SlideShare a Scribd company logo
1 of 21
DEEPWATER HORIZON
By
AKSHAY GUPTA, KUNAL SINGHAL & SAURBH SENGAR
THE TIMELINE
CHRONOLOGICAL SEQUENCE OF EVENTS
OCCURRED AND THEIR CAUSES
1. Centralizers
CHRONOLOGICAL SEQUENCE OF EVENTS
OCCURRED AND THEIR CAUSES
2. Cementing Job:
 ‘Nitrogen foam cement’ was used to lighten the resulting slurry
from approximately 16.7 ppg to 14.5 ppg—thereby reducing the
pressure the cement would exert on the fragile formation.
 Third party test results suggest that the foam cement slurry used for the
Macondo well was likely unstable, resulting in nitrogen breakout.
3. Float Collar and Shoe Track barrier:
 Flow rate of 1 bpm was used and float collar was converted at 3,142
psi inconsistent with the manufacture guidelines of using 5-8 bpm and
500-700 psi. No perfect evidence exist that float collar was converted.
 Shoe track failure could be its contamination by nitrogen
breakdown from the nitrified foam cement.
4. Improper Bottoms- Up circulation
5. Cement bond log test: A test that is required to check the stability
of cement plug was not conducted. The Schlumberger team was
sent back without verifying the integrity of cement plug.
6. Temporary Abandonment Plan
The major flaws in their plan was –
a) 3,300 feet of mud below the mud line was replaced with seawater.
It placed more stress on the cement job at the bottom of the well than
necessary.
b) Used an unusually large amount (425 bbl) of 16 ppg spacer to complete
the displacement.
7. Wrong
interpretation of
Negative
Pressure Test
Results
 For a successful
negative pressure test,
the pressure in
drillpipe and kill line
must be same.
8. Diversion to mud-gas separator
Diversion of hydrocarbons coming through the riser to the mud gas
separator quickly overwhelmed the MSG and failed to control the
hydrocarbons exiting the riser.
9. Failure of BOP
 High pressure
hydrocarbon
degraded the
elastomer in
annular preventer.
 Buckling of pipe
and failure of BSR
to cut the drillpipe.
 Failure of AMF
dead man
10. Failure of fire and gas system
The fire and alarm system
did not prevent the gas from
ignition source and caused
explosion.
 Gas dispersed beyond
electrically classified
areas.
 Gas ingress into engine
rooms via main deck air
intakes.
 The on-line engines were
one potential source of
ignition.
1. Impact to the deep eco-system:
 Affected the coral communities
including extremely vulnerable and
slow to recover corals.
 Severe reduction in abundance and
diversity of bottom-dwelling (or
benthic) organisms.
2. Impact to sea turtles:
 More than 1,000 sea turtles were found
dead following the oil spill.
3. Impacts to Seabirds
 32% of the northern Gulf population of
laughing gull was killed along with 13%
of the royal tern population, 8 percent
of the northern gannet, and 12 percent
of the brown pelican population.
4. Impacts to marine mammals:
 Disaster is acknowledged as the likely
cause of a unusual mortality event (UME-
defined as a stranding that is unexpected;
involves a significant die-off of any marine
mammal population) for dolphins and
whales in the northern Gulf of Mexico.
 Elevated concentrations of genotoxic
metals (such as chromium and nickel)
are found in skin tissues of Gulf
whales which causes genetic mutations
and cancer.
 The chemical dispersants used during the
oil spill, killed cells and damaged cell
DNA of sperm whale skin cells, leading
to sub lethal but perhaps long-term
harmful effects to whales.
More than 60 different species were likely to have been in
the spill region. Of these species, 40 are endemic, or found
only in the Gulf of Mexico.
A number of sub-lethal impacts of oil exposure have been
found in many species, including:
1. Disrupted growth, development, and reproduction
2. Tissue damage
3. Altered cardiac development and function
4. Disrupted immune system
5. Biochemical and cellular alterations
6. Changes in swimming ability
4. Impacts to marine and estuarine habitats
 600 miles of sand beach habitat was oiled, and at least 400 miles of
oiled beaches also experienced some level of impairment due to
response activities.
 Marsh and mangrove habitats that were oiled experienced loss of
vegetative cover and condition.
PREVENTIVE MEASURES THAT SHOULD HAVE BEEN
ADOPTED
1. Liner with Tieback vs. Long String Design
PREVENTIVE MEASURES THAT SHOULD HAVE BEEN
ADOPTED (CONTD.)
2. The second alternative would have been having twenty-one centralizers that
were recommended, instead the six that BP used. Thus, preventing the
issues of gas flow and subsequent cement channelling.
3. As mentioned in the causes, the steps following the improper float collar
conversion aggravated the risks of the blowout. So, if the manufacturing
guidelines had been followed , then the risks would have been minimized.
4. Instead of using a single set of shear rams if 2 set of shear rams can be used
in a BOP placed perpendicular to each other at certain heights then buckling
cannot fail the BOP. Initially only the Lower BOP is activated but if the
problem persists seconds BOP is activated which will finally seal the pipe.
5. There were conflicting goals in the selection of BOP elastomers, specifically
to be flexible at low temperatures, but not extrude out at high temperature.
Elastomers become more fluid with increasing temperature, so it should be
recognized that sustained high flow may ultimately cause wellhead
temperature to exceed elastomer capability and lead to failure.
PREVENTIVE MEASURES THAT SHOULD HAVE BEEN
ADOPTED (CONTD.)
6. The instrumentation and displays used for well monitoring must be improved.
There is a need to develop more sophisticated, automated alarms and
algorithms which can be built into the display system to alert the driller and
mud-logger when anomalies arise. i.e for the kick detection.
7. Automated diversion i.e; the proper channeling of flow through riser could have
been done so as to reduce the direct pressure. With this, pressure in the main
stream can be reduced to a finite extent, thus giving more time to combat
the blowout.
8. Also, we propose to design an alarm whose sensors will be connected to
riser itself at some specific distance like if our riser is of 1000ft then we
will install it at every 250ft so that even any sensor fails then we will be
having a backup option. These sensors will be hydraulically operated as
it will be designed to get activated in case riser encounter a pressure
greater than a certain limit leading to this strengthening the safety
regulations even if hydrocarbons enter the riser before activating the
BOP’S which happened at Deepwater horizon
THANK YOU

More Related Content

What's hot

Open Hole Completion Design
Open Hole Completion DesignOpen Hole Completion Design
Open Hole Completion DesignKamal Abdurahman
 
Acid Fracturing Stimulation
Acid Fracturing StimulationAcid Fracturing Stimulation
Acid Fracturing StimulationHimanshu Rajawat
 
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptxAihamAltayeh1
 
Deepwater Horizon Oil Spill
Deepwater Horizon Oil SpillDeepwater Horizon Oil Spill
Deepwater Horizon Oil Spilltifftai
 
Primary cementing and Secondary Cementing
Primary cementing  and Secondary CementingPrimary cementing  and Secondary Cementing
Primary cementing and Secondary CementingHtet Naing Htoo
 
Deepwater Horizon Accident Investigation Report
Deepwater Horizon Accident Investigation ReportDeepwater Horizon Accident Investigation Report
Deepwater Horizon Accident Investigation ReportGaurav Singh Rajput
 
Le 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and DistributionLe 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and DistributionNsulangi Paul
 
An introduction to oil and gas production
An introduction to oil and gas productionAn introduction to oil and gas production
An introduction to oil and gas productionAndi Anriansyah
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssdElsayed Amer
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsMohamed Elnagar
 
Pressure & Rate Transient Analysis.pdf
Pressure & Rate Transient Analysis.pdfPressure & Rate Transient Analysis.pdf
Pressure & Rate Transient Analysis.pdfSeyedAbolfazlHossein4
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Society of Petroleum Engineers
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellheadElsayed Amer
 
Sucker rod pumping short course!!! ~downhole diagnostic
Sucker rod pumping short course!!!   ~downhole diagnosticSucker rod pumping short course!!!   ~downhole diagnostic
Sucker rod pumping short course!!! ~downhole diagnosticenLightNme888
 

What's hot (20)

Bp oil spill
Bp oil spillBp oil spill
Bp oil spill
 
Open Hole Completion Design
Open Hole Completion DesignOpen Hole Completion Design
Open Hole Completion Design
 
Acid Fracturing Stimulation
Acid Fracturing StimulationAcid Fracturing Stimulation
Acid Fracturing Stimulation
 
Marginal oil fields
Marginal oil fieldsMarginal oil fields
Marginal oil fields
 
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptx
 
Deepwater Horizon Oil Spill
Deepwater Horizon Oil SpillDeepwater Horizon Oil Spill
Deepwater Horizon Oil Spill
 
Primary cementing and Secondary Cementing
Primary cementing  and Secondary CementingPrimary cementing  and Secondary Cementing
Primary cementing and Secondary Cementing
 
Deepwater Horizon Accident Investigation Report
Deepwater Horizon Accident Investigation ReportDeepwater Horizon Accident Investigation Report
Deepwater Horizon Accident Investigation Report
 
Le 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and DistributionLe 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and Distribution
 
An introduction to oil and gas production
An introduction to oil and gas productionAn introduction to oil and gas production
An introduction to oil and gas production
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssd
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
Pressure & Rate Transient Analysis.pdf
Pressure & Rate Transient Analysis.pdfPressure & Rate Transient Analysis.pdf
Pressure & Rate Transient Analysis.pdf
 
Well test analysis
Well test analysisWell test analysis
Well test analysis
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
 
CaseStudyFinalReport.docx
CaseStudyFinalReport.docxCaseStudyFinalReport.docx
CaseStudyFinalReport.docx
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellhead
 
Well stimulation
Well stimulationWell stimulation
Well stimulation
 
Sucker rod pumping short course!!! ~downhole diagnostic
Sucker rod pumping short course!!!   ~downhole diagnosticSucker rod pumping short course!!!   ~downhole diagnostic
Sucker rod pumping short course!!! ~downhole diagnostic
 

Similar to Deepwater horizon

Fact Sheet Hydraulic Fracturing
Fact Sheet Hydraulic FracturingFact Sheet Hydraulic Fracturing
Fact Sheet Hydraulic FracturingSantos Ltd
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06John Grover
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalJohn Grover
 
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...CrimsonPublishersAMMS
 
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.Mike Dupont
 
LOSSES CIRCULATION
LOSSES CIRCULATIONLOSSES CIRCULATION
LOSSES CIRCULATIONfalah hassan
 
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupDEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupBoris Svasta
 
Depleted oil fields regeneration with water shutoff - euco group
Depleted oil fields   regeneration with water shutoff - euco groupDepleted oil fields   regeneration with water shutoff - euco group
Depleted oil fields regeneration with water shutoff - euco groupBoris Svasta
 
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...Pomcert
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Projectashkan ezazi
 
DRILLING FLUIDS FOR THE HPHT ENVIRONMENT
DRILLING FLUIDS FOR THE HPHT ENVIRONMENTDRILLING FLUIDS FOR THE HPHT ENVIRONMENT
DRILLING FLUIDS FOR THE HPHT ENVIRONMENTMohan Doshi
 

Similar to Deepwater horizon (20)

Fact Sheet Hydraulic Fracturing
Fact Sheet Hydraulic FracturingFact Sheet Hydraulic Fracturing
Fact Sheet Hydraulic Fracturing
 
Spe 121557-ms
Spe 121557-msSpe 121557-ms
Spe 121557-ms
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
 
POSTER (Original)
POSTER (Original)POSTER (Original)
POSTER (Original)
 
Expl 2-jb-57-e
Expl 2-jb-57-eExpl 2-jb-57-e
Expl 2-jb-57-e
 
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...
Clay Migration in Proppant during Production in Argillaceous Unconsolidated R...
 
Drilling Fluids
Drilling FluidsDrilling Fluids
Drilling Fluids
 
IPTC-13174-ms
IPTC-13174-msIPTC-13174-ms
IPTC-13174-ms
 
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
 
LOSSES CIRCULATION
LOSSES CIRCULATIONLOSSES CIRCULATION
LOSSES CIRCULATION
 
Aijrfans14 256
Aijrfans14 256Aijrfans14 256
Aijrfans14 256
 
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupDEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
 
Depleted oil fields regeneration with water shutoff - euco group
Depleted oil fields   regeneration with water shutoff - euco groupDepleted oil fields   regeneration with water shutoff - euco group
Depleted oil fields regeneration with water shutoff - euco group
 
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...
1.5 "Environmental Concern and QA/QC in Shale Gas Drilling and Fracturing" - ...
 
Aging of bitumen
Aging of bitumenAging of bitumen
Aging of bitumen
 
Spe 164580-ms
Spe 164580-msSpe 164580-ms
Spe 164580-ms
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Project
 
DRILLING FLUIDS FOR THE HPHT ENVIRONMENT
DRILLING FLUIDS FOR THE HPHT ENVIRONMENTDRILLING FLUIDS FOR THE HPHT ENVIRONMENT
DRILLING FLUIDS FOR THE HPHT ENVIRONMENT
 
Well Integrity.pptx
Well Integrity.pptxWell Integrity.pptx
Well Integrity.pptx
 

Recently uploaded

Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
Philippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyPhilippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyKristineRoseCorrales
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012sapnasaifi408
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhidelih Escorts
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerSuhani Kapoor
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesDr. Salem Baidas
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashikranjana rawat
 
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxPoly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxAgrodome projects LLP
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best ServicesDwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Servicesnajka9823
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一F dds
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Green Marketing Strategies and Challenges
Green Marketing Strategies and ChallengesGreen Marketing Strategies and Challenges
Green Marketing Strategies and ChallengesDr. Salem Baidas
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130Suhani Kapoor
 
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量sehgh15heh
 

Recently uploaded (20)

Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
Philippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyPhilippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copy
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
E-Waste Management
E-Waste ManagementE-Waste Management
E-Waste Management
 
Sustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and ChallengesSustainable Clothing Strategies and Challenges
Sustainable Clothing Strategies and Challenges
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
 
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
 
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxPoly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best ServicesDwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Green Marketing Strategies and Challenges
Green Marketing Strategies and ChallengesGreen Marketing Strategies and Challenges
Green Marketing Strategies and Challenges
 
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
 
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲詹姆斯库克大学毕业证JCU毕业证成绩单留信学历认证保障质量
 

Deepwater horizon

  • 1. DEEPWATER HORIZON By AKSHAY GUPTA, KUNAL SINGHAL & SAURBH SENGAR
  • 3. CHRONOLOGICAL SEQUENCE OF EVENTS OCCURRED AND THEIR CAUSES 1. Centralizers
  • 4. CHRONOLOGICAL SEQUENCE OF EVENTS OCCURRED AND THEIR CAUSES 2. Cementing Job:  ‘Nitrogen foam cement’ was used to lighten the resulting slurry from approximately 16.7 ppg to 14.5 ppg—thereby reducing the pressure the cement would exert on the fragile formation.  Third party test results suggest that the foam cement slurry used for the Macondo well was likely unstable, resulting in nitrogen breakout. 3. Float Collar and Shoe Track barrier:  Flow rate of 1 bpm was used and float collar was converted at 3,142 psi inconsistent with the manufacture guidelines of using 5-8 bpm and 500-700 psi. No perfect evidence exist that float collar was converted.  Shoe track failure could be its contamination by nitrogen breakdown from the nitrified foam cement.
  • 5.
  • 6.
  • 7. 4. Improper Bottoms- Up circulation 5. Cement bond log test: A test that is required to check the stability of cement plug was not conducted. The Schlumberger team was sent back without verifying the integrity of cement plug.
  • 8. 6. Temporary Abandonment Plan The major flaws in their plan was – a) 3,300 feet of mud below the mud line was replaced with seawater. It placed more stress on the cement job at the bottom of the well than necessary. b) Used an unusually large amount (425 bbl) of 16 ppg spacer to complete the displacement.
  • 9. 7. Wrong interpretation of Negative Pressure Test Results  For a successful negative pressure test, the pressure in drillpipe and kill line must be same.
  • 10. 8. Diversion to mud-gas separator Diversion of hydrocarbons coming through the riser to the mud gas separator quickly overwhelmed the MSG and failed to control the hydrocarbons exiting the riser.
  • 11. 9. Failure of BOP  High pressure hydrocarbon degraded the elastomer in annular preventer.  Buckling of pipe and failure of BSR to cut the drillpipe.  Failure of AMF dead man
  • 12. 10. Failure of fire and gas system The fire and alarm system did not prevent the gas from ignition source and caused explosion.  Gas dispersed beyond electrically classified areas.  Gas ingress into engine rooms via main deck air intakes.  The on-line engines were one potential source of ignition.
  • 13.
  • 14. 1. Impact to the deep eco-system:  Affected the coral communities including extremely vulnerable and slow to recover corals.  Severe reduction in abundance and diversity of bottom-dwelling (or benthic) organisms. 2. Impact to sea turtles:  More than 1,000 sea turtles were found dead following the oil spill. 3. Impacts to Seabirds  32% of the northern Gulf population of laughing gull was killed along with 13% of the royal tern population, 8 percent of the northern gannet, and 12 percent of the brown pelican population.
  • 15. 4. Impacts to marine mammals:  Disaster is acknowledged as the likely cause of a unusual mortality event (UME- defined as a stranding that is unexpected; involves a significant die-off of any marine mammal population) for dolphins and whales in the northern Gulf of Mexico.  Elevated concentrations of genotoxic metals (such as chromium and nickel) are found in skin tissues of Gulf whales which causes genetic mutations and cancer.  The chemical dispersants used during the oil spill, killed cells and damaged cell DNA of sperm whale skin cells, leading to sub lethal but perhaps long-term harmful effects to whales.
  • 16. More than 60 different species were likely to have been in the spill region. Of these species, 40 are endemic, or found only in the Gulf of Mexico. A number of sub-lethal impacts of oil exposure have been found in many species, including: 1. Disrupted growth, development, and reproduction 2. Tissue damage 3. Altered cardiac development and function 4. Disrupted immune system 5. Biochemical and cellular alterations 6. Changes in swimming ability
  • 17. 4. Impacts to marine and estuarine habitats  600 miles of sand beach habitat was oiled, and at least 400 miles of oiled beaches also experienced some level of impairment due to response activities.  Marsh and mangrove habitats that were oiled experienced loss of vegetative cover and condition.
  • 18. PREVENTIVE MEASURES THAT SHOULD HAVE BEEN ADOPTED 1. Liner with Tieback vs. Long String Design
  • 19. PREVENTIVE MEASURES THAT SHOULD HAVE BEEN ADOPTED (CONTD.) 2. The second alternative would have been having twenty-one centralizers that were recommended, instead the six that BP used. Thus, preventing the issues of gas flow and subsequent cement channelling. 3. As mentioned in the causes, the steps following the improper float collar conversion aggravated the risks of the blowout. So, if the manufacturing guidelines had been followed , then the risks would have been minimized. 4. Instead of using a single set of shear rams if 2 set of shear rams can be used in a BOP placed perpendicular to each other at certain heights then buckling cannot fail the BOP. Initially only the Lower BOP is activated but if the problem persists seconds BOP is activated which will finally seal the pipe. 5. There were conflicting goals in the selection of BOP elastomers, specifically to be flexible at low temperatures, but not extrude out at high temperature. Elastomers become more fluid with increasing temperature, so it should be recognized that sustained high flow may ultimately cause wellhead temperature to exceed elastomer capability and lead to failure.
  • 20. PREVENTIVE MEASURES THAT SHOULD HAVE BEEN ADOPTED (CONTD.) 6. The instrumentation and displays used for well monitoring must be improved. There is a need to develop more sophisticated, automated alarms and algorithms which can be built into the display system to alert the driller and mud-logger when anomalies arise. i.e for the kick detection. 7. Automated diversion i.e; the proper channeling of flow through riser could have been done so as to reduce the direct pressure. With this, pressure in the main stream can be reduced to a finite extent, thus giving more time to combat the blowout. 8. Also, we propose to design an alarm whose sensors will be connected to riser itself at some specific distance like if our riser is of 1000ft then we will install it at every 250ft so that even any sensor fails then we will be having a backup option. These sensors will be hydraulically operated as it will be designed to get activated in case riser encounter a pressure greater than a certain limit leading to this strengthening the safety regulations even if hydrocarbons enter the riser before activating the BOP’S which happened at Deepwater horizon

Editor's Notes

  1. A Long String casing design consists of a casing string that is a hung from the wellhead and runs the full length of the well. This design requires high quality cementing to prevent the flow of hydrocarbons into the well, because in the case that hydrocarbons bypass the cement, they can flow directly up to the wellhead, causing a potential blowout. Thus, considering this as a major risk ,primary cementing of a liner is more straightforward and less prone to contamination of the cement mix while displacing it into place.