SlideShare a Scribd company logo
1 of 3
Download to read offline
13
THOUGHT LEADERSHIPSgurrEnergy
Developers of offshore wind farms face a number of risks, as do the banks and equity funds
that invest in them. Clean Energy Pipeline interviewed Raya Peterson, Principal Engineer at
SgurrEnergy, to understand how these risks are changing and what strategies can be adopted
to mitigate them. We also discuss emerging financing considerations as project finance
structures become more attractive.
Emerging risks in offshore
wind
Q&A with Raya Peterson, Principal engineer
at SgurrEnergy
Raya Peterson
Principal engineer
SgurrEnergy
What are the most important risks that
developers, equity investors and banks need
to consider when evaluating investments in
offshore wind farms?
Each project is unique and hence needs to be evaluated
with respect to its specific risks. However, some general
recommendations can be given.
As offshore wind farms are large, capital-intensive
infrastructure projects with long implementation
timeframes, a key area for scrutiny is the expertise of
the project team and the involved participants. In our
experience, the success of a project is directly linked to the
track record of those involved and the team’s ability to
draw from past knowledge and make adequately informed
decisions during project development and execution.
Where experience is limited, appropriate measures such as
external checks and peer reviews should be implemented.
Contractors with limited experience generally require a
higher degree of monitoring by the project team, which
needs to be considered.
The supply chain continues to be an area of focus across this
industry. Currently there are only a handful of experienced
contractors available for each work package. The
competition is even less when looking at the wind turbine
supply package. It is therefore critical to evaluate how the
specific project fits into the contractor’s overall planning in
order to gain assurance that they can deliver on time and
are not overcommitted.
The supply and construction schedule should also be
analysed in detail in order to understand both the critical
path and the float in the schedule. It is recommended that
the schedule allows for enough float such that smaller
disruptions do not immediately cause significant knock-on
effects throughout the project.
14
THOUGHT LEADERSHIP SgurrEnergy
Finally, the contingency level for the project should be
appropriate to the project specific risk profile. Having
access to appropriate contingency is critical, as it allows the
project team to react to changes, which will always happen
during the project execution. Probabilistic quantitative cost
risk assessment combined with project stress testing and
integrated cost schedule risk analysis are considered best
practice to make sufficiently educated decisions about the
required contingency amount.
Offshore wind farms are increasingly being
built further out at sea and in deeper waters.
They are also using larger turbines and
foundations. What new risks does this create
for developers? How can these risks be
managed / mitigated?
SgurrEnergy has acted as lender’s technical advisor on
several offshore projects in German waters, all of which are
approaching construction completion. Due to the coastal
protection zones, these German projects are typically located
much further offshore than projects in other countries,
giving us unique insight into the challenges of increasingly
deep water offshore projects.
A key issue for offshore projects located further offshore
is that the project is being constructed in a much harsher
environment, particularly with respect to wave and wind
conditions. While higher wind speeds are favourable
from an energy production perspective, they can present a
significant challenge during installation.
The first step in mitigating this risk is to develop a detailed
understanding with regards to weather conditions on site.
By conducting detailed analysis using site specific weather
data; appropriate weather windows, required working times
and workability limits for the selected marine spread can
be identified and mitigated. Projects need to have in-house
schedule analysis capabilities and either the tools or external
support to conduct such analysis. The derived information
is crucial to be able to make educated decisions about the
installation strategy, vessel selection, installation start dates
and required float between the different activities. This
information can be of significant monetary value during
contract negotiations, specifically when evaluating the
option to transfer weather risk to the contractor.
Finally, SgurrEnergy recommends using the derived insight
to conduct probabilistic quantitative schedule risk analysis
in order to evaluate the probability of achieving the
scheduled completion date.
How can SgurrEnergy assist investors evaluate
the technical, contractual and financial
aspects of offshore wind projects? What
solutions does SgurrEnergy offer lenders and
equity investors after financial close?
SgurrEnergy has been mandated as lender’s technical
advisor for more than 18 offshore wind projects (>5GW),
of which ten have already reached financial close and a
number have been constructed successfully. This track
record is approximately 60% (in terms of capacity) of the
offshore wind projects that have been financed with debt
capital, a large market share that highlights our leading
position in the sector. Furthermore our team has conducted
diverse technical and commercial advisory assignments
for more than 25 additional offshore wind farms located
worldwide.
This includes projects with wind turbines of all major
manufacturers including the Siemens SWT-6.0-154, Senvion
6M, Alstom Haliade 150-6MW and Adwen AD5-116. We’ve
The external involvement of advisors across
the project life cycle is not something that
utilities are accustomed to, but a change
to practice that will prove necessary when
seeking debt for their projects.
“
”
15
SgurrEnergy
Founded in 2002 and headquartered in Scotland,
SgurrEnergy has undergone sustained growth,
maturing into a globally respected, multi-
disciplinary renewable energy consultancy
with a reputation for engineering and technical
excellence, professionalism, integrity and
responsiveness. Operating from our network of
offices around the world, our global team of over
230 engineers and consultants has extensive
international experience and an impressive track
record – having assessed more than 160GW of
renewable energy projects in over 90 countries,
spread across six continents. In addition, our
Galion lidar is transforming how wind data is
collected, offering a unique, all-sky scanning
capability and up to 4km range.
sgurrenergy.com
Raya Peterson
Principal engineer
info@sgurrenergy.com
+44 0141 227 1700
Website:
Contact:
Position:
Email:
Telephone:
been involved in projects using all types of foundation
technology including tripods and jackets and, most recently,
extra-large monopiles with diameters of more than 7.5m.
This considerable and diverse knowledge of each aspect
of offshore wind projects means we draw from a level of
experience that is unrivalled in the industry and allows us
to offer investors unique advisory services. Our services are
tailor-made and depend on the specifics of the transaction
and needs of our clients. For example, we can undertake
full due diligence of all technical and commercial aspects
of the project, advise on industry best practice, construction
methods, contract terms and conditions, risk quantification
and mitigation measures. Furthermore we regularly
conduct independent schedule analysis, peer reviews as
well as probabilistic quantitative cost risk assessment and
contingency sizing.
Following financial close, SgurrEnergy typically follows
implementation and construction closely and monitors
construction progress for the investors. Such assignments
may include preparation of construction monitoring
reports, construction progress verification, site visits or risk
and reserve reviews. For lenders we typically also provide
monthly cost verification including drawdown certification
and technical advice on an as needed basis.
Utilities increasingly seem to be raising project
finance for their offshore wind farms. How do
they need to alter the structure of projects to
make them attractive to equity investors and
banks?
The appetite for risk differs greatly between lenders and
equity investors. Therefore, the strategy to finance the
project will directly influence its structure and needs to be
defined at an early stage of the project development. In past
transactions it has proven to be beneficial to involve credible
technical and legal advisors early to ensure that the lender’s
requirements are reflected and the project is sufficiently de-
risked to reach financial close within target timescales. This
is particularly relevant for project developers who are not
familiar with project financing of offshore wind projects.
In the past utilities generally implemented their projects
under multi-contracting structures. Lenders tend to prefer
more consolidated contracting structures and all construction
contracts need to be finalised to achieve financial close.
Typically this also includes a requirement to have the main
construction vessels secured.
Lenders expect that the construction and operating contracts
are in line with recent market standards for project financed
transactions and any deviation from this will need to
be justified. Based on our experience there are a number
of elements where the lender’s requirements are more
conservative than what we typically see accepted by utilities
on non-project finance transactions.
One final and very important aspect of project finance is
that it requires a high degree of transparency of the project.
The external involvement of advisors across the project life
cycle is not something that utilities are accustomed to, but a
change to practice that will prove necessary when seeking
debt for their projects.
SgurrEnergy has worked in this industry for
many years. To what extent have costs come
down? Where do you believe there is greater
potential for further cost reductions?
Investment costs have yet to come down. When looking
at the development of investment costs over the past ten
years it becomes clear that they have increased since the
first projects were constructed and only in the past few years
have started to level off.
However, we’ve seen some recent projects that are now going
into construction which have lowered the costs significantly.
This indicates that costs may start to come down in the near
future if framework conditions are favourable for offshore
wind and allow for continued rollout of projects.
Areas where we see good potential for cost reduction
include standardisation of individual elements such as the
substation, utilisation of larger wind turbines, economics
of scale in production, greater competition amongst the
contractors and increasing experience of all involved
parties. ◼
THOUGHT LEADERSHIPSgurrEnergy

More Related Content

Viewers also liked

робота майстра виробничого навчання скобилко н.в.
робота майстра виробничого навчання скобилко н.в.робота майстра виробничого навчання скобилко н.в.
робота майстра виробничого навчання скобилко н.в.ymcmb_ua
 
Letters of Recommendation
Letters of RecommendationLetters of Recommendation
Letters of RecommendationJody Cox
 
Thomas zwart digital_view
Thomas zwart digital_viewThomas zwart digital_view
Thomas zwart digital_viewDigitalView
 
Tafseer Ibn-e-Katheer Part 20 (urdu)
Tafseer Ibn-e-Katheer Part 20 (urdu)Tafseer Ibn-e-Katheer Part 20 (urdu)
Tafseer Ibn-e-Katheer Part 20 (urdu)World
 
Cheating your way through Web Testing
Cheating your way through Web Testing Cheating your way through Web Testing
Cheating your way through Web Testing Qualitest
 
Tafseer Ibn-e-Katheer Part 19 (urdu)
Tafseer Ibn-e-Katheer Part 19 (urdu)Tafseer Ibn-e-Katheer Part 19 (urdu)
Tafseer Ibn-e-Katheer Part 19 (urdu)World
 
Tafseer Ibn-e-Katheer Part 18 (urdu)
Tafseer Ibn-e-Katheer Part 18 (urdu)Tafseer Ibn-e-Katheer Part 18 (urdu)
Tafseer Ibn-e-Katheer Part 18 (urdu)World
 
Tafseer Ibn-e-Katheer Part 11 (urdu)
Tafseer Ibn-e-Katheer Part 11 (urdu)Tafseer Ibn-e-Katheer Part 11 (urdu)
Tafseer Ibn-e-Katheer Part 11 (urdu)World
 
Datum: Editors Lab Final
Datum: Editors Lab FinalDatum: Editors Lab Final
Datum: Editors Lab FinalGENinnovate
 

Viewers also liked (12)

робота майстра виробничого навчання скобилко н.в.
робота майстра виробничого навчання скобилко н.в.робота майстра виробничого навчання скобилко н.в.
робота майстра виробничого навчання скобилко н.в.
 
Letters of Recommendation
Letters of RecommendationLetters of Recommendation
Letters of Recommendation
 
Thomas zwart digital_view
Thomas zwart digital_viewThomas zwart digital_view
Thomas zwart digital_view
 
Vaccination in the EU, ENVI Committee, European Parliament 17 June 2015
Vaccination in the EU, ENVI Committee, European Parliament 17 June 2015Vaccination in the EU, ENVI Committee, European Parliament 17 June 2015
Vaccination in the EU, ENVI Committee, European Parliament 17 June 2015
 
Tafseer Ibn-e-Katheer Part 20 (urdu)
Tafseer Ibn-e-Katheer Part 20 (urdu)Tafseer Ibn-e-Katheer Part 20 (urdu)
Tafseer Ibn-e-Katheer Part 20 (urdu)
 
Cheating your way through Web Testing
Cheating your way through Web Testing Cheating your way through Web Testing
Cheating your way through Web Testing
 
Tafseer Ibn-e-Katheer Part 19 (urdu)
Tafseer Ibn-e-Katheer Part 19 (urdu)Tafseer Ibn-e-Katheer Part 19 (urdu)
Tafseer Ibn-e-Katheer Part 19 (urdu)
 
ブッダのめがね
ブッダのめがねブッダのめがね
ブッダのめがね
 
Tafseer Ibn-e-Katheer Part 18 (urdu)
Tafseer Ibn-e-Katheer Part 18 (urdu)Tafseer Ibn-e-Katheer Part 18 (urdu)
Tafseer Ibn-e-Katheer Part 18 (urdu)
 
Maths in food ppt
Maths in food pptMaths in food ppt
Maths in food ppt
 
Tafseer Ibn-e-Katheer Part 11 (urdu)
Tafseer Ibn-e-Katheer Part 11 (urdu)Tafseer Ibn-e-Katheer Part 11 (urdu)
Tafseer Ibn-e-Katheer Part 11 (urdu)
 
Datum: Editors Lab Final
Datum: Editors Lab FinalDatum: Editors Lab Final
Datum: Editors Lab Final
 

Similar to Offshore Wind Risks and Mitigation Strategies

Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_BrochureHieu Phan Trung
 
MEM Capabilities_20160822_Lres
MEM Capabilities_20160822_LresMEM Capabilities_20160822_Lres
MEM Capabilities_20160822_LresAaron Daniels, PMP
 
Proven project management.docx
Proven project management.docxProven project management.docx
Proven project management.docxFairFASST
 
Microgrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cMicrogrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cJames Finlay
 
RONALD CV 17.11.2015
RONALD CV 17.11.2015RONALD CV 17.11.2015
RONALD CV 17.11.2015Ronald Fung
 
brochure template (Autosaved)
brochure template (Autosaved)brochure template (Autosaved)
brochure template (Autosaved)Russell Myers
 
Geothermal Energy Risk Management
Geothermal Energy Risk ManagementGeothermal Energy Risk Management
Geothermal Energy Risk ManagementFernando Penarroyo
 
Corporate Profile 2023.pptx
Corporate Profile 2023.pptxCorporate Profile 2023.pptx
Corporate Profile 2023.pptxMayurHiwarkar4
 
Portsmouth University Presentation
Portsmouth University PresentationPortsmouth University Presentation
Portsmouth University PresentationStavros Thomas
 
MEM Capabilities Statement 2016_LR
MEM Capabilities Statement 2016_LRMEM Capabilities Statement 2016_LR
MEM Capabilities Statement 2016_LRFrancisco Iacona
 
4.GROW Presentation for MPI Event 14th July 2015
4.GROW Presentation for MPI Event 14th July 20154.GROW Presentation for MPI Event 14th July 2015
4.GROW Presentation for MPI Event 14th July 2015Alan Whittaker
 
2-Wave and Tidal RHDHV_Brochure
2-Wave and Tidal RHDHV_Brochure2-Wave and Tidal RHDHV_Brochure
2-Wave and Tidal RHDHV_BrochureHieu Phan Trung
 
Alistair Howson - Curriculum Vitae
Alistair Howson - Curriculum VitaeAlistair Howson - Curriculum Vitae
Alistair Howson - Curriculum VitaeAlistair Howson
 
World Finance Review Sep_2014 Kazakhstan
World Finance Review Sep_2014 KazakhstanWorld Finance Review Sep_2014 Kazakhstan
World Finance Review Sep_2014 KazakhstanRobert Jutson
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasMircea Tomescu
 

Similar to Offshore Wind Risks and Mitigation Strategies (20)

Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure1-Wind Energy RHDHV_Brochure
1-Wind Energy RHDHV_Brochure
 
MEM Capabilities_20160822_Lres
MEM Capabilities_20160822_LresMEM Capabilities_20160822_Lres
MEM Capabilities_20160822_Lres
 
Proven project management.docx
Proven project management.docxProven project management.docx
Proven project management.docx
 
Microgrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cMicrogrid invest risk summary v08-02c
Microgrid invest risk summary v08-02c
 
RONALD CV 17.11.2015
RONALD CV 17.11.2015RONALD CV 17.11.2015
RONALD CV 17.11.2015
 
Marketing Summary Report
Marketing Summary ReportMarketing Summary Report
Marketing Summary Report
 
brochure template (Autosaved)
brochure template (Autosaved)brochure template (Autosaved)
brochure template (Autosaved)
 
Geothermal Energy Risk Management
Geothermal Energy Risk ManagementGeothermal Energy Risk Management
Geothermal Energy Risk Management
 
Corporate Profile 2023.pptx
Corporate Profile 2023.pptxCorporate Profile 2023.pptx
Corporate Profile 2023.pptx
 
Portsmouth University Presentation
Portsmouth University PresentationPortsmouth University Presentation
Portsmouth University Presentation
 
MEM Capabilities Statement 2016_LR
MEM Capabilities Statement 2016_LRMEM Capabilities Statement 2016_LR
MEM Capabilities Statement 2016_LR
 
4.GROW Presentation for MPI Event 14th July 2015
4.GROW Presentation for MPI Event 14th July 20154.GROW Presentation for MPI Event 14th July 2015
4.GROW Presentation for MPI Event 14th July 2015
 
road_map (1)
road_map (1)road_map (1)
road_map (1)
 
2-Wave and Tidal RHDHV_Brochure
2-Wave and Tidal RHDHV_Brochure2-Wave and Tidal RHDHV_Brochure
2-Wave and Tidal RHDHV_Brochure
 
Alistair Howson - Curriculum Vitae
Alistair Howson - Curriculum VitaeAlistair Howson - Curriculum Vitae
Alistair Howson - Curriculum Vitae
 
World Finance Review Sep_2014 Kazakhstan
World Finance Review Sep_2014 KazakhstanWorld Finance Review Sep_2014 Kazakhstan
World Finance Review Sep_2014 Kazakhstan
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
CV Resume
CV ResumeCV Resume
CV Resume
 

Offshore Wind Risks and Mitigation Strategies

  • 1. 13 THOUGHT LEADERSHIPSgurrEnergy Developers of offshore wind farms face a number of risks, as do the banks and equity funds that invest in them. Clean Energy Pipeline interviewed Raya Peterson, Principal Engineer at SgurrEnergy, to understand how these risks are changing and what strategies can be adopted to mitigate them. We also discuss emerging financing considerations as project finance structures become more attractive. Emerging risks in offshore wind Q&A with Raya Peterson, Principal engineer at SgurrEnergy Raya Peterson Principal engineer SgurrEnergy What are the most important risks that developers, equity investors and banks need to consider when evaluating investments in offshore wind farms? Each project is unique and hence needs to be evaluated with respect to its specific risks. However, some general recommendations can be given. As offshore wind farms are large, capital-intensive infrastructure projects with long implementation timeframes, a key area for scrutiny is the expertise of the project team and the involved participants. In our experience, the success of a project is directly linked to the track record of those involved and the team’s ability to draw from past knowledge and make adequately informed decisions during project development and execution. Where experience is limited, appropriate measures such as external checks and peer reviews should be implemented. Contractors with limited experience generally require a higher degree of monitoring by the project team, which needs to be considered. The supply chain continues to be an area of focus across this industry. Currently there are only a handful of experienced contractors available for each work package. The competition is even less when looking at the wind turbine supply package. It is therefore critical to evaluate how the specific project fits into the contractor’s overall planning in order to gain assurance that they can deliver on time and are not overcommitted. The supply and construction schedule should also be analysed in detail in order to understand both the critical path and the float in the schedule. It is recommended that the schedule allows for enough float such that smaller disruptions do not immediately cause significant knock-on effects throughout the project.
  • 2. 14 THOUGHT LEADERSHIP SgurrEnergy Finally, the contingency level for the project should be appropriate to the project specific risk profile. Having access to appropriate contingency is critical, as it allows the project team to react to changes, which will always happen during the project execution. Probabilistic quantitative cost risk assessment combined with project stress testing and integrated cost schedule risk analysis are considered best practice to make sufficiently educated decisions about the required contingency amount. Offshore wind farms are increasingly being built further out at sea and in deeper waters. They are also using larger turbines and foundations. What new risks does this create for developers? How can these risks be managed / mitigated? SgurrEnergy has acted as lender’s technical advisor on several offshore projects in German waters, all of which are approaching construction completion. Due to the coastal protection zones, these German projects are typically located much further offshore than projects in other countries, giving us unique insight into the challenges of increasingly deep water offshore projects. A key issue for offshore projects located further offshore is that the project is being constructed in a much harsher environment, particularly with respect to wave and wind conditions. While higher wind speeds are favourable from an energy production perspective, they can present a significant challenge during installation. The first step in mitigating this risk is to develop a detailed understanding with regards to weather conditions on site. By conducting detailed analysis using site specific weather data; appropriate weather windows, required working times and workability limits for the selected marine spread can be identified and mitigated. Projects need to have in-house schedule analysis capabilities and either the tools or external support to conduct such analysis. The derived information is crucial to be able to make educated decisions about the installation strategy, vessel selection, installation start dates and required float between the different activities. This information can be of significant monetary value during contract negotiations, specifically when evaluating the option to transfer weather risk to the contractor. Finally, SgurrEnergy recommends using the derived insight to conduct probabilistic quantitative schedule risk analysis in order to evaluate the probability of achieving the scheduled completion date. How can SgurrEnergy assist investors evaluate the technical, contractual and financial aspects of offshore wind projects? What solutions does SgurrEnergy offer lenders and equity investors after financial close? SgurrEnergy has been mandated as lender’s technical advisor for more than 18 offshore wind projects (>5GW), of which ten have already reached financial close and a number have been constructed successfully. This track record is approximately 60% (in terms of capacity) of the offshore wind projects that have been financed with debt capital, a large market share that highlights our leading position in the sector. Furthermore our team has conducted diverse technical and commercial advisory assignments for more than 25 additional offshore wind farms located worldwide. This includes projects with wind turbines of all major manufacturers including the Siemens SWT-6.0-154, Senvion 6M, Alstom Haliade 150-6MW and Adwen AD5-116. We’ve The external involvement of advisors across the project life cycle is not something that utilities are accustomed to, but a change to practice that will prove necessary when seeking debt for their projects. “ ”
  • 3. 15 SgurrEnergy Founded in 2002 and headquartered in Scotland, SgurrEnergy has undergone sustained growth, maturing into a globally respected, multi- disciplinary renewable energy consultancy with a reputation for engineering and technical excellence, professionalism, integrity and responsiveness. Operating from our network of offices around the world, our global team of over 230 engineers and consultants has extensive international experience and an impressive track record – having assessed more than 160GW of renewable energy projects in over 90 countries, spread across six continents. In addition, our Galion lidar is transforming how wind data is collected, offering a unique, all-sky scanning capability and up to 4km range. sgurrenergy.com Raya Peterson Principal engineer info@sgurrenergy.com +44 0141 227 1700 Website: Contact: Position: Email: Telephone: been involved in projects using all types of foundation technology including tripods and jackets and, most recently, extra-large monopiles with diameters of more than 7.5m. This considerable and diverse knowledge of each aspect of offshore wind projects means we draw from a level of experience that is unrivalled in the industry and allows us to offer investors unique advisory services. Our services are tailor-made and depend on the specifics of the transaction and needs of our clients. For example, we can undertake full due diligence of all technical and commercial aspects of the project, advise on industry best practice, construction methods, contract terms and conditions, risk quantification and mitigation measures. Furthermore we regularly conduct independent schedule analysis, peer reviews as well as probabilistic quantitative cost risk assessment and contingency sizing. Following financial close, SgurrEnergy typically follows implementation and construction closely and monitors construction progress for the investors. Such assignments may include preparation of construction monitoring reports, construction progress verification, site visits or risk and reserve reviews. For lenders we typically also provide monthly cost verification including drawdown certification and technical advice on an as needed basis. Utilities increasingly seem to be raising project finance for their offshore wind farms. How do they need to alter the structure of projects to make them attractive to equity investors and banks? The appetite for risk differs greatly between lenders and equity investors. Therefore, the strategy to finance the project will directly influence its structure and needs to be defined at an early stage of the project development. In past transactions it has proven to be beneficial to involve credible technical and legal advisors early to ensure that the lender’s requirements are reflected and the project is sufficiently de- risked to reach financial close within target timescales. This is particularly relevant for project developers who are not familiar with project financing of offshore wind projects. In the past utilities generally implemented their projects under multi-contracting structures. Lenders tend to prefer more consolidated contracting structures and all construction contracts need to be finalised to achieve financial close. Typically this also includes a requirement to have the main construction vessels secured. Lenders expect that the construction and operating contracts are in line with recent market standards for project financed transactions and any deviation from this will need to be justified. Based on our experience there are a number of elements where the lender’s requirements are more conservative than what we typically see accepted by utilities on non-project finance transactions. One final and very important aspect of project finance is that it requires a high degree of transparency of the project. The external involvement of advisors across the project life cycle is not something that utilities are accustomed to, but a change to practice that will prove necessary when seeking debt for their projects. SgurrEnergy has worked in this industry for many years. To what extent have costs come down? Where do you believe there is greater potential for further cost reductions? Investment costs have yet to come down. When looking at the development of investment costs over the past ten years it becomes clear that they have increased since the first projects were constructed and only in the past few years have started to level off. However, we’ve seen some recent projects that are now going into construction which have lowered the costs significantly. This indicates that costs may start to come down in the near future if framework conditions are favourable for offshore wind and allow for continued rollout of projects. Areas where we see good potential for cost reduction include standardisation of individual elements such as the substation, utilisation of larger wind turbines, economics of scale in production, greater competition amongst the contractors and increasing experience of all involved parties. ◼ THOUGHT LEADERSHIPSgurrEnergy