Dominic Paione worked on restoring a vintage saxophone over several sessions between September 2011 and March 2012. He met with a project facilitator to learn how to strip down and repad the saxophone. Over multiple sessions, he stripped it down, removed old pads and cork, replaced them, and reassembled the lower and upper stacks. Later meetings focused on detecting and fixing leaks on the new pads. Finally, he stripped it down again for chemical cleaning, polished it, and fully reassembled the saxophone.
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
Project Work Log
1. Product Work Log
Name___DominicPaione________________________________________Date ________________
Product ___Restoration of vintage saxophone_________________________________________
Date/Time: 9/7/2011 Activity :Met with project facilitator Comment/Suggestions:
4:00-5:30 (PM)
Commentary: learned how to strip
down saxophone and repad using
alcohol lamp.
2. Date/Time: 9/12/2011 Activity :Worked on saxophone. Comment/Suggestions:
4:00-6:30 (PM)
Commentary: Stripped down the
saxophone, made and alcohol lamp,
removed old pads.
3. Date/Time: 9/13/2011 Activity :Worked on saxophone. Comment/Suggestions:
4:00-6:30 (PM)
Commentary: Put new pads on,
removed old cork, reassembled lower
stack.
4. Date/Time: 9/20/2011 Activity :Worked on saxophone. Comment/Suggestions:
4:00-6:30 (PM)
Commentary: reassembled upper stack,
replaced cork on neck piece.
5. Date/Time: 10/5/2011 Activity : met with project facilitator Comment/Suggestions:
4:00-5:30 (PM)
Commentary: discussed how to detect
and fix leaks on new pads.
6. Date/Time: 10/6/2011 Activity : Worked on saxophone Comment/Suggestions:
4:00-6:00 (PM)
Commentary: fixed leaks on upper
stack pads.
7. Date/Time: 10/7/2011 Activity : Worked on saxophone Comment/Suggestions:
4:00-6:00 (PM)
Commentary: fixed leaks on lower
stack pads. Replaced cork on neck
piece.
8. Date/Time: 2/13/2012 Activity : Worked on saxophone Comment/Suggestions:
4:30-6:00 (PM)
Commentary: stripped down
saxophone, chemical cleaned horn.
9. Date/Time: 3/6/2012 Activity : Worked on saxophone Comment/Suggestions:
4:30-6:00 (PM)
Commentary: polished and
reassembled saxophone.