JOB EXECUTION
BY
SANTOSH KUMAR MANCHAL
S8-ICED, NSSCE
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 1
CONTENT
■ PLANNIG HINTS
■ SCHEDULING
■ SPECIFYING INSTRUMENTS
■ VENDOR SELECTION
■ SHIPPING, RECEIVING, AND STORING
■ INSTALLATIONS AND PROJECT CHECKOUT
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 2
JOB EXECUTION
■ Job organization depends on
■ Methods covers primary
elements of good organization
■ Apply to any job
■ Most methods are applied in
the earlier phase
■ A few get along as a
continuous process
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 3
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 4
1. PLANNING HINTS
■ Review job to know its extent and complexity
– Follow specific standard procedures
■ Determine quality of help needed
■ Prepare list of instrument required
– Update the list mentioning specification, purchase and
installation details
■ Make list of major work categories and assign them to the
corresponding group
– Examples includes cv, meter run, panel instruments,
gauges, switches, actuators, isa diagrams and charts,
plot and installation plans etc
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 5
■ Schedule the project timing. Draw a man hour vs. time
curve
■ Set priorities and make job assignments.
■ Initial documentation. Categorization. All work
documents must be filled. Reminders.
■ Report job progress/monitor job progress. Check the
schedule maintenance.
■ Make sure addition and deletion to job are well
recorded and informed.
■ Check for available cancellation if product already
bought.
■ All documents, drawings, and paper works must be
accordingly marked, categorized and filedJOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 6
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 7
■ Make sure the item delivered meets the specifications and
requirement, and is not defected.
■ The product must meet the delivery commitments.
■ Examples of difficulties
– Employees on vacation
– Possible delay or Failed delivery due to deliberate or
proper reasons
– Strike ON, Strike ON. Bharath band, hartaal, random MP
CM Actors dead or murder etc
– Displacement of product or damaging during handling and
shipping
– Environmental factors
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 8
2. SCHEDULING
■ In rare cases, delivery of instruments are less shorter.
– Depends on side and nature of manufacturing
■ Adjust work according to possible calculated tolerance
time.
■ Work backward from installation.
– Allow necessary time for shipping fabrication
installation etc
■ Engineering thing- be specific about the product
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 9
■ Consider the infrastructure and other phase of project.
■ Wise use of manpower.
■ Thorough planning
■ Adjust normal sequence of work for long delivery items
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 10
3. SPECIFYING INSTRUMENTS
■ Group them into categories.
■ Purchase in group. Different
types of device in same
category.
– Flow, pressure, temp,etc-
transmitters
■ Based on size
– Control valve sizing
■ Control panel specification
■ Find single vendor.
■ Early purchase
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 11
4. VENDOR SELECTION
■ There are significant reason for selection of certain
vendor, specially for panel mounted.
■ Select the bidder who provide the same or instrument
with equal quality.
■ If no preference is mentioned, go economic
– A poor man,s curry is onion with sauce and spice.
■ Cost must not be the only consideration
– Labor, material, accessories, compatible
converters, quality
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 12
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR
MANCHAL
13
■ Example
– Two sellers selling same transmitter at same cost
but one has 4 wire and other has 2 wire system
compatibility. Choose 2 wire to reduce installation
charge or 4 wire if existing system is compatible.
– Two control valve quote same price for same or
equal quality model, use the valve manufacturer
already in use to reduce inventories.
– i-OS and Android based smart phone
■ Delivery requirement and responsibility.
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 14
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 15
5. SHIPPING, RECEIVING, AND
STORING
■ Often receive very little attention causing large monetary
loss.
■ Make sure the address is correct
– The shipment may reach site than to fabrication
center
■ Ship maximum instrument to their point of use.
– Unless devices are needed to be checked for their
associate wirings
■ Send mounting cases etc. direct to fabricator
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 16
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR
MANCHAL
17
■ Received by people who can verify equipment's
compliance who knows the purchase order
specification.
■ Make sure details of receiving inspector is noted.
■ Necessary steps according to protocol must be taken
in case of wrong or defected or incomplete delivery.
This may further add to labor cost etc.
■ Storage building must be clean and dry, with proper
ventilation or isolation depending on the product.
■ Analytical instruments, control panels and other fragile
instruments must be specially noted and cared for
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR
MANCHAL
18
5. INSTALLATION AND CHECKOUT
■ All instruments must be available when needed.
■ Valves, meters and other process connected
instruments should be ready when associated
lines are installed
■ Underground conduits must be pre installed.
■ Checkout should start well ahead.
■ Schedule checkout depending of which system of
project is to be run first.
■ Check for power requirements
■ Early completion of control panel is required
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 19
reference
■ W G Andrew, H B Williams, “Applied
Instrumentation In The Process
Industries”, Second Edition. Vol 2, Gulf
Publishing Company Book Division,
1980
■ GOOGLE
JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR
MANCHAL
20

More Related Content

What's hot

Retrocommissioning Works
Retrocommissioning WorksRetrocommissioning Works
Retrocommissioning WorksCx Associates
 
Work Experience Presentation version 1
Work Experience Presentation version 1Work Experience Presentation version 1
Work Experience Presentation version 1Karambir Sidhu
 
Maintenance Supervisor Resume template
Maintenance Supervisor Resume templateMaintenance Supervisor Resume template
Maintenance Supervisor Resume templateBobby Key
 
Automated process control and CAM
Automated process control and CAMAutomated process control and CAM
Automated process control and CAMAnoop Singh
 
Experienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor ManagementExperienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor ManagementLakshminarasimman S
 
DIAMULATOR presentation (May 2015)
DIAMULATOR presentation (May 2015)DIAMULATOR presentation (May 2015)
DIAMULATOR presentation (May 2015)Christine Madu
 
Compressor Management System_Sandvik
Compressor Management System_SandvikCompressor Management System_Sandvik
Compressor Management System_SandvikVikas Kataria
 
Using MCMC sampling technique for Well production forecasting
Using MCMC sampling technique for Well production forecastingUsing MCMC sampling technique for Well production forecasting
Using MCMC sampling technique for Well production forecastingMalik Nabeel Aamer
 
DIAMULATOR Sales Presentation (Revised May 2015)
DIAMULATOR Sales Presentation (Revised May 2015)DIAMULATOR Sales Presentation (Revised May 2015)
DIAMULATOR Sales Presentation (Revised May 2015)Daneen Segec
 
Eric Bostwick's resume 5-10-16
Eric Bostwick's resume 5-10-16Eric Bostwick's resume 5-10-16
Eric Bostwick's resume 5-10-16Eric Bostwick
 
Process Control
Process ControlProcess Control
Process ControlShirleyy
 
Clayton Fillyaw Resume 4-2016
Clayton Fillyaw Resume 4-2016Clayton Fillyaw Resume 4-2016
Clayton Fillyaw Resume 4-2016Clayton Fillyaw
 

What's hot (20)

Retrocommissioning Works
Retrocommissioning WorksRetrocommissioning Works
Retrocommissioning Works
 
Work Experience Presentation version 1
Work Experience Presentation version 1Work Experience Presentation version 1
Work Experience Presentation version 1
 
Maintenance Supervisor Resume template
Maintenance Supervisor Resume templateMaintenance Supervisor Resume template
Maintenance Supervisor Resume template
 
Unit 2 manufacturing system design
Unit   2 manufacturing system designUnit   2 manufacturing system design
Unit 2 manufacturing system design
 
Unit 1 manufacturing system design
Unit   1 manufacturing system designUnit   1 manufacturing system design
Unit 1 manufacturing system design
 
Block diagram
Block diagram Block diagram
Block diagram
 
Automated process control and CAM
Automated process control and CAMAutomated process control and CAM
Automated process control and CAM
 
Presentation1
Presentation1Presentation1
Presentation1
 
Experienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor ManagementExperienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor Management
 
DIAMULATOR presentation (May 2015)
DIAMULATOR presentation (May 2015)DIAMULATOR presentation (May 2015)
DIAMULATOR presentation (May 2015)
 
Compressor Management System_Sandvik
Compressor Management System_SandvikCompressor Management System_Sandvik
Compressor Management System_Sandvik
 
RESUM (1)
RESUM (1)RESUM (1)
RESUM (1)
 
Scheduling
SchedulingScheduling
Scheduling
 
Using MCMC sampling technique for Well production forecasting
Using MCMC sampling technique for Well production forecastingUsing MCMC sampling technique for Well production forecasting
Using MCMC sampling technique for Well production forecasting
 
DIAMULATOR Sales Presentation (Revised May 2015)
DIAMULATOR Sales Presentation (Revised May 2015)DIAMULATOR Sales Presentation (Revised May 2015)
DIAMULATOR Sales Presentation (Revised May 2015)
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Process control ch 1
Process control ch 1Process control ch 1
Process control ch 1
 
Eric Bostwick's resume 5-10-16
Eric Bostwick's resume 5-10-16Eric Bostwick's resume 5-10-16
Eric Bostwick's resume 5-10-16
 
Process Control
Process ControlProcess Control
Process Control
 
Clayton Fillyaw Resume 4-2016
Clayton Fillyaw Resume 4-2016Clayton Fillyaw Resume 4-2016
Clayton Fillyaw Resume 4-2016
 

Similar to Job Execution in Industrial System Design

Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceDhanesh S
 
Yashika industries powered by #National #Instruments #NI #LabVIEW
Yashika industries powered by #National #Instruments #NI #LabVIEWYashika industries powered by #National #Instruments #NI #LabVIEW
Yashika industries powered by #National #Instruments #NI #LabVIEWArunkumar Doraiswamy
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Kevin Perry
 
Cfx12 06 review_day1
Cfx12 06 review_day1Cfx12 06 review_day1
Cfx12 06 review_day1Marcushuynh66
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance ManagementVijay325
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revertMike Lewin
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairsJithu John
 
User specification requirements (urs) rash
User specification requirements (urs) rashUser specification requirements (urs) rash
User specification requirements (urs) rashRASHMINasare
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesvideoaakash15
 
Abdalla Ghanem CV.. rotating, reliability and mechanical engineering, and pl...
Abdalla Ghanem CV..  rotating, reliability and mechanical engineering, and pl...Abdalla Ghanem CV..  rotating, reliability and mechanical engineering, and pl...
Abdalla Ghanem CV.. rotating, reliability and mechanical engineering, and pl...Abdalla Ghanem
 
Types of maintenance of industrial pharmacy
Types of maintenance of industrial pharmacyTypes of maintenance of industrial pharmacy
Types of maintenance of industrial pharmacyJessica Fernandes
 
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTREPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTlaxtwinsme
 

Similar to Job Execution in Industrial System Design (20)

CV-4-1 -
CV-4-1 -CV-4-1 -
CV-4-1 -
 
Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of Maintenance
 
Yashika industries powered by #National #Instruments #NI #LabVIEW
Yashika industries powered by #National #Instruments #NI #LabVIEWYashika industries powered by #National #Instruments #NI #LabVIEW
Yashika industries powered by #National #Instruments #NI #LabVIEW
 
Ppc
PpcPpc
Ppc
 
Instrument engineer resume
Instrument engineer resumeInstrument engineer resume
Instrument engineer resume
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
 
Cfx12 06 review_day1
Cfx12 06 review_day1Cfx12 06 review_day1
Cfx12 06 review_day1
 
Production management
Production managementProduction management
Production management
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revert
 
Nitish Sharma.pptx
Nitish Sharma.pptxNitish Sharma.pptx
Nitish Sharma.pptx
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs
 
User specification requirements (urs) rash
User specification requirements (urs) rashUser specification requirements (urs) rash
User specification requirements (urs) rash
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
 
Abdalla Ghanem CV.. rotating, reliability and mechanical engineering, and pl...
Abdalla Ghanem CV..  rotating, reliability and mechanical engineering, and pl...Abdalla Ghanem CV..  rotating, reliability and mechanical engineering, and pl...
Abdalla Ghanem CV.. rotating, reliability and mechanical engineering, and pl...
 
RESUME_SIVA
RESUME_SIVARESUME_SIVA
RESUME_SIVA
 
Types of maintenance of industrial pharmacy
Types of maintenance of industrial pharmacyTypes of maintenance of industrial pharmacy
Types of maintenance of industrial pharmacy
 
Planning for Substation Maintenance and Reliability
Planning for Substation Maintenance and ReliabilityPlanning for Substation Maintenance and Reliability
Planning for Substation Maintenance and Reliability
 
Facility inspector resume
Facility inspector resumeFacility inspector resume
Facility inspector resume
 
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTREPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

Job Execution in Industrial System Design

  • 1. JOB EXECUTION BY SANTOSH KUMAR MANCHAL S8-ICED, NSSCE JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 1
  • 2. CONTENT ■ PLANNIG HINTS ■ SCHEDULING ■ SPECIFYING INSTRUMENTS ■ VENDOR SELECTION ■ SHIPPING, RECEIVING, AND STORING ■ INSTALLATIONS AND PROJECT CHECKOUT JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 2
  • 3. JOB EXECUTION ■ Job organization depends on ■ Methods covers primary elements of good organization ■ Apply to any job ■ Most methods are applied in the earlier phase ■ A few get along as a continuous process JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 3
  • 4. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 4
  • 5. 1. PLANNING HINTS ■ Review job to know its extent and complexity – Follow specific standard procedures ■ Determine quality of help needed ■ Prepare list of instrument required – Update the list mentioning specification, purchase and installation details ■ Make list of major work categories and assign them to the corresponding group – Examples includes cv, meter run, panel instruments, gauges, switches, actuators, isa diagrams and charts, plot and installation plans etc JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 5
  • 6. ■ Schedule the project timing. Draw a man hour vs. time curve ■ Set priorities and make job assignments. ■ Initial documentation. Categorization. All work documents must be filled. Reminders. ■ Report job progress/monitor job progress. Check the schedule maintenance. ■ Make sure addition and deletion to job are well recorded and informed. ■ Check for available cancellation if product already bought. ■ All documents, drawings, and paper works must be accordingly marked, categorized and filedJOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 6
  • 7. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 7
  • 8. ■ Make sure the item delivered meets the specifications and requirement, and is not defected. ■ The product must meet the delivery commitments. ■ Examples of difficulties – Employees on vacation – Possible delay or Failed delivery due to deliberate or proper reasons – Strike ON, Strike ON. Bharath band, hartaal, random MP CM Actors dead or murder etc – Displacement of product or damaging during handling and shipping – Environmental factors JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 8
  • 9. 2. SCHEDULING ■ In rare cases, delivery of instruments are less shorter. – Depends on side and nature of manufacturing ■ Adjust work according to possible calculated tolerance time. ■ Work backward from installation. – Allow necessary time for shipping fabrication installation etc ■ Engineering thing- be specific about the product JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 9
  • 10. ■ Consider the infrastructure and other phase of project. ■ Wise use of manpower. ■ Thorough planning ■ Adjust normal sequence of work for long delivery items JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 10
  • 11. 3. SPECIFYING INSTRUMENTS ■ Group them into categories. ■ Purchase in group. Different types of device in same category. – Flow, pressure, temp,etc- transmitters ■ Based on size – Control valve sizing ■ Control panel specification ■ Find single vendor. ■ Early purchase JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 11
  • 12. 4. VENDOR SELECTION ■ There are significant reason for selection of certain vendor, specially for panel mounted. ■ Select the bidder who provide the same or instrument with equal quality. ■ If no preference is mentioned, go economic – A poor man,s curry is onion with sauce and spice. ■ Cost must not be the only consideration – Labor, material, accessories, compatible converters, quality JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 12
  • 13. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 13
  • 14. ■ Example – Two sellers selling same transmitter at same cost but one has 4 wire and other has 2 wire system compatibility. Choose 2 wire to reduce installation charge or 4 wire if existing system is compatible. – Two control valve quote same price for same or equal quality model, use the valve manufacturer already in use to reduce inventories. – i-OS and Android based smart phone ■ Delivery requirement and responsibility. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 14
  • 15. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 15
  • 16. 5. SHIPPING, RECEIVING, AND STORING ■ Often receive very little attention causing large monetary loss. ■ Make sure the address is correct – The shipment may reach site than to fabrication center ■ Ship maximum instrument to their point of use. – Unless devices are needed to be checked for their associate wirings ■ Send mounting cases etc. direct to fabricator JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 16
  • 17. JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 17
  • 18. ■ Received by people who can verify equipment's compliance who knows the purchase order specification. ■ Make sure details of receiving inspector is noted. ■ Necessary steps according to protocol must be taken in case of wrong or defected or incomplete delivery. This may further add to labor cost etc. ■ Storage building must be clean and dry, with proper ventilation or isolation depending on the product. ■ Analytical instruments, control panels and other fragile instruments must be specially noted and cared for JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 18
  • 19. 5. INSTALLATION AND CHECKOUT ■ All instruments must be available when needed. ■ Valves, meters and other process connected instruments should be ready when associated lines are installed ■ Underground conduits must be pre installed. ■ Checkout should start well ahead. ■ Schedule checkout depending of which system of project is to be run first. ■ Check for power requirements ■ Early completion of control panel is required JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 19
  • 20. reference ■ W G Andrew, H B Williams, “Applied Instrumentation In The Process Industries”, Second Edition. Vol 2, Gulf Publishing Company Book Division, 1980 ■ GOOGLE JOB DESCRIPTION | INSTRUMENTATION SYSTEM DESIGN | ©SANTOSH KUMAR MANCHAL 20