SlideShare a Scribd company logo
1 of 49
1
FIRE DETECTION AND PROTECTION SYSTEM
2
CONTENTS
BLOCK DIAGRAM OF FDA SYSTEM
COMPONENTS USED IN FDA
WATER SPRAY SYSTEM
FOAM SYSTEM
FDPS PRESENT STATUS
3
Block diagram of FDA system
3
Input
Devices
Output
Devices
Control
Panel
Deluge valve
4
Components used in FDA
INPUTS & OUTPUTS
1.MSD(multi sensor detectors)
2.Heat detectors
3.Manual call points
4.Beam detector
5.LHS(linear heat sensing)cable
7.IR detectors
8.Hooter & Alarms
9.Foam system
5
Heat detector
MSD
6
6
Photoelectric smoke detector principal
 Uses a photocell coupled with a specific light source.
 Basically smoke entering the smoke detector chamber disrupts the light beam
causing an alarm signal to be initiated
 More sensitive to smoldering fires Smoke detection with selectable sensitivity from
1.5 to 3.7 % per ft. obscuration. Temperature sensitivity rating 57oC
1: optical chamber
2: cover
3: case moulding
4: Photodiode (detector)
5: infrared LED
7
Operate on the principle that the temperature in a room will increase
faster from fire than from atmospheric temperature, Will initiate an
alarm when the rise in temp. exceeds 12-15° F (8.3- 11.1° C) per
minute.
Fixed temperature is independent of rate of raise sensing and set
point is 68° C
Heat detector principle
8
MSD’S mounted in cable gallery Cable gallery sprinkler system
9
Beam detector & reflector
9
MCP
10
Probe type heat detector Linear heat sensing cable
11
12
S.No PLANT AREA TYPE OF DETECTORS
1. Main control room, Computer
room, Electronic cubicle
room, panel room
Combination of -
Photo electric type smoke detector (AFC, BFC)
2. Battery rooms and chemically
corrosive areas.
Heat detector (Corrosion resistant, Rate of rise of
temperature heat detector with fixed temperature setting.
3. Office rooms / storage rooms,
Switchgear rooms in main
Plant and outlying areas
Multi sensor detector
4. Cable gallery Multi sensor detectors and Linear heat sensor running
above all HV and LV power cable trays. Unless the vertical
distance between cable tray is less than 500 mm in which case
alternate trays (in addition to the top and bottom trays). The
optical smoke detector and LHS detectors along with
necessary number of interface units in the cable gallery will be
cross zoned to actuate the water spray system
Selection of Detectors for different Area
13
13
5. Coal Conveyors digital Linear heat sensor cable, infra red detectors.
water spray system is provided the LHS cable will be burnt
and short circuited to actuate the same
6. Dusty areas in coal handling
plants like crusher house
Flame proof manual call points.
7. Junction towers Flame proof heat detectors, flame proof manual call points
8. Hazardous plant areas such
as fuel oil / lube oil tanks
Probe type heat detector with fixed element and flame proof
MCP
14
CONTROL PANELS
MFAP (main fire alarm panel)
SFAP (Sub fire alarm panel)
RFAP (Repeater fire alarm panel)
CCAP (Control cum annunciation panel)
CFAP (Conventional fire alarm panel)
15
ALARM SILENCE- It is programmed to silence the audible hooter at field and allow strobe light to continue
(strobes still flashing) until acknowledge the fire alarm.
16
Fire Alarm Ack- acknowledges a Fire Alarm condition, logs the
acknowledge, silences the operator panel and all annunciator
tone alerts, and displays sequential alarm list
17
SUPV ACK acknowledges system supervisory conditions, logs the
acknowledge, silences the operator panel and all annunciator tone alerts, and
displays sequential supervisory condition list
18
SYSTEM TROUBLE ACK acknowledges system troubles, logs the
acknowledge, silences the operator panel and all annunciator tone alerts,
and displays sequential trouble list.
19
TG CONTROL
BUILDING
13.7M LEVEL
MSD=84/84
HD=22/22
MCP=1/1
HTR=1/1
RI=22/22
IS=4/4
CABLE=1583M
TG CONTROL
BUILDING
19.9M LEVEL
MSD=30/30
MCP=1/1
HTR=1/1
CABLE=403M
TG CONTROL
BUILDING
13.7 M INERT
GAS SYSTEM
MM=12/12
CM=12/12
ABS=6/6
MCP=6/6
DI=6/6
PDI=6/6
CABLE=83M
TG LOOP 1
20
TG CONTROL
BUILDING
23.0M LEVEL
MSD=41/41
MCP=1/1
HTR=1/1
CABLE=215
2.5SQ MM
CABLE=500
TG CONTROL
BUILDING (10.7M)
MSD=50/50
MCP=2/2
HTR=2/2
CABLE=403M
TG CONTROL
BUILDING
(6.9/6.1M)
MSD=56/56
MCP=1/7
HTR=1/7
HD=12/12
CABLE=632
TG CONTROL
BUILDING
6.9M INERT GAS
SYSTEM
MM=2/2
MCP=1/1
DI=1/1
PDI=1/1
TG LOOP 2
21
TG LOOP 3
TG CONTROL
BUILDING
(3.1M)
MSD=30/31
MCP=0/2
HTR=0/2
CABLE=401M
TG CONTROL
BUILDING (0.0M)
MSD=29/29
HD=19/19
HTR=1/5
MCP=1/5
INERT GAS
SYSTEM
CABLE=339M
TG CABLE GALERY
DV’S
10.7M DV=3/3
3.1M DV=3/3
19.9M DV=1/1
BCN 6A/B DV’S
(DV 2,3,4,5)=4/4
U#1 BIOLER
BURNER HVWS
DV’S=2/2
U#2 BIOLER
BURNER HVWS
DV’S=2/2
22
TG LOOP 4
BCN 6A/6B
(BUNKER FLOOR)
MM=16/16
IRD=0/4
EOL=12/12
LHS=690/690
DVCP NO 1 AT JNT 10=1/1
CABLE=1500/1500
23
TG LOOP 5
GIS BUILDING
MSD=29/29
MCP=6/6
HTR=6/6
HD=4/4
MM=2/2
CM=6/6
BM=1/1
DVCP FOR HVWS
FOR 125MVA
REACTOR
DVCP=1/1
MM=1/1
MM=1/1
DVCP FOR GIS
CABLE GALERY
DVCP=0/1
CM=0/1
MM=0/1
24
TG LOOP 6
HVWS DV’S NEAR
UNIT 1
TRANSFORMER
YARD
DV’S=0/13
MCP=1/2
HTR=1/2
CABLE=403M
25
TG LOOP 7
HVWS DV’S NEAR
UNIT 2
TRANSFORMER
YARD
DV’S=0/14
MCP=1/2
HTR=1/2
CABLE=403M
BCN 6A/B DV 6
=0/1
UNIT 2 TG 3.1M
CABLE GALERY DV
=0/1
26
ESP 1 SUB FIRE ALARM PANEL LOOP 1
ESP
CONTROL
BUILDING-2
MSD=30/28
MCP=4/4
MM=4/4
HTR=4/4
CM=4/4
DVCP FOR
MVWS OF
CABLE
SPREADER ESP 2
CM=0/2
MM=0/2
DVCP=0/1
DVCP FOR
MVWS OF
CONVEYOR
4A/B
(JNT8-JNT9)
CM=5/5
IRD=8/8
MM=19/19
DVCP=11/11
27
ESP 1 SUB FIRE ALARM PANEL LOOP 2
ESP CONTROL
BUILDING-1
MSD=30/30
MCP=4/4
MM=4/4
HTR=4/4
CM=4/4
DVCP FOR MVWS OF
CABLE SPREADERIN ESP
CONTROL
CM=0/1
MM=0/1
DVCP=0/1
CONVEYOR 5A/B
IR=4/4
MM=9/9
CM=5/5
EOL=5/5
DVCP=5/5
LHS=1200/1200
1.5SQ MM CAB=600/600
2.5SQ MM CAB=350/350
28
ESP 1 SUB FIRE ALARM PANEL LOOP 3
HCSD
MSD=32/32
MCP=0/5
HD=1/1
HT=0/5
CM=0/5
RI=0/5
RM=0/4
MM=0/1
DVCP=0/1
29
AHP
MSD=35/35
MCP=0/4
HD=6/6
HT=0/4
CM=0/4
MM=0/2
RI=0/4
RM=0/2
DVCP FOR
HVWS FOR AHP
TRANSFORMER
DVCP=0/2
WORK SHOP
MSD=0/15
MCP=0/2
MM=2
HTR=0/2
CM=0/2
BM=0/1
COMPRESSOR HOUSE
MSD=2/2
HTR=0/2
MCP=0/2
MM=2
RI=0/1
RM=0/3
CM=0/2
30
Manual Call Point (MCP)
31
Some body PULL DOWN the Manual Call Point (MCP) leaver,
then alarm came Fire alarm panel, By using key only we
normalize this MCP. Once open the key then lever will settled in
normal position.
32
First we press the ALARM SILENCE button in the panel, then
Alarm silence in progress.
Second we press the Fire acknowledge button in the panel, we
get the detailed alarm description
33
Particular alarm silence LED illuminated in the panel
34
After normalizing the MCP, Fire alarm is changed to normal alarm
35
After normal alarms came press the SYSTEM REST button in the panel,
“system reset in progress”
36
Normal alarms shows like this
37
For viewing the alarms history
Press the menu then display this page
38
By pressing the “next button” select the “Historical Logs”
display this page
39
By pressing the “Alarm log view”, Alarm log will displayed, press “page
down” we get the previous alarms
40
By pressing the “Trouble log view”, Trouble log will displayed,
press “page down” we get the previous troubles list
41
HVWS & MVWS
The system consists of Deluge valve, Isolation valves, Strainer, Spray nozzle, Quartzoid
bulb detector, Detecting & Protecting Pressure switch, Pressure gauge and pipes &
Fittings.
42
HVWS
WATER SPRAY SYSTEM
43
MVWS
44
INLET
OUTLET
IMPULSE
LINE
45
MVWS DV
DVCP
SOV
PRESS SWITCH
TRIM LINE
46
S.NO DELUGE VALVE AREA TOTAL COMPLETED
1 Generator Transformer Unit 1 &2 6 6
2 Spare GT 1 1
3 Station Transformer Unit 1 &2 2 2
4 Station Auxiliary Transformer unit 1 &2 2 2
5 Unit Transformer unit 1 &2 4 4
6 Unit Auxiliary Transformer unit 1 &2 4 4
7 Reactor Transformer GIS 1 1
8 Turbine Lube Oil Storage Tank & Purifier #1&2 2 2
9 Generator Seal Oil Tank & Cooler Assembly # 1&2 2 2
10 Clean & Dirty Oil Tank unit 1 &2 2 2
11 Boiler Feed Pumps Lube Oil Tanks Cooler & Consoles # 1&2 2 2
12 Boiler-Burner Elevation # 1&2 4 4
HVWS
47
MVWS
1 JNT-1E to JNT-3 (BCN 1E A/B to BCN 1A/B) 12 12
2 JNT-4 to JNT -10 (BCN-3 to BCN-5) 28 28
3 BCN 2A/B/C 3 2
4 Bunker -1 ( BCN-6) 3 3
5 Bunker -2 ( BCN-6) 3 2
6 CHP -1 Cable gallery 1 -
7 CHP -2 Cable gallery 1 -
8 HFO/LDO Tank (FOPH) 6 6
9 FOPH Cable gallery 1 1
10 ESP-1 &2 Cable gallery 2 2
11 WTP Cable gallery 1 1
12 ETP Cable gallery 1 1
13 ECP Cable gallery 1 1
14 TG Cable gallery 8 7
15 GIS Cable gallery 1 1
16 HCSD 1 1
17 Ash recovery Cable gallery 1 -
48
MSD SENSOR BASE PICS
49

More Related Content

Similar to fire fighting ppt sop.pptx

2000 Nissan Sentra Service Repair Manual.pdf
2000 Nissan Sentra Service Repair Manual.pdf2000 Nissan Sentra Service Repair Manual.pdf
2000 Nissan Sentra Service Repair Manual.pdffujskekdjdmkm3e
 
2000 nissan sentra service repair manual
2000 nissan sentra service repair manual2000 nissan sentra service repair manual
2000 nissan sentra service repair manualdfjjsjekfkskemme
 
2001 NISSAN SENTRA Service Repair Manual.pdf
2001 NISSAN SENTRA Service Repair Manual.pdf2001 NISSAN SENTRA Service Repair Manual.pdf
2001 NISSAN SENTRA Service Repair Manual.pdfxwm10319888
 
2001 nissan sentra service repair manual
2001 nissan sentra service repair manual2001 nissan sentra service repair manual
2001 nissan sentra service repair manualfjkskekxsdcmdmme
 
Burner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptBurner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptmkpq pasha
 
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptx
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptxUNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptx
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptxYudarliRodriguez
 
fire detection and alarm system
fire detection and alarm systemfire detection and alarm system
fire detection and alarm systemsingh1515
 
L3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxL3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxMarkWootton11
 
Crowcon Flamgard Plus Fixed Gas Detector - Spec Sheet
Crowcon Flamgard Plus Fixed Gas Detector - Spec SheetCrowcon Flamgard Plus Fixed Gas Detector - Spec Sheet
Crowcon Flamgard Plus Fixed Gas Detector - Spec SheetThorne & Derrick UK
 
Automatic gas detection system
Automatic  gas  detection  systemAutomatic  gas  detection  system
Automatic gas detection systemSayanSarkar55
 
K85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfK85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfSecorpSAS
 
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor Instructions To Use Electronic Controller Logik 25-S in Screw Compressor
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor Eaton Compressor & Fabrication
 

Similar to fire fighting ppt sop.pptx (20)

2000 Nissan Sentra Service Repair Manual.pdf
2000 Nissan Sentra Service Repair Manual.pdf2000 Nissan Sentra Service Repair Manual.pdf
2000 Nissan Sentra Service Repair Manual.pdf
 
2000 nissan sentra service repair manual
2000 nissan sentra service repair manual2000 nissan sentra service repair manual
2000 nissan sentra service repair manual
 
2001 NISSAN SENTRA Service Repair Manual.pdf
2001 NISSAN SENTRA Service Repair Manual.pdf2001 NISSAN SENTRA Service Repair Manual.pdf
2001 NISSAN SENTRA Service Repair Manual.pdf
 
2001 nissan sentra service repair manual
2001 nissan sentra service repair manual2001 nissan sentra service repair manual
2001 nissan sentra service repair manual
 
Burner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptBurner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-ppt
 
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptx
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptxUNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptx
UNA DISCUSIÓN TÉCNICA ACERCA DEL SISTEMA DE ADMINISTRACIÓN DE QUEMADOR.pptx
 
fire detection and alarm system
fire detection and alarm systemfire detection and alarm system
fire detection and alarm system
 
L3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptxL3 Unit 11 LO 3 Fire Systems Master .pptx
L3 Unit 11 LO 3 Fire Systems Master .pptx
 
13.Safety & navigation
13.Safety & navigation13.Safety & navigation
13.Safety & navigation
 
Crowcon Flamgard Plus Fixed Gas Detector - Spec Sheet
Crowcon Flamgard Plus Fixed Gas Detector - Spec SheetCrowcon Flamgard Plus Fixed Gas Detector - Spec Sheet
Crowcon Flamgard Plus Fixed Gas Detector - Spec Sheet
 
Automatic gas detection system
Automatic  gas  detection  systemAutomatic  gas  detection  system
Automatic gas detection system
 
K85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfK85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdf
 
9206Manual.pdf
9206Manual.pdf9206Manual.pdf
9206Manual.pdf
 
Fire alarm systems
Fire alarm systemsFire alarm systems
Fire alarm systems
 
Presentation1
Presentation1Presentation1
Presentation1
 
Fire suppression
Fire suppressionFire suppression
Fire suppression
 
KTM LC4/LC8 Failure code
KTM LC4/LC8 Failure codeKTM LC4/LC8 Failure code
KTM LC4/LC8 Failure code
 
Solution Over View
Solution Over ViewSolution Over View
Solution Over View
 
Presentation1
Presentation1Presentation1
Presentation1
 
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor Instructions To Use Electronic Controller Logik 25-S in Screw Compressor
Instructions To Use Electronic Controller Logik 25-S in Screw Compressor
 

Recently uploaded

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 

Recently uploaded (20)

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 

fire fighting ppt sop.pptx

  • 1. 1 FIRE DETECTION AND PROTECTION SYSTEM
  • 2. 2 CONTENTS BLOCK DIAGRAM OF FDA SYSTEM COMPONENTS USED IN FDA WATER SPRAY SYSTEM FOAM SYSTEM FDPS PRESENT STATUS
  • 3. 3 Block diagram of FDA system 3 Input Devices Output Devices Control Panel Deluge valve
  • 4. 4 Components used in FDA INPUTS & OUTPUTS 1.MSD(multi sensor detectors) 2.Heat detectors 3.Manual call points 4.Beam detector 5.LHS(linear heat sensing)cable 7.IR detectors 8.Hooter & Alarms 9.Foam system
  • 6. 6 6 Photoelectric smoke detector principal  Uses a photocell coupled with a specific light source.  Basically smoke entering the smoke detector chamber disrupts the light beam causing an alarm signal to be initiated  More sensitive to smoldering fires Smoke detection with selectable sensitivity from 1.5 to 3.7 % per ft. obscuration. Temperature sensitivity rating 57oC 1: optical chamber 2: cover 3: case moulding 4: Photodiode (detector) 5: infrared LED
  • 7. 7 Operate on the principle that the temperature in a room will increase faster from fire than from atmospheric temperature, Will initiate an alarm when the rise in temp. exceeds 12-15° F (8.3- 11.1° C) per minute. Fixed temperature is independent of rate of raise sensing and set point is 68° C Heat detector principle
  • 8. 8 MSD’S mounted in cable gallery Cable gallery sprinkler system
  • 9. 9 Beam detector & reflector 9 MCP
  • 10. 10 Probe type heat detector Linear heat sensing cable
  • 11. 11
  • 12. 12 S.No PLANT AREA TYPE OF DETECTORS 1. Main control room, Computer room, Electronic cubicle room, panel room Combination of - Photo electric type smoke detector (AFC, BFC) 2. Battery rooms and chemically corrosive areas. Heat detector (Corrosion resistant, Rate of rise of temperature heat detector with fixed temperature setting. 3. Office rooms / storage rooms, Switchgear rooms in main Plant and outlying areas Multi sensor detector 4. Cable gallery Multi sensor detectors and Linear heat sensor running above all HV and LV power cable trays. Unless the vertical distance between cable tray is less than 500 mm in which case alternate trays (in addition to the top and bottom trays). The optical smoke detector and LHS detectors along with necessary number of interface units in the cable gallery will be cross zoned to actuate the water spray system Selection of Detectors for different Area
  • 13. 13 13 5. Coal Conveyors digital Linear heat sensor cable, infra red detectors. water spray system is provided the LHS cable will be burnt and short circuited to actuate the same 6. Dusty areas in coal handling plants like crusher house Flame proof manual call points. 7. Junction towers Flame proof heat detectors, flame proof manual call points 8. Hazardous plant areas such as fuel oil / lube oil tanks Probe type heat detector with fixed element and flame proof MCP
  • 14. 14 CONTROL PANELS MFAP (main fire alarm panel) SFAP (Sub fire alarm panel) RFAP (Repeater fire alarm panel) CCAP (Control cum annunciation panel) CFAP (Conventional fire alarm panel)
  • 15. 15 ALARM SILENCE- It is programmed to silence the audible hooter at field and allow strobe light to continue (strobes still flashing) until acknowledge the fire alarm.
  • 16. 16 Fire Alarm Ack- acknowledges a Fire Alarm condition, logs the acknowledge, silences the operator panel and all annunciator tone alerts, and displays sequential alarm list
  • 17. 17 SUPV ACK acknowledges system supervisory conditions, logs the acknowledge, silences the operator panel and all annunciator tone alerts, and displays sequential supervisory condition list
  • 18. 18 SYSTEM TROUBLE ACK acknowledges system troubles, logs the acknowledge, silences the operator panel and all annunciator tone alerts, and displays sequential trouble list.
  • 19. 19 TG CONTROL BUILDING 13.7M LEVEL MSD=84/84 HD=22/22 MCP=1/1 HTR=1/1 RI=22/22 IS=4/4 CABLE=1583M TG CONTROL BUILDING 19.9M LEVEL MSD=30/30 MCP=1/1 HTR=1/1 CABLE=403M TG CONTROL BUILDING 13.7 M INERT GAS SYSTEM MM=12/12 CM=12/12 ABS=6/6 MCP=6/6 DI=6/6 PDI=6/6 CABLE=83M TG LOOP 1
  • 20. 20 TG CONTROL BUILDING 23.0M LEVEL MSD=41/41 MCP=1/1 HTR=1/1 CABLE=215 2.5SQ MM CABLE=500 TG CONTROL BUILDING (10.7M) MSD=50/50 MCP=2/2 HTR=2/2 CABLE=403M TG CONTROL BUILDING (6.9/6.1M) MSD=56/56 MCP=1/7 HTR=1/7 HD=12/12 CABLE=632 TG CONTROL BUILDING 6.9M INERT GAS SYSTEM MM=2/2 MCP=1/1 DI=1/1 PDI=1/1 TG LOOP 2
  • 21. 21 TG LOOP 3 TG CONTROL BUILDING (3.1M) MSD=30/31 MCP=0/2 HTR=0/2 CABLE=401M TG CONTROL BUILDING (0.0M) MSD=29/29 HD=19/19 HTR=1/5 MCP=1/5 INERT GAS SYSTEM CABLE=339M TG CABLE GALERY DV’S 10.7M DV=3/3 3.1M DV=3/3 19.9M DV=1/1 BCN 6A/B DV’S (DV 2,3,4,5)=4/4 U#1 BIOLER BURNER HVWS DV’S=2/2 U#2 BIOLER BURNER HVWS DV’S=2/2
  • 22. 22 TG LOOP 4 BCN 6A/6B (BUNKER FLOOR) MM=16/16 IRD=0/4 EOL=12/12 LHS=690/690 DVCP NO 1 AT JNT 10=1/1 CABLE=1500/1500
  • 23. 23 TG LOOP 5 GIS BUILDING MSD=29/29 MCP=6/6 HTR=6/6 HD=4/4 MM=2/2 CM=6/6 BM=1/1 DVCP FOR HVWS FOR 125MVA REACTOR DVCP=1/1 MM=1/1 MM=1/1 DVCP FOR GIS CABLE GALERY DVCP=0/1 CM=0/1 MM=0/1
  • 24. 24 TG LOOP 6 HVWS DV’S NEAR UNIT 1 TRANSFORMER YARD DV’S=0/13 MCP=1/2 HTR=1/2 CABLE=403M
  • 25. 25 TG LOOP 7 HVWS DV’S NEAR UNIT 2 TRANSFORMER YARD DV’S=0/14 MCP=1/2 HTR=1/2 CABLE=403M BCN 6A/B DV 6 =0/1 UNIT 2 TG 3.1M CABLE GALERY DV =0/1
  • 26. 26 ESP 1 SUB FIRE ALARM PANEL LOOP 1 ESP CONTROL BUILDING-2 MSD=30/28 MCP=4/4 MM=4/4 HTR=4/4 CM=4/4 DVCP FOR MVWS OF CABLE SPREADER ESP 2 CM=0/2 MM=0/2 DVCP=0/1 DVCP FOR MVWS OF CONVEYOR 4A/B (JNT8-JNT9) CM=5/5 IRD=8/8 MM=19/19 DVCP=11/11
  • 27. 27 ESP 1 SUB FIRE ALARM PANEL LOOP 2 ESP CONTROL BUILDING-1 MSD=30/30 MCP=4/4 MM=4/4 HTR=4/4 CM=4/4 DVCP FOR MVWS OF CABLE SPREADERIN ESP CONTROL CM=0/1 MM=0/1 DVCP=0/1 CONVEYOR 5A/B IR=4/4 MM=9/9 CM=5/5 EOL=5/5 DVCP=5/5 LHS=1200/1200 1.5SQ MM CAB=600/600 2.5SQ MM CAB=350/350
  • 28. 28 ESP 1 SUB FIRE ALARM PANEL LOOP 3 HCSD MSD=32/32 MCP=0/5 HD=1/1 HT=0/5 CM=0/5 RI=0/5 RM=0/4 MM=0/1 DVCP=0/1
  • 29. 29 AHP MSD=35/35 MCP=0/4 HD=6/6 HT=0/4 CM=0/4 MM=0/2 RI=0/4 RM=0/2 DVCP FOR HVWS FOR AHP TRANSFORMER DVCP=0/2 WORK SHOP MSD=0/15 MCP=0/2 MM=2 HTR=0/2 CM=0/2 BM=0/1 COMPRESSOR HOUSE MSD=2/2 HTR=0/2 MCP=0/2 MM=2 RI=0/1 RM=0/3 CM=0/2
  • 31. 31 Some body PULL DOWN the Manual Call Point (MCP) leaver, then alarm came Fire alarm panel, By using key only we normalize this MCP. Once open the key then lever will settled in normal position.
  • 32. 32 First we press the ALARM SILENCE button in the panel, then Alarm silence in progress. Second we press the Fire acknowledge button in the panel, we get the detailed alarm description
  • 33. 33 Particular alarm silence LED illuminated in the panel
  • 34. 34 After normalizing the MCP, Fire alarm is changed to normal alarm
  • 35. 35 After normal alarms came press the SYSTEM REST button in the panel, “system reset in progress”
  • 37. 37 For viewing the alarms history Press the menu then display this page
  • 38. 38 By pressing the “next button” select the “Historical Logs” display this page
  • 39. 39 By pressing the “Alarm log view”, Alarm log will displayed, press “page down” we get the previous alarms
  • 40. 40 By pressing the “Trouble log view”, Trouble log will displayed, press “page down” we get the previous troubles list
  • 41. 41 HVWS & MVWS The system consists of Deluge valve, Isolation valves, Strainer, Spray nozzle, Quartzoid bulb detector, Detecting & Protecting Pressure switch, Pressure gauge and pipes & Fittings.
  • 46. 46 S.NO DELUGE VALVE AREA TOTAL COMPLETED 1 Generator Transformer Unit 1 &2 6 6 2 Spare GT 1 1 3 Station Transformer Unit 1 &2 2 2 4 Station Auxiliary Transformer unit 1 &2 2 2 5 Unit Transformer unit 1 &2 4 4 6 Unit Auxiliary Transformer unit 1 &2 4 4 7 Reactor Transformer GIS 1 1 8 Turbine Lube Oil Storage Tank & Purifier #1&2 2 2 9 Generator Seal Oil Tank & Cooler Assembly # 1&2 2 2 10 Clean & Dirty Oil Tank unit 1 &2 2 2 11 Boiler Feed Pumps Lube Oil Tanks Cooler & Consoles # 1&2 2 2 12 Boiler-Burner Elevation # 1&2 4 4 HVWS
  • 47. 47 MVWS 1 JNT-1E to JNT-3 (BCN 1E A/B to BCN 1A/B) 12 12 2 JNT-4 to JNT -10 (BCN-3 to BCN-5) 28 28 3 BCN 2A/B/C 3 2 4 Bunker -1 ( BCN-6) 3 3 5 Bunker -2 ( BCN-6) 3 2 6 CHP -1 Cable gallery 1 - 7 CHP -2 Cable gallery 1 - 8 HFO/LDO Tank (FOPH) 6 6 9 FOPH Cable gallery 1 1 10 ESP-1 &2 Cable gallery 2 2 11 WTP Cable gallery 1 1 12 ETP Cable gallery 1 1 13 ECP Cable gallery 1 1 14 TG Cable gallery 8 7 15 GIS Cable gallery 1 1 16 HCSD 1 1 17 Ash recovery Cable gallery 1 -
  • 49. 49