SlideShare a Scribd company logo
1 of 17
Download to read offline
1
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Presenter:
Location:
1
International Oil Shale Symposium
2016
RisksAssessmentMatrix and its
importance in Oil Shale Mining Projects
Dr Sergei Sabanov, Principal Consultant, Mining Engineering (CEng, MIMMM)
Tallinn, Estonia, 2016
2
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Content
• Introduction
• Risk assessment matrix
• Deposit Risks Estimation
• Project Value Risks
• Mine Planning and Scheduling Considerations
• Conclusions
3
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Introduction
• Risks Assessments in oil shale mining
projects are based on technical,
operational, financial, economic,
environmental and social criteria.
• The Risk Assessment process is used to
ensure that risks are suitably quantified
and mitigation plans put in place where
necessary.
• Risk classification provides a context for
the level of evaluation required for
different estimation processes.
4
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
RiskAssessment Matrix
Ranking an event on a risk matrix can be done
in three ways:
• Worst case scenario. This is done by taking
the worst that could happen. For instance in the
case of a slope failure, there will be multiple
fatalities and it might be likely to occur.
Essentially when looking at the worst case
scenario, all barriers are ignored and only the
Hazard, Top event and Consequences are
considered. These types of incidents might
occur in reality, but they will most likely be the
exception, not the rule.
• Current situation strategy tries to evaluate the
severity and probability of the average event.
So the average severity for a slope failure might
be a single fatality, and it’s unlikely to happen.
This strategy takes into account all the barriers
that are currently implemented.
• Future situation strategy tries to make an
estimate of how the risk might go down after
improvements to barriers, or implementation of
new barriers. It aims to estimate the future
average of incidents.
5
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
RiskAssessment main steps
1. Problem Area or Activity: The phase, area or activity that is likely to face risks.
2. Risks Identified: A list of the likely risks associated with each of the activities identified.
3. Description: A short description of the kind of risk and the possible damages it can cause.
4. Probability of Occurrence: The risks can be categorized as very likely, probable and unlikely based on the
likelihood of these risks cropping up.
5. Impact Intensity: The impact intensity of the risk can be categorized as High, Medium and Low depending on
how critical the risk and its effects can be.
6. Priority: Based on the probability of occurrence then the intensity of the impact, the risk factors can be
assigned a priority level using a scale ranging from for instance 1 to 5, where 1 means high priority and 5
means least important.
7. Existing Measures: The policies, procedures and resources which are already available to prevent or reduce
the impact of the risk.
8. Mitigation Strategy: After analyzing all the aspects of the risks and the existing preventive measures that can
be used, the project team needs to decide on the mitigation strategy to deal with the risk.
9. Additional Measures: This field needs to be filled in only for those risks for which control mitigation strategy is
decided.
10.Contingency Plan: A contingency plan can also be added for high impact risks with a high probability of
occurrence, just in case the basic measures fail to perform.
http://www.brighthubpm.com/risk-management/87576-making-the-risk-assessment-process-more-fluid-use-this-sample-form/
6
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
RiskAssessment Form (a brief example)
Name Risk Factors Probability Impact Risk Indicators Risk Control
Oil Shale
Reserves
Estimate
Low confidence study: Lack of
water for processing; Impact of
density on tonnage, Impact of
lower recovery due to grinding
High High Independent consultants on
project board
Project Manager to check off
project deliverables and ensure
Resources and Reserves tables
signed-off by Competent Persons
Financial Poor Financial Strategy, Debt
and interest rate, Amortisation,
Capital and Operational
Expenses
High High Information from any source
accounting for risk. Regular
reporting mechanisms to
funder and institutional finance
Further refinement of a project cost
estimates are undertaken in order to
optimise Project profitability; The
financial model is updated regularly
to reflect new information relative to
revised production plans and
resource estimates.
Legislative Revision to the current fiscal terms Low Medium Disputes with staff unions, or
need to address concerns of
public representative bodies
Public relations and normal
negotiating procedures in place
7
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Greenfield Exploration – generally high risk
• No known mines or prospects
• Requires background data
• Some companies may do their own research
• Others may rely on data from other companies
(unsuccessful exploration programs?)
• Or government data – sponsored programs
• Typically starts with soil sampling or geophysics
• Many near surface targets have been found
Greenfield vs Brownfield Risk Considerations
• The operating mine, old mine site, industrial complex
• Could have legacy issues - indemnity
• Has a track record in the past
• There may have been economic changes since it was
closed eg commodity prices have increased or
technology has advanced
• Some risks that investors may look for:
o Presence of sulphur that can present refinery issues
in a project
o The old mine was low grade, are there higher grade
extensions?
o What role can new technology play?
o Can bulk mining be considered?
Brownfield Exploration – generally lower risk
8
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Resources vs Reserves
The Humble Cut-off Grade
• Grade of any oil shale deposit is key to economic viability
• Tend to be two extremes – small tonnage deposit but high grade
or large tonnage with low grade
• Cut off grade (CoG) is key to assessing a deposit viability and is
a function of commodity price, grade of the deposit, process
recovery and operating costs for mining and processing
• The CoG is the grade or amount of contained oil or calorific value
that is required to cover the cost of mining and processing the oil
shale
• The average grade of the oil shale from the mine must be higher
than the CoG – this is because the CoG is based on the
operating costs and a reasonable margin is required to pay back
capital investment
• If you have a list of oil shale deposits and the oil content is less
than 3-5% then is will not be attractive to investors because many
know that the basic economics require more grade
• A deposit may have an oil shale where only 40% of the oil can be
recovered with current technology. This factor must always be
considered
• A Resource is a concentration of oil shale that has
reasonable prospects of economic extraction
• A Reserve is a concentration of oil shale that is
economic to mine under prevailing conditions
• A Resource may remain a resource until high
commodity prices are higher or technology allows
oil shale to be recovered
Why are all deposits not viable?
9
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.More investment in the project, the higher the value
Project Value Risks
• Most of oil shale
projects are early
stage – but they
are not worth
much
• Advanced
projects are
worth more but
require risk
capital to be
invested
Confidence
10
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Miningmodifying factors
Technical factors
Oil shale
Interburden
waste rock
Oil shale
Interburden
waste rock
Volume, tonnage, density, moisture,
thickness, swell factor, excavatability,
losses and extraction ratios, dilutions, grade
and deleterious elements (sulphur), cut-off
grade, beneficiation/processing recovery
and mass yield, product content and grade,
haulage distance
24 gal/t
32 gal/t
38 gal/t
Volume, tonnage, density, moisture,
thickness, swell factor, rock excavatability,
haulage distance, disturbed surface
Economic factors
Mining cost, haulage cost, dumping and
rehabilitation
Mining, haulage, crushing,
beneficiation/processing, transportation,
G&A costs. Royalties, Selling price.
Beneficiation
recovery 91%
Beneficiation
recovery 82%
Beneficiation
recovery 88%
6.4MJ/kg 8.5 MJ/kg
10 MJ/kg
11
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Mine planning and scheduling considerations
By running mine optimisation, the
mine planner determines which
areas or oil shale seams in the
mine are economic:
• some mining blocks can be split
vertically for selective mining
• mining sequence should be
applied for the highest value
blocks in the deposit
$/gal $/gal $/gal $/gal
$/gal $/gal $/gal $/gal
$/gal $/gal $/gal $/gal
$/gal $/gal $/gal $/gal
$/gal $/gal $/gal $/gal
12
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Margin Ranking results
10 gall/t
15 gall/t
20 gall/t
25 gall/t
30 gall/t
35 gall/t
40 gall/t
45 gall/t
50 gall/t
55 gall/t
A
C
B
D
13
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Cumulative Net Cash Flow
• NPV can be increased by
minimising the stripping
ratio in early years,
selective mining or blast
and sieving options. Also
on optimisation of mine
phases and design.
• The reduction in capital
expenditure early in the
mine life can significantly
improve project
economics.
14
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Conclusions
• A properly undertaken Risk Assessment can determine that all risks have been appropriately
mitigated and appropriate design measures implemented prior to construction.
• SRK’s experience shows generally that certain risk factors, such as the accuracy of the
resource estimate, may be low and that other factors over the projected life of the project, such
as selling price and future changes in environmental legislation, are less predictable and higher
risk.
15
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
Thank You for Your Attention!
ssabanov@srk.kz
16
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
SRK Office Locations
>1,500 профессионалов в 50 офисах, 22 странах, на 6 континентах
ssabanov@srk.kz моб.+7 701 8876922
17
© SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.
COPYRIGHT AND DISCLAIMER
Copyright (and any other applicable intellectual property rights) in this document and any accompanying data or models which are
created by SRK Consulting (Kazakhstan) Limited ("SRK") is reserved by SRK and is protected by international copyright and other
laws. Copyright in any component parts of this document such as images is owned and reserved by the copyright owner so noted
within this document.
The use of this document is strictly subject to terms licensed by SRK to the named recipient or recipients of this document or
persons to whom SRK has agreed that it may be transferred to (the “Recipients”). Unless otherwise agreed by SRK, this does not
grant rights to any third party. This document shall only be distributed to any third party in full as provided by SRK and may not be
reproduced or circulated in the public domain (in whole or in part) or in any edited, abridged or otherwise amended form unless
expressly agreed by SRK. Any other copyright owner’s work may not be separated from this document, used or reproduced for any
other purpose other than with this document in full as licensed by SRK. In the event that this document is disclosed or distributed
to any third party, no such third party shall be entitled to place reliance upon any information, warranties or representations which
may be contained within this document and the Recipients of this document shall indemnify SRK against all and any claims, losses
and costs which may be incurred by SRK relating to such third parties.
This document is issued subject to the confidentiality provisions in SRK’s Terms and Conditions, which are included in the
Commercial Appendices and contain mutual confidentiality obligations. Accordingly, any references in the confidentiality provisions
in SRK’s Terms and Conditions to the “Client” should be read as “Recipients”. SRK respects the general confidentiality of its
potential clients’ confidential information whether formally agreed with them or not and SRK therefore expects the contents of this
document to be treated as confidential by the Recipients. The Recipients may not release the technical and pricing information
contained in this document or any other documents submitted by SRK to the Recipients, or otherwise make it or them available to
any third party without the express written consent of SRK.
© SRK Consulting (Kazakhstan) Limited 2016
version: JAN 2015
ssabanov@srk.kz моб.+7 701 8876922

More Related Content

Similar to Risks Assessment Matrix and its importance in Oil Shale Mining Projects

Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKT
Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKTWalkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKT
Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKTHong Bao Media
 
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...Kristy Marshall
 
Sigve Hamilton Aspelund CV linkedin 072015
Sigve Hamilton Aspelund CV linkedin 072015Sigve Hamilton Aspelund CV linkedin 072015
Sigve Hamilton Aspelund CV linkedin 072015Sigve Hamilton Aspelund
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
Due Dilligence_Oil Shale_Colorado 2014_Sabanov
Due Dilligence_Oil Shale_Colorado 2014_SabanovDue Dilligence_Oil Shale_Colorado 2014_Sabanov
Due Dilligence_Oil Shale_Colorado 2014_SabanovSergei Sabanov
 
October - Corporatre Presentation
October - Corporatre PresentationOctober - Corporatre Presentation
October - Corporatre Presentationglevel
 
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...Shrikant Kate
 
Llg corporate presentation february 2018
Llg   corporate presentation february 2018Llg   corporate presentation february 2018
Llg corporate presentation february 2018masongraphite
 
Overview of the problem.pptx
Overview of the problem.pptxOverview of the problem.pptx
Overview of the problem.pptxSabiPurba
 
Stratas Advisors' Global Syngas Overview by Dr. Habib Khan
Stratas Advisors' Global Syngas Overview by Dr. Habib KhanStratas Advisors' Global Syngas Overview by Dr. Habib Khan
Stratas Advisors' Global Syngas Overview by Dr. Habib KhanStratas Advisors
 
Llg corporate presentation march 2018
Llg   corporate presentation march 2018Llg   corporate presentation march 2018
Llg corporate presentation march 2018masongraphite
 
Llg corporate presentation march 2018
Llg   corporate presentation march 2018Llg   corporate presentation march 2018
Llg corporate presentation march 2018masongraphite
 
Llg corporate presentation december 2017
Llg   corporate presentation december 2017Llg   corporate presentation december 2017
Llg corporate presentation december 2017masongraphite
 
Sand Control
Sand Control Sand Control
Sand Control petroEDGE
 
Llg corporate presentation january 2018
Llg   corporate presentation january 2018Llg   corporate presentation january 2018
Llg corporate presentation january 2018masongraphite
 
Project Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesProject Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesAlabo BRIGGS
 
Mohamed Shady_C.V_Jan. 2016
Mohamed Shady_C.V_Jan. 2016Mohamed Shady_C.V_Jan. 2016
Mohamed Shady_C.V_Jan. 2016Mohamed Shady
 

Similar to Risks Assessment Matrix and its importance in Oil Shale Mining Projects (20)

Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKT
Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKTWalkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKT
Walkabout Resources Lindi Jumbo Graphite Project Ready for Development ASX:WKT
 
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
 
Sigve Hamilton Aspelund CV linkedin 072015
Sigve Hamilton Aspelund CV linkedin 072015Sigve Hamilton Aspelund CV linkedin 072015
Sigve Hamilton Aspelund CV linkedin 072015
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Due Dilligence_Oil Shale_Colorado 2014_Sabanov
Due Dilligence_Oil Shale_Colorado 2014_SabanovDue Dilligence_Oil Shale_Colorado 2014_Sabanov
Due Dilligence_Oil Shale_Colorado 2014_Sabanov
 
October - Corporatre Presentation
October - Corporatre PresentationOctober - Corporatre Presentation
October - Corporatre Presentation
 
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
Risk Management and Value Engineering _ Unit 4 _ Construction Management _ Fi...
 
Llg corporate presentation february 2018
Llg   corporate presentation february 2018Llg   corporate presentation february 2018
Llg corporate presentation february 2018
 
Overview of the problem.pptx
Overview of the problem.pptxOverview of the problem.pptx
Overview of the problem.pptx
 
Stratas Advisors' Global Syngas Overview by Dr. Habib Khan
Stratas Advisors' Global Syngas Overview by Dr. Habib KhanStratas Advisors' Global Syngas Overview by Dr. Habib Khan
Stratas Advisors' Global Syngas Overview by Dr. Habib Khan
 
Llg corporate presentation march 2018
Llg   corporate presentation march 2018Llg   corporate presentation march 2018
Llg corporate presentation march 2018
 
Llg corporate presentation march 2018
Llg   corporate presentation march 2018Llg   corporate presentation march 2018
Llg corporate presentation march 2018
 
Mineral economic
Mineral economicMineral economic
Mineral economic
 
Llg corporate presentation december 2017
Llg   corporate presentation december 2017Llg   corporate presentation december 2017
Llg corporate presentation december 2017
 
Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)
 
Sand Control
Sand Control Sand Control
Sand Control
 
Llg corporate presentation january 2018
Llg   corporate presentation january 2018Llg   corporate presentation january 2018
Llg corporate presentation january 2018
 
Project Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesProject Synopsis - Modular Refineries
Project Synopsis - Modular Refineries
 
Mohamed Shady_C.V_Jan. 2016
Mohamed Shady_C.V_Jan. 2016Mohamed Shady_C.V_Jan. 2016
Mohamed Shady_C.V_Jan. 2016
 
Cv sigve hamilton aspelund 122019
Cv sigve hamilton aspelund 122019Cv sigve hamilton aspelund 122019
Cv sigve hamilton aspelund 122019
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Risks Assessment Matrix and its importance in Oil Shale Mining Projects

  • 1. 1 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Presenter: Location: 1 International Oil Shale Symposium 2016 RisksAssessmentMatrix and its importance in Oil Shale Mining Projects Dr Sergei Sabanov, Principal Consultant, Mining Engineering (CEng, MIMMM) Tallinn, Estonia, 2016
  • 2. 2 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Content • Introduction • Risk assessment matrix • Deposit Risks Estimation • Project Value Risks • Mine Planning and Scheduling Considerations • Conclusions
  • 3. 3 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Introduction • Risks Assessments in oil shale mining projects are based on technical, operational, financial, economic, environmental and social criteria. • The Risk Assessment process is used to ensure that risks are suitably quantified and mitigation plans put in place where necessary. • Risk classification provides a context for the level of evaluation required for different estimation processes.
  • 4. 4 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. RiskAssessment Matrix Ranking an event on a risk matrix can be done in three ways: • Worst case scenario. This is done by taking the worst that could happen. For instance in the case of a slope failure, there will be multiple fatalities and it might be likely to occur. Essentially when looking at the worst case scenario, all barriers are ignored and only the Hazard, Top event and Consequences are considered. These types of incidents might occur in reality, but they will most likely be the exception, not the rule. • Current situation strategy tries to evaluate the severity and probability of the average event. So the average severity for a slope failure might be a single fatality, and it’s unlikely to happen. This strategy takes into account all the barriers that are currently implemented. • Future situation strategy tries to make an estimate of how the risk might go down after improvements to barriers, or implementation of new barriers. It aims to estimate the future average of incidents.
  • 5. 5 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. RiskAssessment main steps 1. Problem Area or Activity: The phase, area or activity that is likely to face risks. 2. Risks Identified: A list of the likely risks associated with each of the activities identified. 3. Description: A short description of the kind of risk and the possible damages it can cause. 4. Probability of Occurrence: The risks can be categorized as very likely, probable and unlikely based on the likelihood of these risks cropping up. 5. Impact Intensity: The impact intensity of the risk can be categorized as High, Medium and Low depending on how critical the risk and its effects can be. 6. Priority: Based on the probability of occurrence then the intensity of the impact, the risk factors can be assigned a priority level using a scale ranging from for instance 1 to 5, where 1 means high priority and 5 means least important. 7. Existing Measures: The policies, procedures and resources which are already available to prevent or reduce the impact of the risk. 8. Mitigation Strategy: After analyzing all the aspects of the risks and the existing preventive measures that can be used, the project team needs to decide on the mitigation strategy to deal with the risk. 9. Additional Measures: This field needs to be filled in only for those risks for which control mitigation strategy is decided. 10.Contingency Plan: A contingency plan can also be added for high impact risks with a high probability of occurrence, just in case the basic measures fail to perform. http://www.brighthubpm.com/risk-management/87576-making-the-risk-assessment-process-more-fluid-use-this-sample-form/
  • 6. 6 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. RiskAssessment Form (a brief example) Name Risk Factors Probability Impact Risk Indicators Risk Control Oil Shale Reserves Estimate Low confidence study: Lack of water for processing; Impact of density on tonnage, Impact of lower recovery due to grinding High High Independent consultants on project board Project Manager to check off project deliverables and ensure Resources and Reserves tables signed-off by Competent Persons Financial Poor Financial Strategy, Debt and interest rate, Amortisation, Capital and Operational Expenses High High Information from any source accounting for risk. Regular reporting mechanisms to funder and institutional finance Further refinement of a project cost estimates are undertaken in order to optimise Project profitability; The financial model is updated regularly to reflect new information relative to revised production plans and resource estimates. Legislative Revision to the current fiscal terms Low Medium Disputes with staff unions, or need to address concerns of public representative bodies Public relations and normal negotiating procedures in place
  • 7. 7 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Greenfield Exploration – generally high risk • No known mines or prospects • Requires background data • Some companies may do their own research • Others may rely on data from other companies (unsuccessful exploration programs?) • Or government data – sponsored programs • Typically starts with soil sampling or geophysics • Many near surface targets have been found Greenfield vs Brownfield Risk Considerations • The operating mine, old mine site, industrial complex • Could have legacy issues - indemnity • Has a track record in the past • There may have been economic changes since it was closed eg commodity prices have increased or technology has advanced • Some risks that investors may look for: o Presence of sulphur that can present refinery issues in a project o The old mine was low grade, are there higher grade extensions? o What role can new technology play? o Can bulk mining be considered? Brownfield Exploration – generally lower risk
  • 8. 8 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Resources vs Reserves The Humble Cut-off Grade • Grade of any oil shale deposit is key to economic viability • Tend to be two extremes – small tonnage deposit but high grade or large tonnage with low grade • Cut off grade (CoG) is key to assessing a deposit viability and is a function of commodity price, grade of the deposit, process recovery and operating costs for mining and processing • The CoG is the grade or amount of contained oil or calorific value that is required to cover the cost of mining and processing the oil shale • The average grade of the oil shale from the mine must be higher than the CoG – this is because the CoG is based on the operating costs and a reasonable margin is required to pay back capital investment • If you have a list of oil shale deposits and the oil content is less than 3-5% then is will not be attractive to investors because many know that the basic economics require more grade • A deposit may have an oil shale where only 40% of the oil can be recovered with current technology. This factor must always be considered • A Resource is a concentration of oil shale that has reasonable prospects of economic extraction • A Reserve is a concentration of oil shale that is economic to mine under prevailing conditions • A Resource may remain a resource until high commodity prices are higher or technology allows oil shale to be recovered Why are all deposits not viable?
  • 9. 9 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved.More investment in the project, the higher the value Project Value Risks • Most of oil shale projects are early stage – but they are not worth much • Advanced projects are worth more but require risk capital to be invested Confidence
  • 10. 10 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Miningmodifying factors Technical factors Oil shale Interburden waste rock Oil shale Interburden waste rock Volume, tonnage, density, moisture, thickness, swell factor, excavatability, losses and extraction ratios, dilutions, grade and deleterious elements (sulphur), cut-off grade, beneficiation/processing recovery and mass yield, product content and grade, haulage distance 24 gal/t 32 gal/t 38 gal/t Volume, tonnage, density, moisture, thickness, swell factor, rock excavatability, haulage distance, disturbed surface Economic factors Mining cost, haulage cost, dumping and rehabilitation Mining, haulage, crushing, beneficiation/processing, transportation, G&A costs. Royalties, Selling price. Beneficiation recovery 91% Beneficiation recovery 82% Beneficiation recovery 88% 6.4MJ/kg 8.5 MJ/kg 10 MJ/kg
  • 11. 11 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Mine planning and scheduling considerations By running mine optimisation, the mine planner determines which areas or oil shale seams in the mine are economic: • some mining blocks can be split vertically for selective mining • mining sequence should be applied for the highest value blocks in the deposit $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal $/gal
  • 12. 12 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Margin Ranking results 10 gall/t 15 gall/t 20 gall/t 25 gall/t 30 gall/t 35 gall/t 40 gall/t 45 gall/t 50 gall/t 55 gall/t A C B D
  • 13. 13 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Cumulative Net Cash Flow • NPV can be increased by minimising the stripping ratio in early years, selective mining or blast and sieving options. Also on optimisation of mine phases and design. • The reduction in capital expenditure early in the mine life can significantly improve project economics.
  • 14. 14 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Conclusions • A properly undertaken Risk Assessment can determine that all risks have been appropriately mitigated and appropriate design measures implemented prior to construction. • SRK’s experience shows generally that certain risk factors, such as the accuracy of the resource estimate, may be low and that other factors over the projected life of the project, such as selling price and future changes in environmental legislation, are less predictable and higher risk.
  • 15. 15 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. Thank You for Your Attention! ssabanov@srk.kz
  • 16. 16 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. SRK Office Locations >1,500 профессионалов в 50 офисах, 22 странах, на 6 континентах ssabanov@srk.kz моб.+7 701 8876922
  • 17. 17 © SRK Consulting (Kazakhstan) Ltd 2016. All rights reserved. COPYRIGHT AND DISCLAIMER Copyright (and any other applicable intellectual property rights) in this document and any accompanying data or models which are created by SRK Consulting (Kazakhstan) Limited ("SRK") is reserved by SRK and is protected by international copyright and other laws. Copyright in any component parts of this document such as images is owned and reserved by the copyright owner so noted within this document. The use of this document is strictly subject to terms licensed by SRK to the named recipient or recipients of this document or persons to whom SRK has agreed that it may be transferred to (the “Recipients”). Unless otherwise agreed by SRK, this does not grant rights to any third party. This document shall only be distributed to any third party in full as provided by SRK and may not be reproduced or circulated in the public domain (in whole or in part) or in any edited, abridged or otherwise amended form unless expressly agreed by SRK. Any other copyright owner’s work may not be separated from this document, used or reproduced for any other purpose other than with this document in full as licensed by SRK. In the event that this document is disclosed or distributed to any third party, no such third party shall be entitled to place reliance upon any information, warranties or representations which may be contained within this document and the Recipients of this document shall indemnify SRK against all and any claims, losses and costs which may be incurred by SRK relating to such third parties. This document is issued subject to the confidentiality provisions in SRK’s Terms and Conditions, which are included in the Commercial Appendices and contain mutual confidentiality obligations. Accordingly, any references in the confidentiality provisions in SRK’s Terms and Conditions to the “Client” should be read as “Recipients”. SRK respects the general confidentiality of its potential clients’ confidential information whether formally agreed with them or not and SRK therefore expects the contents of this document to be treated as confidential by the Recipients. The Recipients may not release the technical and pricing information contained in this document or any other documents submitted by SRK to the Recipients, or otherwise make it or them available to any third party without the express written consent of SRK. © SRK Consulting (Kazakhstan) Limited 2016 version: JAN 2015 ssabanov@srk.kz моб.+7 701 8876922