15 Annual General
Meeting
CONSTRUCTION ASSOCIATION OF BHUTAN | 9TH MAY 2016 | BCCI
CONFERENCE HALL
Submission to Hon’ble
Prime Minister
1. Scores for fresh engineers and VTI
graduates in Evaluation Guidelines
•In the current evaluation system, fresh
engineers and VTI graduates do not fetch
points
•Only engineers with 3 years and above
experience fetch points
•Requested for a minimum of 5-10 points for
fresh engineers and VTI graduates
2. Evaluation report to be made
public
•Contractors not happy with the evaluation
report being not disclosed
•Requested for exhaustive evaluation report
•Report to be displayed in client’s notice board
and website
•Accords fairness and transparency
3. Late declaration of evaluation
report
•Some clients take very long to declare the
evaluation result
•Unlike large complex project, nothing to evaluate
•EMD in the form of mortgage is tied up with client
•Delay costing opportunity
•Evaluation report to be declared as soon as possible
4. Evaluation Criteria
•Financial aspect most important component of
current evaluation system
•Technical aspect is just a qualification criteria for
next stage
•To ensure quality, equal importance to be given to
both the aspects
•Proposed for 60 (financial) / 40 (technical) system
5. HR/ Equipments required as per
the specification and nature of work
•Some client agencies include non-required
HR/Equipments
•Such inclusions are tailored to suit some particular
firms
•Loophole for corruptive practices
•Discourage such practices
•Deployment of machineries throughout
construction period needed amendment
6. Use of labors in different sites within one
dzongkhag/labor has to exit and re-enter/labor
entry from any point
•Labor from one site cannot be transferred to
another site within a dzongkhag
•Labor has to exit and re-enter
•Labors cannot enter from any point convenient
•E.g Assam labors have to strictly enter via Gelephu
•Huge expenditure for contractors/time constraint
•Not conducive
7. Realistic Project Duration
•Project durations driven by factors such as
project deadline, fiscal year closing
•Contractors land up paying huge liquidity
damages
•Technical approach needs to be adopted for
estimation of project duration
8. Realistic Budget Estimate
•Budget estimate based on BSR by clients
•Bidders estimate based on actual market rates
•Mismatch leads to rejection of genuine bids
and often leads to re-tendering
•Adoption of standard approach for budget
estimate
•10% provision in estimate for unforeseen
contingencies
9. Detailed drawing & specification
of Items for Small tender
•Some client do not provide detailed drawings &
specifications for Small tender
•Such practices creates room for client to change the
scope of work, site, items
•Difficult for the contractor to execute the work
•Payment problems due to deviations
•Must provide all technical specifications & drawings
10.Revision in work ceiling for Small
Class
•Small Class allowed to execute 2 works within 4
million
•But its not possible to get 2 works meeting the
4 million ceiling
•Requested for 2 works with 4 million each
11.Deviation clause for Small Class
•Absence of deviation clause for small class
•Deviation occurs in small tenders also
•Absence of deviation has invited many
litigations
•Deviation clause to be incorporated
12.Escalation clause for Small Class
•Absence of escalation clause for small class
•Deviation occurs in small tenders also
•Absence of deviation has invited many
litigations
•Deviation clause to be incorporated
13.Differential Security
•Low quoted and unbalanced bid requires differential
security
•Some agencies require differential security for bids just
5% while some require for 13%
•Not uniform during implementation
•Lower limit be defined beyond which differential
security to be applied
•-20% margin to be applied for differential security
14.Re-tender
•Clients opt for re-tender if lowest bidder is
disqualified or bid price is slightly higher than
estimate
•Clients can re-tender if bid price is abnormally high
•If bid price within a tolerable range, re-tender
should not be initiated
•Upper limit to be defined beyond which re-tender
can be initiated
15.Lottery system for awarding of
Limited Tenders
•Clients invite bids from only few known bidders
•Those bidders are favoured
•Award system not fair and transparent
•Section 4.2.3.1 of PRR requires clients to invite for
all contractors within that dzongkhag
•Requested for strict compliance of the above clause
and introduction of lottery system of award
16.CPI instead of WPI for Price
Adjustment
•SBD mandates WPI to be used for price adjustment
•WPI is not applicable to Bhutan
•WPI do not cover transportation, tax etc
•CPI to be used for Bhutan
•Few agencies are already using CPI
•CPI not uniformly applied when only few agenices
entertain it
17.Time extension for deviated
works as per approved drawings
•Deviated works require allotment of additional time
•Early warning GCC 32.1 to 32.4 mandates
contractor to notify to the Project Manager
•If failed to notify within 30 days, the time extension
is not entertained
•The clause needs to amended
18.Bank Guarantee Charges
•Bank guarantee needs to be renewed every year
•Bank guarantee not as per the length of the project
•Contractors pay a huge amount in the form of bank
guarantee fees
•Bank guarantee to be issued as per the length of
the project
•Fees for the guarantee to be reduced
19.Community Contract
•Work ceiling for community contract is Nu. 1.5
Million
•Most works fall within this ceiling
•Large numbers of Small Contractors (3247)
•Small Contractors are deprive of work
opportunities
•Ceiling needs to be brought down to 0.5
million
20. Conflict of information in bidding data
sheet requirements and evaluation
parameters
•Requirements in bid data sheet appears to be
with lock out specifications
•Bids not meeting the requirements are treated
not responsive
•Direct abuse of evaluation parameters
•Such requirements are tailored to suit certain
bidders only
21. Department execution of
works/labor contract/machineries hiring
•Departmental execution permitted only if the
work is specialized in nature
•However, DoR execute works departmentally
irrespective of work being specialized in
nature
•Government loose huge money because such
works are neither time frame nor have budget
ceiling
22.CDCL
•Mandate of CDCL was to act as a lead agency
•Undertake works beyond the capacity of local
contractors
•Currently CDCL involved in works that can be
undertaken by local contractors
•Direct award of contracts to CDCL by some agencies
•Request for no direct award/have to go through
competitive bidding process
23. Gov. training slots to be extended to
private sectors
•Construction industry blamed for lack of
professionalism
•Capacity development required
•Any trainings related to construction sector be given
to CAB directly
24.Construction Development Fund
•SRL fund to be used as CDF
•The purpose of the CDF is therefore:
1. To finance development and promotional programs of the
Construction Industry
2. Facilitate those developmental activities that do not have budgetary
support from government or donors.
3. Make it available to the government in need for the improvement of
the construction based activities in the country.
•Requested Gov. for collection of 0.15% SRL with 2% TDS
•Source deduction of SRL by procuring agencies from first
running bill
25.Tender cost despite contractors
bearing the tender cost
•Tenders are available in most of client’s website
•Contractors download and print the documents
themselves
•The cost is born by contractors
•However, contractors still have to pay for the tender
cost
•Some clients ask for tender cost while some do not
•Not consistent and uniform
26.Uniform application of PRR
•Different agencies have their own way of
interpreting the provisions of PRR
•Rule accepted by one agency is not honored by
other agencies
•Confusion in the procurement system
27.Auditing
•Pvt. Limited companies require hiring of CA from
India for auditing
•Causes inconvenience and incurs huge expenditure
to contractors
•Requested for making the requirement of CA from
India be made optional
•Allow local private accounting firms to carry out the
auditing
28.Tax Assessment
•Tax assessment is delayed
•Often delayed for 1 to 2 years
•Contractors pay 24% penalty per annum on taxable
amount when the filing is wrong
•Huge penalties incurred
•Contractors can avoid penalties if the assessment is timely
•Also requested for inclusion of liquidated penalties under
expenditure
29.Establishment of Stone quarry and
Stone aggregate crushing plant
•All structures in Bumthang are to be build using
local materials and maintain traditional
architectural design
•This requires constant and huge amount of stone
and stone aggregates
•No quarry and aggregate plants
•Requesting government to setup such plants &
quarry
30.CDB renewal fees
•Substantial revision in CDB renewal fees was
unexpected
•Old fee was Nu. 400 for small class which was
revised to Nu. 8500
•Contractors request for revision
•To be brought down to 50% of current fee
31.Up-gradation of CDB certificate with
work in hand
•Contractors wishing to upgrade to higher class
requires to complete work in hand
•Such rules are not favorable
•A contractor with work in hand with project
duration of 2 or 3 years have to wait till the project
is complete
•Requested for discontinuation of the notification
from CDB
32.Locking of resources/Different set of HR &
Equipment required for every tender
•E-tool system requires contractors to commit new set of
resources for every new bid
•Any resources used for a bid is locked in the e-tool till the
evaluation is complete
•Large contractors can take up 5 projects at a time, so to
maintain 5 sets of HR/Equipments is not in the capacity of
any contractors
•Opportunity cost and overhead cost for contractors
•Request amendment
33.Strengthening of Construction
Association of Bhutan (CAB) office
•Members not happy with services of CAB
•Following initiatives and improvements recommended
1. Establishment of Training Wing (Manpower pooling)
2. Establishment of Commercial Wing (Hiring/Spare Parts/Repair &
Maintenance)
3. Any other activities to generate income for CAB
34.Establishment of CAB Service Center (18
Dzongkhags)
•Member requested for establisment of CAB Service
Centers during the dzongkhag tour
•Purpose was to reach out to every members in the far
flung dzongkhags
•And to support and provide services at dzonkhag level
35. Online Registration System by
CDB
•Launching of Online Registration system on 2nd day of
Annual General Meeting
•As a result following issues where important to be
discussed with CDB during 3rd day of the meeting
1. Clearance from CAB during the renewal of CDB Certificate
2. Contractors representatives in the CDB Board
3. Submission of Tax Clearance & declaration of employee’s provident fund
Thank you!

More Related Content

What's hot

Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
USFR Hot Topics and Updates
USFR Hot Topics and UpdatesUSFR Hot Topics and Updates
USFR Hot Topics and UpdatesDiane Bradley
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeepSandeep Yadav
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction ProvisionRichard Retita
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancygrahamelanders
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTADVj NiroSh
 
Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...Green Realtech Projects Pvt. Ltd
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...SSudhaVelan
 

What's hot (19)

Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
USFR Hot Topics and Updates
USFR Hot Topics and UpdatesUSFR Hot Topics and Updates
USFR Hot Topics and Updates
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction Provision
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancy
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
 
Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...
 

Viewers also liked

Viewers also liked (15)

Kecerdasan
KecerdasanKecerdasan
Kecerdasan
 
Higiene y seguridad
Higiene y seguridadHigiene y seguridad
Higiene y seguridad
 
Dzo Tour Presentation
Dzo Tour PresentationDzo Tour Presentation
Dzo Tour Presentation
 
Riesgos de higiene industrial
Riesgos de higiene industrialRiesgos de higiene industrial
Riesgos de higiene industrial
 
Rajendra kumar (4) (1)
Rajendra kumar (4) (1)Rajendra kumar (4) (1)
Rajendra kumar (4) (1)
 
Farnishwar Dehriya
Farnishwar DehriyaFarnishwar Dehriya
Farnishwar Dehriya
 
Puneet
PuneetPuneet
Puneet
 
Fab MeetUp Vol.5
Fab MeetUp Vol.5Fab MeetUp Vol.5
Fab MeetUp Vol.5
 
Competitive Differentiation
Competitive DifferentiationCompetitive Differentiation
Competitive Differentiation
 
Virtual corte natali lopez final.ppsx1
Virtual corte natali lopez final.ppsx1Virtual corte natali lopez final.ppsx1
Virtual corte natali lopez final.ppsx1
 
riesgo laboral
riesgo laboralriesgo laboral
riesgo laboral
 
Innovation Triggers
Innovation TriggersInnovation Triggers
Innovation Triggers
 
BLE Boot Camp
BLE Boot CampBLE Boot Camp
BLE Boot Camp
 
Job Design and Delegation
Job Design and DelegationJob Design and Delegation
Job Design and Delegation
 
Higiene industrial
Higiene industrial Higiene industrial
Higiene industrial
 

Similar to 15 Annual General Meeting Construction

Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx2ke21cv405
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017Saurabh
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 
Self Redevelopment of Housing Society
Self Redevelopment of Housing SocietySelf Redevelopment of Housing Society
Self Redevelopment of Housing SocietyKirti Jain
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02jitendra kumar biswas
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Add on Project.pptx
Add on Project.pptxAdd on Project.pptx
Add on Project.pptxKartikS19
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile ContractNUS-ISS
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxTTconstructionspvtlt
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016Sanjeewa Mahawedage
 

Similar to 15 Annual General Meeting Construction (20)

Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017
WealthZap Research Services-NBCC Ltd MultiBagger Recommendation for March-2017
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Self Redevelopment of Housing Society
Self Redevelopment of Housing SocietySelf Redevelopment of Housing Society
Self Redevelopment of Housing Society
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Final FRA
Final FRAFinal FRA
Final FRA
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Add on Project.pptx
Add on Project.pptxAdd on Project.pptx
Add on Project.pptx
 
iom case.pptx
iom case.pptxiom case.pptx
iom case.pptx
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile Contract
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
 

15 Annual General Meeting Construction

  • 1. 15 Annual General Meeting CONSTRUCTION ASSOCIATION OF BHUTAN | 9TH MAY 2016 | BCCI CONFERENCE HALL
  • 3. 1. Scores for fresh engineers and VTI graduates in Evaluation Guidelines •In the current evaluation system, fresh engineers and VTI graduates do not fetch points •Only engineers with 3 years and above experience fetch points •Requested for a minimum of 5-10 points for fresh engineers and VTI graduates
  • 4. 2. Evaluation report to be made public •Contractors not happy with the evaluation report being not disclosed •Requested for exhaustive evaluation report •Report to be displayed in client’s notice board and website •Accords fairness and transparency
  • 5. 3. Late declaration of evaluation report •Some clients take very long to declare the evaluation result •Unlike large complex project, nothing to evaluate •EMD in the form of mortgage is tied up with client •Delay costing opportunity •Evaluation report to be declared as soon as possible
  • 6. 4. Evaluation Criteria •Financial aspect most important component of current evaluation system •Technical aspect is just a qualification criteria for next stage •To ensure quality, equal importance to be given to both the aspects •Proposed for 60 (financial) / 40 (technical) system
  • 7. 5. HR/ Equipments required as per the specification and nature of work •Some client agencies include non-required HR/Equipments •Such inclusions are tailored to suit some particular firms •Loophole for corruptive practices •Discourage such practices •Deployment of machineries throughout construction period needed amendment
  • 8. 6. Use of labors in different sites within one dzongkhag/labor has to exit and re-enter/labor entry from any point •Labor from one site cannot be transferred to another site within a dzongkhag •Labor has to exit and re-enter •Labors cannot enter from any point convenient •E.g Assam labors have to strictly enter via Gelephu •Huge expenditure for contractors/time constraint •Not conducive
  • 9. 7. Realistic Project Duration •Project durations driven by factors such as project deadline, fiscal year closing •Contractors land up paying huge liquidity damages •Technical approach needs to be adopted for estimation of project duration
  • 10. 8. Realistic Budget Estimate •Budget estimate based on BSR by clients •Bidders estimate based on actual market rates •Mismatch leads to rejection of genuine bids and often leads to re-tendering •Adoption of standard approach for budget estimate •10% provision in estimate for unforeseen contingencies
  • 11. 9. Detailed drawing & specification of Items for Small tender •Some client do not provide detailed drawings & specifications for Small tender •Such practices creates room for client to change the scope of work, site, items •Difficult for the contractor to execute the work •Payment problems due to deviations •Must provide all technical specifications & drawings
  • 12. 10.Revision in work ceiling for Small Class •Small Class allowed to execute 2 works within 4 million •But its not possible to get 2 works meeting the 4 million ceiling •Requested for 2 works with 4 million each
  • 13. 11.Deviation clause for Small Class •Absence of deviation clause for small class •Deviation occurs in small tenders also •Absence of deviation has invited many litigations •Deviation clause to be incorporated
  • 14. 12.Escalation clause for Small Class •Absence of escalation clause for small class •Deviation occurs in small tenders also •Absence of deviation has invited many litigations •Deviation clause to be incorporated
  • 15. 13.Differential Security •Low quoted and unbalanced bid requires differential security •Some agencies require differential security for bids just 5% while some require for 13% •Not uniform during implementation •Lower limit be defined beyond which differential security to be applied •-20% margin to be applied for differential security
  • 16. 14.Re-tender •Clients opt for re-tender if lowest bidder is disqualified or bid price is slightly higher than estimate •Clients can re-tender if bid price is abnormally high •If bid price within a tolerable range, re-tender should not be initiated •Upper limit to be defined beyond which re-tender can be initiated
  • 17. 15.Lottery system for awarding of Limited Tenders •Clients invite bids from only few known bidders •Those bidders are favoured •Award system not fair and transparent •Section 4.2.3.1 of PRR requires clients to invite for all contractors within that dzongkhag •Requested for strict compliance of the above clause and introduction of lottery system of award
  • 18. 16.CPI instead of WPI for Price Adjustment •SBD mandates WPI to be used for price adjustment •WPI is not applicable to Bhutan •WPI do not cover transportation, tax etc •CPI to be used for Bhutan •Few agencies are already using CPI •CPI not uniformly applied when only few agenices entertain it
  • 19. 17.Time extension for deviated works as per approved drawings •Deviated works require allotment of additional time •Early warning GCC 32.1 to 32.4 mandates contractor to notify to the Project Manager •If failed to notify within 30 days, the time extension is not entertained •The clause needs to amended
  • 20. 18.Bank Guarantee Charges •Bank guarantee needs to be renewed every year •Bank guarantee not as per the length of the project •Contractors pay a huge amount in the form of bank guarantee fees •Bank guarantee to be issued as per the length of the project •Fees for the guarantee to be reduced
  • 21. 19.Community Contract •Work ceiling for community contract is Nu. 1.5 Million •Most works fall within this ceiling •Large numbers of Small Contractors (3247) •Small Contractors are deprive of work opportunities •Ceiling needs to be brought down to 0.5 million
  • 22. 20. Conflict of information in bidding data sheet requirements and evaluation parameters •Requirements in bid data sheet appears to be with lock out specifications •Bids not meeting the requirements are treated not responsive •Direct abuse of evaluation parameters •Such requirements are tailored to suit certain bidders only
  • 23. 21. Department execution of works/labor contract/machineries hiring •Departmental execution permitted only if the work is specialized in nature •However, DoR execute works departmentally irrespective of work being specialized in nature •Government loose huge money because such works are neither time frame nor have budget ceiling
  • 24. 22.CDCL •Mandate of CDCL was to act as a lead agency •Undertake works beyond the capacity of local contractors •Currently CDCL involved in works that can be undertaken by local contractors •Direct award of contracts to CDCL by some agencies •Request for no direct award/have to go through competitive bidding process
  • 25. 23. Gov. training slots to be extended to private sectors •Construction industry blamed for lack of professionalism •Capacity development required •Any trainings related to construction sector be given to CAB directly
  • 26. 24.Construction Development Fund •SRL fund to be used as CDF •The purpose of the CDF is therefore: 1. To finance development and promotional programs of the Construction Industry 2. Facilitate those developmental activities that do not have budgetary support from government or donors. 3. Make it available to the government in need for the improvement of the construction based activities in the country. •Requested Gov. for collection of 0.15% SRL with 2% TDS •Source deduction of SRL by procuring agencies from first running bill
  • 27. 25.Tender cost despite contractors bearing the tender cost •Tenders are available in most of client’s website •Contractors download and print the documents themselves •The cost is born by contractors •However, contractors still have to pay for the tender cost •Some clients ask for tender cost while some do not •Not consistent and uniform
  • 28. 26.Uniform application of PRR •Different agencies have their own way of interpreting the provisions of PRR •Rule accepted by one agency is not honored by other agencies •Confusion in the procurement system
  • 29. 27.Auditing •Pvt. Limited companies require hiring of CA from India for auditing •Causes inconvenience and incurs huge expenditure to contractors •Requested for making the requirement of CA from India be made optional •Allow local private accounting firms to carry out the auditing
  • 30. 28.Tax Assessment •Tax assessment is delayed •Often delayed for 1 to 2 years •Contractors pay 24% penalty per annum on taxable amount when the filing is wrong •Huge penalties incurred •Contractors can avoid penalties if the assessment is timely •Also requested for inclusion of liquidated penalties under expenditure
  • 31. 29.Establishment of Stone quarry and Stone aggregate crushing plant •All structures in Bumthang are to be build using local materials and maintain traditional architectural design •This requires constant and huge amount of stone and stone aggregates •No quarry and aggregate plants •Requesting government to setup such plants & quarry
  • 32. 30.CDB renewal fees •Substantial revision in CDB renewal fees was unexpected •Old fee was Nu. 400 for small class which was revised to Nu. 8500 •Contractors request for revision •To be brought down to 50% of current fee
  • 33. 31.Up-gradation of CDB certificate with work in hand •Contractors wishing to upgrade to higher class requires to complete work in hand •Such rules are not favorable •A contractor with work in hand with project duration of 2 or 3 years have to wait till the project is complete •Requested for discontinuation of the notification from CDB
  • 34. 32.Locking of resources/Different set of HR & Equipment required for every tender •E-tool system requires contractors to commit new set of resources for every new bid •Any resources used for a bid is locked in the e-tool till the evaluation is complete •Large contractors can take up 5 projects at a time, so to maintain 5 sets of HR/Equipments is not in the capacity of any contractors •Opportunity cost and overhead cost for contractors •Request amendment
  • 35. 33.Strengthening of Construction Association of Bhutan (CAB) office •Members not happy with services of CAB •Following initiatives and improvements recommended 1. Establishment of Training Wing (Manpower pooling) 2. Establishment of Commercial Wing (Hiring/Spare Parts/Repair & Maintenance) 3. Any other activities to generate income for CAB
  • 36. 34.Establishment of CAB Service Center (18 Dzongkhags) •Member requested for establisment of CAB Service Centers during the dzongkhag tour •Purpose was to reach out to every members in the far flung dzongkhags •And to support and provide services at dzonkhag level
  • 37. 35. Online Registration System by CDB •Launching of Online Registration system on 2nd day of Annual General Meeting •As a result following issues where important to be discussed with CDB during 3rd day of the meeting 1. Clearance from CAB during the renewal of CDB Certificate 2. Contractors representatives in the CDB Board 3. Submission of Tax Clearance & declaration of employee’s provident fund