Concept of Evaluation
Course : Monitioring , Evaluation and Impact Assessment
(FEX -506)
Presented by
Shafiya Zahoor
MSFY-2022-176
Course in Charge
Dr Hanuman L. Verma
Assistant professor
Contents
SWOT Analysis
Steps in Programme Evaluation
Milestone Chart
Gantt Chart
Programme Evaluation And Review Technique
Critical Path Method
Bennett’s Hierarchy of Evaluation
Logical Framework Approach
SWOT analysis is a framework for identifying
and analyzing an organization ‘s strengths,
weaknesses, opportunities and threats. These
words make up the SWOT acronym.
The primary goal of SWOT analysis is to
increase awareness of the factors that go into
making a business decision or establishing a
business strategy.
Technique is credited to Stanford University in
the 1960s and 1970s.
SWOT
Analysis
strength
weakness
threats
opportunities
What is SWOT Analysis
A strength is a resource or capacity the organization can use effectively to achieve its objectives.
Strength describes what an organization excels at and what separates it from the competition: a strong
brand ,loyal customer base, a strong balance sheet ,unique technology and so on .
A weakness is a limitation, fault, or defect in the organization that will keep it from achieving its
objectives. They are the areas where the business needs to improve to remain competitive : a weak
brand, higher-than- average turnover, higher level of debt, an inadequate supply chain ,or lack of capital.
An opportunity is any favorable situation in the organization's environment. It is usually a trend or change
of some kind or an overlooked need that increases demand for a product or service and permits the firm
to enhance its position by supplying it .Opportunities could arise from changes in the market, emerging
trends, new technologies, partnership etc.
A threat is any unfavorable situation in the organization's environment that is potentially damaging to its
strategy. The threat may be a barrier, a constraint, or anything external that might cause problems,
damage or injury .For example rising cost for material, increasing competition ,tight labor supply and so
on.
According to Boyle and Johns :
Programme evaluation is determination of the extent to which the desired
objectives have been attained or the amount of movement that has been made
in the desired direction .
Programme evaluation
Steps in programme evaluation
Step 1 : Define the Purpose and Scope :
Clearly articulate the objectives of the evaluation and the specific aspects of the program to be assessed.
Identify the stakeholders involved and their information needs.
Step 2 :Engage Stakeholders:
Involve key stakeholders in the evaluation process from the beginning. Understand their perspectives,
expectations, and concerns about the program.
Step 3 :Develop a Logic Model or Theory of Change :
Create a visual representation of the program’s components, activities, outputs, outcomes, and intended
impacts. This helps to clarify the program’s theory of how it will bring about desired changes.
Step 4 :Determine Evaluation Questions :
Based on the program’s objectives and logic model, develop specific evaluation questions that will guide the
data collection and analysis.
Step 5 :Select Evaluation Design :
Choose the appropriate evaluation design that fits the program’s context and resources. Common designs
include pre-post evaluations, quasi-experimental designs, and randomized controlled trials (RCTs)
Step 6 :Develop Data Collection Methods
Determine the data sources and methods to be used for data collection. This can include surveys,
interviews, focus groups, observations, and reviewing existing data.
Step 7 : Collect Data:
Implement the data collection plan and gather relevant information from the program participants,
staff, and other relevant sources.
Step 8 :Analyze Data:
Use appropriate statistical and qualitative analysis techniques to interpret the data collected and
answer the evaluation questions.
Step 9 :Interpret Findings:
Analyze the evaluation results in the context of the program’s goals and objectives. Identify
strengths, weaknesses, successes, and areas for improvement.
Step 10 :Communicate Results:
Present the evaluation findings in a clear and meaningful way to stakeholders. Provide
actionable recommendations based on the results of the evaluation.
Milestone chart
Milestones are the check points .They show your team
when an activity or phase has been completed.
Milestones simplify your role as the project manager.
They motivate and align your team members while
showing your stakeholders that the project is
progressing .
A milestone chart is a visual representation of the task your team needs to
complete through the project .Once these specific tasks are completed ,they turn
into milestone.
Step 1 : Define project goal
Create a rough timeline and define your project goal and objectives.
Step 2 : Create task list
Write down all the project task in chronological order.
Step 3 : Identify milestone
Milestone are powerful because they demonstrate forward progress in your project
plan.
Step 4 : Create your timeline
Assemble your timeline. Define dependencies and adjust phases to ensure that they
won’t cause any bottlenecks.
Step 5 : Share time line
Ask your team for feedback and adjust the timeline to prevent issue later on.
Step 6 : Add documentation
Add files ,notes to your timeline during the project lifecycle to make relevant
information accessible to everyone on your team.
Step 7 : Celebrate milestone
Acknowledge when your team reaches a new milestone by celebrating them.
How to create a Milestone chart step by step
A Gantt chart is a type of bar chart that illustrates a project scheduled
,named after its inventor Henry Gantt who designed such a chart around
the year 1910 -1915.
This chart lists the tasks to be performed on the vertical axis ,and time
interval on the horizontal axis.
The width of the horizontal bars in the graph shows the duration of each
activity
It illustrates the start and finish dates of the terminal elements and
summary elements of each project
Gantt Chart
Gantt charts help visualize various tasks and projects that
occur simultaneously within an organization, and how far
along they have progressed .
They are used by management to plan and schedule such projects so
that resources can be allocated in an optimal way and that projects
that are prioritized can finish before less important ones begin.
What are Gantt chart used for…
Project Evaluation and Review Technique (pert)
Creating a PERT Chart
Benefitsof using PERT in projectmanagement:
1. It helps maximize the use of resources.
2. It makes project planning more manageable.
3. It’s useful even if there is little or no previous schedule data.
4. It enables project managers to better estimate or determine a more definite
completion date .
5. Useful for managing uncertainty.
1
2
3
4
5
6 8
7
2 weeks
12 weeks
2 weeks 12 weeks
Nodes represent project events .These events are the large components that make up project.
Tasks ( a )are what need to be completed in order for your nodes to be implemented.
Dependencies ( )is when a task is connected to another task .These tasks rely on one another and
cannot be completed without the other.
20 weeks
PERT Chart
12 weeks
Critical pathmethod(CPM)
Critical path is a sequence of activities between a project start and
finish that takes the longest time to complete .
Critical path method is based on mathematical calculations and it is
used for scheduling project activities .
The CPM was first developed in the 1950’s by Morgan R. walker of
DuPont (chemical Company )and James E. Kelley of Remington Rand
( Machine Manufacturer).
It was first used in a missile-defense construction project .
Finding the critical path is very helpful for project managers
because it allows them to:
1.
Bennett's Hierarchy is a type of logic model tailored for programs that provide
information or education.
Bennett’s Hierarchy describes seven steps that are necessary to get from input (the first
step) to impact (the final step).
Step 1
Inputs: These are the resources to be used for the program. i.e. What you are giving?
Step 2
Activities: This is a description of what you will be doing.
Step 3
Participation: This is a description of two things. First, who is the target audience?
Second, how many people are participating, for how long, how often, etc.? e.g. scope,
frequency, duration, intensity.
Step 4
Reactions: This is a description of what the participants immediate reactions should be
to the program. Did they find the program interesting, enjoyable, informative, etc.? You
can also call this the participant’s experience.
Bennett’s Hierarchy of Evaluation
1. Inputs
2. Programme and activities
3. Programme delivery and client participation
4. Client’s reactions/satisfactions
5. Changes in Knowledge ,attitudes ,skills and aspirations
6. Change in practice
7. End results (improved social, economical and
environmental condition )
Bennett’s hierarchy – chain of events in extension programming
 An LFA is a management tool for effective planning and implementation of
developmental projects. It provides clear, concise and systematic information
about a project through a framework.
We know about various components of a project such as goal, objectives,
activities, results and indicators. The LFA helps in connecting all these components
in one framework, presenting the tight relationship between them, leading to the
achievement of the expected outcomes.
Logical framework approach (LFA)
During initial stages, it can be used to test project
ideas and concepts for relevance and usefulness.
It guides systematic and logical analysis of the key
interrelated elements that constitute a well-
designed project .
It defines linkages between the project and
external factors.
Advantage Disadvantage
Butt,H .W (1961). Principles and Philosophy of Extension Education .In Extension Education in Community
Development, New Delhi, Directorate of Extensions , Ministry of Food and Agriculture, Government.
ICA (1984).Learning and Education Process, the IERD Co-ordination Centre, Rue Amedee Lymen Stroat,
8,1030.Brussels,Belgium.
Misra D.C (1990). Defining Agricultural Extension for 1990’s. Directorate of Extension New Delhi.
Van den Ban and Hawkins H.s (1998). Agricultural Extension Longman Scientific Tectorial Essex ,UK 1988.
concept of evaluation "Character insight"

More Related Content

Similar to concept of evaluation "Character insight"

3 proj plan notes
3 proj plan notes3 proj plan notes
3 proj plan notes
Tony
 
Program Rationale and Logic for Post Monitoring
Program Rationale and Logic for Post MonitoringProgram Rationale and Logic for Post Monitoring
Program Rationale and Logic for Post Monitoring
Thabang Nare
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acm
Alberto Mico
 
Projects Management
Projects ManagementProjects Management
Projects Management
Nirmal Shah
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course review
Asa Chan
 
June 20 2010 bsi christie
June 20 2010 bsi christieJune 20 2010 bsi christie
June 20 2010 bsi christie
harrindl
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
AynetuTerefe2
 

Similar to concept of evaluation "Character insight" (20)

Project Planning module 5 presenter notes
Project Planning module 5 presenter notesProject Planning module 5 presenter notes
Project Planning module 5 presenter notes
 
3 proj plan notes
3 proj plan notes3 proj plan notes
3 proj plan notes
 
Program Rationale and Logic for Post Monitoring
Program Rationale and Logic for Post MonitoringProgram Rationale and Logic for Post Monitoring
Program Rationale and Logic for Post Monitoring
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acm
 
Outcome-Mapping.pdf
Outcome-Mapping.pdfOutcome-Mapping.pdf
Outcome-Mapping.pdf
 
Module-7-Program-Monitoring-and-Evaluation.pptx
Module-7-Program-Monitoring-and-Evaluation.pptxModule-7-Program-Monitoring-and-Evaluation.pptx
Module-7-Program-Monitoring-and-Evaluation.pptx
 
Projects Management
Projects ManagementProjects Management
Projects Management
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course review
 
June 20 2010 bsi christie
June 20 2010 bsi christieJune 20 2010 bsi christie
June 20 2010 bsi christie
 
5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs
 
Ch04
Ch04Ch04
Ch04
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
 
Ngo’s project management
Ngo’s project managementNgo’s project management
Ngo’s project management
 
Project Management
Project ManagementProject Management
Project Management
 
A2011214171642 1
A2011214171642 1A2011214171642 1
A2011214171642 1
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015
 
Assignment
Assignment Assignment
Assignment
 
Lfa
LfaLfa
Lfa
 

Recently uploaded

Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
LR1709MUSIC
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
bleessingsbender
 

Recently uploaded (20)

Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
 
Moradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in PenacovaMoradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in Penacova
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024
 
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdfThe Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
PALWAL CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN PALWAL ESCORTS
PALWAL CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN PALWAL ESCORTSPALWAL CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN PALWAL ESCORTS
PALWAL CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN PALWAL ESCORTS
 
UJJAIN CALL GIRL ❤ 8272964427❤ CALL GIRLS IN UJJAIN ESCORTS SERVICE PROVIDE
UJJAIN CALL GIRL ❤ 8272964427❤ CALL GIRLS IN UJJAIN ESCORTS SERVICE PROVIDEUJJAIN CALL GIRL ❤ 8272964427❤ CALL GIRLS IN UJJAIN ESCORTS SERVICE PROVIDE
UJJAIN CALL GIRL ❤ 8272964427❤ CALL GIRLS IN UJJAIN ESCORTS SERVICE PROVIDE
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertainty
 
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDEJIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
 
Top Quality adbb 5cl-a-d-b Best precursor raw material
Top Quality adbb 5cl-a-d-b Best precursor raw materialTop Quality adbb 5cl-a-d-b Best precursor raw material
Top Quality adbb 5cl-a-d-b Best precursor raw material
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
 

concept of evaluation "Character insight"

  • 1. Concept of Evaluation Course : Monitioring , Evaluation and Impact Assessment (FEX -506) Presented by Shafiya Zahoor MSFY-2022-176 Course in Charge Dr Hanuman L. Verma Assistant professor
  • 2. Contents SWOT Analysis Steps in Programme Evaluation Milestone Chart Gantt Chart Programme Evaluation And Review Technique Critical Path Method Bennett’s Hierarchy of Evaluation Logical Framework Approach
  • 3. SWOT analysis is a framework for identifying and analyzing an organization ‘s strengths, weaknesses, opportunities and threats. These words make up the SWOT acronym. The primary goal of SWOT analysis is to increase awareness of the factors that go into making a business decision or establishing a business strategy. Technique is credited to Stanford University in the 1960s and 1970s. SWOT Analysis strength weakness threats opportunities What is SWOT Analysis
  • 4. A strength is a resource or capacity the organization can use effectively to achieve its objectives. Strength describes what an organization excels at and what separates it from the competition: a strong brand ,loyal customer base, a strong balance sheet ,unique technology and so on . A weakness is a limitation, fault, or defect in the organization that will keep it from achieving its objectives. They are the areas where the business needs to improve to remain competitive : a weak brand, higher-than- average turnover, higher level of debt, an inadequate supply chain ,or lack of capital. An opportunity is any favorable situation in the organization's environment. It is usually a trend or change of some kind or an overlooked need that increases demand for a product or service and permits the firm to enhance its position by supplying it .Opportunities could arise from changes in the market, emerging trends, new technologies, partnership etc. A threat is any unfavorable situation in the organization's environment that is potentially damaging to its strategy. The threat may be a barrier, a constraint, or anything external that might cause problems, damage or injury .For example rising cost for material, increasing competition ,tight labor supply and so on.
  • 5. According to Boyle and Johns : Programme evaluation is determination of the extent to which the desired objectives have been attained or the amount of movement that has been made in the desired direction . Programme evaluation
  • 6. Steps in programme evaluation Step 1 : Define the Purpose and Scope : Clearly articulate the objectives of the evaluation and the specific aspects of the program to be assessed. Identify the stakeholders involved and their information needs. Step 2 :Engage Stakeholders: Involve key stakeholders in the evaluation process from the beginning. Understand their perspectives, expectations, and concerns about the program. Step 3 :Develop a Logic Model or Theory of Change : Create a visual representation of the program’s components, activities, outputs, outcomes, and intended impacts. This helps to clarify the program’s theory of how it will bring about desired changes. Step 4 :Determine Evaluation Questions : Based on the program’s objectives and logic model, develop specific evaluation questions that will guide the data collection and analysis. Step 5 :Select Evaluation Design : Choose the appropriate evaluation design that fits the program’s context and resources. Common designs include pre-post evaluations, quasi-experimental designs, and randomized controlled trials (RCTs)
  • 7. Step 6 :Develop Data Collection Methods Determine the data sources and methods to be used for data collection. This can include surveys, interviews, focus groups, observations, and reviewing existing data. Step 7 : Collect Data: Implement the data collection plan and gather relevant information from the program participants, staff, and other relevant sources. Step 8 :Analyze Data: Use appropriate statistical and qualitative analysis techniques to interpret the data collected and answer the evaluation questions. Step 9 :Interpret Findings: Analyze the evaluation results in the context of the program’s goals and objectives. Identify strengths, weaknesses, successes, and areas for improvement. Step 10 :Communicate Results: Present the evaluation findings in a clear and meaningful way to stakeholders. Provide actionable recommendations based on the results of the evaluation.
  • 8. Milestone chart Milestones are the check points .They show your team when an activity or phase has been completed. Milestones simplify your role as the project manager. They motivate and align your team members while showing your stakeholders that the project is progressing .
  • 9. A milestone chart is a visual representation of the task your team needs to complete through the project .Once these specific tasks are completed ,they turn into milestone.
  • 10. Step 1 : Define project goal Create a rough timeline and define your project goal and objectives. Step 2 : Create task list Write down all the project task in chronological order. Step 3 : Identify milestone Milestone are powerful because they demonstrate forward progress in your project plan. Step 4 : Create your timeline Assemble your timeline. Define dependencies and adjust phases to ensure that they won’t cause any bottlenecks. Step 5 : Share time line Ask your team for feedback and adjust the timeline to prevent issue later on. Step 6 : Add documentation Add files ,notes to your timeline during the project lifecycle to make relevant information accessible to everyone on your team. Step 7 : Celebrate milestone Acknowledge when your team reaches a new milestone by celebrating them. How to create a Milestone chart step by step
  • 11. A Gantt chart is a type of bar chart that illustrates a project scheduled ,named after its inventor Henry Gantt who designed such a chart around the year 1910 -1915. This chart lists the tasks to be performed on the vertical axis ,and time interval on the horizontal axis. The width of the horizontal bars in the graph shows the duration of each activity It illustrates the start and finish dates of the terminal elements and summary elements of each project Gantt Chart
  • 12. Gantt charts help visualize various tasks and projects that occur simultaneously within an organization, and how far along they have progressed . They are used by management to plan and schedule such projects so that resources can be allocated in an optimal way and that projects that are prioritized can finish before less important ones begin. What are Gantt chart used for…
  • 13. Project Evaluation and Review Technique (pert)
  • 15. Benefitsof using PERT in projectmanagement: 1. It helps maximize the use of resources. 2. It makes project planning more manageable. 3. It’s useful even if there is little or no previous schedule data. 4. It enables project managers to better estimate or determine a more definite completion date . 5. Useful for managing uncertainty.
  • 16. 1 2 3 4 5 6 8 7 2 weeks 12 weeks 2 weeks 12 weeks Nodes represent project events .These events are the large components that make up project. Tasks ( a )are what need to be completed in order for your nodes to be implemented. Dependencies ( )is when a task is connected to another task .These tasks rely on one another and cannot be completed without the other. 20 weeks PERT Chart 12 weeks
  • 17. Critical pathmethod(CPM) Critical path is a sequence of activities between a project start and finish that takes the longest time to complete . Critical path method is based on mathematical calculations and it is used for scheduling project activities . The CPM was first developed in the 1950’s by Morgan R. walker of DuPont (chemical Company )and James E. Kelley of Remington Rand ( Machine Manufacturer). It was first used in a missile-defense construction project .
  • 18. Finding the critical path is very helpful for project managers because it allows them to: 1.
  • 19. Bennett's Hierarchy is a type of logic model tailored for programs that provide information or education. Bennett’s Hierarchy describes seven steps that are necessary to get from input (the first step) to impact (the final step). Step 1 Inputs: These are the resources to be used for the program. i.e. What you are giving? Step 2 Activities: This is a description of what you will be doing. Step 3 Participation: This is a description of two things. First, who is the target audience? Second, how many people are participating, for how long, how often, etc.? e.g. scope, frequency, duration, intensity. Step 4 Reactions: This is a description of what the participants immediate reactions should be to the program. Did they find the program interesting, enjoyable, informative, etc.? You can also call this the participant’s experience. Bennett’s Hierarchy of Evaluation
  • 20.
  • 21. 1. Inputs 2. Programme and activities 3. Programme delivery and client participation 4. Client’s reactions/satisfactions 5. Changes in Knowledge ,attitudes ,skills and aspirations 6. Change in practice 7. End results (improved social, economical and environmental condition ) Bennett’s hierarchy – chain of events in extension programming
  • 22.  An LFA is a management tool for effective planning and implementation of developmental projects. It provides clear, concise and systematic information about a project through a framework. We know about various components of a project such as goal, objectives, activities, results and indicators. The LFA helps in connecting all these components in one framework, presenting the tight relationship between them, leading to the achievement of the expected outcomes. Logical framework approach (LFA)
  • 23. During initial stages, it can be used to test project ideas and concepts for relevance and usefulness. It guides systematic and logical analysis of the key interrelated elements that constitute a well- designed project . It defines linkages between the project and external factors. Advantage Disadvantage
  • 24. Butt,H .W (1961). Principles and Philosophy of Extension Education .In Extension Education in Community Development, New Delhi, Directorate of Extensions , Ministry of Food and Agriculture, Government. ICA (1984).Learning and Education Process, the IERD Co-ordination Centre, Rue Amedee Lymen Stroat, 8,1030.Brussels,Belgium. Misra D.C (1990). Defining Agricultural Extension for 1990’s. Directorate of Extension New Delhi. Van den Ban and Hawkins H.s (1998). Agricultural Extension Longman Scientific Tectorial Essex ,UK 1988.