The Greedy Method 1
The Greedy Method
The Greedy Method 2
Outline and Reading
The Greedy Method Technique (§5.1)
Fractional Knapsack Problem (§5.1.1)
Task Scheduling (§5.1.2)
Minimum Spanning Trees (§7.3) [future lecture]
The Greedy Method 3
The Greedy Method
Technique
The greedy method is a general algorithm
design paradigm, built on the following
elements:
 configurations: different choices, collections, or
values to find
 objective function: a score assigned to
configurations, which we want to either maximize or
minimize
It works best when applied to problems with the
greedy-choice property:
 a globally-optimal solution can always be found by a
series of local improvements from a starting
configuration.
The Greedy Method 4
Making Change
Problem: A dollar amount to reach and a collection of
coin amounts to use to get there.
Configuration: A dollar amount yet to return to a
customer plus the coins already returned
Objective function: Minimize number of coins returned.
Greedy solution: Always return the largest coin you can
Example 1: Coins are valued $.32, $.08, $.01
 Has the greedy-choice property, since no amount over $.32 can
be made with a minimum number of coins by omitting a $.32
coin (similarly for amounts over $.08, but under $.32).
Example 2: Coins are valued $.30, $.20, $.05, $.01
 Does not have greedy-choice property, since $.40 is best made
with two $.20’s, but the greedy solution will pick three coins
(which ones?)
The Greedy Method 5
The Fractional Knapsack
Problem
Given: A set S of n items, with each item i having
 bi - a positive benefit
 wi - a positive weight
Goal: Choose items with maximum total benefit but with
weight at most W.
If we are allowed to take fractional amounts, then this is
the fractional knapsack problem.
 In this case, we let xi denote the amount we take of item i
 Objective: maximize
 Constraint:

S
i
i
i
i w
x
b )
/
(



S
i
i W
x
The Greedy Method 6
Example
Given: A set S of n items, with each item i having
 bi - a positive benefit
 wi - a positive weight
Goal: Choose items with maximum total benefit but with
weight at most W.
Weight:
Benefit:
1 2 3 4 5
4 ml 8 ml 2 ml 6 ml 1 ml
$12 $32 $40 $30 $50
Items:
Value: 3
($ per ml)
4 20 5 50
10 ml
Solution:
• 1 ml of 5
• 2 ml of 3
• 6 ml of 4
• 1 ml of 2
“knapsack”
The Greedy Method 7
The Fractional Knapsack
Algorithm
Greedy choice: Keep taking
item with highest value
(benefit to weight ratio)
 Since
 Run time: O(n log n). Why?
Correctness: Suppose there
is a better solution
 there is an item i with higher
value than a chosen item j,
but xi<wi, xj>0 and vi<vj
 If we substitute some i with j,
we get a better solution
 How much of i: min{wi-xi, xj}
 Thus, there is no better
solution than the greedy one
Algorithm fractionalKnapsack(S, W)
Input: set S of items w/ benefit bi
and weight wi; max. weight W
Output: amount xi of each item i
to maximize benefit w/ weight
at most W
for each item i in S
xi  0
vi  bi / wi {value}
w  0 {total weight}
while w < W
remove item i w/ highest vi
xi  min{wi , W - w}
w  w + min{wi , W - w}

 


S
i
i
i
i
S
i
i
i
i x
w
b
w
x
b )
/
(
)
/
(
The Greedy Method 8
Task Scheduling
Given: a set T of n tasks, each having:
 A start time, si
 A finish time, fi (where si < fi)
Goal: Perform all the tasks using a minimum number of
“machines.”
1 9
8
7
6
5
4
3
2
Machine 1
Machine 3
Machine 2
The Greedy Method 9
Task Scheduling
Algorithm
Greedy choice: consider tasks
by their start time and use as
few machines as possible with
this order.
 Run time: O(n log n). Why?
Correctness: Suppose there is a
better schedule.
 We can use k-1 machines
 The algorithm uses k
 Let i be first task scheduled
on machine k
 Machine i must conflict with
k-1 other tasks
 But that means there is no
non-conflicting schedule
using k-1 machines
Algorithm taskSchedule(T)
Input: set T of tasks w/ start time si
and finish time fi
Output: non-conflicting schedule
with minimum number of machines
m  0 {no. of machines}
while T is not empty
remove task i w/ smallest si
if there’s a machine j for i then
schedule i on machine j
else
m  m + 1
schedule i on machine m
The Greedy Method 10
Example
Given: a set T of n tasks, each having:
 A start time, si
 A finish time, fi (where si < fi)
 [1,4], [1,3], [2,5], [3,7], [4,7], [6,9], [7,8] (ordered by start)
Goal: Perform all tasks on min. number of machines
1 9
8
7
6
5
4
3
2
Machine 1
Machine 3
Machine 2

More Related Content

Similar to Greedy with Task Scheduling Algorithm.ppt

Greedy algorithms -Making change-Knapsack-Prim's-Kruskal's
Greedy algorithms -Making change-Knapsack-Prim's-Kruskal'sGreedy algorithms -Making change-Knapsack-Prim's-Kruskal's
Greedy algorithms -Making change-Knapsack-Prim's-Kruskal'sJay Patel
 
data structures and algorithms Unit 4
data structures and algorithms Unit 4data structures and algorithms Unit 4
data structures and algorithms Unit 4infanciaj
 
daa-unit-3-greedy method
daa-unit-3-greedy methoddaa-unit-3-greedy method
daa-unit-3-greedy methodhodcsencet
 
Introduction to Optimization revised.ppt
Introduction to Optimization revised.pptIntroduction to Optimization revised.ppt
Introduction to Optimization revised.pptJahnaviGautam
 
5.1 greedyyy 02
5.1 greedyyy 025.1 greedyyy 02
5.1 greedyyy 02Krish_ver2
 
376951072-3-Greedy-Method-new-ppt.ppt
376951072-3-Greedy-Method-new-ppt.ppt376951072-3-Greedy-Method-new-ppt.ppt
376951072-3-Greedy-Method-new-ppt.pptRohitPaul71
 
module3_Greedymethod_2022.pdf
module3_Greedymethod_2022.pdfmodule3_Greedymethod_2022.pdf
module3_Greedymethod_2022.pdfShiwani Gupta
 
Ms nikita greedy agorithm
Ms nikita greedy agorithmMs nikita greedy agorithm
Ms nikita greedy agorithmNikitagupta123
 
lecture 26
lecture 26lecture 26
lecture 26sajinsc
 
Lecture34
Lecture34Lecture34
Lecture34farazch
 

Similar to Greedy with Task Scheduling Algorithm.ppt (20)

Greedy algorithms -Making change-Knapsack-Prim's-Kruskal's
Greedy algorithms -Making change-Knapsack-Prim's-Kruskal'sGreedy algorithms -Making change-Knapsack-Prim's-Kruskal's
Greedy algorithms -Making change-Knapsack-Prim's-Kruskal's
 
12 Greeddy Method
12 Greeddy Method12 Greeddy Method
12 Greeddy Method
 
data structures and algorithms Unit 4
data structures and algorithms Unit 4data structures and algorithms Unit 4
data structures and algorithms Unit 4
 
Unit V.pdf
Unit V.pdfUnit V.pdf
Unit V.pdf
 
Fractional knapsack problem
Fractional knapsack problemFractional knapsack problem
Fractional knapsack problem
 
daa-unit-3-greedy method
daa-unit-3-greedy methoddaa-unit-3-greedy method
daa-unit-3-greedy method
 
Introduction to Optimization revised.ppt
Introduction to Optimization revised.pptIntroduction to Optimization revised.ppt
Introduction to Optimization revised.ppt
 
5.1 greedyyy 02
5.1 greedyyy 025.1 greedyyy 02
5.1 greedyyy 02
 
376951072-3-Greedy-Method-new-ppt.ppt
376951072-3-Greedy-Method-new-ppt.ppt376951072-3-Greedy-Method-new-ppt.ppt
376951072-3-Greedy-Method-new-ppt.ppt
 
module3_Greedymethod_2022.pdf
module3_Greedymethod_2022.pdfmodule3_Greedymethod_2022.pdf
module3_Greedymethod_2022.pdf
 
linear programming
linear programming linear programming
linear programming
 
Ms nikita greedy agorithm
Ms nikita greedy agorithmMs nikita greedy agorithm
Ms nikita greedy agorithm
 
Daa chapter4
Daa chapter4Daa chapter4
Daa chapter4
 
greedy method.pdf
greedy method.pdfgreedy method.pdf
greedy method.pdf
 
lect
lectlect
lect
 
lect
lectlect
lect
 
Lecture34
Lecture34Lecture34
Lecture34
 
lec
leclec
lec
 
lecture 26
lecture 26lecture 26
lecture 26
 
Lecture34
Lecture34Lecture34
Lecture34
 

More from Ruchika Sinha

Greedy Algorithms WITH Activity Selection Problem.ppt
Greedy Algorithms WITH Activity Selection Problem.pptGreedy Algorithms WITH Activity Selection Problem.ppt
Greedy Algorithms WITH Activity Selection Problem.pptRuchika Sinha
 
Greedy Algorithms Huffman Coding.ppt
Greedy Algorithms  Huffman Coding.pptGreedy Algorithms  Huffman Coding.ppt
Greedy Algorithms Huffman Coding.pptRuchika Sinha
 
DynProg_Knapsack.ppt
DynProg_Knapsack.pptDynProg_Knapsack.ppt
DynProg_Knapsack.pptRuchika Sinha
 
Greedy with Task Scheduling Algorithm.ppt
Greedy with Task Scheduling Algorithm.pptGreedy with Task Scheduling Algorithm.ppt
Greedy with Task Scheduling Algorithm.pptRuchika Sinha
 
Installation of motherboard
Installation of motherboardInstallation of motherboard
Installation of motherboardRuchika Sinha
 
Bellman ford algorithm
Bellman ford algorithmBellman ford algorithm
Bellman ford algorithmRuchika Sinha
 
Optimization problems
Optimization problemsOptimization problems
Optimization problemsRuchika Sinha
 
Backtrack search-algorithm
Backtrack search-algorithmBacktrack search-algorithm
Backtrack search-algorithmRuchika Sinha
 
Software for encrypting and decrypting text file powerpointpresentation
Software for encrypting and decrypting text file powerpointpresentationSoftware for encrypting and decrypting text file powerpointpresentation
Software for encrypting and decrypting text file powerpointpresentationRuchika Sinha
 

More from Ruchika Sinha (20)

Greedy Algorithms WITH Activity Selection Problem.ppt
Greedy Algorithms WITH Activity Selection Problem.pptGreedy Algorithms WITH Activity Selection Problem.ppt
Greedy Algorithms WITH Activity Selection Problem.ppt
 
Greedy Algorithms Huffman Coding.ppt
Greedy Algorithms  Huffman Coding.pptGreedy Algorithms  Huffman Coding.ppt
Greedy Algorithms Huffman Coding.ppt
 
DynProg_Knapsack.ppt
DynProg_Knapsack.pptDynProg_Knapsack.ppt
DynProg_Knapsack.ppt
 
Dijkstra.ppt
Dijkstra.pptDijkstra.ppt
Dijkstra.ppt
 
Greedy with Task Scheduling Algorithm.ppt
Greedy with Task Scheduling Algorithm.pptGreedy with Task Scheduling Algorithm.ppt
Greedy with Task Scheduling Algorithm.ppt
 
Clipping
ClippingClipping
Clipping
 
Lec22 intel
Lec22 intelLec22 intel
Lec22 intel
 
Pc assembly
Pc assemblyPc assembly
Pc assembly
 
Casing
CasingCasing
Casing
 
Installation of motherboard
Installation of motherboardInstallation of motherboard
Installation of motherboard
 
Shortest path
Shortest pathShortest path
Shortest path
 
Bellman ford algorithm
Bellman ford algorithmBellman ford algorithm
Bellman ford algorithm
 
Python material
Python materialPython material
Python material
 
Python3
Python3Python3
Python3
 
Optimization problems
Optimization problemsOptimization problems
Optimization problems
 
Regular Grammar
Regular GrammarRegular Grammar
Regular Grammar
 
Software Teting
Software TetingSoftware Teting
Software Teting
 
Backtrack search-algorithm
Backtrack search-algorithmBacktrack search-algorithm
Backtrack search-algorithm
 
XML
XMLXML
XML
 
Software for encrypting and decrypting text file powerpointpresentation
Software for encrypting and decrypting text file powerpointpresentationSoftware for encrypting and decrypting text file powerpointpresentation
Software for encrypting and decrypting text file powerpointpresentation
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Greedy with Task Scheduling Algorithm.ppt

  • 1. The Greedy Method 1 The Greedy Method
  • 2. The Greedy Method 2 Outline and Reading The Greedy Method Technique (§5.1) Fractional Knapsack Problem (§5.1.1) Task Scheduling (§5.1.2) Minimum Spanning Trees (§7.3) [future lecture]
  • 3. The Greedy Method 3 The Greedy Method Technique The greedy method is a general algorithm design paradigm, built on the following elements:  configurations: different choices, collections, or values to find  objective function: a score assigned to configurations, which we want to either maximize or minimize It works best when applied to problems with the greedy-choice property:  a globally-optimal solution can always be found by a series of local improvements from a starting configuration.
  • 4. The Greedy Method 4 Making Change Problem: A dollar amount to reach and a collection of coin amounts to use to get there. Configuration: A dollar amount yet to return to a customer plus the coins already returned Objective function: Minimize number of coins returned. Greedy solution: Always return the largest coin you can Example 1: Coins are valued $.32, $.08, $.01  Has the greedy-choice property, since no amount over $.32 can be made with a minimum number of coins by omitting a $.32 coin (similarly for amounts over $.08, but under $.32). Example 2: Coins are valued $.30, $.20, $.05, $.01  Does not have greedy-choice property, since $.40 is best made with two $.20’s, but the greedy solution will pick three coins (which ones?)
  • 5. The Greedy Method 5 The Fractional Knapsack Problem Given: A set S of n items, with each item i having  bi - a positive benefit  wi - a positive weight Goal: Choose items with maximum total benefit but with weight at most W. If we are allowed to take fractional amounts, then this is the fractional knapsack problem.  In this case, we let xi denote the amount we take of item i  Objective: maximize  Constraint:  S i i i i w x b ) / (    S i i W x
  • 6. The Greedy Method 6 Example Given: A set S of n items, with each item i having  bi - a positive benefit  wi - a positive weight Goal: Choose items with maximum total benefit but with weight at most W. Weight: Benefit: 1 2 3 4 5 4 ml 8 ml 2 ml 6 ml 1 ml $12 $32 $40 $30 $50 Items: Value: 3 ($ per ml) 4 20 5 50 10 ml Solution: • 1 ml of 5 • 2 ml of 3 • 6 ml of 4 • 1 ml of 2 “knapsack”
  • 7. The Greedy Method 7 The Fractional Knapsack Algorithm Greedy choice: Keep taking item with highest value (benefit to weight ratio)  Since  Run time: O(n log n). Why? Correctness: Suppose there is a better solution  there is an item i with higher value than a chosen item j, but xi<wi, xj>0 and vi<vj  If we substitute some i with j, we get a better solution  How much of i: min{wi-xi, xj}  Thus, there is no better solution than the greedy one Algorithm fractionalKnapsack(S, W) Input: set S of items w/ benefit bi and weight wi; max. weight W Output: amount xi of each item i to maximize benefit w/ weight at most W for each item i in S xi  0 vi  bi / wi {value} w  0 {total weight} while w < W remove item i w/ highest vi xi  min{wi , W - w} w  w + min{wi , W - w}      S i i i i S i i i i x w b w x b ) / ( ) / (
  • 8. The Greedy Method 8 Task Scheduling Given: a set T of n tasks, each having:  A start time, si  A finish time, fi (where si < fi) Goal: Perform all the tasks using a minimum number of “machines.” 1 9 8 7 6 5 4 3 2 Machine 1 Machine 3 Machine 2
  • 9. The Greedy Method 9 Task Scheduling Algorithm Greedy choice: consider tasks by their start time and use as few machines as possible with this order.  Run time: O(n log n). Why? Correctness: Suppose there is a better schedule.  We can use k-1 machines  The algorithm uses k  Let i be first task scheduled on machine k  Machine i must conflict with k-1 other tasks  But that means there is no non-conflicting schedule using k-1 machines Algorithm taskSchedule(T) Input: set T of tasks w/ start time si and finish time fi Output: non-conflicting schedule with minimum number of machines m  0 {no. of machines} while T is not empty remove task i w/ smallest si if there’s a machine j for i then schedule i on machine j else m  m + 1 schedule i on machine m
  • 10. The Greedy Method 10 Example Given: a set T of n tasks, each having:  A start time, si  A finish time, fi (where si < fi)  [1,4], [1,3], [2,5], [3,7], [4,7], [6,9], [7,8] (ordered by start) Goal: Perform all tasks on min. number of machines 1 9 8 7 6 5 4 3 2 Machine 1 Machine 3 Machine 2