The document outlines the key phases and elements of a project including initiation, planning, execution, monitoring and control, and closing. It discusses defining goals and evaluating alternatives in the initiation phase. Planning involves gathering information, evaluating resources, and team building. Execution consists of operational control and making corrections. Monitoring and control analyzes results. Closing includes reporting, celebrating, and expressing gratitude.
12. Dear Project manager,
I want You to build Ultimate Weapon for me!
The maximum budget is 14,5 millions
credits.
We have 10 years till Rebels will attack us.
Do Your best!
12
13. 13
You can choose how big Death Star to build, It could consist from
190 000, 210 000 or 240 000 sections.
To complete one section we need one day of work 20 droids or 15
stormtroopers.
Droids work 7 days a week
Stormtroopers work 5 days a week.
Energy for droids – 0,5 credit a day
Payment for stormtroopers 22 credits per month.
You have available 987 droids and 477 stormtroopers.
You can deliver steel for sections from 2 planets Tatooine and
Coruscant.
From Tatooine for one section steel costs – 50 credtis
From Coruscant - 30 credits
The distance between planets are 220 light-years.
The transportation cost – 0.07 credits per section/per light-year
At Tatooine avalibility of steel is – 300 000 sections
At Coruscant – 100 000 sections
14. 14
Make a presentation which includes
- TIME,
- COSTS,
- size and location of yours Death Star.
35. Project flow
Recall the four types of task dependencies
1. Finish-to-start (FS): The finish date of the predecessor task determines the start date of the
successor task.
2. 2. Start-to-start (SS): The start date of the predecessor task determines the start date of the
successor task.
3. 3. Finish-to-finish (FF): The finish date of the predecessor task determines the finish date of
the successor task.
4. 4. Start-to-finish (SF): The start date of the predecessor task determines the finish date of
the successor task.
35
44. Constraints for the tasks
As Soon As Possible ASAP
As Late As Possible ALAP
Start No Earlier Than SNET
Finish No Earlier Than FNET
Must Start On MSO
Must Finish On MFO
Start No Later Than SNLT
Finish No Later Than FNLT