4. Hearst Park & Pool
Overall Design
- Newly graded field
- Irriga;on System
- Playground Shade
- Playground Structure
- Walking Trail
- Bio-filtra;on areas
- Trees and Plan;ngs
- Site Furnishing
- New ADA Improvements
- Vegeta;on Enhancement
on East & South Slopes
- New Outdoor Pool &
Pool House
- New tennis courts
25. Next Steps:
• This presenta;on will be posted on the DGS website
• Next community mee;ng will be held in April, 2019.
• Field Restora;on – summer 2019
• Stormwater Remedia;on – summer 2019
• Playground Construc;on – summer 2019
• Pool and Pool House Construc;on Start – fall 2019
• Project Comple;on – Summer 2020