SlideShare a Scribd company logo
1 of 13
Paint Plant. Data Driven Quality
Performance Improvement .
September 2014 – January 2016
QUALITYQUALITY
Plan- GLOBAL 8D. Structured
Approach using 8 Disciplines.
D1. Form the Team.
Cross Functional selected from Paint and Maintenance
departments
1.Facilitator P.Cunningham.
2.Champions S.Fitter. Yogi Krawetz. P.Segui
DIRT 8D Team . Pre Clean, Base Coat, Lacquer, Polish,
Maintenance personnel and Paint Team Leader
Plan- GLOBAL 8D. Structured
Approach using 8 Disciplines.
D2. Describing the Problem.
1.Variable Right First Time Performance on painted Bodies
viewed at Gateway 3 Buy Off. During September 2014
Averaging 70 % Failures which required Paint repairs.
2. Highest RFT Failure Mode on bodies was for dirt. Dirt count
from 300 to 700 pieces on all panels around the body.
3.Variable ability to support track requirement which is
between 8-10 bodies per day. Track stoppages waiting for
Bodies to be available after Paint Combi repairs. Body bank
for track was empty. The Body bank should have a minimum
of 2 and a Maximum of 10 ready to go on Pre Mount.
4. Various opinions of where Dirt originates from.
Plan – Implement Gateway 3 RFT
Measuring from Week 33 2014
2014 to 2015 Week 33 to Week 52 RFT
Comparisons
wk 45 2014.Unable to carry
out cleaning procedures
during October shutdown
Plan – Analyse RFT Failures.
2014 to 2015 Comparisons
Count
PercentPaint Plant. Gateway 3 Defects
Count 3 1
Percent 34.319.7 17.914.9 5.7 3.6 1.8
115
0.9 0.9 0.3
Cum % 34.354.0 71.986.992.596.1
66
97.998.899.7100.0
60 50 19 12 6 3
Other
Sealer
Dry
Spray.( Inside
and
Out)
ContactDam
age
LO
B
PaintDam
age
Runs
Dent
Craters
Dirt
350
300
250
200
150
100
50
0
100
80
60
40
20
0
Paint RFT Failures weeks 33 to 52 2014
Count
Percent
Paint Plant. Gateway 3 Defects
Count 2 2 1 1 0
Percent 41 17 12 7
39
6 5 3 2 2 2 1 1 0
Cum %
16
41 58 69 77 83 88 92 94 96 98
11
99 100100
7 6 5 3 2
Other
Sags
( d/leg)
Gun
Spills
Sealer
Dry
Spray. ( Inside
and
Out)
Contact Dam
age
LO
B
Splashes
Dent
Prep
M
arks
Runs
PaintDam
age
Dirt
100
80
60
40
20
0
100
80
60
40
20
0
Paint RFT Failures weeks 33 to 52 2015
Wk 33 to 52 2014 – 374 RFT Fails to Combi
Average 21 Bodies per week
requiring Combi repairs
Wk 33 to 52 2014 – 374 RFT Fails to Combi
Average 21 Bodies per week
requiring Combi repairs
Wk 33 to 52 2015 – 95 RFT Fails to Combi
Average 5 Bodies per week
requiring Combi repairs
Wk 33 to 52 2015 – 95 RFT Fails to Combi
Average 5 Bodies per week
requiring Combi repairs
Do- GLOBAL 8D. Structured
Approach using 8 Disciplines.
D3. Containment.
Protecting the Customer. Our Customers are Gateway 3 Buy Off and
Pre Mount on the Track.
These are the Containment Actions that were implemented.
1.BIW – Green Room. A more thorough vacuum of bodies for iron
filings from BIW rework.
2.Post Scuff Booth blowing off of dust. Tak off Bodies inside and
out. Water Wash and Tak off bodies before going into Pre Clean
Room.
3.Pre Clean. Clean with White Spirit ,tak off and heat with infa red
lamp.
4.Base Coat .Final Tak, Base and Dry.
5.Lacquer booth . Dry , Tak and Lacquer.
Do- GLOBAL 8D Structured
Approach using 8 Diciplines
D4. Root Cause Analysis. Team Based Input.
Cause and Effects Dirt in Painted Parts. 17 High Ranked Potential Causes
Do.GLOBAL 8D.Structured
Approach using 8 Diciplines.
D4. Root Cause Analysis.
Areas of focus resulting from 17 Ranked High Potential Causes.
1.The condition of the Paint Facility through wear and tear
particularly through the aggressive nature of Lacquer.
2.Little or no Booth Cleaning Programme. No regular frequencies.
3.A review of Critical to Quality Maintenance. Inclusive of Base and
Lacquer fans that incur high build ups of paint material that lead to
fans being out of balance. This increases vibration of the booths
which leads to increases of dirt onto the vehicles from the ceilings
of Base Coat and Lacquer Booths.
4.Frequency and level of cleaning and re sealing of oven floor.
This is not structured or regular.
5. Lack of early warning “Trigger Points “ for Dirt levels that
could be increasing at Critical stages of Processing.
Do.GLOBAL 8D.Structured
Approach using 8 Diciplines.
D5.Permanent Corrective Actions.
1. Facility Deep Clean. Develop a working standard for elements that
were failing or broken. The initial 30% was carried out in September
2014. The remaining 70% carried out at Shutdowns in October,
Christmas and Easter 2015. Lessons learnt put into Maintenance
PPM’s schedules.
2. Development and Implementation of Pre Clean, Base Coat and
Lacquer booth Daily and Weekly Cleaning program.
3. Oven Maintenance . Weekly and Fortnightly vacuum and Floor
Resealing
4. Fortnightly Base Coat and Lacquer Fans cleaning. Continuous
rotation. Of fan cleaning.
5. Oven Floor repairs and re sealing around floor filters where floor
breaking away and increasing dirt levels.
6. Closed Door Policy introduced for all booth areas from BIW Combi
through paint plant to end of Oven. Doors are kept closed.
7. Better organisation of overalls and consumables for Spraying.
8. Clean up of Blowers and improved rotation for cleaning when fouled
with Base Coat and Lacquer paint.
Check.GLOBAL 8D.Structured
Approach using 8 Diciplines.
D6. Validation.
“ Being Proactive as opposed to Reactive”
1.Pre Start Checks on Critical to Quality Parameters. For Pre Clean
Room , Base Coat and Lacquer Booths.
2. Statistical Process Control chart ( SPC ) monitoring Twice Daily
After Lacquer v Post Oven Dirt counts on Bodies. Monitoring
Individual and Range . Identifying Trends.
3. Statistical Process Control chart ( SPC ) Chart monitoring Body
to Body dirt counts on Bodies at Gateway 3 Buy Off. Monitoring
Average and Range. Identifying Trends.
4. Use of Thermal Imaging camera inside oven weekly, to monitor
temperature levels and also to identify heat leaks.( cracks in oven
floor.)
Check.GLOBAL 8D.Structured
Approach using 8 Diciplines.
D6. Validation – Trigger Points.
Pre Start Checks. 07.00 Daily.
Pre Clean, Base Coat and Lacquer booths.
1.Walk and Audit .
2.Adhering to established Care Point
Standards
SPC.At Lacquer v Post Oven. Twice Daily. 2
Pts rising = STOP and validate Pre Clean to
Oven
SPC Body to Body Gateway 3. 4 Points rising
= STOP and Validate Pre Clean to Oven
Act..GLOBAL 8D.Structured
Approach using 8 Diciplines.
D7. Prevention. Using Data to make informed decision making.
“Being Proactive rather than Reactive”
1.Pre Start Checks on Critical to Quality Parameters. Stop / Fix
Approach. Pre Clean Room, Base Coat and Lacquer booths.
2.Statistical Process Control . (SPC) Dirt After Lacquer v Post Oven.
After Lacquer 50 pieces + 10 pieces. After Oven 150 pieces + 20 Max /
2 Points rising is a Stop / Validate Processes and Facility from Pre
Clean ,Base Coat, Lacquer and Oven.
3.Statistical Process Control. ( SPC ) Dirt Body to Body 150 pieces +
50 pieces / 4 Points rising or an extreme High Count is a Stop /
Validate Processes from Pre Clean, Base Coat ,Lacquer and Oven.
“Right Routines for the Right Reasons at the Right Time- Every Time!!!”
“We do not knowingly – Accept, create or pass on Defects.”
A Picture Says a Thousand Words.
Well Done the Team !!!!!!
D8.Congratulate the Team.

More Related Content

Similar to Paint Plant RFT Continuous Improvement Presentation (2) (2)

karthick resume
karthick resumekarthick resume
karthick resumekarthick N
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1Maricel Molina
 
Getting the lead out
Getting the lead outGetting the lead out
Getting the lead outjoshuaglazov
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
VRI project presentation Spool Throughput 2013
VRI project presentation Spool Throughput 2013VRI project presentation Spool Throughput 2013
VRI project presentation Spool Throughput 2013D9 Process Improvement
 
Cotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case StudyCotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case StudyJohn William
 
China-Retail-and-Product-Related-Issues New
China-Retail-and-Product-Related-Issues  NewChina-Retail-and-Product-Related-Issues  New
China-Retail-and-Product-Related-Issues Newkhaledali gap
 
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATION
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATIONRESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATION
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATIONMaypray Guimbarda
 
CARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCarpet America Recovery Effort
 
3 GIS QA Process - Denim
3  GIS QA Process - Denim3  GIS QA Process - Denim
3 GIS QA Process - DenimBarun Naha
 

Similar to Paint Plant RFT Continuous Improvement Presentation (2) (2) (20)

karthick resume
karthick resumekarthick resume
karthick resume
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1
 
Getting the lead out
Getting the lead outGetting the lead out
Getting the lead out
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
VRI project presentation Spool Throughput 2013
VRI project presentation Spool Throughput 2013VRI project presentation Spool Throughput 2013
VRI project presentation Spool Throughput 2013
 
Qit Powder Buster
Qit   Powder BusterQit   Powder Buster
Qit Powder Buster
 
Personal Resume of Darrell CordeiroV3
Personal Resume of Darrell CordeiroV3Personal Resume of Darrell CordeiroV3
Personal Resume of Darrell CordeiroV3
 
apea REV1
apea REV1apea REV1
apea REV1
 
Project Review Presentation (2)
Project Review Presentation (2)Project Review Presentation (2)
Project Review Presentation (2)
 
Cotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case StudyCotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case Study
 
Environmental Product Declarations and asphalt
Environmental Product Declarations and asphaltEnvironmental Product Declarations and asphalt
Environmental Product Declarations and asphalt
 
China-Retail-and-Product-Related-Issues New
China-Retail-and-Product-Related-Issues  NewChina-Retail-and-Product-Related-Issues  New
China-Retail-and-Product-Related-Issues New
 
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATION
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATIONRESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATION
RESUME OF QAQC INSPECTOR COATING/PAINTING AND INSULATION
 
PMG Newsletter (Volume 2. Issue 5)- DIGITAL.pdf
PMG Newsletter (Volume 2. Issue 5)- DIGITAL.pdfPMG Newsletter (Volume 2. Issue 5)- DIGITAL.pdf
PMG Newsletter (Volume 2. Issue 5)- DIGITAL.pdf
 
Portfolio
PortfolioPortfolio
Portfolio
 
Apea rev2
Apea rev2Apea rev2
Apea rev2
 
CARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the Pandemic
 
3 GIS QA Process - Denim
3  GIS QA Process - Denim3  GIS QA Process - Denim
3 GIS QA Process - Denim
 
Finishing manual
Finishing manualFinishing manual
Finishing manual
 

Paint Plant RFT Continuous Improvement Presentation (2) (2)

  • 1. Paint Plant. Data Driven Quality Performance Improvement . September 2014 – January 2016 QUALITYQUALITY
  • 2. Plan- GLOBAL 8D. Structured Approach using 8 Disciplines. D1. Form the Team. Cross Functional selected from Paint and Maintenance departments 1.Facilitator P.Cunningham. 2.Champions S.Fitter. Yogi Krawetz. P.Segui DIRT 8D Team . Pre Clean, Base Coat, Lacquer, Polish, Maintenance personnel and Paint Team Leader
  • 3. Plan- GLOBAL 8D. Structured Approach using 8 Disciplines. D2. Describing the Problem. 1.Variable Right First Time Performance on painted Bodies viewed at Gateway 3 Buy Off. During September 2014 Averaging 70 % Failures which required Paint repairs. 2. Highest RFT Failure Mode on bodies was for dirt. Dirt count from 300 to 700 pieces on all panels around the body. 3.Variable ability to support track requirement which is between 8-10 bodies per day. Track stoppages waiting for Bodies to be available after Paint Combi repairs. Body bank for track was empty. The Body bank should have a minimum of 2 and a Maximum of 10 ready to go on Pre Mount. 4. Various opinions of where Dirt originates from.
  • 4. Plan – Implement Gateway 3 RFT Measuring from Week 33 2014 2014 to 2015 Week 33 to Week 52 RFT Comparisons wk 45 2014.Unable to carry out cleaning procedures during October shutdown
  • 5. Plan – Analyse RFT Failures. 2014 to 2015 Comparisons Count PercentPaint Plant. Gateway 3 Defects Count 3 1 Percent 34.319.7 17.914.9 5.7 3.6 1.8 115 0.9 0.9 0.3 Cum % 34.354.0 71.986.992.596.1 66 97.998.899.7100.0 60 50 19 12 6 3 Other Sealer Dry Spray.( Inside and Out) ContactDam age LO B PaintDam age Runs Dent Craters Dirt 350 300 250 200 150 100 50 0 100 80 60 40 20 0 Paint RFT Failures weeks 33 to 52 2014 Count Percent Paint Plant. Gateway 3 Defects Count 2 2 1 1 0 Percent 41 17 12 7 39 6 5 3 2 2 2 1 1 0 Cum % 16 41 58 69 77 83 88 92 94 96 98 11 99 100100 7 6 5 3 2 Other Sags ( d/leg) Gun Spills Sealer Dry Spray. ( Inside and Out) Contact Dam age LO B Splashes Dent Prep M arks Runs PaintDam age Dirt 100 80 60 40 20 0 100 80 60 40 20 0 Paint RFT Failures weeks 33 to 52 2015 Wk 33 to 52 2014 – 374 RFT Fails to Combi Average 21 Bodies per week requiring Combi repairs Wk 33 to 52 2014 – 374 RFT Fails to Combi Average 21 Bodies per week requiring Combi repairs Wk 33 to 52 2015 – 95 RFT Fails to Combi Average 5 Bodies per week requiring Combi repairs Wk 33 to 52 2015 – 95 RFT Fails to Combi Average 5 Bodies per week requiring Combi repairs
  • 6. Do- GLOBAL 8D. Structured Approach using 8 Disciplines. D3. Containment. Protecting the Customer. Our Customers are Gateway 3 Buy Off and Pre Mount on the Track. These are the Containment Actions that were implemented. 1.BIW – Green Room. A more thorough vacuum of bodies for iron filings from BIW rework. 2.Post Scuff Booth blowing off of dust. Tak off Bodies inside and out. Water Wash and Tak off bodies before going into Pre Clean Room. 3.Pre Clean. Clean with White Spirit ,tak off and heat with infa red lamp. 4.Base Coat .Final Tak, Base and Dry. 5.Lacquer booth . Dry , Tak and Lacquer.
  • 7. Do- GLOBAL 8D Structured Approach using 8 Diciplines D4. Root Cause Analysis. Team Based Input. Cause and Effects Dirt in Painted Parts. 17 High Ranked Potential Causes
  • 8. Do.GLOBAL 8D.Structured Approach using 8 Diciplines. D4. Root Cause Analysis. Areas of focus resulting from 17 Ranked High Potential Causes. 1.The condition of the Paint Facility through wear and tear particularly through the aggressive nature of Lacquer. 2.Little or no Booth Cleaning Programme. No regular frequencies. 3.A review of Critical to Quality Maintenance. Inclusive of Base and Lacquer fans that incur high build ups of paint material that lead to fans being out of balance. This increases vibration of the booths which leads to increases of dirt onto the vehicles from the ceilings of Base Coat and Lacquer Booths. 4.Frequency and level of cleaning and re sealing of oven floor. This is not structured or regular. 5. Lack of early warning “Trigger Points “ for Dirt levels that could be increasing at Critical stages of Processing.
  • 9. Do.GLOBAL 8D.Structured Approach using 8 Diciplines. D5.Permanent Corrective Actions. 1. Facility Deep Clean. Develop a working standard for elements that were failing or broken. The initial 30% was carried out in September 2014. The remaining 70% carried out at Shutdowns in October, Christmas and Easter 2015. Lessons learnt put into Maintenance PPM’s schedules. 2. Development and Implementation of Pre Clean, Base Coat and Lacquer booth Daily and Weekly Cleaning program. 3. Oven Maintenance . Weekly and Fortnightly vacuum and Floor Resealing 4. Fortnightly Base Coat and Lacquer Fans cleaning. Continuous rotation. Of fan cleaning. 5. Oven Floor repairs and re sealing around floor filters where floor breaking away and increasing dirt levels. 6. Closed Door Policy introduced for all booth areas from BIW Combi through paint plant to end of Oven. Doors are kept closed. 7. Better organisation of overalls and consumables for Spraying. 8. Clean up of Blowers and improved rotation for cleaning when fouled with Base Coat and Lacquer paint.
  • 10. Check.GLOBAL 8D.Structured Approach using 8 Diciplines. D6. Validation. “ Being Proactive as opposed to Reactive” 1.Pre Start Checks on Critical to Quality Parameters. For Pre Clean Room , Base Coat and Lacquer Booths. 2. Statistical Process Control chart ( SPC ) monitoring Twice Daily After Lacquer v Post Oven Dirt counts on Bodies. Monitoring Individual and Range . Identifying Trends. 3. Statistical Process Control chart ( SPC ) Chart monitoring Body to Body dirt counts on Bodies at Gateway 3 Buy Off. Monitoring Average and Range. Identifying Trends. 4. Use of Thermal Imaging camera inside oven weekly, to monitor temperature levels and also to identify heat leaks.( cracks in oven floor.)
  • 11. Check.GLOBAL 8D.Structured Approach using 8 Diciplines. D6. Validation – Trigger Points. Pre Start Checks. 07.00 Daily. Pre Clean, Base Coat and Lacquer booths. 1.Walk and Audit . 2.Adhering to established Care Point Standards SPC.At Lacquer v Post Oven. Twice Daily. 2 Pts rising = STOP and validate Pre Clean to Oven SPC Body to Body Gateway 3. 4 Points rising = STOP and Validate Pre Clean to Oven
  • 12. Act..GLOBAL 8D.Structured Approach using 8 Diciplines. D7. Prevention. Using Data to make informed decision making. “Being Proactive rather than Reactive” 1.Pre Start Checks on Critical to Quality Parameters. Stop / Fix Approach. Pre Clean Room, Base Coat and Lacquer booths. 2.Statistical Process Control . (SPC) Dirt After Lacquer v Post Oven. After Lacquer 50 pieces + 10 pieces. After Oven 150 pieces + 20 Max / 2 Points rising is a Stop / Validate Processes and Facility from Pre Clean ,Base Coat, Lacquer and Oven. 3.Statistical Process Control. ( SPC ) Dirt Body to Body 150 pieces + 50 pieces / 4 Points rising or an extreme High Count is a Stop / Validate Processes from Pre Clean, Base Coat ,Lacquer and Oven. “Right Routines for the Right Reasons at the Right Time- Every Time!!!” “We do not knowingly – Accept, create or pass on Defects.”
  • 13. A Picture Says a Thousand Words. Well Done the Team !!!!!! D8.Congratulate the Team.