Plant layout and cost related to construction of a dairy or food industry
1. MINI PROJECT REPORT
BSC FOOD PROCESSING AND
QUALITY MANAGEMENT
SUBMITTED BY
Parvathy Nandana
Nandana Suresh
Tiny Shaju
Anitta PJ
Ajin Das
2. INTRODUCTION
The kerala co-operative milk marketing federation (KCMMF) know by it’s trade name milma . Is a
state government cooperative society established in 1980 headquartered in Thiruvananthapuram
.Milma is a state government cooperative owned by the Ministry of corporation, Government of
Kerala . The objective includes To channelise marketable surplus milk from the rural areas to urban
deficit areas to maximize the returns to the producer and provide quality milk and milk products to
the consumers.To carryout activities for promoting Production, Procurement, Processing and
Marketing of milk and milk products for economic development of the farming community To build
up a viable dairy industry in the State.
LOCATION
Wayanad dairy is located at chuzhali, kalpetta in wayanad district was established on 9th
October
2008. The dairy is located 1 ½ kilometres far from the town.
EMPLOYEE DETAILS
Selection of the employees is done by the HRD officer.In the industry permanant , contract,
and fixed period embloyees are working. The salary of the employees is dealing by the
finance department.
Permanent Employees
Embloyee details Salary/month
HR officer 60000
P&I officer 60000
Technical officer 60000
Technical
superintendent
55000
Quality assurance
officer
60000
Assistant quality
assurance officer
50000
Finance Manager 40000
Assistant finance
manager
30000
Dairy engineer 50000
Assistant dairy
engineer
45000
Purchase officer 45000
Purchase supervisor 30000
Marketing officer 45000
Marketing supervisor 25000
P&I senior supervisor 50000
P&I junior supervisor 45000
Technicians 35000
3. Lab technicians 45000
Total 8,30000
Temporary Embloyees
Embloyee details Salary
Office staff 15000
Laboratory
technicians
10000
Trainees 10000
Department staffs 10000
Total 45000
Contract embloyees
Embloyee details Salary/month
Tanker driver 15000
Technicians 25000
Cleaning staffs 10000
Gardener 10000
Canteen worker’s 15000
Production workers
(ladies)
16000
Production workers
(male)
20000
Total 1,11000
CONSTRUCTION
The foundation is laid and the building is constructed on a 40000 sq.ft. The labourers
required for the construction process are around 80 persons. The time required for the
construction is 6 months, where an engineer works planning the layout for 15 days. The list
of the construction materials, plumbing and electrical materials and the budget required for
the procurement of all these materials are as follows:
Sl.No Item Total
quantity
Cost
per
piece
Total
amount
1 Stones 10000 40 40000
2 Steel 12.2 t 6600 792000
3 Sand 12000cft 120 144000
4 Cement 1400bag 400 560000
5 Tiles 640 600000
6 Putti 85 bag 300 25500
7 Paint 110litre 4550 500500
4. 8 Plumbing
materials
110000
9 Lengthy
pipes
110nos 55000
10 Electric
materials
70000
11 Wood
and
furniture
materials
110
sheets
plywood
1lakh
Total 29,97000
STAFF REQUIREMENTS
Staff requirements are very important in milma industry for the identification and safety
purpose. All the staff requirements are stored in purchase section. The list of the staff
requirements are follows;
Sl.No Items Total Quantity Cost per price Total
1 Head cap 2000 5 10,000
2 Gloves 2000 10 25,000
3 Mask 1000 5 5000
4 Uniform 600 320 2,10,000
5 Lab coat 30 500 15000
Total 2,65,000
STATIONERY
Stationary refers to commercially manufactured writing materials, including cut paper,
envelopes, writing implements, continuous form paper and other office supplies. The list of
the stationary items are follows;
Sl.No Items Total Quantity Cost per piece Total Amount
1 Register 30 100 3000
2 A4 sheets 4packet 499 1996
3 Pen 50 nos 5 250
4 Pencil 25 5 125
5 Eraser 10 3 30
6 Sharpener 10 5 50
7 Stapler & pin 20 55 1100
8 File 200 15 300
5. 9 Notebook 50 20 1000
10 Scale 15 5 75
11 Correction pen 10 5 50
12 Gum 30 10 300
13 Chart 50 5 250
14 Paper punch 10 50 500
15 Thread 10nos 10 100
16 Tissue paper 2 box 265 530
17 Marker 50 10 500
18 Seal 30 100 3000
19 Ink 10 50 500
20 Scissorss 25 25 500
21 Sellotape
Total
50 20 1000
15156
CLEANING ESSENTIALS
Most of the cleaning agents or hard-surface cleaners are substances used to remove dirt,
including dust, stains, foul odors, and clutter on surfaces. Purposes of cleaning agents
include health, beauty, removing offensive odor, and avoiding the spread of dirt and
contaminants to oneself and others.
Sl
No
Items Total
quantity
Coast
per
piece
Total
amount
1 Alkali
caustic
soda
100kg 50₹ 5000₹
2 Acid -
nitric acid
100kg 35 3500₹
3 Mop 30 130₹ 3900₹
4 Wiper 50 229₹ 10450₹
5 Broom 50 70₹ 3500₹
6 Floor Mat 70 180₹ 12600₹
7 Dust pan 30 45₹ 1350₹
8 Dust bin 30 149₹ 4470₹
9 Harpic 60 194₹ 11640₹
10 Bucket 50 140₹ 170₹
11 Cup 50 50₹ 2500₹
12 Soap 60 45₹ 2700₹
13 Liquid
dish wash
50 209₹ 10450₹
14 Lizol 100 220₹ 22000₹
15 Dettol 100 214₹ 21400₹
16 Brush 50 140₹ 7000₹
6. 17 Hand
wash
50 96₹ 4800₹
18 Test tube
brush
70 5₹ 350₹
19 Towel 150 100₹ 15000₹
20 Tissue
paper
500 21₹ 10500₹
21 Cotton 50kg 80₹ 4000₹
22 Detergent
powder
80 kg 164₹ 13120₹
23 Scrub 100 10₹ 1000₹
Total 183100₹
VEHICLES
Transportation Of Milk And Milk Products From Dairy To Marketing Depots Under Milma
Wayanad Dairy On Contract Basis For A Period Of Four Years.There are 4 depots are there,
Nilambur, Ulliyeri, Malappuram.
SI.
No
No. Of
Torus
Cost per
vehicle
Total
amount
1 12 2700000 32400000
No. Of
milk
tanker
Cost per
vehicle
Total
amount
2 15 3500000 52500000
Total 8,49,00000
EQUIPMENTS
Most of the equipment used in Milma dairy follows latest technology and innovations
except some of them. The equipments and machinery selected for different products
manufacturing is from companies that sells high quality machines.According to the need
they change and adopt machines timely. All of the equipments are very efficient and in a
good condition.
EquipMents for Plant
Sl.No Total
quantity
Cost per
piece
Total amount
1. 2 75000 150000
2 2 4Lakh 8lakh
3 2 15lakh 30lakh
7. 4 2 2.5 lakh 5lakh
5 6 8lakh 48lakh
6 4 1lakh 4lakh
7 1 1lakh 1lakh
8 6 5.16lakh 30.96lakh
9 4 6 lakh 24lakh
10 2 2.35lakh 4.7lakh
11 2 2.76lakh 55.2lakh
21236000
Equipments for Curd production unit
Sl.No Item Total quantity Cost per
piece
Total
amount
1 Curd pasteurizer 1 6lakh 6lakh
2 Curd HMST 4 1lakh 4 lakh
Total 1000000
Equipments for Paneer production unit
Sl.No Item Total
quantity
Cost per
piece
Total
amount
1 Paneer vat 1 50000 50000
2 Paneer milk
pasteurizer
1 5.5lakh 5.5lakh
Total 600000
Equipments for Butter production unit
Sl.No Item Total quantity Cost per
piece
Total amount
1 Butter
churner
1 1.5lakh 1.5lakh
2 Pre melting
vat
1 1.36lakg 1.36lakh
3 Cream
storage tank
2 2lakh 4lakh
Total 686000
Equipments for lassi production unit
Sl.No Item Total quantity Cost per piece Total amount
1 Lassi storage
tank
2 5lakh 10lakh
8. Total 1000000
Equipments for Ghee production
Sl.No Item Total quantity Cost per piece Total
1 Ghee melting
vat
2 2lakh 4lakh
2 Storage tank 4 3.5lakh 14lakh
3 Clarifier 1 3lakh 3lakh
Total 2100000
Equipments for Peda production Unit
Sl.No Item Total quantity Cost per piece Total amount
1 Peda vat 6 2lakh 12lakh
2 Moulding
machine
4 2.75lakh 11lakh
3 Planetary
mixer
1 60000 60000
4 Form fill seal
machine
1 2lakh 2lakh
5 Printing
machine
1 2.50lakh 2.50lakh
Total 2810000
Equipments for Palada production unit
Sl.No Item Total quantity Cost per piece Total amount
1 Palada vat 6 80000 4.8lakh
2 Sugar melting
tank
1 1lakh 1lakh
Total 580000
Equipments for Ghee biscuit production unit
Sl.No Item Total quantity Cost per piece Total amount
1 Planetary
mixer
1 60000 60000
2 Weighing scale 1 5000 5000
3 Oven 1 2.40lakh 2.40lakh
4 Moulding
machine
1 3.6lakh 3.6lakh
Total 665000
Equipments for Mango bar production unit
9. Sl.No Item Total quantity Cost per
piece
Total
amount
1 Cream filling
Machine
1 2.35lakh 2.35lakh
2 Icecream mould 12 6000 72000
3 Glycoolers 2 1.40lakh 2.80lakh
4 Freezer 1 1.50lakh 1.50lakh
Total 737000
Equipments for RMRD Lab
Sl.No Item Total quantity Cost per piece Total amount
1 Hot air oven 2 1.80lakh 3.60lakh
2 Centrifuge 2 24000 48000
3 Water bath 1 40000 40000
4 Cooler 1 30000 30000
5 FTIR
milkoscanner
1 2lakh 2lakh
6 Pipettes 20 1500 30000
7 Burette 10 999 9990
8 Burette stand 2 580 1160
9 Ultra snap kit 1 1lakh 1lakh
10 Test tubes 80 250 20000
11 Test tube
stopper
100 80 8000
12 Butyrometer 10 800 8000
13 Conical flask 5 970 4850
14 Beaker 10 1250 12500
15 Beaker
(plastic)
20 150 3000
16 Gas cylinder 1 1500 1500
17 Test tube
holder
8 150 1200
Total 870200
Equipments for Microbiology lab
Sl no Item Total quantity Cost per piece Total amount
1 Hot air oven 4 1.80lakh 7.20lakh
2 Deep freezer 2 1.40lakh 2.8lakh
3 Cooler 2 30000 60000
4 Fridge 1 40000 40000
5 Incubator 1 125000 125000
6 Compound
microscope
1 3.5lakh 3.5lakh
10. 7 Autoclave 5 1lakh 5lakh
8 Microwave 1 11000 11000
9 Test tubes 40 250
10 Test tube
holder
4 150 600
11 Burette 5 999 4995
12 Burette stand 3 580 1740
13 Beaker 10 1250 12500
14 Conical flask 5 970 4850
15 Glass rod 5 120 600
16 Petriplates 60 400 24000
17 PC 1 30000 30000
Total 2165185
Equipments for product lab
Sl.No Item Total quantity Cost per piece Total amount
1 Test tube 50 250 12500
2 Test tube
stand
10 50 500
3 Petriplates 30 400 12000
4 Microwave 1 11000 11000
5 Burette 4 999 3996
6 Burette stand 2 580 1160
7 Water bath 1 40000 40000
8 PC 1 30000 30000
Total 111156
Equipments for R&D lab
Sl No Item Total quantity Cost per piece Total amount
1 Pressure
cooker
2 800 1600
2 Sauces pan 1 580 580
3 Serving bowl 4 350 1400
4 Wooden
spatula
2 80 160
5 Containers 20 40 800
6 Gas stove 1 2000 2000
7 Gas cylinder 1 3600 3600
8 Steel tray 2 250 500
9 Microwave
oven
1 11000 11000
10 Cooler 1 30000 30000
11. 11 Measuring
cylinder
1 380 380
12 Scissors 1 40 40
13 Knife 1 120 120
Total 52180
Equipments used in engineering section
Sl.No Item Total quantity Cost per
piece
Total amount
1 Boiler 2 12lakh 24lakh
2 Vapour compressed
refrigeration system
1 40lakh 40lakh
3 Generator 4 30lakh 12000000
Total 18400000
Grand total of the total equipments used in the plant = 5,30,12,721.
12. CHEMICALS USED
These are the chemicals used in the industry
S.no Iteams Total quantity Cost per piece Total amount
1 Sulphuric acid 5 bottle 200 1000
2 Nitric acid 5 bottle 450 2250
3 Amyl alcohol 5 bottle 230 1150
4 Methylene blue 5 bottle 100 500
5 Phenolphthalin 2 bottle 500 1000
6 Acetic acid 4 bottle 50 200
7 Gdl 5 KG 180 900
8 Vitamin a&e 10 200 2000
9 Aflatoxin test kit 10 22500 225000
10 Antibiotic test kit 10 20000 200000
11 Caustic soda 10 KG 66 660
12 Potassium sorbate 5 KG 650 3250
13 Calsium chloride 5 KG 14 70
14 Naoh 5 bottle 639 3195
Total 441175
S.no Cost per piece Total amount
1 Sulphuric acid 5 bottle 200 1000
2 Nitric acid 5 bottle 450 2250
3 Amyl alcohol 5 bottle 230 1150
4 Methylene blue 5 bottle 100 500
5 Phenolphthalin 2 bottle 500 1000
6 Acetic acid 4 bottle 50 200
7 Gdl 5 KG 180 900
8 Vitamin a&e 10 200 2000
9 Aflatoxin test kit 10 22500 225000
10 Antibiotic test kit 10 20000 200000
11 Caustic soda 10 KG 66 660
12 Potassium sorbate 5 KG 650 3250
13 5 KG 14 70
14 Naoh 5 bottle 639 3195
Total 441175
13. CONCLUSION
At the end of the project we got an idea about the dairy industry. The total construction
cost of the dairy is above 24 crore and for the working of the dairy they require lots of
amounts in a year that includes the salary of the embloyees, stationary purchase,
epuipment maintenance and etc.