAD
GENERATOR
UTILITY
UTILITY
GENERATOR
43. OPERATING MODES – ZPT
UTIL MW
6
LOAD MW
6
GEN MW
0
GEN
BREAKER
OPEN
BREAKER
CLOSED
ZPT MODE INITIATED – GENSET
STARTED
44. OPERATING MODES – ZPT
UTIL MW
6
LOAD MW
6
GEN MW
0
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET PARALLELED TO
UTILITY
52. OPERATING MODES – ZPT
UTIL MW
7
LOAD MW
7
GEN MW
0
GEN
BREAKER
CLOSED
BREAKER
CLOSED
GENSET OUTPUT DECREASED
TO NEAR ZERO.
53. OPERATING MODES – ZPT
UTIL MW
7
LOAD MW
7
GEN MW
0
GEN
BREAKER
OPEN
BREAKER
CLOSED
WHEN GENERATOR OUTPUT
NEAR ZERO, GENERATOR
BREAKER OPENS AND ENGINE
RAN FOR COOL DOWN PERIOD.
54. Utility “islanding” is a condition that occurs when the utility
source becomes un-available and the site generation is still
connected to the utilities “high line” or network.
Usually caused by a re-closure opening due to a fault, lightning,
downed lines, etc.
Protective relaying is used to detect this condition and opens or
trips the main incoming utility circuit breaker to the facility.
With proper logic and control, the design is such that the
generator system will go into emergency or standby mode
automatically after the utility breaker is tripped by the protective
relays.
UTILITY ISLANDING
56. ISLANDING PROTECTION
FACTORY #3FACTORY #2
RECLOSER WILL
THEN RE-CLOSE AFTER
TIME DELAY. GEN MUST
BE ISOLATED BY OPENING
PLANT UTILITY BREAKER
BEFORE RECLOSER
CLOSES.
BREAKER
OPEN
57. ISLANDING PROTECTION
FACTORY #3FACTORY #2
BREAKER
CLOSED
IF UTILITY LINE IS ISLANDED, GENERATOR
OVERLOAD COULD OCCUR WHICH CAUSES
GENERATOR UNDER FREQUENCY AND OR
OVER/UNDER VOLTAGE.
RECLOSER POSITION
NOT MONITORED AT
PLANT.
58. ISLANDING PROTECTION
FACTORY #3FACTORY #2
PROTECTIVE RELAYING DETECT
ABNORMAL FREQUENCY AND OR VOLTAGE
CONDITION AND OPENS PLANT UTILITY
BREAKER BEFORE RECLOSER CLOSES
BREAKER
OPEN
RECLOSER POSITION
NOT MONITORED AT
PLANT
59. ISLANDING PROTECTION
BREAKER
CLOSED
IF UTILITY LINE IS ISLANDED, GENERATOR
UNDER LOAD COULD OCCUR WHICH CAUSES
GENERATOR OVER FREQUENCY AND OR
UNDER/OVER VOLTAGE.
RECLOSER POSITION
NOT MONITORED AT
PLANT
61. If generator voltage is higher than utility voltage, the generator is
referred to as being overexcited. Excessive vars are generated
which can result in generator power factor being lower than the
0.8 PF. lagging rating thus overloading the generator.
If generator voltage is lower than utility voltage, the generator is
referred to as being underexcited. Vars are consumed which can
result in generator power factor being leading thus causing
excessive heating in the windings of the generator. Can cause
shutdown from reverse vars relay.
POWER FACTOR CONTROL
62. Monitors phase angle between current and voltage and changes
excitation to maintain preset PF. (phase angle).
Utility voltage usually not regulated at sites.
Generator set voltage regulators typically regulate output 0.25
to 0.5% accuracy.
Power factor control required anytime generator is paralleled to
utility.
POWER FACTOR CONTROL cont…
63. WITHOUT GENERATION
Kw kVARS kVA pF.
LOAD CONSUMTION: 1000 750 1250 0.8
UTILITY CONTRIBUTION: 1000 750 1250 0.8
GENERATION WITHOUT PROPER PF CONTROLLER ADJUSTMENT
Kw kVARS kVA pF.
LOAD CONSUMTION: 1000 750 1250 0.8
UTILITY CONTRIBUTION: 500 525 725 0.69
GEN. CONTRIBUTION: 500 225 548 0.91 -- PF. SET
GENERATION WITH PROPER PF CONTROLLER ADJUSTMENT
Kw kVARS kVA pF.
LOAD CONSUMTION: 1000 750 1250 0.8
UTILITY CONTRIBUTION: 500 375 625 0.8
GEN. CONTRIBUTION: 500 375 625 0.8 -- PF. SET
POWER FACTOR CONTROL cont…