SlideShare a Scribd company logo
1 of 2
Download to read offline
© ALSTOM 2014. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it
is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is
subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Alstom contributes to the protection of the environment. This leaflet is printed on environmentally-friendly paper.
TPWR/CASE/HI/EN/2.2014/CHE/2002
Alstom has won an EPC (Engineering, Procurement and Construction) contract with
Dalia Power Energies Ltd to build the 834 MW Haruvit power plant in Israel. The
project represents Alstom’s first entry into the Israeli gas market under a full EPC
contract and will be the country’s largest privately-owned power station.
The power plant is located near Kfar Menachem, 40 km south-east of Tel Aviv. The
834 MW provided to the national grid by the Haruvit Power Plant corresponds with
about 7% of the country’s current installed power generation capacity. The location of
the Haruvit Power Plant at the intersection of the national electricity grids will enable
feeding electricity to both the grid’s northern and southern sections, increasing the
reliability of electricity supply to end users.
The EPC contract covers the supply and construction of two 417 MW, dual-fuel,
combined-cycle units with Alstom’s KA26 single-shaft configuration as well as
the associated civil works, balance of plant, distributed control system (DCS) and
switchyard equipment to connect the power station to the grid.
In addition Alstom was also awarded a 20-years O&M contract for full operation and
maintenance of the two gas-fired combined-cycle units. This contract will ensure that
the plant generates electricity at high efficiency and reliability levels, thus significantly
improving the market fuel utilisation and security of electricity supply.
The Israeli government is encouraging investments by IPPs (Independent Power
Producers), and the recent discoveries of major gas reserves near the Israeli coasts are
likely to encourage investment in gas-fired combined-cycle power stations.
Customer:...................................... Dalia Power Energies Ltd.
Scope of supply:............................ EPC turnkey contract for 2 x KA26-1 SS units
+ 20-years OM contract
Electrical output:........................... 834 MW
Fuel:............................................... Natural gas / Fuel oil as backup
Cooling System:............................. Air-cooled condenser (ACC)
Application:.................................... Power generation
Alstom to construct the
biggest power project ever
executed in Israel by an
IPP
CASE STUDY: GAS PRODUCT SOLUTIONS
Haruvit – Israel
KA26 combined-cycle power plant
ADVANTAGES
•	Prominent operational
and fuel flexibility
•	High reliability
•	Superior part-load
performance
•	Low NOx emissions over
a wide load range
With its environmental and
economic advantages, this
plant is another example of
Alstom’s capability to deliver
clean integrated power
solutions
© ALSTOM 2014. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it
is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is
subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Alstom contributes to the protection of the environment. This leaflet is printed on environmentally-friendly paper.
TPWR/CASE/HI/EN/2.2014/CHE/2002
CASE STUDY: GAS PRODUCT SOLUTIONS
KA26 CCPP HARUVIT - ISRAEL
PROJECT FEATURES
The Haruvit Project benefits from the superior integration resulting from Alstom’s
project management skills, EPC capabilities and the state-of-the-art key components
manufactured by Alstom:
•	2 highly flexible and clean-power producing GT26 gas turbines with unique sequential
combustion
•	2 horizontal triple-pressure heat recovery steam generators for high plant efficiency
•	2 STF15C steam turbines with axial exhaust for flexible, highly efficient operation
•	2 TOPGAS turbogenerators, hydrogen-cooled, for high efficiency, availability, and
simplicity
•	Distributed control system (DCS) Alspa Series 6
•	Generator step-up transformers
•	400kV switchyard equipment to connect the power station to the grid.
CLEAN POWER, CLEAR SOLUTIONSTM
Alstom helps you meet the challenges of energy sustainability. Our power generation
offering is based on a deep understanding of power markets and our customers’ needs. It is
organised around three levers to maximise the return on assets over their entire lifecycle.
•	Reducing the cost of electricity
•	Lowering the environmental footprint
•	Increasing flexibility  reliability.
An environmentally
friendly plant with
high efficiency
With 58% gross efficiency, the
most efficient power plant
in the country, providing
substantial fuel costs savings
350 g CO2/kWh close to half
of the Israeli Average
REDUCING
COST OF ELECTRICITY
LOWERING
ENVIRONMENTAL FOOTPRINT
For more information
please contact Alstom Power:
ALSTOM (Switzerland) Ltd.
Brown Boveri Strasse 7
5401 Baden
Switzerland
Visit us online: www.alstom.com

More Related Content

What's hot

Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Finnish_Energy_Hub
 
Tidal energy takes scotland inner sound
Tidal energy takes scotland inner soundTidal energy takes scotland inner sound
Tidal energy takes scotland inner soundmuhammed alaadin
 
Online variable topology type photovoltaic grid-connected inverter
Online variable topology type photovoltaic grid-connected inverterOnline variable topology type photovoltaic grid-connected inverter
Online variable topology type photovoltaic grid-connected inverterLeMeniz Infotech
 
Engage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution WebinarEngage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution WebinarKTN
 
Low Load Diesel All Energy 2017
Low Load Diesel All Energy 2017Low Load Diesel All Energy 2017
Low Load Diesel All Energy 2017james hamilton
 
Geothermal To the World
Geothermal To the WorldGeothermal To the World
Geothermal To the WorldCyril Stahl
 
European wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcEuropean wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcSustainableEnergyAut
 
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-english
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-englishWeg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-english
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-englishDaniel García
 
Km186 steam power plant with single dynamo
Km186 steam power plant with single dynamoKm186 steam power plant with single dynamo
Km186 steam power plant with single dynamo1000kv technologies
 
Goldwind - Wind Solar Colocation
Goldwind - Wind  Solar ColocationGoldwind - Wind  Solar Colocation
Goldwind - Wind Solar Colocationgoldwindaus
 
Combining TSI Inverters and Fuel Cells
Combining TSI Inverters and Fuel CellsCombining TSI Inverters and Fuel Cells
Combining TSI Inverters and Fuel CellsCE+T Power
 
Siemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark HamiltonSiemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark HamiltonThane Heins
 

What's hot (20)

Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)
 
Tidal energy takes scotland inner sound
Tidal energy takes scotland inner soundTidal energy takes scotland inner sound
Tidal energy takes scotland inner sound
 
Solar plant
Solar plantSolar plant
Solar plant
 
Online variable topology type photovoltaic grid-connected inverter
Online variable topology type photovoltaic grid-connected inverterOnline variable topology type photovoltaic grid-connected inverter
Online variable topology type photovoltaic grid-connected inverter
 
Engage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution WebinarEngage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution Webinar
 
The way to off grid power
The way to off grid powerThe way to off grid power
The way to off grid power
 
Low Load Diesel All Energy 2017
Low Load Diesel All Energy 2017Low Load Diesel All Energy 2017
Low Load Diesel All Energy 2017
 
Geothermal To the World
Geothermal To the WorldGeothermal To the World
Geothermal To the World
 
AGX Slides
AGX SlidesAGX Slides
AGX Slides
 
European wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcEuropean wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrc
 
Triac1
Triac1Triac1
Triac1
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
 
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-english
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-englishWeg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-english
Weg weg-releases-high-efficiency-wmagnet-drive-system™-technical-article-english
 
Tayf1
Tayf1Tayf1
Tayf1
 
Km186 steam power plant with single dynamo
Km186 steam power plant with single dynamoKm186 steam power plant with single dynamo
Km186 steam power plant with single dynamo
 
Wärtsilä Zero Emmisions Ferry Concept
Wärtsilä Zero Emmisions Ferry ConceptWärtsilä Zero Emmisions Ferry Concept
Wärtsilä Zero Emmisions Ferry Concept
 
Lexe1742 01
Lexe1742 01Lexe1742 01
Lexe1742 01
 
Goldwind - Wind Solar Colocation
Goldwind - Wind  Solar ColocationGoldwind - Wind  Solar Colocation
Goldwind - Wind Solar Colocation
 
Combining TSI Inverters and Fuel Cells
Combining TSI Inverters and Fuel CellsCombining TSI Inverters and Fuel Cells
Combining TSI Inverters and Fuel Cells
 
Siemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark HamiltonSiemens 2 Report Signed Data Sheets Mark Hamilton
Siemens 2 Report Signed Data Sheets Mark Hamilton
 

Similar to Tzafit

tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-planttuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-plantDaniel ANG
 
EPR™, the 1600+ MWe Reactor - 2009 Issue
EPR™, the 1600+ MWe Reactor - 2009 IssueEPR™, the 1600+ MWe Reactor - 2009 Issue
EPR™, the 1600+ MWe Reactor - 2009 IssueAREVA
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice ReportPaul Soko
 
Comprehensive Power Introduction July 2013
Comprehensive Power Introduction July 2013Comprehensive Power Introduction July 2013
Comprehensive Power Introduction July 2013Jeff Sable
 
4 cseg presentation
4 cseg presentation4 cseg presentation
4 cseg presentationBilal Janjua
 
ADANI COMPLETE PROJECT 1
ADANI COMPLETE PROJECT 1ADANI COMPLETE PROJECT 1
ADANI COMPLETE PROJECT 1dashdeepak33
 
Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Jeff Sable
 
Comprehensive Power Introduction Aug2013
Comprehensive Power Introduction  Aug2013Comprehensive Power Introduction  Aug2013
Comprehensive Power Introduction Aug2013Jeff Sable
 
Latest presentation wind 2010 eng luk
Latest presentation wind 2010 eng lukLatest presentation wind 2010 eng luk
Latest presentation wind 2010 eng lukEuropages2
 
Comprehensive Power Introduction Oct2013
Comprehensive Power Introduction Oct2013Comprehensive Power Introduction Oct2013
Comprehensive Power Introduction Oct2013Jeff Sable
 
FPCL power plant report (MECHANICAL)
FPCL power plant report (MECHANICAL)FPCL power plant report (MECHANICAL)
FPCL power plant report (MECHANICAL)Syed Asif
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebAmber Thomas
 
Yokogawa's Vigilant Plant | Success Stories | Power industry
Yokogawa's Vigilant Plant | Success Stories | Power industryYokogawa's Vigilant Plant | Success Stories | Power industry
Yokogawa's Vigilant Plant | Success Stories | Power industryYokogawa
 

Similar to Tzafit (20)

Samra
SamraSamra
Samra
 
tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-planttuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
 
Az Zour EPP08
Az Zour EPP08Az Zour EPP08
Az Zour EPP08
 
HYpact brochure EN
HYpact brochure ENHYpact brochure EN
HYpact brochure EN
 
EPR™, the 1600+ MWe Reactor - 2009 Issue
EPR™, the 1600+ MWe Reactor - 2009 IssueEPR™, the 1600+ MWe Reactor - 2009 Issue
EPR™, the 1600+ MWe Reactor - 2009 Issue
 
Heat exchangers
Heat exchangersHeat exchangers
Heat exchangers
 
GenCell Award Write Up
GenCell Award Write UpGenCell Award Write Up
GenCell Award Write Up
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice Report
 
Comprehensive Power Introduction July 2013
Comprehensive Power Introduction July 2013Comprehensive Power Introduction July 2013
Comprehensive Power Introduction July 2013
 
4 cseg presentation
4 cseg presentation4 cseg presentation
4 cseg presentation
 
ADANI COMPLETE PROJECT 1
ADANI COMPLETE PROJECT 1ADANI COMPLETE PROJECT 1
ADANI COMPLETE PROJECT 1
 
Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013
 
Comprehensive Power Introduction Aug2013
Comprehensive Power Introduction  Aug2013Comprehensive Power Introduction  Aug2013
Comprehensive Power Introduction Aug2013
 
Latest presentation wind 2010 eng luk
Latest presentation wind 2010 eng lukLatest presentation wind 2010 eng luk
Latest presentation wind 2010 eng luk
 
Comprehensive Power Introduction Oct2013
Comprehensive Power Introduction Oct2013Comprehensive Power Introduction Oct2013
Comprehensive Power Introduction Oct2013
 
FPCL power plant report (MECHANICAL)
FPCL power plant report (MECHANICAL)FPCL power plant report (MECHANICAL)
FPCL power plant report (MECHANICAL)
 
GTX CCPP22 project
GTX CCPP22 projectGTX CCPP22 project
GTX CCPP22 project
 
Micks CV_10_07_16
Micks CV_10_07_16Micks CV_10_07_16
Micks CV_10_07_16
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - Web
 
Yokogawa's Vigilant Plant | Success Stories | Power industry
Yokogawa's Vigilant Plant | Success Stories | Power industryYokogawa's Vigilant Plant | Success Stories | Power industry
Yokogawa's Vigilant Plant | Success Stories | Power industry
 

Tzafit

  • 1. © ALSTOM 2014. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Alstom contributes to the protection of the environment. This leaflet is printed on environmentally-friendly paper. TPWR/CASE/HI/EN/2.2014/CHE/2002 Alstom has won an EPC (Engineering, Procurement and Construction) contract with Dalia Power Energies Ltd to build the 834 MW Haruvit power plant in Israel. The project represents Alstom’s first entry into the Israeli gas market under a full EPC contract and will be the country’s largest privately-owned power station. The power plant is located near Kfar Menachem, 40 km south-east of Tel Aviv. The 834 MW provided to the national grid by the Haruvit Power Plant corresponds with about 7% of the country’s current installed power generation capacity. The location of the Haruvit Power Plant at the intersection of the national electricity grids will enable feeding electricity to both the grid’s northern and southern sections, increasing the reliability of electricity supply to end users. The EPC contract covers the supply and construction of two 417 MW, dual-fuel, combined-cycle units with Alstom’s KA26 single-shaft configuration as well as the associated civil works, balance of plant, distributed control system (DCS) and switchyard equipment to connect the power station to the grid. In addition Alstom was also awarded a 20-years O&M contract for full operation and maintenance of the two gas-fired combined-cycle units. This contract will ensure that the plant generates electricity at high efficiency and reliability levels, thus significantly improving the market fuel utilisation and security of electricity supply. The Israeli government is encouraging investments by IPPs (Independent Power Producers), and the recent discoveries of major gas reserves near the Israeli coasts are likely to encourage investment in gas-fired combined-cycle power stations. Customer:...................................... Dalia Power Energies Ltd. Scope of supply:............................ EPC turnkey contract for 2 x KA26-1 SS units + 20-years OM contract Electrical output:........................... 834 MW Fuel:............................................... Natural gas / Fuel oil as backup Cooling System:............................. Air-cooled condenser (ACC) Application:.................................... Power generation Alstom to construct the biggest power project ever executed in Israel by an IPP CASE STUDY: GAS PRODUCT SOLUTIONS Haruvit – Israel KA26 combined-cycle power plant ADVANTAGES • Prominent operational and fuel flexibility • High reliability • Superior part-load performance • Low NOx emissions over a wide load range With its environmental and economic advantages, this plant is another example of Alstom’s capability to deliver clean integrated power solutions
  • 2. © ALSTOM 2014. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Alstom contributes to the protection of the environment. This leaflet is printed on environmentally-friendly paper. TPWR/CASE/HI/EN/2.2014/CHE/2002 CASE STUDY: GAS PRODUCT SOLUTIONS KA26 CCPP HARUVIT - ISRAEL PROJECT FEATURES The Haruvit Project benefits from the superior integration resulting from Alstom’s project management skills, EPC capabilities and the state-of-the-art key components manufactured by Alstom: • 2 highly flexible and clean-power producing GT26 gas turbines with unique sequential combustion • 2 horizontal triple-pressure heat recovery steam generators for high plant efficiency • 2 STF15C steam turbines with axial exhaust for flexible, highly efficient operation • 2 TOPGAS turbogenerators, hydrogen-cooled, for high efficiency, availability, and simplicity • Distributed control system (DCS) Alspa Series 6 • Generator step-up transformers • 400kV switchyard equipment to connect the power station to the grid. CLEAN POWER, CLEAR SOLUTIONSTM Alstom helps you meet the challenges of energy sustainability. Our power generation offering is based on a deep understanding of power markets and our customers’ needs. It is organised around three levers to maximise the return on assets over their entire lifecycle. • Reducing the cost of electricity • Lowering the environmental footprint • Increasing flexibility reliability. An environmentally friendly plant with high efficiency With 58% gross efficiency, the most efficient power plant in the country, providing substantial fuel costs savings 350 g CO2/kWh close to half of the Israeli Average REDUCING COST OF ELECTRICITY LOWERING ENVIRONMENTAL FOOTPRINT For more information please contact Alstom Power: ALSTOM (Switzerland) Ltd. Brown Boveri Strasse 7 5401 Baden Switzerland Visit us online: www.alstom.com