SlideShare a Scribd company logo
1 of 20
Limitation Act Reform:
   The Canadian Perspective

     Shortening The Time To Sue &
The Impact On The Construction Industry

                     USLAW Spring 2013 Client Conference
                        Presented by Samantha Ip, Partner
                                               April 2013
Limitation Act Reform: The Canadian Perspective

Overview
•Limitation Act Reform in British
Columbia

•Limitation Acts in other Canadian
Provinces

•Impact on Construction Industry
   – The good and the bad




                                                  2
Limitation Act Reform: The Canadian Perspective

Introduction
•Canada’s new limitation regime
   – Sets out the time limits by which a legal claim must be
     commenced
   – Comes into force in B.C. on June 1, 2013
   – Regime already in place in other Provinces
   – Significantly changes law on limitation periods
   – Represents a response to numerous calls for reform by
     multiple stakeholders, including the building design and
     construction sectors (architects, engineers, builders,
     developers, etc.)



                                                                3
Limitation Act Reform: The Canadian Perspective

Current Limitation Regime
•Variable system – 2, 6, 10, 30
   – Prescribes specified periods calculated from the date of the
     event giving rise to the claim – subject to interpretation –
     leading to uncertainty
   – Applicable period depends on the nature of the claim

•Most construction related claims – 6 year limitation period
   – Construction defects, delay claims, fee disputes, contract
     claims




                                                                    4
Limitation Act Reform: The Canadian Perspective

Current Limitation Regime
•Liens – different rules apply (Builders Lien Act)
   – Must commence action 1 year from the date of filing a lien
     (must also file Certificate of Pending Litigation)
   – For action against trustee (contractor or sub) for holdback -
     must commence action not later than 1 year after the head
     contract is completed, abandoned or terminated or, if there is
     no head contractor, 1 year after completion or abandonment
     of the improvement
   – For action to enforce lien on holdback – 6 year limitation
     period applies



                                                                      5
Limitation Act Reform: The Canadian Perspective

Current Limitation Regime
•Ultimate limitation period of 30 years
   – Clock starts running when all elements of a cause of action
     have accrued

•Discoverability rule – common law
   – Running of limitation period is postponed until plaintiff knew
     or ought have known of cause of action and identity of
     defendants
   – Deficiencies claim – running of limitation period often delayed
     until expert report indicating clear “systemic failure”



                                                                       6
Limitation Act Reform: The Canadian Perspective

Current Limitation Regime
•Contribution and indemnity
   – Limitation period does not start to run until the main action is
     determined
   – Defendant may wait and see whether it loses at trial before
     claiming against third parties

•Adding parties – you get an extra year or more
   – In B.C. plaintiffs are entitled to the limitation period plus 1 year
     when adding a party to an action (not commencing the action
     against the party for the first time)
   – A party may be added as a defendant beyond the limitation
     period plus one year in certain circumstances, usually where no
     prejudice results
                                                                            7
Limitation Act Reform: The Canadian Perspective

Problems and Impetus for Change
•Uncertain application
   – Resulted in significant amounts of litigation and issues with
     risk management

•Inconsistent application
   – Unfair balance between plaintiff and defendant’s rights

•Need for uniformity
   – Need to bring BC limitations law in line with other provinces
     with which BC has the greatest economic connections



                                                                     8
Limitation Act Reform: The Canadian Perspective

New Limitation Regime
•Basic 2 year limitation period
   – Applies to all claims, except those in relation to debts owed to
     the government

   Subject to this Act, a court proceeding in respect of a claim must
     not be commenced more than 2 years after the day on which
     the claim is discovered.

   • Construction related claims affected
   – All construction claims relating to defects, delay, and fee and
     contract disputes must be brought within 2 years and not the
     current 6 year period

                                                                        9
Limitation Act Reform: The Canadian Perspective

New Limitation Regime
•Lien claims partially affected
   – Actions to enforce liens on holdbacks will likely have to be
     commenced within two years as opposed to the current six
     year period

•Ultimate limitation period of 15 years
   – Clock starts running at the time of the original act or omission,
     whether damage has occurred or the claim has been discovered
   – Extends to private remedies (e.g. right to arbitration in a
     construction contract)




                                                                         10
Limitation Act Reform: The Canadian Perspective

New Limitation Regime
•Discoverability is central to the new regime
   – Subjective / objective test
   …a claim is discovered by a person on the first day on which the person
     knew or reasonably ought to have known all of the following:

   (a) that injury, loss or damage had occurred;
   (b) that the injury, loss or damage was caused by or contributed to by an
       act or omission;
   (c) that the act or omission was that of the person against whom the claim
       is or may be made;
   (d) that, having regard to the nature of the injury, loss or damage, a court
       proceeding would be an appropriate means to seek to remedy the injury,
       loss or damage. Construction defects, delay claims, fee disputes,
       contract claims
                                                                                  11
Limitation Act Reform: The Canadian Perspective

New Limitation Regime
•Contribution and indemnity
   – Special discovery rules will apply to claims for contribution and
     indemnity, effectively preventing defendants from waiting for
     a lose at initial trial before suing third parties

•Summary of key changes – B.C.
                                      OLD ACT            NEW ACT
  Default Limitation Period           6 Years             2 Years
  Construction Claims
  Ultimate Limitation Period          30 Years           15 Years
  Discoverability Rule               Exception            Default
  Contribution and Indemnity         After Trial          At Trial
                                                                         12
Limitation Act Reform: The Canadian Perspective

Transitional Provision
•When the new regime comes into force in B.C., the applicable
limitation period will be based on discovery…
      1. If the claim is discovered before the new regime comes
         into force the old regime will apply; and

      2. If the claim is discovered after the new regime comes into
         force the new regime will apply, regardless of whether
         the act or omission giving rise to the claim occurred
         before the new regime

   – The ultimate limitation period will start to run on June 1, 2013
     for claims relating to all previous acts or omissions, with a few
     exceptions
                                                                         13
Limitation Act Reform: The Canadian Perspective

Rationale for Shortening the Limitation Periods
•Certainty
   – Potential defendants should not be held accountable for
     ancient obligations

•Evidentiary
   – Claims based on stale evidence should be foreclosed


•Diligence
   – Plaintiffs should have to act diligently and not “sleep on their
     rights”


                                                                        14
Limitation Act Reform: The Canadian Perspective

Canadian Limitation Acts
                                                    Ultimate Limitation
     Provinces         Basic Limitation Period                               Discoverability Rule
                                                          Period
 British Columbia       Single limit – 2 years            15 yrs             All claims – O/S test*
 Alberta                Single limit – 2 years            10 yrs             All claims – O/S test
 Saskatchewan           Single limit – 2 years            15 yrs             All claims – O/S test
 Manitoba**           Variable limit – 2 to 6 yrs         30 yrs                 Common law
 Ontario                Single limit – 2 years            15 yrs             All claims – O/S test
 New Brunswick          Single limit – 2 years            15 yrs             All claims – O/S test
 Nova Scotia**       Variable limit – 2 to 20 yrs   No prescribed limit          Common law
                       Variable Limit – 2 to 10
 Newfoundland                                             30 yrs                 Common law
                                 yrs
 P.E.I.              Variable limit – 1 to 10 yrs   No prescribed limit          Common law
 * O/S test = objective /subjective test, “knew or ought to have known”
 ** Nova Scotia and Manitoba are in the process of bringing in new limitations legislation
    with single 2 year limits, 15 year ultimate limitation periods, and codified discovery rules.
                                                                                                      15
Limitation Act Reform: The Canadian Perspective

Impact on Construction Industry – Risk Management

1.Need for Investigation
   –   If there are signs of a deficiency, then an owner should carry out an
       investigation to determine the extent of the defect as the 2 year
       limitation period will likely have started to run
   –   There is greater emphasis and obligation on “discovering”

1.Record Keeping
   –   There is a lesser need to keep project documents for extended
       periods time




                                                                               16
Limitation Act Reform: The Canadian Perspective

Impact on Construction Industry – Risk Management

3.CCDC 2008 – GC 12.1: Indemnification

   – Requires notice in writing within 6 years from Substantial
     Performance of the Work but GC is subject to applicable
     limitation period, which means that a party who complies with
     this GC may still be prohibited from a claim by the statute

   – The incompatibility of the CCDC with the new Limitation Act
     will create ambiguity and hence litigation  (just kidding)




                                                                     17
Limitation Act Reform: The Canadian Perspective

Impact on Construction Industry – Risk Management
4.CCDC 2008 – GC 12.2: Waiver of Claims
   – Owners’ claim against contractor for deficiencies limited to
     local limitation statute (i.e. 2 years) despite requirement of
     notice within 6 years
       • Note that the B.C. Limitation Act (old and new) is silent on the
         issue of whether a party can contract out of the statutory
         limitation periods

5.Overall shorter risk period
   – All parties in construction who may be sued will benefit in
     terms of risk management from a shorter risk period



                                                                            18
Limitation Act Reform: The Canadian Perspective

Impact on Construction Industry
6.Higher risk for plaintiffs - latent defects
    – A serious systemic defect may not show itself until after 15
      years from construction

6.Insurance
    – Insurers can better assess the risk of underwriting
      professionals on errors and omissions policies based on a
      shorter risk period

8.Project Costs
    – Construction project costs are likely to decrease as insurance
      becomes more readily available and at better pricing given the
      ability of underwriters to better assess the risk
                                                                       19
Please direct inquiries or comments to:

Samantha Ip, Partner, Clark Wilson LLP
email: ssi@cwilson.com; direct: (604) 643-3172

www.cwilson.com




THANK YOU

More Related Content

Viewers also liked

General exceptions Indian Penal Code, (S. 76 to 106)
General  exceptions Indian Penal Code, (S. 76 to 106)General  exceptions Indian Penal Code, (S. 76 to 106)
General exceptions Indian Penal Code, (S. 76 to 106)Dr. Sandeep Kulshrestha
 
Specific Relief Act 1963
Specific Relief Act 1963Specific Relief Act 1963
Specific Relief Act 1963mahesh lone
 
Indian contract act 1872 m
Indian contract act 1872 mIndian contract act 1872 m
Indian contract act 1872 mbanzal
 
Business law contract act
Business law contract actBusiness law contract act
Business law contract actNitin Patil
 
Indian contract act 1872
Indian contract act 1872Indian contract act 1872
Indian contract act 1872Deborah Sharon
 
Constitutions of pakistan
Constitutions of pakistanConstitutions of pakistan
Constitutions of pakistanknowledge1995
 

Viewers also liked (8)

General exceptions Indian Penal Code, (S. 76 to 106)
General  exceptions Indian Penal Code, (S. 76 to 106)General  exceptions Indian Penal Code, (S. 76 to 106)
General exceptions Indian Penal Code, (S. 76 to 106)
 
Specific Relief Act 1963
Specific Relief Act 1963Specific Relief Act 1963
Specific Relief Act 1963
 
Summary of Specific relief act
Summary of Specific relief actSummary of Specific relief act
Summary of Specific relief act
 
Limitation act
Limitation actLimitation act
Limitation act
 
Indian contract act 1872 m
Indian contract act 1872 mIndian contract act 1872 m
Indian contract act 1872 m
 
Business law contract act
Business law contract actBusiness law contract act
Business law contract act
 
Indian contract act 1872
Indian contract act 1872Indian contract act 1872
Indian contract act 1872
 
Constitutions of pakistan
Constitutions of pakistanConstitutions of pakistan
Constitutions of pakistan
 

Similar to Limitation Act Reform - The Canadian Perspective

The Bankruptcy and Debt Advice (Scotland) Bill 2013
The Bankruptcy and Debt Advice (Scotland) Bill 2013The Bankruptcy and Debt Advice (Scotland) Bill 2013
The Bankruptcy and Debt Advice (Scotland) Bill 2013Alan McIntosh
 
Debt Restructuring and Cross Class Cram Down rule.pptx
Debt Restructuring and Cross Class Cram Down rule.pptxDebt Restructuring and Cross Class Cram Down rule.pptx
Debt Restructuring and Cross Class Cram Down rule.pptxLyla Latif
 
Trends in Energy Regulatory Law
Trends in Energy Regulatory LawTrends in Energy Regulatory Law
Trends in Energy Regulatory LawNow Dentons
 
Aw burlington pres_high_court_enforcement_post_tce_act
Aw burlington pres_high_court_enforcement_post_tce_actAw burlington pres_high_court_enforcement_post_tce_act
Aw burlington pres_high_court_enforcement_post_tce_actBurlington Group
 
CBA Natural Resources Presentation
CBA Natural Resources PresentationCBA Natural Resources Presentation
CBA Natural Resources Presentationbennettjones
 
Amendments to the Alberta and British Columbia Insurance Acts
Amendments to the Alberta and British Columbia Insurance ActsAmendments to the Alberta and British Columbia Insurance Acts
Amendments to the Alberta and British Columbia Insurance ActsNow Dentons
 
Public sector planning club - June 2017, Nottingham
Public sector planning club - June 2017, NottinghamPublic sector planning club - June 2017, Nottingham
Public sector planning club - June 2017, NottinghamKatie Wigley
 
The New Ability to Repay and Qualified Mortgage Rule
The New Ability to Repay and Qualified Mortgage RuleThe New Ability to Repay and Qualified Mortgage Rule
The New Ability to Repay and Qualified Mortgage RuleLaura Hite
 
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...Dana Bonsell
 
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State Law
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State LawTILA Disclosures Lost at Sea - Auto-Renewals under TILA and State Law
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State LawJustin Hosie
 
Jamie Watts and Matthew Hawke- Recent Developments in Securityof Payment
Jamie Watts and Matthew Hawke- Recent Developments in Securityof PaymentJamie Watts and Matthew Hawke- Recent Developments in Securityof Payment
Jamie Watts and Matthew Hawke- Recent Developments in Securityof PaymentResolution Institute
 
Planning & development club, June 2018, Nottingham
Planning & development club, June 2018, Nottingham Planning & development club, June 2018, Nottingham
Planning & development club, June 2018, Nottingham Browne Jacobson LLP
 
Tila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesTila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesKaufman & Canoles
 
Key Bankruptcy Considerations Heading into a Recession
Key Bankruptcy Considerations Heading into a RecessionKey Bankruptcy Considerations Heading into a Recession
Key Bankruptcy Considerations Heading into a RecessionQuarles & Brady
 
Canadian Employment Law 101 for U.S. Legal & HR
Canadian Employment Law 101 for U.S. Legal & HRCanadian Employment Law 101 for U.S. Legal & HR
Canadian Employment Law 101 for U.S. Legal & HRNow Dentons
 
Recent Overtime Class Actions and Best Practices to Manage Your Risk
Recent Overtime Class Actions and Best Practices to Manage Your RiskRecent Overtime Class Actions and Best Practices to Manage Your Risk
Recent Overtime Class Actions and Best Practices to Manage Your RiskNow Dentons
 
Understanding the CFPB's New Lending Standards
Understanding the CFPB's New Lending StandardsUnderstanding the CFPB's New Lending Standards
Understanding the CFPB's New Lending StandardsDavid Rocheford
 

Similar to Limitation Act Reform - The Canadian Perspective (20)

9.16 9.18 .ppt
9.16 9.18 .ppt9.16 9.18 .ppt
9.16 9.18 .ppt
 
The Bankruptcy and Debt Advice (Scotland) Bill 2013
The Bankruptcy and Debt Advice (Scotland) Bill 2013The Bankruptcy and Debt Advice (Scotland) Bill 2013
The Bankruptcy and Debt Advice (Scotland) Bill 2013
 
Debt Restructuring and Cross Class Cram Down rule.pptx
Debt Restructuring and Cross Class Cram Down rule.pptxDebt Restructuring and Cross Class Cram Down rule.pptx
Debt Restructuring and Cross Class Cram Down rule.pptx
 
Trends in Energy Regulatory Law
Trends in Energy Regulatory LawTrends in Energy Regulatory Law
Trends in Energy Regulatory Law
 
Aw burlington pres_high_court_enforcement_post_tce_act
Aw burlington pres_high_court_enforcement_post_tce_actAw burlington pres_high_court_enforcement_post_tce_act
Aw burlington pres_high_court_enforcement_post_tce_act
 
CBA Natural Resources Presentation
CBA Natural Resources PresentationCBA Natural Resources Presentation
CBA Natural Resources Presentation
 
Amendments to the Alberta and British Columbia Insurance Acts
Amendments to the Alberta and British Columbia Insurance ActsAmendments to the Alberta and British Columbia Insurance Acts
Amendments to the Alberta and British Columbia Insurance Acts
 
Public sector planning club - June 2017, Nottingham
Public sector planning club - June 2017, NottinghamPublic sector planning club - June 2017, Nottingham
Public sector planning club - June 2017, Nottingham
 
TRID Training Presentation
TRID Training PresentationTRID Training Presentation
TRID Training Presentation
 
The New Ability to Repay and Qualified Mortgage Rule
The New Ability to Repay and Qualified Mortgage RuleThe New Ability to Repay and Qualified Mortgage Rule
The New Ability to Repay and Qualified Mortgage Rule
 
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...
CoesterVMS and James Milano Present The New Ability to Repay and Qualified Mo...
 
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State Law
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State LawTILA Disclosures Lost at Sea - Auto-Renewals under TILA and State Law
TILA Disclosures Lost at Sea - Auto-Renewals under TILA and State Law
 
Regulation Revolution
Regulation RevolutionRegulation Revolution
Regulation Revolution
 
Jamie Watts and Matthew Hawke- Recent Developments in Securityof Payment
Jamie Watts and Matthew Hawke- Recent Developments in Securityof PaymentJamie Watts and Matthew Hawke- Recent Developments in Securityof Payment
Jamie Watts and Matthew Hawke- Recent Developments in Securityof Payment
 
Planning & development club, June 2018, Nottingham
Planning & development club, June 2018, Nottingham Planning & development club, June 2018, Nottingham
Planning & development club, June 2018, Nottingham
 
Tila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesTila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decades
 
Key Bankruptcy Considerations Heading into a Recession
Key Bankruptcy Considerations Heading into a RecessionKey Bankruptcy Considerations Heading into a Recession
Key Bankruptcy Considerations Heading into a Recession
 
Canadian Employment Law 101 for U.S. Legal & HR
Canadian Employment Law 101 for U.S. Legal & HRCanadian Employment Law 101 for U.S. Legal & HR
Canadian Employment Law 101 for U.S. Legal & HR
 
Recent Overtime Class Actions and Best Practices to Manage Your Risk
Recent Overtime Class Actions and Best Practices to Manage Your RiskRecent Overtime Class Actions and Best Practices to Manage Your Risk
Recent Overtime Class Actions and Best Practices to Manage Your Risk
 
Understanding the CFPB's New Lending Standards
Understanding the CFPB's New Lending StandardsUnderstanding the CFPB's New Lending Standards
Understanding the CFPB's New Lending Standards
 

More from Samantha Ip

Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution ExclusionSamantha Ip
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantSamantha Ip
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Samantha Ip
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureSamantha Ip
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Samantha Ip
 
When It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerWhen It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerSamantha Ip
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsSamantha Ip
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Samantha Ip
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesSamantha Ip
 

More from Samantha Ip (11)

Sports & Events
Sports & EventsSports & Events
Sports & Events
 
Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution Exclusion
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the Consultant
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O Exposure
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
 
When It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerWhen It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The Payer
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal Issues
 

Recently uploaded

Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 

Recently uploaded (20)

Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 

Limitation Act Reform - The Canadian Perspective

  • 1. Limitation Act Reform: The Canadian Perspective Shortening The Time To Sue & The Impact On The Construction Industry USLAW Spring 2013 Client Conference Presented by Samantha Ip, Partner April 2013
  • 2. Limitation Act Reform: The Canadian Perspective Overview •Limitation Act Reform in British Columbia •Limitation Acts in other Canadian Provinces •Impact on Construction Industry – The good and the bad 2
  • 3. Limitation Act Reform: The Canadian Perspective Introduction •Canada’s new limitation regime – Sets out the time limits by which a legal claim must be commenced – Comes into force in B.C. on June 1, 2013 – Regime already in place in other Provinces – Significantly changes law on limitation periods – Represents a response to numerous calls for reform by multiple stakeholders, including the building design and construction sectors (architects, engineers, builders, developers, etc.) 3
  • 4. Limitation Act Reform: The Canadian Perspective Current Limitation Regime •Variable system – 2, 6, 10, 30 – Prescribes specified periods calculated from the date of the event giving rise to the claim – subject to interpretation – leading to uncertainty – Applicable period depends on the nature of the claim •Most construction related claims – 6 year limitation period – Construction defects, delay claims, fee disputes, contract claims 4
  • 5. Limitation Act Reform: The Canadian Perspective Current Limitation Regime •Liens – different rules apply (Builders Lien Act) – Must commence action 1 year from the date of filing a lien (must also file Certificate of Pending Litigation) – For action against trustee (contractor or sub) for holdback - must commence action not later than 1 year after the head contract is completed, abandoned or terminated or, if there is no head contractor, 1 year after completion or abandonment of the improvement – For action to enforce lien on holdback – 6 year limitation period applies 5
  • 6. Limitation Act Reform: The Canadian Perspective Current Limitation Regime •Ultimate limitation period of 30 years – Clock starts running when all elements of a cause of action have accrued •Discoverability rule – common law – Running of limitation period is postponed until plaintiff knew or ought have known of cause of action and identity of defendants – Deficiencies claim – running of limitation period often delayed until expert report indicating clear “systemic failure” 6
  • 7. Limitation Act Reform: The Canadian Perspective Current Limitation Regime •Contribution and indemnity – Limitation period does not start to run until the main action is determined – Defendant may wait and see whether it loses at trial before claiming against third parties •Adding parties – you get an extra year or more – In B.C. plaintiffs are entitled to the limitation period plus 1 year when adding a party to an action (not commencing the action against the party for the first time) – A party may be added as a defendant beyond the limitation period plus one year in certain circumstances, usually where no prejudice results 7
  • 8. Limitation Act Reform: The Canadian Perspective Problems and Impetus for Change •Uncertain application – Resulted in significant amounts of litigation and issues with risk management •Inconsistent application – Unfair balance between plaintiff and defendant’s rights •Need for uniformity – Need to bring BC limitations law in line with other provinces with which BC has the greatest economic connections 8
  • 9. Limitation Act Reform: The Canadian Perspective New Limitation Regime •Basic 2 year limitation period – Applies to all claims, except those in relation to debts owed to the government Subject to this Act, a court proceeding in respect of a claim must not be commenced more than 2 years after the day on which the claim is discovered. • Construction related claims affected – All construction claims relating to defects, delay, and fee and contract disputes must be brought within 2 years and not the current 6 year period 9
  • 10. Limitation Act Reform: The Canadian Perspective New Limitation Regime •Lien claims partially affected – Actions to enforce liens on holdbacks will likely have to be commenced within two years as opposed to the current six year period •Ultimate limitation period of 15 years – Clock starts running at the time of the original act or omission, whether damage has occurred or the claim has been discovered – Extends to private remedies (e.g. right to arbitration in a construction contract) 10
  • 11. Limitation Act Reform: The Canadian Perspective New Limitation Regime •Discoverability is central to the new regime – Subjective / objective test …a claim is discovered by a person on the first day on which the person knew or reasonably ought to have known all of the following: (a) that injury, loss or damage had occurred; (b) that the injury, loss or damage was caused by or contributed to by an act or omission; (c) that the act or omission was that of the person against whom the claim is or may be made; (d) that, having regard to the nature of the injury, loss or damage, a court proceeding would be an appropriate means to seek to remedy the injury, loss or damage. Construction defects, delay claims, fee disputes, contract claims 11
  • 12. Limitation Act Reform: The Canadian Perspective New Limitation Regime •Contribution and indemnity – Special discovery rules will apply to claims for contribution and indemnity, effectively preventing defendants from waiting for a lose at initial trial before suing third parties •Summary of key changes – B.C. OLD ACT NEW ACT Default Limitation Period 6 Years 2 Years Construction Claims Ultimate Limitation Period 30 Years 15 Years Discoverability Rule Exception Default Contribution and Indemnity After Trial At Trial 12
  • 13. Limitation Act Reform: The Canadian Perspective Transitional Provision •When the new regime comes into force in B.C., the applicable limitation period will be based on discovery… 1. If the claim is discovered before the new regime comes into force the old regime will apply; and 2. If the claim is discovered after the new regime comes into force the new regime will apply, regardless of whether the act or omission giving rise to the claim occurred before the new regime – The ultimate limitation period will start to run on June 1, 2013 for claims relating to all previous acts or omissions, with a few exceptions 13
  • 14. Limitation Act Reform: The Canadian Perspective Rationale for Shortening the Limitation Periods •Certainty – Potential defendants should not be held accountable for ancient obligations •Evidentiary – Claims based on stale evidence should be foreclosed •Diligence – Plaintiffs should have to act diligently and not “sleep on their rights” 14
  • 15. Limitation Act Reform: The Canadian Perspective Canadian Limitation Acts Ultimate Limitation Provinces Basic Limitation Period Discoverability Rule Period British Columbia Single limit – 2 years 15 yrs All claims – O/S test* Alberta Single limit – 2 years 10 yrs All claims – O/S test Saskatchewan Single limit – 2 years 15 yrs All claims – O/S test Manitoba** Variable limit – 2 to 6 yrs 30 yrs Common law Ontario Single limit – 2 years 15 yrs All claims – O/S test New Brunswick Single limit – 2 years 15 yrs All claims – O/S test Nova Scotia** Variable limit – 2 to 20 yrs No prescribed limit Common law Variable Limit – 2 to 10 Newfoundland 30 yrs Common law yrs P.E.I. Variable limit – 1 to 10 yrs No prescribed limit Common law * O/S test = objective /subjective test, “knew or ought to have known” ** Nova Scotia and Manitoba are in the process of bringing in new limitations legislation with single 2 year limits, 15 year ultimate limitation periods, and codified discovery rules. 15
  • 16. Limitation Act Reform: The Canadian Perspective Impact on Construction Industry – Risk Management 1.Need for Investigation – If there are signs of a deficiency, then an owner should carry out an investigation to determine the extent of the defect as the 2 year limitation period will likely have started to run – There is greater emphasis and obligation on “discovering” 1.Record Keeping – There is a lesser need to keep project documents for extended periods time 16
  • 17. Limitation Act Reform: The Canadian Perspective Impact on Construction Industry – Risk Management 3.CCDC 2008 – GC 12.1: Indemnification – Requires notice in writing within 6 years from Substantial Performance of the Work but GC is subject to applicable limitation period, which means that a party who complies with this GC may still be prohibited from a claim by the statute – The incompatibility of the CCDC with the new Limitation Act will create ambiguity and hence litigation  (just kidding) 17
  • 18. Limitation Act Reform: The Canadian Perspective Impact on Construction Industry – Risk Management 4.CCDC 2008 – GC 12.2: Waiver of Claims – Owners’ claim against contractor for deficiencies limited to local limitation statute (i.e. 2 years) despite requirement of notice within 6 years • Note that the B.C. Limitation Act (old and new) is silent on the issue of whether a party can contract out of the statutory limitation periods 5.Overall shorter risk period – All parties in construction who may be sued will benefit in terms of risk management from a shorter risk period 18
  • 19. Limitation Act Reform: The Canadian Perspective Impact on Construction Industry 6.Higher risk for plaintiffs - latent defects – A serious systemic defect may not show itself until after 15 years from construction 6.Insurance – Insurers can better assess the risk of underwriting professionals on errors and omissions policies based on a shorter risk period 8.Project Costs – Construction project costs are likely to decrease as insurance becomes more readily available and at better pricing given the ability of underwriters to better assess the risk 19
  • 20. Please direct inquiries or comments to: Samantha Ip, Partner, Clark Wilson LLP email: ssi@cwilson.com; direct: (604) 643-3172 www.cwilson.com THANK YOU