SlideShare a Scribd company logo
1 of 7
Download to read offline
CASE STUDY
Western Power Distribution
Pole Storage Creosote Pollution &
ISO14001/EA Compliance Challenges
ase study
Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 1
The Western Power Distribution (WPD) Wapley site had an imminent ISO 14001
audit. The facility had no containment provision around the pole storage area and
some contamination was occurring from creosote leaching out of the poles and into
the environment. This would lead to a non‐compliance during the annual ISO14001
audit and failure to adhere to Environment Agency regulations, specifically PPG5.
The Depot and Environmental Managers needed to identify a quick, effective and
permanent solution to be installed and commissioned prior to the site audit.
CONTENTS
Background
Solution
Environmental Compliance
Health and Safety Risk Liability Decreased
Reduced Project & Operational Costs
2
3
5
5
5
Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 2
Background
Western Power Distribution utilise high volumes of creosote impregnated distribution
poles during its day‐to‐day operations. Distribution poles are installed during planned
capital works programs, repair and maintenance, and emergency works. The high
volume of planned and reactive installations means that WPD need to store creosote
impregnated timber distribution poles at strategic geographical locations across
its network.
A positive environmental impact is a paramount concern and focus for any WPD facility, and this directly
influenced a review and upgrade of the environmental protection systems to prevent pollutants entering the
ground at Wapley (Bristol) sub‐station ‐ home to a distribution pole bulk storage site.
The facility had no containment provision around the pole storage area and some contamination was
occurring from creosote leaching out of the poles and into the environment. This would lead to a non‐
compliance during the annual ISO14001 audit and failure to adhere to Environment Agency regulations,
specifically PPG5. The EA has the power to apply financial penalties for non‐compliance and/or pollution of
the environment up to a £50k maximum.
Utility pole storage with no environment protection.
The Western Power Distribution
Wapley site had an imminent ISO
14001 audit, so the Depot and
Environmental Managers needed
to identify a quick, effective and
permanent solution to be installed
and commissioned. Capture Green
was engaged by WPD to undertake
an evaluation, then propose and
recommend a resolution that could
be implemented and delivered in an
extremely cost efficient way.
•
•
•
•
•
•
•
•
•
•
Full site survey and written proposal development completed within 1​4​days.
Construction start date within 1​3 ​days of WPD’s proposal acceptance.
No significant or timely groundwork preparation.
No or only a small amount of concrete construction formations.
A permanent solution to creosote pollution at a significant lower CAPEX to comparable concrete containment.
Easy access for inspection and service.
Low frequency of preventative maintenance interventions.
Full polluted water remediation to meet with the EA’s excepted discharge levels.
A solution which assimilates with the surrounding area.
Complete project delivered and commissioned within 3 weeks.
The stakeholders outlined the following criteria which Capture Green needed to address:
Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 3
Solution
A secondary containment and water remediation system for the safe compliant
storage of creosote impregnated timber utility poles.
Capture Green has worked closely with WPD to design a pole storage system that
ensures it meets its corporate, social and regulatory responsibilities by preventing
creosote contaminants from entering the environment. The system has also been
designed to work to the specific requirements of the site.
Secondary containment and water remediation system for the safe compliant storage of creosote impregnated timber utility poles.
The secondary containment installation comprises of two 135m2 (9x15m) storage bays that join end‐
to‐end. Both bays are hydraulically linked. The containment areas have been formed with a selection of
resilient impermeable and puncture‐resistant membrane materials, on an area of stabilised land capable of
withstanding the loads subjected by a quantity of stored distribution poles.
Situated at the centre of the two bays, buried beneath the final level of pea shingle reinstatement, is a
water retention area, also known as a sustainable (urban) drainage system (SUDS). This is essentially a
void created below the ground that enables large volumes of water to be stored before processing or
natural ground percolation occurs. Capture Green Ltd integrate this feature to alleviate the burden on the
remediation system during heavy rainfall and flash flooding. The retention area slows the drainage process
down, ensuring the remedial chamber has time to process contaminated surface water.
A stillage is formed in each bay to prevent excessive movement of stored poles. The stillage comprises of
driven vertical timber posts that are held in place with structural concrete. Timber laterals are bolted between
the uprights and these form bearers that the stored poles sit on top of. The laterals timbers not only spread
content weight but also keep the load off the ground. This brings a number of benefits in areas like water
flow, logistics, and protecting the liner by lifting the load off the bed of the site. HDPE top hat sleeves are
formed around timber uprights and fused to the lined base to seal the joint between the two components.
Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 4
Each bay has been designed to hold around 80 poles. Together, the two bays enable approximately 160
poles to be safely stored at the site.
During the design phase, it was decided that a third bay may be required at a later date. With this in mind,
Capture Green designed the water remediation system with enough capacity that a third bay could be easily
linked to it at a later date.
The Capture Green Water Remediation Chamber houses a number of water processing devices that remove
compounds typically found in water arising from pole storage sites. This includes hydrocarbons (used for
diluting the creosote down), sediment and debris (often contaminated), phenols and cresols.
There is a common misconception that traditional oil water separation systems can be installed to carry
out the task of removing creosote from water. This is not the case – and inevitably results (carcinogenic)
Polycyclic Aromatic Hydrocarbons PAH’s migrating into the environment. Water solubility increases as
compounds start to breakdown (emulsify), particularly during warmer months. Compounds less dense
than water that would typically be separated in a conventional system can be carried through the discharge
point as they adhere to heavier contaminants. To counter this, Capture Green have design a remediation
system specifically for creosote, utilising a number of proprietary filtration and biological processes to remove
compounds (typically found in creosote) from surface water.
Discreet Compact Water Remediation Chamber
WPD Wapley
Capture Green Pole Storage Layout
Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 5
Health and Safety Risk Liability Decreased
It is important to acknowledge all of the health and safety benefits associated with the installation and
utilisation of the Capture Green Pole Storage System. These are not just limited to the “day‐to‐day”
operational use.
The Pole Storage System at Wapley took 3 weeks to install. Contrastingly, a typical concrete containment
installation at a site the size of Wapley would take around 10 weeks to construct. This demonstrates a 70%
reduction in time on site and a significant reduction in the possibility of time on site associated health and
safety breaches.
Looking at ongoing health and safety benefits, the stillage installed within the containment area aids risk
management efforts by minimising pole movement during loading and unloading. Capture Green have also
designed a clear, safe working area around the stillage, reducing potential contact between plant,
poles and operatives.
Reduced Project & Operational Costs
Since Capture Green have pioneered the creosote containment and removal concept within the industry,
direct cost comparisons are a challenge. Capture Green are aware that some of its clients have built
concrete containment areas costing hundreds of thousands of pounds. Carrying out an analysis of
the particulars of the site against a hypothetical concrete containment design, we are confident that
cost savings will be in the region of 30 to 35% less CAPEX. This is a direct comparison of a concrete
containment area against a turnkey Capture Green containment and remediation solution, not accounting for
the ongoing operational costs of vacuum tankers to remove contaminated water.
Environmental Compliance
The system has been solely designed to mitigate environmental risk. It is an offence to knowingly pollute
the environment by allowing harmful compounds to enter it. The system design and installation ensures that
WPD always remain compliant and importantly meet ISO14001 requirements.
Completed Bulk Pole Storage Facility
6Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges
Further information
+44 (0) 1206 299388Address:
Unit 3
Gattinetts
Hadleigh Road
East Bergholt
Colchester
C07 6QT contact@capturegreen.com
www.capturegreen.com
About the Author
Rees Westley is an accomplished and dynamic
project manager, helping develop pollution prevention
solutions for electrical utilities. He’s used to working
in the most challenging and deadline-driven industry
environments. His ability to instill a “can do” positive
attitude creates a motivated, cohesive team, enabling
the safe delivery of a project, on time and under
budget, with healthy profits.
Capture Green Limited is a company dedicated to providing electrical utilities with
total solutions to prevent dielectric fluid and creosote pollutants entering the
eco‐system, therefore protecting the environment.
Rees Westley
Operations Director at Capture Green Limited

More Related Content

Viewers also liked

Sortida Guàrdia Urbana
Sortida Guàrdia UrbanaSortida Guàrdia Urbana
Sortida Guàrdia UrbanaTrg86912
 
Cloenda apadrinament lector 2016
Cloenda apadrinament lector 2016Cloenda apadrinament lector 2016
Cloenda apadrinament lector 2016Trg86912
 
Sortida bicicletes guàrdia urbana
Sortida bicicletes guàrdia urbanaSortida bicicletes guàrdia urbana
Sortida bicicletes guàrdia urbanaTrg86912
 
Introduction to ITsavvy
Introduction to ITsavvyIntroduction to ITsavvy
Introduction to ITsavvyPatrick Epps
 
WCRF_Four_Basic_Machine_Apps
WCRF_Four_Basic_Machine_AppsWCRF_Four_Basic_Machine_Apps
WCRF_Four_Basic_Machine_AppsJaycen Rigger
 
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!HORTUS Digital
 
презентация директора2
презентация директора2презентация директора2
презентация директора2kosh_62
 

Viewers also liked (16)

Raghavendra Swami resume
Raghavendra Swami resumeRaghavendra Swami resume
Raghavendra Swami resume
 
BOOBIES_Megedit
BOOBIES_MegeditBOOBIES_Megedit
BOOBIES_Megedit
 
Estrategia de aprendizaje-evaluación
Estrategia de aprendizaje-evaluaciónEstrategia de aprendizaje-evaluación
Estrategia de aprendizaje-evaluación
 
Mata
MataMata
Mata
 
Sortida Guàrdia Urbana
Sortida Guàrdia UrbanaSortida Guàrdia Urbana
Sortida Guàrdia Urbana
 
Ficha Curso de Funcionamiento del Mundo de la Telefonía
Ficha Curso de Funcionamiento del Mundo de la TelefoníaFicha Curso de Funcionamiento del Mundo de la Telefonía
Ficha Curso de Funcionamiento del Mundo de la Telefonía
 
Cloenda apadrinament lector 2016
Cloenda apadrinament lector 2016Cloenda apadrinament lector 2016
Cloenda apadrinament lector 2016
 
Sortida bicicletes guàrdia urbana
Sortida bicicletes guàrdia urbanaSortida bicicletes guàrdia urbana
Sortida bicicletes guàrdia urbana
 
Newspaper lithuania
Newspaper lithuaniaNewspaper lithuania
Newspaper lithuania
 
La psicología forense.
La psicología forense.La psicología forense.
La psicología forense.
 
Introduction to ITsavvy
Introduction to ITsavvyIntroduction to ITsavvy
Introduction to ITsavvy
 
HT16 - DA354A - OOP
HT16 - DA354A - OOPHT16 - DA354A - OOP
HT16 - DA354A - OOP
 
WatchOS 2 Opportunity for native apps
WatchOS 2 Opportunity for native appsWatchOS 2 Opportunity for native apps
WatchOS 2 Opportunity for native apps
 
WCRF_Four_Basic_Machine_Apps
WCRF_Four_Basic_Machine_AppsWCRF_Four_Basic_Machine_Apps
WCRF_Four_Basic_Machine_Apps
 
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!
5 iemesli, kāpēc Tev ir nepieciešams ERP Pērtiķa gadā!
 
презентация директора2
презентация директора2презентация директора2
презентация директора2
 

Similar to WPD-Case study-Utility Pole Storage

Us Flood E Brochure
Us Flood E BrochureUs Flood E Brochure
Us Flood E BrochureCherylwitmer
 
Concept Tanks PFAS Storage & Containment
Concept Tanks PFAS Storage & ContainmentConcept Tanks PFAS Storage & Containment
Concept Tanks PFAS Storage & ContainmentAndrew Bilton
 
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...Jeffrey Kocian
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas FieldsNeil Barnard
 
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the risk
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the riskFM Magazine - August & September 2013 - Water Scarcity - Mitigating the risk
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the riskPaul Angus
 
Capture Green emailable brochure.
Capture Green emailable brochure.Capture Green emailable brochure.
Capture Green emailable brochure.Ross Atkin
 
Projects_Brochure_web - email
Projects_Brochure_web - emailProjects_Brochure_web - email
Projects_Brochure_web - emailRees Westley
 
Projects_Brochure_web - email
Projects_Brochure_web - emailProjects_Brochure_web - email
Projects_Brochure_web - emailRees Westley
 
LOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE
 
Desalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeDesalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeRick Nabett
 
Desalination the sustainable alternative
Desalination the sustainable alternativeDesalination the sustainable alternative
Desalination the sustainable alternativeRick Nabett
 
Enhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP'sEnhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP'sContech Engineered Solutions
 
DEGRÉMONT FOOD AND BEVERAGE BROCHURE
 DEGRÉMONT FOOD AND BEVERAGE BROCHURE DEGRÉMONT FOOD AND BEVERAGE BROCHURE
DEGRÉMONT FOOD AND BEVERAGE BROCHURERick Nabett
 
UK AD Biogas 2016: Day One Purple Seminar - 6 July
UK AD Biogas 2016: Day One Purple Seminar - 6 July UK AD Biogas 2016: Day One Purple Seminar - 6 July
UK AD Biogas 2016: Day One Purple Seminar - 6 July UKADBiogas
 
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdf
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdfINNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdf
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdfPRITI CHHATOI
 

Similar to WPD-Case study-Utility Pole Storage (20)

Us Flood E Brochure
Us Flood E BrochureUs Flood E Brochure
Us Flood E Brochure
 
Concept Tanks PFAS Storage & Containment
Concept Tanks PFAS Storage & ContainmentConcept Tanks PFAS Storage & Containment
Concept Tanks PFAS Storage & Containment
 
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...
Work sample done by Jeff Kocian - pH adjustment for hydro demolition jobs bro...
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
 
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the risk
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the riskFM Magazine - August & September 2013 - Water Scarcity - Mitigating the risk
FM Magazine - August & September 2013 - Water Scarcity - Mitigating the risk
 
Capture Green emailable brochure.
Capture Green emailable brochure.Capture Green emailable brochure.
Capture Green emailable brochure.
 
Projects_Brochure_web - email
Projects_Brochure_web - emailProjects_Brochure_web - email
Projects_Brochure_web - email
 
Projects_Brochure_web - email
Projects_Brochure_web - emailProjects_Brochure_web - email
Projects_Brochure_web - email
 
Compactsolutionforcso
CompactsolutionforcsoCompactsolutionforcso
Compactsolutionforcso
 
LOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE Waste Conditioning
LOESCHE Waste Conditioning
 
Drenes Atlantis Guia Productos 2016
Drenes Atlantis Guia Productos 2016Drenes Atlantis Guia Productos 2016
Drenes Atlantis Guia Productos 2016
 
Desalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeDesalination, The Sustainable Alternative
Desalination, The Sustainable Alternative
 
Desalination the sustainable alternative
Desalination the sustainable alternativeDesalination the sustainable alternative
Desalination the sustainable alternative
 
Retawater pools_Client_Deck.pdf
Retawater pools_Client_Deck.pdfRetawater pools_Client_Deck.pdf
Retawater pools_Client_Deck.pdf
 
Enhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP'sEnhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP's
 
DEGRÉMONT FOOD AND BEVERAGE BROCHURE
 DEGRÉMONT FOOD AND BEVERAGE BROCHURE DEGRÉMONT FOOD AND BEVERAGE BROCHURE
DEGRÉMONT FOOD AND BEVERAGE BROCHURE
 
UK AD Biogas 2016: Day One Purple Seminar - 6 July
UK AD Biogas 2016: Day One Purple Seminar - 6 July UK AD Biogas 2016: Day One Purple Seminar - 6 July
UK AD Biogas 2016: Day One Purple Seminar - 6 July
 
ORP FY13 Budget Workshop
ORP FY13 Budget WorkshopORP FY13 Budget Workshop
ORP FY13 Budget Workshop
 
WP_Extreme_2016 (2)
WP_Extreme_2016 (2)WP_Extreme_2016 (2)
WP_Extreme_2016 (2)
 
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdf
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdfINNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdf
INNOVATIVE APPROACH OF SEWAGE DISPOSAL SYSTEM.pdf
 

WPD-Case study-Utility Pole Storage

  • 1. CASE STUDY Western Power Distribution Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges ase study
  • 2. Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 1 The Western Power Distribution (WPD) Wapley site had an imminent ISO 14001 audit. The facility had no containment provision around the pole storage area and some contamination was occurring from creosote leaching out of the poles and into the environment. This would lead to a non‐compliance during the annual ISO14001 audit and failure to adhere to Environment Agency regulations, specifically PPG5. The Depot and Environmental Managers needed to identify a quick, effective and permanent solution to be installed and commissioned prior to the site audit. CONTENTS Background Solution Environmental Compliance Health and Safety Risk Liability Decreased Reduced Project & Operational Costs 2 3 5 5 5
  • 3. Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 2 Background Western Power Distribution utilise high volumes of creosote impregnated distribution poles during its day‐to‐day operations. Distribution poles are installed during planned capital works programs, repair and maintenance, and emergency works. The high volume of planned and reactive installations means that WPD need to store creosote impregnated timber distribution poles at strategic geographical locations across its network. A positive environmental impact is a paramount concern and focus for any WPD facility, and this directly influenced a review and upgrade of the environmental protection systems to prevent pollutants entering the ground at Wapley (Bristol) sub‐station ‐ home to a distribution pole bulk storage site. The facility had no containment provision around the pole storage area and some contamination was occurring from creosote leaching out of the poles and into the environment. This would lead to a non‐ compliance during the annual ISO14001 audit and failure to adhere to Environment Agency regulations, specifically PPG5. The EA has the power to apply financial penalties for non‐compliance and/or pollution of the environment up to a £50k maximum. Utility pole storage with no environment protection. The Western Power Distribution Wapley site had an imminent ISO 14001 audit, so the Depot and Environmental Managers needed to identify a quick, effective and permanent solution to be installed and commissioned. Capture Green was engaged by WPD to undertake an evaluation, then propose and recommend a resolution that could be implemented and delivered in an extremely cost efficient way. • • • • • • • • • • Full site survey and written proposal development completed within 1​4​days. Construction start date within 1​3 ​days of WPD’s proposal acceptance. No significant or timely groundwork preparation. No or only a small amount of concrete construction formations. A permanent solution to creosote pollution at a significant lower CAPEX to comparable concrete containment. Easy access for inspection and service. Low frequency of preventative maintenance interventions. Full polluted water remediation to meet with the EA’s excepted discharge levels. A solution which assimilates with the surrounding area. Complete project delivered and commissioned within 3 weeks. The stakeholders outlined the following criteria which Capture Green needed to address:
  • 4. Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 3 Solution A secondary containment and water remediation system for the safe compliant storage of creosote impregnated timber utility poles. Capture Green has worked closely with WPD to design a pole storage system that ensures it meets its corporate, social and regulatory responsibilities by preventing creosote contaminants from entering the environment. The system has also been designed to work to the specific requirements of the site. Secondary containment and water remediation system for the safe compliant storage of creosote impregnated timber utility poles. The secondary containment installation comprises of two 135m2 (9x15m) storage bays that join end‐ to‐end. Both bays are hydraulically linked. The containment areas have been formed with a selection of resilient impermeable and puncture‐resistant membrane materials, on an area of stabilised land capable of withstanding the loads subjected by a quantity of stored distribution poles. Situated at the centre of the two bays, buried beneath the final level of pea shingle reinstatement, is a water retention area, also known as a sustainable (urban) drainage system (SUDS). This is essentially a void created below the ground that enables large volumes of water to be stored before processing or natural ground percolation occurs. Capture Green Ltd integrate this feature to alleviate the burden on the remediation system during heavy rainfall and flash flooding. The retention area slows the drainage process down, ensuring the remedial chamber has time to process contaminated surface water. A stillage is formed in each bay to prevent excessive movement of stored poles. The stillage comprises of driven vertical timber posts that are held in place with structural concrete. Timber laterals are bolted between the uprights and these form bearers that the stored poles sit on top of. The laterals timbers not only spread content weight but also keep the load off the ground. This brings a number of benefits in areas like water flow, logistics, and protecting the liner by lifting the load off the bed of the site. HDPE top hat sleeves are formed around timber uprights and fused to the lined base to seal the joint between the two components.
  • 5. Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 4 Each bay has been designed to hold around 80 poles. Together, the two bays enable approximately 160 poles to be safely stored at the site. During the design phase, it was decided that a third bay may be required at a later date. With this in mind, Capture Green designed the water remediation system with enough capacity that a third bay could be easily linked to it at a later date. The Capture Green Water Remediation Chamber houses a number of water processing devices that remove compounds typically found in water arising from pole storage sites. This includes hydrocarbons (used for diluting the creosote down), sediment and debris (often contaminated), phenols and cresols. There is a common misconception that traditional oil water separation systems can be installed to carry out the task of removing creosote from water. This is not the case – and inevitably results (carcinogenic) Polycyclic Aromatic Hydrocarbons PAH’s migrating into the environment. Water solubility increases as compounds start to breakdown (emulsify), particularly during warmer months. Compounds less dense than water that would typically be separated in a conventional system can be carried through the discharge point as they adhere to heavier contaminants. To counter this, Capture Green have design a remediation system specifically for creosote, utilising a number of proprietary filtration and biological processes to remove compounds (typically found in creosote) from surface water. Discreet Compact Water Remediation Chamber WPD Wapley Capture Green Pole Storage Layout
  • 6. Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges 5 Health and Safety Risk Liability Decreased It is important to acknowledge all of the health and safety benefits associated with the installation and utilisation of the Capture Green Pole Storage System. These are not just limited to the “day‐to‐day” operational use. The Pole Storage System at Wapley took 3 weeks to install. Contrastingly, a typical concrete containment installation at a site the size of Wapley would take around 10 weeks to construct. This demonstrates a 70% reduction in time on site and a significant reduction in the possibility of time on site associated health and safety breaches. Looking at ongoing health and safety benefits, the stillage installed within the containment area aids risk management efforts by minimising pole movement during loading and unloading. Capture Green have also designed a clear, safe working area around the stillage, reducing potential contact between plant, poles and operatives. Reduced Project & Operational Costs Since Capture Green have pioneered the creosote containment and removal concept within the industry, direct cost comparisons are a challenge. Capture Green are aware that some of its clients have built concrete containment areas costing hundreds of thousands of pounds. Carrying out an analysis of the particulars of the site against a hypothetical concrete containment design, we are confident that cost savings will be in the region of 30 to 35% less CAPEX. This is a direct comparison of a concrete containment area against a turnkey Capture Green containment and remediation solution, not accounting for the ongoing operational costs of vacuum tankers to remove contaminated water. Environmental Compliance The system has been solely designed to mitigate environmental risk. It is an offence to knowingly pollute the environment by allowing harmful compounds to enter it. The system design and installation ensures that WPD always remain compliant and importantly meet ISO14001 requirements. Completed Bulk Pole Storage Facility
  • 7. 6Case Study: Western Power Distribution / Pole Storage Creosote Pollution & ISO14001/EA Compliance Challenges Further information +44 (0) 1206 299388Address: Unit 3 Gattinetts Hadleigh Road East Bergholt Colchester C07 6QT contact@capturegreen.com www.capturegreen.com About the Author Rees Westley is an accomplished and dynamic project manager, helping develop pollution prevention solutions for electrical utilities. He’s used to working in the most challenging and deadline-driven industry environments. His ability to instill a “can do” positive attitude creates a motivated, cohesive team, enabling the safe delivery of a project, on time and under budget, with healthy profits. Capture Green Limited is a company dedicated to providing electrical utilities with total solutions to prevent dielectric fluid and creosote pollutants entering the eco‐system, therefore protecting the environment. Rees Westley Operations Director at Capture Green Limited