SlideShare a Scribd company logo
1 of 19
Download to read offline
SPM #5 PERIODIC SHUT DOWN REPORT
Page 1 of 12
OVERVIEW:
Once in every three years the floating hoses are subjected detailed inspection to review condition of
the hoses and the suitability to re-use the hoses. Any hose that shows any signs of deterioration is
replaced. The ramification of a mid-cycle shut down cannot be overemphasized. The hoses are
flushed out, disconnected from the SPM, towed to the shore side where the inspection regime is
carried out and likewise re-commissioned.
Inspection regime comprises of
• Marine growth removal and cleaning
• Visual inspection for cuts, abrasions, bulges, warning system ect.
• Electrical continuity test
• Hydrostatic test (including elongation check)
• Vacuum test.
MAINTENACE SCHEDULE OF FLOATING HOSE:
HOSE TYPE* FOB MAIN LINE REDUCER TAIL TANKER RAIL
Single / Double
carcass
(SPM 4&5)
12 Months 36 M then
after annually.
36 M then
after annually.
36 M then
after annually.
12 Months
*Double carcass hose is designed so that if the main carcass fails, the secondary carcass contains
the leak and protects the ambient environment. An alarm system alerts the operator when the primary
carcass fails.
The first task is to disconnect the floating hoses from their connections and transfer them to the
testing site, in a SAFE manner, without impacting the environment. The floating hoses are flushed
through with sea water until they are rid of traces of oil, there after they are transferred to the
testing area.
DESCRIPTION OF LAYOUT
The connection between pipe arm piping and tanker manifold consists of two(2) No. 20-Inch hose
strings. The Inboard string is of total length 795 feet, while the Outboard string is of total length 835
feet, due to insertion of one additional 40 foot mainline hose. The Pipeline End Manifold (PLEM) is a
subsea unit from which rise two subsea Hoses (pipe lines of 20”ø and 30”ø) to connect to the Multi-
product Delivery Unit (MPDU) located on the top of the SPM. Each one of these pipes has two
hydraulically operated butterfly vales connected, adjacent to the PLEM. The outlets from the MPDU
are connected to the flexible hosing. All flexible hoses are of flange-ended construction. The first
length of Flexible hose nearest to the SPM is known “FIRST OFF BOUY HOSE” (20”ø x 40’) that is a
“half-floating” Hose of heavier construction electrically continuous to be fitted on J tube of SPM.
This hose is followed by 15 lengths of FLOATING MAIN HOSE (20” ø X 40’) that are “fully-floating”
and electrically continuous, next is 1 length of “fully-floating” REDUCER HOSE (20” ø >16” ø X 40’),
next 3 lengths of “FLOATING TAIL HOSE” (16” ø X40’) electrically discontinuous and finally 1 length of
“TANKER RAIL HOSE” (16”ø X 35’x 1) electrically discontinuous, that gets connected to the Tanker.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 2 of 12
FLUSHING OPERATION FOR CRUDE OIL FLOATING HOSES:
A suitable tanker requires to be identified for receiving the flushing slops from the floating hoses.
The floating hoses are flushed with sea water taken from the fire line of the tanker. Standard fire line
connections are 4” in diameter. The Tanker Rail Hoses are connected to the manifold in the tanker,
leading to the SLOP Tanks.
The 4” flexible hose is connected to the PLEM, the 30”ø valves and closed and the 24ø valves are
kept open. The flushing commences at a low pressure and when slops are received on board the
tanker, the pressure is increased to 4 Kg/cm2
. Flushing is carried out in 5 sessions each of 30 minute
duration. Samples of the slops are drawn every 30 minutes to monitor the Slops. Once the Slop is
“CLEAN” the Tanker rail hoses are disconnected and flanged and prepared for the towing operation.
Depending on the tidal condition, the flushing hose will have to be disconnected and reconnected.
The process described above is conventional procedure where the SPM does not have
Surge Tank
FLUSHING LINE DIAGRAM:
SPM
Inner Hose
Outer Hose
20” PLEM v/v
30” v/v
30” v/v
12
SEABED
27m CD + Tide
4” isolation valve
4” Flushing Connections
Flood Tide
Ebb Tide
4” Flexible Hose
4” Flexible Hose
Tanker end
4” line conn.
4” isolation valve
MPDU
PLEM
SPM #5 PERIODIC SHUT DOWN REPORT
Page 3 of 12
Informatively, surge tanks form an integral part of the discharge system that accommodates
pressure surges. In case of a surge in line pressure, the surge relief valve set at 15Kg/cm2
releases the cargo into the surge tank. An alarm is activated when the surge tank come to
50% capacity and the system shuts down when the level reaches 75% capacity. A Wilden
pump is also provided to transfer oil from the surge tank to the system.
In the case the SPM has surge tanks a different procedure as described below can be
adopted. SPM 5 has surge tanks and hence this procedure was adopted. The fire line of the
tanker that is used for flushing operation is bifurcated into 1½”ø branches. These are
connected to the surge line valves on the deck of the SPM. The interconnecting valve
between the 24”ø subsea hoses (SSH) and the surge tank (Normally Open) are kept shut.
The 20”ø and 30”ø are kept shut. The flushing seawater enters the system and enters the
subsea hoses up to the 20”ø valve. Being heavier than oil, the sea water slowly displaces the
oil in the subsea hoses. Displaced oil enters the MPDU and finally gets back to the tanker
Slop Tanks. Flushing is carried out in 5 sessions each of 30 minute duration. Samples of the slops
are drawn every 30 minutes to monitor the Slops. Once the Slop is “CLEAN” the Tanker rail hoses are
disconnected and flanged and prepared for the towing operation. Quantity of liquid pumped to
tanker should be about 250 KL per string.
Advantages:
Less man power required.
Diving operation not required.
Flushing can be continued without any breaks irrespective of tidal changes.
Time saved about 1.5 days.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 4 of 12
SPM #5 PERIODIC SHUT DOWN REPORT
Page 5 of 12
Once the Flushing operation is completed, the mooring hawser is disconnected and secured on the
DSV deck. To facilitate easy towage to the testing site, the First off Buoy hoses, are secured to
floating jackets. Recall that these hoses are “half-floating” and hence need these buoyancy jackets.
The First off Buoy hoses are disconnected from the SPM “J” pipe
Floating jackets secured on First off Buoy hoses First off Buoy hoses disconnected from SPM J pipe
Towing:
6 ‘’ PP to be secured for both Inner and Outer Hoses.
Remove Winker lights and secure on DSV.
Connect Towing ropes on Tanker rail hose and FOB end.
FOB hose end to be blind flanged, to prevent drift wood passing through the bore during
towing.
Floating Hose strings to be towed under supervision from SPM buoy to LOLO Jetty.
Secure both strings to DSV at LOLO Jetty.
Max. Towing speed not be exceeded by 05 Knots.
Transferring Hoses to DSV deck All Hoses transferred on deck of DSV
SPM #5 PERIODIC SHUT DOWN REPORT
Page 6 of 12
Hoses transferred to the Jetty
Lifting, Dismantling & Visual Inspection:
Both Strings FOB and TRH to be pulled and secured on DSV deck.
Floats to be disconnected from FOB.
Dismantling can be started from any end preferably from TRH.
Dismantling should be carried out individual strings.
Each hoses dismantled to be marked with hose number and string(Inner/Outer).
Hoses to be inspected for external damage.
Marine Growth to be cleaned externally for inspection by Scrapper and wire brush.
Hoses to be lifted only by using Spreader Bar.
Do Not Use Wire Ropes For Lifting Hoses.
Do Not Lift By Single Point Or By The Ends.
ON SHORE INSPECTION:
Inspect Floating Hoses both Internally and Externally for any Kinks, Deformation, Cracking,
separation, cut marks, abrasion, corrosion spool piece/Flanges
All repairable parts to be attended before re installation of hoses.
In case of any major defects observed hoses can be rejected.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 7 of 12
HYDRO TEST PROCEDURE:
Place the hose on ground level as straight as possible on supports that permit the hose to be
elongated freely.
Blind both ends of the hoses with rated flanges.
Fill the Hose with water through one side of the hose and vent air from other end.
When constant stream of water is delivered through the venting side of the flange close the
vent valve.
Apply pressure of 0.7 bar and note the time.
Measure the overall length of the hose assembly L1 (Example: L1 = 12.20 m)
Increase the pressure over a period of 5 Min from 0.7 bar to half the rated pressure of hose.
Hold the pressure for 30 Min, then reduce the pressure over a period of 5 Min to Zero bar.
Raise the Pressure over a period of 5 Min to rated pressure of hose.
Measure Length L2 (Example: L2 = 12.24 m)
Reduce the pressure over a period of 5 Min to Zero Bar.
After an interval of 15 Minutes, raise Pressure to 0.7 Bar.
Measure overall length L3 (example: L3 = 12.20 m).
Reduce the pressure to Zero then Drain the Hose.
Measure L1, L2 and L3 are used to measure Temporary and permanent elongation.
Temporary Elongation: T= {(L2-L1)/L1} X 100.
Permanent Elongation: P= {(L3-L1)/L1} X 100.
Hose Retirement Criteria:
Temporary elongation (T) is > +2% of the Temporary elongation recorded during FAT (Tf)
Permanent elongation (P) is > +2% of the Permanent elongation recorded during FAT (Pf)
SPM #5 PERIODIC SHUT DOWN REPORT
Page 8 of 12
VACUUM TEST PROCEDURE:
Vacuum test to be carried out after hydrostatic pressure test and not more than four days.
Blank off both end of the hose with transparent Perspex flange using a rubber gaskets to
obtain seal and also secure with C- Clamp.
Apply a vacuum of at least 510 mmHg and hold for 10 Min.
Use a bright flashlight, or mirror to direct the sunlight, and examine the bore for,
Blisters or bulges- these indicates the separation of lining from carcass.
Bubbles of water appearing around the fitting area, or at any point along the bore, which
indicates cuts and lining separation.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 9 of 12
HOSE THAT FAILED
DURING VACUUM TEST
Internal implosion
occurred at the location
indicated by the arrow.
Electrical Continuity Test:
Hoses should be either electrically Continuous or Discontinuous. Resistance of hose should
be measured by means of a 500 Volt Megger
Continuous: The conductivity should be checked when the hose is under pressure and
again after the completion of pressure test. The test to be conducted by connecting a
wire to each flange to complete a circuit with a small 4.5 V battery and a 4V,3A lamp or
by using Multi meter.
Discontinuous: The discontinuous test should be carried out before or after the pressure
test when hose is dry. The resistance of the hose should not be less than 25000 ohms.
Assembly:
Each Hose to be lowered on DSV deck as per serial number AS BUILT SHEET.
New gaskets and studs to be used and tightened to the requisite torque
Assembling of Break-away Coupling in between Reducer and Tail hose with proper gasket
and studs (Direction of Flow to be checked prior installing).
Support Buoy is to be fixed for Break Away coupling and FOB.
Assembling of pick-up chains on tanker rail hose.
Assembling of Butterfly Valve, Spool Piece and cam lock on other end of Tanker rail hose.
Tightening of all studs of 150# and 300# series flanges to be done in sequence using a
calibrated torque wrench as per following table.
20” X 150# flange Joints (Main line) 900 Nm
20” X 300# flange Joints ( Fob J tube end) 1100 Nm
16” X 150# flange Joints (Tail, Rail and Break away) 600 Nm.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 10 of 12
AS BUILT SHEET FOR REFERENCE
Pressure Testing Of Assembled Floating Hose String, Towing & FOB Connection :
Assembled floating hose strings are to be pressure tested. Pressure test at 15 bars and held
for one hour and observe for any pressure drop.
If any pressure drop noticed, check the tightness of the hose and flange connection.
If the pressure holds for one hour, slowly depressurize the floating hose string and blind end
of the string.
Upon satisfactory pressure testing, hoses can be towed back to SPM Buoy as per procedure.
First Off Buoy hoses are to be connected to J pipe with new gaskets.
SPM #5 PERIODIC SHUT DOWN REPORT
Page 11 of 12
Pressure Testing Of Assembled FHS and System To PLEM:
Moor the DSV by bow on SPM buoy and keep Tanker rail hose on deck of DSV for pressuring
the FHS strings.
Pressurize both floating hoses strings individually against the PLEM valves up to 15 bar and
hold for one hour.
Open both deck valve and centre chamber valve.
Upon satisfactory completion of pressure test, depressurize the floating hoses strings slowly up to 10
Kg/cm2
and inspect the butterfly valve for any leak. If butterfly valve found satisfactory then release
the pressure slowly. Lower the Tanker rail hose in water.
SINGLE POINT MOORING BUOY (ELEVATION)
Chamber valves
Deck valves
SPM #5 PERIODIC SHUT DOWN REPORT
Page 12 of 12
SINGLE POINT MOORING BUOY (PLAN)
RECOMMISSIONING OF SPM
Open both deck valve and central chamber valves.
Close surge valves on deck.
Check High Pressure Unit oil level
Accumulators pressure to be checked.
HPU unit to be pressed up to 320 Bar.
Open 30” Manually operated PLEM Valve.
Open 12” valve to surge tanks for both inner and outer.
Appendix
Date Time Activity
7-Apr-15 Preparation for Flushing
1048 Hrs - 1536 Hrs Outer Strings Flushing Carried Out
1624 Hrs - 2048 Hrs. Inner Strings Flushing Carried Out
0800 Hrs - 1200 Hrs. FON Floats Installation & PPE Rope Secured.
1000 Hrs -1500 Hrs "J" tube- FOB Hose disconnection
1500 Hrs to 1630 Hrs FHS Both Strings Towed To LO-LO Jetty.
1715 Hrs - 2300 Hrs.
Floating Hose Strings Lifting and Disconnection.(total 9 Hoses
Disconnected)
0700 Hrs - 0900 Hrs.
Floating Hose Strings Lifting and Disconnection.(total 4 Hoses
Disconnected)
0930 Hrs - 2000 Hrs.
Hydrostatic pressure Test , Vacuum Test, Electrical Continuity &
Discontinuity Test Of All 13 Hoses
0600 - 2000 Hrs Lowering Of Hoses and Connection Of Hoses.
1800 hrs -2400 hrs
0000 hrs - 0300 hrs
0600 hrs - 0800 hrs Towing of both string to the SPM
1100 hrs -1900 hrs FOB Connection and Hydrotest of assembly
0900hrs -1200 hrs SPM pre-commissioning checks
1500 Hrs Tanker berthed at SPM
ACTIVITY LOG-SHEET
Hydro Test OF Both Strings
12-Apr-15
13-Apr-15
8-Apr-15
9-Apr-15
10-Apr-15
11-Apr-15
TEST ACCEPTANCE CERTIFICATE
Company Reliance Date 4/11/2015
Unit Section
This is to certify that the Inner floating strings
From First of buoy hose
To Tanker rail hose
Was tested as outlined below.
Type of test Hydrostatic
Location of test unit LO-LO jetty
Maximum pressure recorded during test period 15 Kg/ cm2
Duration of Operation Time Date
From 21:00 Hrs 4/11/2015
To 03:10 Hrs 4/12/2015
Filling of hose strings commenced at 21:00 Hrs 4/11/2015
Filling of hose strings Stopped at 22:45 Hrs 4/11/2015
Hydrostatic Pump Started at 22:45 Hrs 4/11/2015
Vent plug closed at 22:50 Hrs 4/11/2015
Time taken for building up pressure from 0 to 15 kg/cm2 22:45 to 00:01 Hrs
Any Pressure drop noticed from 00:01 Hrs to 02:02 Hrs 0.5 Kg/cm2
Pressure released at 02:05 Hrs
Attained ZERO pressure at 03:10 Hrs
Instrument Details Mfg. Calibration date
Pressure Gauge FGB March 31 2015
Completed & witnessed By
RIL Rep. OSL Rep.
SPM - 5
INNER STRING PRESSURE TEST
Serial No.
C130766
TEST ACCEPTANCE CERTIFICATE
Company Reliance Date 4/11/2015
Unit Section
This is to certify that the Outer floating strings
From First of buoy hose
To Tanker rail hose
Was tested as outlined below.
Type of test Hydrostatic
Location of test unit LO-LO jetty
Maximum pressure recorded during test period 15 Kg/ cm2
Duration of Operation Time Date
From 16:15 Hrs 4/11/2015
To 22:32 Hrs 4/11/2015
Filling of hose strings commenced at 16:15 Hrs 4/11/2015
Filling of hose strings Stopped at 19:30 Hrs 4/11/2015
Hydrostatic Pump Started at 19:30 Hrs 4/11/2015
Vent plug closed at 19:35 Hrs 4/11/2015
Time taken for building up pressure from 0 to 15 kg/cm2 19:30 to 20:30 Hrs
Any Pressure drop noticed from 20:30 Hrs to 21:30 Hrs 0.5 Kg/cm2
Pressure released at 21:35 Hrs
Attained ZERO pressure at 22:32 Hrs
Instrument Details Mfg. Calibration date
Pressure Gauge FGB March 31 2015
Completed & witnessed By
RIL Rep. OSL Rep.
SPM - 5 OUTER STRING
PRESSURE TEST
Serial No.
C130760
TEST ACCEPTANCE CERTIFICATE
Company Reliance Date 4/12/2015
Unit Section
This is to certify that the Inner floating strings
From Tanker rail hose
To PLEM Valve
Was tested as outlined below.
Type of test Leak Test
Location of test unit SPM - 5
Maximum pressure recorded during test period 15 Kg/ cm2
Duration of Operation Time Date
From 11:50 Hrs 4/12/2015
To 16:20 Hrs 4/12/2015
Filling of hose strings commenced at 11:50 Hrs 4/12/2015
Filling of hose strings Stopped at 12:55 Hrs 4/12/2015
Hydrostatic Pump Started at 12:55 Hrs 4/12/2015
Vent plug closed at 13:00 Hrs 4/12/2015
Time taken for building up pressure from 0 to 15 kg/cm2 12:55 to 14:15Hrs
Any Pressure drop noticed from 14:15 Hrs to 15:15Hrs 0.5 Kg/cm2
Pressure released at 15:17 Hrs
Attained ZERO pressure at 16:20 Hrs
Instrument Details Mfg. Calibration date
Pressure Gauge FGB 30.03.2015
Completed & witnessed By
RIL Rep. OSL Rep.
SPM - 5 INNER STRING SYSTEM PRESSURE
TEST
Serial No.
C130766
TEST ACCEPTANCE CERTIFICATE
Company Reliance Date 4/12/2015
Unit Section
This is to certify that the Outer floating strings
From Tanker rail hose
To PLEM Valve
Was tested as outlined below.
Type of test Leak Test
Location of test unit SPM - 5
Maximum pressure recorded during test period 15 Kg/ cm2
Duration of Operation Time Date
From 16:00 Hrs 4/12/2015
To 19:00 Hrs 4/12/2015
Filling of hose strings commenced at 16:00 Hrs 4/12/2015
Filling of hose strings Stopped at 16:30 Hrs 4/12/2015
Hydrostatic Pump Started at 16:30 Hrs 4/12/2015
Vent plug closed at 16:35 Hrs 4/12/2015
Time taken for building up pressure from 0 to 15 kg/cm2 16:30 to17:15 Hrs
Any Pressure drop noticed from 17:15 Hrs to 18:15 Hrs 0.5 Kg/cm2
Pressure released at 18:15 Hrs
Attained ZERO pressure at 19:00 Hrs
Instrument Details Mfg. Calibration date
Pressure Gauge FGB 30.03.2015
Completed & witnessed By
RIL Rep. OSL Rep.
SPM - 5 OUTER STRING SYSTEM
PRESSURE TEST
Serial No.
C130760

More Related Content

What's hot

Offshore Structures Presentation
Offshore Structures PresentationOffshore Structures Presentation
Offshore Structures Presentationsurya3303
 
Storage tank inspection presentation
Storage tank inspection presentationStorage tank inspection presentation
Storage tank inspection presentationIan Moore
 
Marine piping systems
Marine piping systemsMarine piping systems
Marine piping systemskmsu
 
Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipplesElsayed Amer
 
Continuous machinery survey
Continuous machinery surveyContinuous machinery survey
Continuous machinery surveyViktor Bily
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesvinod kumar
 
0020 introduction to fpso design
0020 introduction to fpso design0020 introduction to fpso design
0020 introduction to fpso designChieu Nguyen
 
Wellhead function, rating and selection
Wellhead function, rating and selectionWellhead function, rating and selection
Wellhead function, rating and selectionElsayed Amer
 
Wireline Operation 2018 - Oil and Gas Industry
Wireline Operation 2018 - Oil and Gas IndustryWireline Operation 2018 - Oil and Gas Industry
Wireline Operation 2018 - Oil and Gas IndustryGamal Eldien Tarek
 
Snubbing bop
Snubbing bopSnubbing bop
Snubbing bopwomgroup
 
Horizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptHorizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptAmar Gaikwad
 
HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTINGPaul Sumal
 

What's hot (20)

Offshore Structures Presentation
Offshore Structures PresentationOffshore Structures Presentation
Offshore Structures Presentation
 
Packers GFK
Packers GFKPackers GFK
Packers GFK
 
Storage tank inspection presentation
Storage tank inspection presentationStorage tank inspection presentation
Storage tank inspection presentation
 
Marine piping systems
Marine piping systemsMarine piping systems
Marine piping systems
 
Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipples
 
Continuous machinery survey
Continuous machinery surveyContinuous machinery survey
Continuous machinery survey
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelines
 
0020 introduction to fpso design
0020 introduction to fpso design0020 introduction to fpso design
0020 introduction to fpso design
 
Wellhead function, rating and selection
Wellhead function, rating and selectionWellhead function, rating and selection
Wellhead function, rating and selection
 
subsea
subseasubsea
subsea
 
Wireline Operation 2018 - Oil and Gas Industry
Wireline Operation 2018 - Oil and Gas IndustryWireline Operation 2018 - Oil and Gas Industry
Wireline Operation 2018 - Oil and Gas Industry
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
Mechanical seal for pumps
Mechanical seal for pumpsMechanical seal for pumps
Mechanical seal for pumps
 
Well intervention
Well interventionWell intervention
Well intervention
 
Well intervention
Well  interventionWell  intervention
Well intervention
 
Pipe rack & rack piping
Pipe rack & rack pipingPipe rack & rack piping
Pipe rack & rack piping
 
Snubbing bop
Snubbing bopSnubbing bop
Snubbing bop
 
Horizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptHorizontal vertical christmas tree ppt
Horizontal vertical christmas tree ppt
 
Valves and Testing .pdf
Valves and Testing .pdfValves and Testing .pdf
Valves and Testing .pdf
 
HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTING
 

Similar to SPM FHS SHUT DOWN REPORT

4_5854850146042385629.pdf
4_5854850146042385629.pdf4_5854850146042385629.pdf
4_5854850146042385629.pdfsalem123gmaal
 
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETC
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETCFIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETC
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETCGaurav Singh Rajput
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxholegajendra
 
unlocked-461fd952f4656fee70de599ef77bd2ba.pptx
unlocked-461fd952f4656fee70de599ef77bd2ba.pptxunlocked-461fd952f4656fee70de599ef77bd2ba.pptx
unlocked-461fd952f4656fee70de599ef77bd2ba.pptxWaledFekry1
 
Hydraulic Ram Made from Standard Plumbing Parts - University of Georgia
Hydraulic Ram Made from Standard Plumbing Parts - University of GeorgiaHydraulic Ram Made from Standard Plumbing Parts - University of Georgia
Hydraulic Ram Made from Standard Plumbing Parts - University of GeorgiaFatin62c
 
air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) Rhitesh Gupta
 
Instalação em terminais _ Milton Roy
Instalação em terminais _ Milton RoyInstalação em terminais _ Milton Roy
Instalação em terminais _ Milton RoyVibropac
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualFatin62c
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfamgothusandeep
 
Valves in Pipelines-December 20150Final
Valves in Pipelines-December 20150FinalValves in Pipelines-December 20150Final
Valves in Pipelines-December 20150Finalgobindkhiani
 

Similar to SPM FHS SHUT DOWN REPORT (20)

4_5854850146042385629.pdf
4_5854850146042385629.pdf4_5854850146042385629.pdf
4_5854850146042385629.pdf
 
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETC
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETCFIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETC
FIRE WATER HOSE I ITS PART l HOSE CONNECTION I HOSE LAYING ETC
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
 
Control Valves
Control ValvesControl Valves
Control Valves
 
Hydraulic Ram Made from Standard Plumbing Parts
Hydraulic Ram Made from Standard Plumbing PartsHydraulic Ram Made from Standard Plumbing Parts
Hydraulic Ram Made from Standard Plumbing Parts
 
unlocked-461fd952f4656fee70de599ef77bd2ba.pptx
unlocked-461fd952f4656fee70de599ef77bd2ba.pptxunlocked-461fd952f4656fee70de599ef77bd2ba.pptx
unlocked-461fd952f4656fee70de599ef77bd2ba.pptx
 
Catalyst unloading details
Catalyst unloading detailsCatalyst unloading details
Catalyst unloading details
 
2 delugevalve a
2 delugevalve a2 delugevalve a
2 delugevalve a
 
VALVE AND TESTING.pdf
VALVE AND TESTING.pdfVALVE AND TESTING.pdf
VALVE AND TESTING.pdf
 
pipe friction for laminar
pipe friction for laminarpipe friction for laminar
pipe friction for laminar
 
Hydraulic Ram Made from Standard Plumbing Parts - University of Georgia
Hydraulic Ram Made from Standard Plumbing Parts - University of GeorgiaHydraulic Ram Made from Standard Plumbing Parts - University of Georgia
Hydraulic Ram Made from Standard Plumbing Parts - University of Georgia
 
Leak Tests.pptx
Leak Tests.pptxLeak Tests.pptx
Leak Tests.pptx
 
sewage layy out lec
sewage layy out lecsewage layy out lec
sewage layy out lec
 
pipe friction for laminar
pipe friction for laminarpipe friction for laminar
pipe friction for laminar
 
air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump)
 
Instalação em terminais _ Milton Roy
Instalação em terminais _ Milton RoyInstalação em terminais _ Milton Roy
Instalação em terminais _ Milton Roy
 
8013 _0
8013  _08013  _0
8013 _0
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdf
 
Valves in Pipelines-December 20150Final
Valves in Pipelines-December 20150FinalValves in Pipelines-December 20150Final
Valves in Pipelines-December 20150Final
 

SPM FHS SHUT DOWN REPORT

  • 1.
  • 2. SPM #5 PERIODIC SHUT DOWN REPORT Page 1 of 12 OVERVIEW: Once in every three years the floating hoses are subjected detailed inspection to review condition of the hoses and the suitability to re-use the hoses. Any hose that shows any signs of deterioration is replaced. The ramification of a mid-cycle shut down cannot be overemphasized. The hoses are flushed out, disconnected from the SPM, towed to the shore side where the inspection regime is carried out and likewise re-commissioned. Inspection regime comprises of • Marine growth removal and cleaning • Visual inspection for cuts, abrasions, bulges, warning system ect. • Electrical continuity test • Hydrostatic test (including elongation check) • Vacuum test. MAINTENACE SCHEDULE OF FLOATING HOSE: HOSE TYPE* FOB MAIN LINE REDUCER TAIL TANKER RAIL Single / Double carcass (SPM 4&5) 12 Months 36 M then after annually. 36 M then after annually. 36 M then after annually. 12 Months *Double carcass hose is designed so that if the main carcass fails, the secondary carcass contains the leak and protects the ambient environment. An alarm system alerts the operator when the primary carcass fails. The first task is to disconnect the floating hoses from their connections and transfer them to the testing site, in a SAFE manner, without impacting the environment. The floating hoses are flushed through with sea water until they are rid of traces of oil, there after they are transferred to the testing area. DESCRIPTION OF LAYOUT The connection between pipe arm piping and tanker manifold consists of two(2) No. 20-Inch hose strings. The Inboard string is of total length 795 feet, while the Outboard string is of total length 835 feet, due to insertion of one additional 40 foot mainline hose. The Pipeline End Manifold (PLEM) is a subsea unit from which rise two subsea Hoses (pipe lines of 20”ø and 30”ø) to connect to the Multi- product Delivery Unit (MPDU) located on the top of the SPM. Each one of these pipes has two hydraulically operated butterfly vales connected, adjacent to the PLEM. The outlets from the MPDU are connected to the flexible hosing. All flexible hoses are of flange-ended construction. The first length of Flexible hose nearest to the SPM is known “FIRST OFF BOUY HOSE” (20”ø x 40’) that is a “half-floating” Hose of heavier construction electrically continuous to be fitted on J tube of SPM. This hose is followed by 15 lengths of FLOATING MAIN HOSE (20” ø X 40’) that are “fully-floating” and electrically continuous, next is 1 length of “fully-floating” REDUCER HOSE (20” ø >16” ø X 40’), next 3 lengths of “FLOATING TAIL HOSE” (16” ø X40’) electrically discontinuous and finally 1 length of “TANKER RAIL HOSE” (16”ø X 35’x 1) electrically discontinuous, that gets connected to the Tanker.
  • 3. SPM #5 PERIODIC SHUT DOWN REPORT Page 2 of 12 FLUSHING OPERATION FOR CRUDE OIL FLOATING HOSES: A suitable tanker requires to be identified for receiving the flushing slops from the floating hoses. The floating hoses are flushed with sea water taken from the fire line of the tanker. Standard fire line connections are 4” in diameter. The Tanker Rail Hoses are connected to the manifold in the tanker, leading to the SLOP Tanks. The 4” flexible hose is connected to the PLEM, the 30”ø valves and closed and the 24ø valves are kept open. The flushing commences at a low pressure and when slops are received on board the tanker, the pressure is increased to 4 Kg/cm2 . Flushing is carried out in 5 sessions each of 30 minute duration. Samples of the slops are drawn every 30 minutes to monitor the Slops. Once the Slop is “CLEAN” the Tanker rail hoses are disconnected and flanged and prepared for the towing operation. Depending on the tidal condition, the flushing hose will have to be disconnected and reconnected. The process described above is conventional procedure where the SPM does not have Surge Tank FLUSHING LINE DIAGRAM: SPM Inner Hose Outer Hose 20” PLEM v/v 30” v/v 30” v/v 12 SEABED 27m CD + Tide 4” isolation valve 4” Flushing Connections Flood Tide Ebb Tide 4” Flexible Hose 4” Flexible Hose Tanker end 4” line conn. 4” isolation valve MPDU PLEM
  • 4. SPM #5 PERIODIC SHUT DOWN REPORT Page 3 of 12 Informatively, surge tanks form an integral part of the discharge system that accommodates pressure surges. In case of a surge in line pressure, the surge relief valve set at 15Kg/cm2 releases the cargo into the surge tank. An alarm is activated when the surge tank come to 50% capacity and the system shuts down when the level reaches 75% capacity. A Wilden pump is also provided to transfer oil from the surge tank to the system. In the case the SPM has surge tanks a different procedure as described below can be adopted. SPM 5 has surge tanks and hence this procedure was adopted. The fire line of the tanker that is used for flushing operation is bifurcated into 1½”ø branches. These are connected to the surge line valves on the deck of the SPM. The interconnecting valve between the 24”ø subsea hoses (SSH) and the surge tank (Normally Open) are kept shut. The 20”ø and 30”ø are kept shut. The flushing seawater enters the system and enters the subsea hoses up to the 20”ø valve. Being heavier than oil, the sea water slowly displaces the oil in the subsea hoses. Displaced oil enters the MPDU and finally gets back to the tanker Slop Tanks. Flushing is carried out in 5 sessions each of 30 minute duration. Samples of the slops are drawn every 30 minutes to monitor the Slops. Once the Slop is “CLEAN” the Tanker rail hoses are disconnected and flanged and prepared for the towing operation. Quantity of liquid pumped to tanker should be about 250 KL per string. Advantages: Less man power required. Diving operation not required. Flushing can be continued without any breaks irrespective of tidal changes. Time saved about 1.5 days.
  • 5. SPM #5 PERIODIC SHUT DOWN REPORT Page 4 of 12
  • 6. SPM #5 PERIODIC SHUT DOWN REPORT Page 5 of 12 Once the Flushing operation is completed, the mooring hawser is disconnected and secured on the DSV deck. To facilitate easy towage to the testing site, the First off Buoy hoses, are secured to floating jackets. Recall that these hoses are “half-floating” and hence need these buoyancy jackets. The First off Buoy hoses are disconnected from the SPM “J” pipe Floating jackets secured on First off Buoy hoses First off Buoy hoses disconnected from SPM J pipe Towing: 6 ‘’ PP to be secured for both Inner and Outer Hoses. Remove Winker lights and secure on DSV. Connect Towing ropes on Tanker rail hose and FOB end. FOB hose end to be blind flanged, to prevent drift wood passing through the bore during towing. Floating Hose strings to be towed under supervision from SPM buoy to LOLO Jetty. Secure both strings to DSV at LOLO Jetty. Max. Towing speed not be exceeded by 05 Knots. Transferring Hoses to DSV deck All Hoses transferred on deck of DSV
  • 7. SPM #5 PERIODIC SHUT DOWN REPORT Page 6 of 12 Hoses transferred to the Jetty Lifting, Dismantling & Visual Inspection: Both Strings FOB and TRH to be pulled and secured on DSV deck. Floats to be disconnected from FOB. Dismantling can be started from any end preferably from TRH. Dismantling should be carried out individual strings. Each hoses dismantled to be marked with hose number and string(Inner/Outer). Hoses to be inspected for external damage. Marine Growth to be cleaned externally for inspection by Scrapper and wire brush. Hoses to be lifted only by using Spreader Bar. Do Not Use Wire Ropes For Lifting Hoses. Do Not Lift By Single Point Or By The Ends. ON SHORE INSPECTION: Inspect Floating Hoses both Internally and Externally for any Kinks, Deformation, Cracking, separation, cut marks, abrasion, corrosion spool piece/Flanges All repairable parts to be attended before re installation of hoses. In case of any major defects observed hoses can be rejected.
  • 8. SPM #5 PERIODIC SHUT DOWN REPORT Page 7 of 12 HYDRO TEST PROCEDURE: Place the hose on ground level as straight as possible on supports that permit the hose to be elongated freely. Blind both ends of the hoses with rated flanges. Fill the Hose with water through one side of the hose and vent air from other end. When constant stream of water is delivered through the venting side of the flange close the vent valve. Apply pressure of 0.7 bar and note the time. Measure the overall length of the hose assembly L1 (Example: L1 = 12.20 m) Increase the pressure over a period of 5 Min from 0.7 bar to half the rated pressure of hose. Hold the pressure for 30 Min, then reduce the pressure over a period of 5 Min to Zero bar. Raise the Pressure over a period of 5 Min to rated pressure of hose. Measure Length L2 (Example: L2 = 12.24 m) Reduce the pressure over a period of 5 Min to Zero Bar. After an interval of 15 Minutes, raise Pressure to 0.7 Bar. Measure overall length L3 (example: L3 = 12.20 m). Reduce the pressure to Zero then Drain the Hose. Measure L1, L2 and L3 are used to measure Temporary and permanent elongation. Temporary Elongation: T= {(L2-L1)/L1} X 100. Permanent Elongation: P= {(L3-L1)/L1} X 100. Hose Retirement Criteria: Temporary elongation (T) is > +2% of the Temporary elongation recorded during FAT (Tf) Permanent elongation (P) is > +2% of the Permanent elongation recorded during FAT (Pf)
  • 9. SPM #5 PERIODIC SHUT DOWN REPORT Page 8 of 12 VACUUM TEST PROCEDURE: Vacuum test to be carried out after hydrostatic pressure test and not more than four days. Blank off both end of the hose with transparent Perspex flange using a rubber gaskets to obtain seal and also secure with C- Clamp. Apply a vacuum of at least 510 mmHg and hold for 10 Min. Use a bright flashlight, or mirror to direct the sunlight, and examine the bore for, Blisters or bulges- these indicates the separation of lining from carcass. Bubbles of water appearing around the fitting area, or at any point along the bore, which indicates cuts and lining separation.
  • 10. SPM #5 PERIODIC SHUT DOWN REPORT Page 9 of 12 HOSE THAT FAILED DURING VACUUM TEST Internal implosion occurred at the location indicated by the arrow. Electrical Continuity Test: Hoses should be either electrically Continuous or Discontinuous. Resistance of hose should be measured by means of a 500 Volt Megger Continuous: The conductivity should be checked when the hose is under pressure and again after the completion of pressure test. The test to be conducted by connecting a wire to each flange to complete a circuit with a small 4.5 V battery and a 4V,3A lamp or by using Multi meter. Discontinuous: The discontinuous test should be carried out before or after the pressure test when hose is dry. The resistance of the hose should not be less than 25000 ohms. Assembly: Each Hose to be lowered on DSV deck as per serial number AS BUILT SHEET. New gaskets and studs to be used and tightened to the requisite torque Assembling of Break-away Coupling in between Reducer and Tail hose with proper gasket and studs (Direction of Flow to be checked prior installing). Support Buoy is to be fixed for Break Away coupling and FOB. Assembling of pick-up chains on tanker rail hose. Assembling of Butterfly Valve, Spool Piece and cam lock on other end of Tanker rail hose. Tightening of all studs of 150# and 300# series flanges to be done in sequence using a calibrated torque wrench as per following table. 20” X 150# flange Joints (Main line) 900 Nm 20” X 300# flange Joints ( Fob J tube end) 1100 Nm 16” X 150# flange Joints (Tail, Rail and Break away) 600 Nm.
  • 11. SPM #5 PERIODIC SHUT DOWN REPORT Page 10 of 12 AS BUILT SHEET FOR REFERENCE Pressure Testing Of Assembled Floating Hose String, Towing & FOB Connection : Assembled floating hose strings are to be pressure tested. Pressure test at 15 bars and held for one hour and observe for any pressure drop. If any pressure drop noticed, check the tightness of the hose and flange connection. If the pressure holds for one hour, slowly depressurize the floating hose string and blind end of the string. Upon satisfactory pressure testing, hoses can be towed back to SPM Buoy as per procedure. First Off Buoy hoses are to be connected to J pipe with new gaskets.
  • 12. SPM #5 PERIODIC SHUT DOWN REPORT Page 11 of 12 Pressure Testing Of Assembled FHS and System To PLEM: Moor the DSV by bow on SPM buoy and keep Tanker rail hose on deck of DSV for pressuring the FHS strings. Pressurize both floating hoses strings individually against the PLEM valves up to 15 bar and hold for one hour. Open both deck valve and centre chamber valve. Upon satisfactory completion of pressure test, depressurize the floating hoses strings slowly up to 10 Kg/cm2 and inspect the butterfly valve for any leak. If butterfly valve found satisfactory then release the pressure slowly. Lower the Tanker rail hose in water. SINGLE POINT MOORING BUOY (ELEVATION) Chamber valves Deck valves
  • 13. SPM #5 PERIODIC SHUT DOWN REPORT Page 12 of 12 SINGLE POINT MOORING BUOY (PLAN) RECOMMISSIONING OF SPM Open both deck valve and central chamber valves. Close surge valves on deck. Check High Pressure Unit oil level Accumulators pressure to be checked. HPU unit to be pressed up to 320 Bar. Open 30” Manually operated PLEM Valve. Open 12” valve to surge tanks for both inner and outer.
  • 15. Date Time Activity 7-Apr-15 Preparation for Flushing 1048 Hrs - 1536 Hrs Outer Strings Flushing Carried Out 1624 Hrs - 2048 Hrs. Inner Strings Flushing Carried Out 0800 Hrs - 1200 Hrs. FON Floats Installation & PPE Rope Secured. 1000 Hrs -1500 Hrs "J" tube- FOB Hose disconnection 1500 Hrs to 1630 Hrs FHS Both Strings Towed To LO-LO Jetty. 1715 Hrs - 2300 Hrs. Floating Hose Strings Lifting and Disconnection.(total 9 Hoses Disconnected) 0700 Hrs - 0900 Hrs. Floating Hose Strings Lifting and Disconnection.(total 4 Hoses Disconnected) 0930 Hrs - 2000 Hrs. Hydrostatic pressure Test , Vacuum Test, Electrical Continuity & Discontinuity Test Of All 13 Hoses 0600 - 2000 Hrs Lowering Of Hoses and Connection Of Hoses. 1800 hrs -2400 hrs 0000 hrs - 0300 hrs 0600 hrs - 0800 hrs Towing of both string to the SPM 1100 hrs -1900 hrs FOB Connection and Hydrotest of assembly 0900hrs -1200 hrs SPM pre-commissioning checks 1500 Hrs Tanker berthed at SPM ACTIVITY LOG-SHEET Hydro Test OF Both Strings 12-Apr-15 13-Apr-15 8-Apr-15 9-Apr-15 10-Apr-15 11-Apr-15
  • 16. TEST ACCEPTANCE CERTIFICATE Company Reliance Date 4/11/2015 Unit Section This is to certify that the Inner floating strings From First of buoy hose To Tanker rail hose Was tested as outlined below. Type of test Hydrostatic Location of test unit LO-LO jetty Maximum pressure recorded during test period 15 Kg/ cm2 Duration of Operation Time Date From 21:00 Hrs 4/11/2015 To 03:10 Hrs 4/12/2015 Filling of hose strings commenced at 21:00 Hrs 4/11/2015 Filling of hose strings Stopped at 22:45 Hrs 4/11/2015 Hydrostatic Pump Started at 22:45 Hrs 4/11/2015 Vent plug closed at 22:50 Hrs 4/11/2015 Time taken for building up pressure from 0 to 15 kg/cm2 22:45 to 00:01 Hrs Any Pressure drop noticed from 00:01 Hrs to 02:02 Hrs 0.5 Kg/cm2 Pressure released at 02:05 Hrs Attained ZERO pressure at 03:10 Hrs Instrument Details Mfg. Calibration date Pressure Gauge FGB March 31 2015 Completed & witnessed By RIL Rep. OSL Rep. SPM - 5 INNER STRING PRESSURE TEST Serial No. C130766
  • 17. TEST ACCEPTANCE CERTIFICATE Company Reliance Date 4/11/2015 Unit Section This is to certify that the Outer floating strings From First of buoy hose To Tanker rail hose Was tested as outlined below. Type of test Hydrostatic Location of test unit LO-LO jetty Maximum pressure recorded during test period 15 Kg/ cm2 Duration of Operation Time Date From 16:15 Hrs 4/11/2015 To 22:32 Hrs 4/11/2015 Filling of hose strings commenced at 16:15 Hrs 4/11/2015 Filling of hose strings Stopped at 19:30 Hrs 4/11/2015 Hydrostatic Pump Started at 19:30 Hrs 4/11/2015 Vent plug closed at 19:35 Hrs 4/11/2015 Time taken for building up pressure from 0 to 15 kg/cm2 19:30 to 20:30 Hrs Any Pressure drop noticed from 20:30 Hrs to 21:30 Hrs 0.5 Kg/cm2 Pressure released at 21:35 Hrs Attained ZERO pressure at 22:32 Hrs Instrument Details Mfg. Calibration date Pressure Gauge FGB March 31 2015 Completed & witnessed By RIL Rep. OSL Rep. SPM - 5 OUTER STRING PRESSURE TEST Serial No. C130760
  • 18. TEST ACCEPTANCE CERTIFICATE Company Reliance Date 4/12/2015 Unit Section This is to certify that the Inner floating strings From Tanker rail hose To PLEM Valve Was tested as outlined below. Type of test Leak Test Location of test unit SPM - 5 Maximum pressure recorded during test period 15 Kg/ cm2 Duration of Operation Time Date From 11:50 Hrs 4/12/2015 To 16:20 Hrs 4/12/2015 Filling of hose strings commenced at 11:50 Hrs 4/12/2015 Filling of hose strings Stopped at 12:55 Hrs 4/12/2015 Hydrostatic Pump Started at 12:55 Hrs 4/12/2015 Vent plug closed at 13:00 Hrs 4/12/2015 Time taken for building up pressure from 0 to 15 kg/cm2 12:55 to 14:15Hrs Any Pressure drop noticed from 14:15 Hrs to 15:15Hrs 0.5 Kg/cm2 Pressure released at 15:17 Hrs Attained ZERO pressure at 16:20 Hrs Instrument Details Mfg. Calibration date Pressure Gauge FGB 30.03.2015 Completed & witnessed By RIL Rep. OSL Rep. SPM - 5 INNER STRING SYSTEM PRESSURE TEST Serial No. C130766
  • 19. TEST ACCEPTANCE CERTIFICATE Company Reliance Date 4/12/2015 Unit Section This is to certify that the Outer floating strings From Tanker rail hose To PLEM Valve Was tested as outlined below. Type of test Leak Test Location of test unit SPM - 5 Maximum pressure recorded during test period 15 Kg/ cm2 Duration of Operation Time Date From 16:00 Hrs 4/12/2015 To 19:00 Hrs 4/12/2015 Filling of hose strings commenced at 16:00 Hrs 4/12/2015 Filling of hose strings Stopped at 16:30 Hrs 4/12/2015 Hydrostatic Pump Started at 16:30 Hrs 4/12/2015 Vent plug closed at 16:35 Hrs 4/12/2015 Time taken for building up pressure from 0 to 15 kg/cm2 16:30 to17:15 Hrs Any Pressure drop noticed from 17:15 Hrs to 18:15 Hrs 0.5 Kg/cm2 Pressure released at 18:15 Hrs Attained ZERO pressure at 19:00 Hrs Instrument Details Mfg. Calibration date Pressure Gauge FGB 30.03.2015 Completed & witnessed By RIL Rep. OSL Rep. SPM - 5 OUTER STRING SYSTEM PRESSURE TEST Serial No. C130760