4. Hearst Park & Pool
Overall Design
- Newly graded field
- Irriga2on System
- Playground Shade
- Playground Structure
- Walking Trail
- Bio-filtra2on areas
- Trees and Plan2ngs
- Site Furnishing
- New ADA Improvements
- Vegeta2on Enhancement
on East & South Slopes
- New tennis courts
- New Outdoor Pool &
Pool House
23. Next Steps:
• This presenta2on will be posted on the DGS website
• Next community mee2ng will be held in April 23, 2019.
• Field Restora2on – summer 2019 - fall of 2019
• Playground Construc2on – summer 2019 (aher June 17th) ~ 1 month
• No summer DPR camps summer 2019
• Stormwater Remedia2on – summer 2019
• Pool and Pool House Construc2on Start – fall 2019 (tennis courts offline)
• Project Comple2on – Summer 2020