Planning and Project Controls 
under NEC4
Copyright @ 2011. All rights reserved
About the Speakers
Hezron Ricketts
 Senior Manager at Th3rd Curve
 Project Controls specialist
 Previously planning manager HS2
 Now Thames Tideway
`
Glenn Hide
 NEC management consultant
 Provide NEC training/consultancy
 NEC specialist resources
 Owner NEC People LinkedIn group
Copyright @ 2011. All rights reserved
Planning and Project Controls under NEC4
Contents
1. New NEC4 family of contracts
2. Programme requirements new to NEC4
3. Project Controls along side NEC4 – working and not 
working
4. Sources of support information
New members of the NEC4 family :
•Design Build and Operate 
Contract
•Alliance Contract
•Dispute Resolution Service 
Contract (revised)
•Professional Services 
Subcontract 
•Term Service Subcontract
Significant overhaul/structure
•Establishing a Procurement 
and Contract Strategy
•Selecting a Supplier
•Preparing a … contract
•Managing a … contract
No flow charts!
NEC4 Box 2 :
ECC Contract:
Main changes from a
planning perspective
Clause 13 - communication
• 13.2 – states if Scope confirms use
of contract administration tool, the
date of communication has effect
when entered into that system.
Otherwise as before the address as
stated in CD1
• 13.4 – amendment to wording that
requires Project Manager to confirm
reasons for rejection in sufficient
detail to allow the Contractor to
correct the matter
Clause 15(not 16) – Early Warnings
• 15.1 – introduces Early Warning
Register rather than Risk Register
• 15.2 – now obligates the Project
Manager to produce and issue the first
Early Warning Register within one week
of the starting date
• Project Manager also instructs
Contractor to attend first early warning
meeting within 2 weeks of starting date
• 15.2 confirms that later meetings will
be as instructed by either party, or at
intervals stated in Contract Data
• 15.2 states that Subcontractor
can attend if it would assist to
decide actions to be taken
• 15.3 – extra emphasis on early
warning meeting to review
previous actions and decide if any
different actions need to be taken
and who should take them
• 15.4 – obligation on Project
Manager to reissue Early Warning
Register within one week
Clause 15 - Early Warnings
Clause 16 – Contractor Proposals
• 16.1 – Contractor can propose to
Project Manager a change in
Scope in order to reduce the
amount the Client pays the
Contractor to provide the Works
• 16.2 – within four weeks the
Project Manager accepts the
proposal and issues instruction
changing Scope, instructs a
proposed quotation, or rejects
proposal
• 63.12 (A/B) confirms that changes to
Client Scope proposed by Contractor
and accepted, the Prices are reduced
by an amount calculated by applying
the value engineering percentage in
contract data (clients be careful you
get this the right way round!)
• 63.13 (C/D) verifies that change to
Client Scope proposed by Contractor
will NOT reduce the total of the Prices
– and so assessed as part of
gainshare
Clause 16 – Contractor Proposals
Section 3: Programme
• 31.2 - Only change to 31.2 is last line
“a programme issued for acceptance is
in the form stated in the Scope”
•
• 31.3 – If Project Manager fails to
respond to programme within two
weeks, Contractor can notify this non-
response. Failure to respond within
further one week by Project Manager
will mean that the programme is
“deemed accepted”.
• 32.1 – deleted requirement to show
implemented compensation events on
a revised programme
13
Contractor shown on each revised
programme:
• the actual progress achieved on
each operation and its effect upon
the timing of the remaining work
• implemented compensation events
• how the Contractor plans to deal
with any delays
• other changes the Contractor
proposes to make
NEC3 ECC Clause 32.1
NEC4
Section 3: Acceleration
• 36.1 – Project Manager can no longer
instruct quote for acceleration
• either party can propose, and if BOTH
are prepared to consider the change
then the Project Manager can instruct a
quotation to accelerate
• now there are timescales of up to
three weeks to produce quotation and
three weeks to reply
• also includes response to acceleration
quotation as core clause now
• 50.2 – obligates the Contractor to submit
applications detailing how they have been
assessed and in the form stated in the
Scope
• 50.4 – if the Contractor does not submit an
application then the amount due will either
be the amount at the previous application or
whatever the Project Manager assesses –
whichever is lower i.e. Contractor obligated
to put in an application if they want paying
that month!
• 50.5 – previously 50.3 where 25% can be
withheld for first programme not submitted
showing information contract requires
Section 5: Payments
Two new ones:
• 60.1(20) – Project Manager
notifies the Contractor that a
quotation for a proposed
instruction is not accepted
• 60.1(21) – additional
compensation events as stated
in contract data part 1
Section 6: Compensation
Events
• 61.4 response to notified compensation
event clarifies that if compensation not
notified within timescales of contract, the
Project Manager would confirm no
change to Prices/Key Date/ Completion
Date
• 63.1 – adds the term “dividing date” in
terms of actual/defined cost. Dividing
date is the date of the Project Manager
instruction/changed decision, or for all
other compensation events the dividing
date is the date the compensation event
is notified.
Section 6: Compensation
Events
• 63.5 (old 63.3) delay to Completion
Date assessed as the length of time
that due to the compensation event
planned Completion is later than
planned Completion as shown on the
Accepted Programme current at the
dividing date. Repeats for Key Dates.
• new sentence in 63.5: “When
assessing delay only those operations
which the Contractor has not completed
and which are affected by the
compensation event are changed” - ???
Section 6: Compensation
Events
NEC4 Practice Note 1 -
positives
• download a copy from gmhplanning
website or pick up a copy from our stand
today
• well written by four experienced
practitioners
• says what I have been saying in other
published articles in past ten years
• summary: whilst you use the last Accepted
Programme to assess compensation events
against, you first have to take into account
progress and other compensation events
that have occurred up to the dividing date
• this has been so late in coming!
• guidance notes are not part of the
contract
• still currently left with last line if 63.5
which we don’t know what it means
• only specifically written for NEC4 ECC,
although principles should be exactly
the same for NEC3 and all contracts
where a programme is operated
• potentially 1) contract clause 63.5,
2) guidance notes and 3) practice not
are not aligned with each other!
NEC4 Practice Note 1 -
negatives
This is a flavour of NEC4…
Full NEC4 comparison
document available to download
(for free) on our website for
ECC, TSC, PSC, ECS, ECSC
Hezron
Ricketts
th3rdcurve.com Where I have seen Project
Controls and the NEC working…
and not working together?
th3rdcurve.com
Why do some of our major projects and
programmes choose not to adopt true
controls and performance management
whilst using the NEC form of contract?
Ultimately when delivering projects the default position is that
Contract is King, to often the Commercial Argument takes
precedent over honest reporting and pushing the job forward.
A Lack of Understanding drives behaviours that cause us
to stay in our comfort zone despite the numbers telling us we
far from it. In addition the application of project controls
across our project follows No Industry Standard, this has
led to the production of a Lack of Clear, Consistent Data
with which to measure performance, subsequently
Confidence in applying proper controls with the contract isn’t
always the default choice.
Aren’t We Forgetting 
Something?
NEC4 & Project Controls
th3rdcurve.com
Contract is King…
or is it the Client?
• Project Control is mechanism for
us to ensure that we do what we
said we could
• to identify problems early enough to
minimise their impact
• to ensure those who gave the
remit to build something get what
they bargained for
• to keep the ratio of costs to benefits
within a realm that the client can
justify
th3rdcurve.com
• RESET
Regular programme acceptance effectively resets the
basis of measurement with each iteration, the
standard NEC contract does not dictate the use of a
baseline. Performance measurement is redundant.
So what’s the real issue?
• Programme
Submission
Acceptance
• Programme
Submission
Acceptance
• Programme
Submission
Acceptance
• Programme
Submission
Acceptance
Monthly
Process
Project
change
th3rdcurve.com
The Solution – “Performance
Measurement Baseline”
PM
B
Scope
Time
Cost
th3rdcurve.com
The Solution – “Performance
Measurement Baseline”
• Takes a snapshot of the first accepted
programme and locks it down
• Updated each period with Implemented
Compensation
• Matches change with an un-
progressed version of the original
programme
• Acts as a traditional baseline filling the
gap between the Starting Date and
Completion Date (and key dates, sectional
completions) with a full programme
th3rdcurve.com Requires Concurrent Update
Alongside PfA
• PMB
+ ICE’S
• PMB
+ ICE’S
• PMB
+ ICE’S
• PMB
+ ICE’S
So what’s the big deal?
NEC4 & Project Controls
The Cons
• Well, its twice the work isn’t it.
• General changes to the
programme outside of contract
change are not applied to the PMB.
• The impacts of CE’s can become
difficult to directly compare with a
PMB and the PfA.
• Requires more front end work to
set up integrated systems and
processes.
th3rdcurve.com
The Cons…Sorted
• Well, its twice the work isn’t it.
• Not really if we actually use those systems we put
more work into setting up.
• General changes to the programme outside of
contract change are not applied to the PMB.
• If we apply the usage of work and planning packages
these impacts can be minimized.
• The impacts of CE’s can become difficult to directly
compare with a PMB and the PfA.
• This is the essence of CE assessment and should be
where the focus of work is concentrated to agree
change.
• Requires more front end work to set up integrated
systems and processes.
• With the benefit of saving time throughout the lifetime
of the project.
th3rdcurve.com
4 things to consider
• The ethos of both PM and Contractor teams needs
to be to close out contract admin in a timely manner
There will be a “deemed acceptance” of the
programme if the Project Manager fails to
respond to the issued programme and a
subsequent reminder (GMHPlanning)
th3rdcurve.com
Contract Administration
• The collaboration of Controls (Planning,
Cost & Risk) and Commercial teams in the
assessment of changes is essential to
effectively forecast the full impact of changes,
in particular when trying to apply to both the
PfA, Last accepted programme and the PMB
th3rdcurve.com
Joint effort
th3rdcurve.com
Controls Integration
Schedule Estimate
Technical
Baseline – Work
Bank
WBS
CBS
OBS
Reporting
Performance
Analysis &
Reporting
Control
Accounts
Suppliers /
Finance Data
Risk &
Opportunity
Management
The behaviours around interpreting EV data
must be well educated throughout the
organisation and supply chain. The use of the
data will dictate the effectiveness of the
decision making off of the back of analysing
results.
th3rdcurve.com
Education
CLOSE OUT
BuiltIntelligence eLearning academy
NEC People LinkedIn forum
Q&A Portal – Reachback (&App)
GMH Planning website
Th3rd Curve website
Questions…
 www.th3rdcurve.co.uk
 www.gmhplanning.co.uk
 www.reachback.builtintelligence.com
 LinkedIn: BuiltIntelligence NEC People 
managing NEC3/NEC4 contracts

More Related Content

What's hot

Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3Project Controls Expo
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
Prequalification document(1)
Prequalification document(1)Prequalification document(1)
Prequalification document(1)Muhammad Akram
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 

What's hot (20)

Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Prequalification document(1)
Prequalification document(1)Prequalification document(1)
Prequalification document(1)
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Project procurement management PMBOK Sixth Edition
Project procurement management PMBOK Sixth EditionProject procurement management PMBOK Sixth Edition
Project procurement management PMBOK Sixth Edition
 

Similar to Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn Hide" and "Hezron Ricketts" at Project Controls Expo 2017, Arsenal Stadium, London

NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017Browne Jacobson LLP
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxMy own
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile ContractNUS-ISS
 
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...Project Controls Expo
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02jitendra kumar biswas
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aForbes Chanakira
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersReady to Train
 

Similar to Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn Hide" and "Hezron Ricketts" at Project Controls Expo 2017, Arsenal Stadium, London (20)

NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile Contract
 
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
NEC3 programme
NEC3 programmeNEC3 programme
NEC3 programme
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureProject Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)Basil Achie
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 

Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn Hide" and "Hezron Ricketts" at Project Controls Expo 2017, Arsenal Stadium, London

  • 2. Copyright @ 2011. All rights reserved About the Speakers Hezron Ricketts  Senior Manager at Th3rd Curve  Project Controls specialist  Previously planning manager HS2  Now Thames Tideway ` Glenn Hide  NEC management consultant  Provide NEC training/consultancy  NEC specialist resources  Owner NEC People LinkedIn group
  • 4. New members of the NEC4 family : •Design Build and Operate  Contract •Alliance Contract •Dispute Resolution Service  Contract (revised) •Professional Services  Subcontract  •Term Service Subcontract
  • 6. ECC Contract: Main changes from a planning perspective
  • 7. Clause 13 - communication • 13.2 – states if Scope confirms use of contract administration tool, the date of communication has effect when entered into that system. Otherwise as before the address as stated in CD1 • 13.4 – amendment to wording that requires Project Manager to confirm reasons for rejection in sufficient detail to allow the Contractor to correct the matter
  • 8. Clause 15(not 16) – Early Warnings • 15.1 – introduces Early Warning Register rather than Risk Register • 15.2 – now obligates the Project Manager to produce and issue the first Early Warning Register within one week of the starting date • Project Manager also instructs Contractor to attend first early warning meeting within 2 weeks of starting date • 15.2 confirms that later meetings will be as instructed by either party, or at intervals stated in Contract Data
  • 9. • 15.2 states that Subcontractor can attend if it would assist to decide actions to be taken • 15.3 – extra emphasis on early warning meeting to review previous actions and decide if any different actions need to be taken and who should take them • 15.4 – obligation on Project Manager to reissue Early Warning Register within one week Clause 15 - Early Warnings
  • 10. Clause 16 – Contractor Proposals • 16.1 – Contractor can propose to Project Manager a change in Scope in order to reduce the amount the Client pays the Contractor to provide the Works • 16.2 – within four weeks the Project Manager accepts the proposal and issues instruction changing Scope, instructs a proposed quotation, or rejects proposal
  • 11. • 63.12 (A/B) confirms that changes to Client Scope proposed by Contractor and accepted, the Prices are reduced by an amount calculated by applying the value engineering percentage in contract data (clients be careful you get this the right way round!) • 63.13 (C/D) verifies that change to Client Scope proposed by Contractor will NOT reduce the total of the Prices – and so assessed as part of gainshare Clause 16 – Contractor Proposals
  • 12. Section 3: Programme • 31.2 - Only change to 31.2 is last line “a programme issued for acceptance is in the form stated in the Scope” • • 31.3 – If Project Manager fails to respond to programme within two weeks, Contractor can notify this non- response. Failure to respond within further one week by Project Manager will mean that the programme is “deemed accepted”. • 32.1 – deleted requirement to show implemented compensation events on a revised programme
  • 13. 13 Contractor shown on each revised programme: • the actual progress achieved on each operation and its effect upon the timing of the remaining work • implemented compensation events • how the Contractor plans to deal with any delays • other changes the Contractor proposes to make NEC3 ECC Clause 32.1 NEC4
  • 14. Section 3: Acceleration • 36.1 – Project Manager can no longer instruct quote for acceleration • either party can propose, and if BOTH are prepared to consider the change then the Project Manager can instruct a quotation to accelerate • now there are timescales of up to three weeks to produce quotation and three weeks to reply • also includes response to acceleration quotation as core clause now
  • 15. • 50.2 – obligates the Contractor to submit applications detailing how they have been assessed and in the form stated in the Scope • 50.4 – if the Contractor does not submit an application then the amount due will either be the amount at the previous application or whatever the Project Manager assesses – whichever is lower i.e. Contractor obligated to put in an application if they want paying that month! • 50.5 – previously 50.3 where 25% can be withheld for first programme not submitted showing information contract requires Section 5: Payments
  • 16. Two new ones: • 60.1(20) – Project Manager notifies the Contractor that a quotation for a proposed instruction is not accepted • 60.1(21) – additional compensation events as stated in contract data part 1 Section 6: Compensation Events
  • 17. • 61.4 response to notified compensation event clarifies that if compensation not notified within timescales of contract, the Project Manager would confirm no change to Prices/Key Date/ Completion Date • 63.1 – adds the term “dividing date” in terms of actual/defined cost. Dividing date is the date of the Project Manager instruction/changed decision, or for all other compensation events the dividing date is the date the compensation event is notified. Section 6: Compensation Events
  • 18. • 63.5 (old 63.3) delay to Completion Date assessed as the length of time that due to the compensation event planned Completion is later than planned Completion as shown on the Accepted Programme current at the dividing date. Repeats for Key Dates. • new sentence in 63.5: “When assessing delay only those operations which the Contractor has not completed and which are affected by the compensation event are changed” - ??? Section 6: Compensation Events
  • 19.
  • 20.
  • 21. NEC4 Practice Note 1 - positives • download a copy from gmhplanning website or pick up a copy from our stand today • well written by four experienced practitioners • says what I have been saying in other published articles in past ten years • summary: whilst you use the last Accepted Programme to assess compensation events against, you first have to take into account progress and other compensation events that have occurred up to the dividing date
  • 22. • this has been so late in coming! • guidance notes are not part of the contract • still currently left with last line if 63.5 which we don’t know what it means • only specifically written for NEC4 ECC, although principles should be exactly the same for NEC3 and all contracts where a programme is operated • potentially 1) contract clause 63.5, 2) guidance notes and 3) practice not are not aligned with each other! NEC4 Practice Note 1 - negatives
  • 23. This is a flavour of NEC4… Full NEC4 comparison document available to download (for free) on our website for ECC, TSC, PSC, ECS, ECSC
  • 25. th3rdcurve.com Where I have seen Project Controls and the NEC working… and not working together?
  • 26. th3rdcurve.com Why do some of our major projects and programmes choose not to adopt true controls and performance management whilst using the NEC form of contract? Ultimately when delivering projects the default position is that Contract is King, to often the Commercial Argument takes precedent over honest reporting and pushing the job forward. A Lack of Understanding drives behaviours that cause us to stay in our comfort zone despite the numbers telling us we far from it. In addition the application of project controls across our project follows No Industry Standard, this has led to the production of a Lack of Clear, Consistent Data with which to measure performance, subsequently Confidence in applying proper controls with the contract isn’t always the default choice.
  • 28. th3rdcurve.com Contract is King… or is it the Client? • Project Control is mechanism for us to ensure that we do what we said we could • to identify problems early enough to minimise their impact • to ensure those who gave the remit to build something get what they bargained for • to keep the ratio of costs to benefits within a realm that the client can justify
  • 29. th3rdcurve.com • RESET Regular programme acceptance effectively resets the basis of measurement with each iteration, the standard NEC contract does not dictate the use of a baseline. Performance measurement is redundant. So what’s the real issue? • Programme Submission Acceptance • Programme Submission Acceptance • Programme Submission Acceptance • Programme Submission Acceptance Monthly Process Project change
  • 30. th3rdcurve.com The Solution – “Performance Measurement Baseline” PM B Scope Time Cost
  • 31. th3rdcurve.com The Solution – “Performance Measurement Baseline” • Takes a snapshot of the first accepted programme and locks it down • Updated each period with Implemented Compensation • Matches change with an un- progressed version of the original programme • Acts as a traditional baseline filling the gap between the Starting Date and Completion Date (and key dates, sectional completions) with a full programme
  • 32. th3rdcurve.com Requires Concurrent Update Alongside PfA • PMB + ICE’S • PMB + ICE’S • PMB + ICE’S • PMB + ICE’S
  • 33. So what’s the big deal? NEC4 & Project Controls
  • 34. The Cons • Well, its twice the work isn’t it. • General changes to the programme outside of contract change are not applied to the PMB. • The impacts of CE’s can become difficult to directly compare with a PMB and the PfA. • Requires more front end work to set up integrated systems and processes. th3rdcurve.com
  • 35. The Cons…Sorted • Well, its twice the work isn’t it. • Not really if we actually use those systems we put more work into setting up. • General changes to the programme outside of contract change are not applied to the PMB. • If we apply the usage of work and planning packages these impacts can be minimized. • The impacts of CE’s can become difficult to directly compare with a PMB and the PfA. • This is the essence of CE assessment and should be where the focus of work is concentrated to agree change. • Requires more front end work to set up integrated systems and processes. • With the benefit of saving time throughout the lifetime of the project. th3rdcurve.com
  • 36. 4 things to consider
  • 37. • The ethos of both PM and Contractor teams needs to be to close out contract admin in a timely manner There will be a “deemed acceptance” of the programme if the Project Manager fails to respond to the issued programme and a subsequent reminder (GMHPlanning) th3rdcurve.com Contract Administration
  • 38. • The collaboration of Controls (Planning, Cost & Risk) and Commercial teams in the assessment of changes is essential to effectively forecast the full impact of changes, in particular when trying to apply to both the PfA, Last accepted programme and the PMB th3rdcurve.com Joint effort
  • 39. th3rdcurve.com Controls Integration Schedule Estimate Technical Baseline – Work Bank WBS CBS OBS Reporting Performance Analysis & Reporting Control Accounts Suppliers / Finance Data Risk & Opportunity Management
  • 40. The behaviours around interpreting EV data must be well educated throughout the organisation and supply chain. The use of the data will dictate the effectiveness of the decision making off of the back of analysing results. th3rdcurve.com Education
  • 48.  www.th3rdcurve.co.uk  www.gmhplanning.co.uk  www.reachback.builtintelligence.com  LinkedIn: BuiltIntelligence NEC People  managing NEC3/NEC4 contracts