SlideShare a Scribd company logo
1 of 34
Prof. Mohsin A Mulla
Assistant Professor, EE
SITCOE Yadrav
◦ Effects of power quality
◦ Power Quality definitions revisited
◦ What is needed for PQ monitoring ?
◦ GE Multilin’s solution
 PQMII
 EPM9000 series
◦ Summary
Monitor and Analyze Power Disturbances, Disruptions & Harmonics
Power Quality issues cause business problems
such as:
◦ Lost productivity, idle people and
equipment
◦ Lost orders, good will, customers and
profits
◦ Lost transactions and orders not being
processed
◦ Revenue and accounting problems
◦ Customer and/or management
dissatisfaction
◦ Overtime required to make up for lost work
time
According to Electric Light and Power Magazine, 30 to 40 Percent
of All Business Downtime Is Related to Power Quality Problems.
◦ The sensitivity of today’s electronic equipment
makes it susceptible to power disturbances
◦ For some devices, a momentary disturbance can
cause
 scrambled data
 interrupted communications
 a frozen mouse
 system crashes and equipment failure
◦ Berkeley Lab Study Estimates $80 Billion
Annual Cost of Power Interruptions …
Research News, Berkeley Lab, February 2,
2005
◦ $50 billon per year in the USA is lost as a
results of power quality breakdowns ….
Bank of America Report
◦ A manufacturing company lost more than $3
million one day last summer in Silicon Valley
when the “lights went out.” … New York
Times January 2000
◦ “A voltage sag in a paper mill can waste a
whole day of production - $250,000 loss” …
Business Week, June 17,, 1996
◦ Half of all computer problems and one-third
of all data loss can be traced back to the
power line … Contingency Planning
Research, LAN Times
◦ Lost production
◦ Scrap
◦ Costs to restart
◦ Labor costs
◦ Equipment damage and
repair
◦ Other costs
• High Cost Facilities
o Semiconductor plants
o Pharmaceuticals
o Data centers
• Medium Cost Facilities
o Automotive manufacturing
o Glass plants
o Plastics & Chemicals
o Textiles
IEEE Categories
Std 1159-1995
Short Duration
Variations
Typical
Duration
Instantaneous Sag 0.5 – 30 cycles
Momentary Sag 30 cycles – 3
sec
Temporary Sag 3 sec – 1 min
IEEE Categories
Std 1159-1995
Short Duration
Variations
Typical
Duration
Instantaneous Sag 0.5 – 30 cycles
Momentary Sag 30 cycles – 3
sec.
Temporary Sag 3 sec – 1 min.
Instantaneous Swell 0.5 – 30 cycles
Momentary Swell 30 cycles – 3
sec.
Temporary Swell 3 sec – 1 min.
IEEE Categories
Std 1159-1995
Short Duration
Variations
Typical
Duration
Instantaneous Sag 0.5 – 30 cycles
Momentary Sag 30 cycles – 3
sec.
Temporary Sag 3 sec – 1 min.
Instantaneous Swell 0.5 – 30 cycles
Momentary Swell 30 cycles – 3
sec.
Temporary Swell 3 sec – 1 min.
Momentary Interruptions 0.5 – 30 cycles
Temporary Interruptions 30 cycles – 3
sec.
IEEE Categories
Std 1159-1995
Long Duration
Variations
Typical
Duration
Sustained interruptions > 1 min
Under voltages > 1 min
Over voltages > 1 min
IEEE Categories
Std 1159-1995
Long Duration
Variations
Typical
Duration
Sustained interruptions > 1 min
Under voltages > 1 min
Over voltages > 1 min
Voltage imbalance Steady state
Waveform Distortion
IEEE Categories
Std 1159-1995
Long Duration
Variations
Typical
Duration
Sustained interruptions > 1 min
Under voltages > 1 min
Over voltages > 1 min
Voltage imbalance Steady state
Waveform Distortion
DC offset Steady state
Harmonics Steady state
Inter harmonics Steady state
For Electric Utilities Control of Voltage and Prevention of Outages is Power
Quality
Utility Sources
◦ Lightning
◦ PF Correction
Equipment
◦ Faults
◦ Switching
Internal Sources
• Individual Loads –Lighting, Elevators, Coolers,
HVAC
• Uninterruptible Power Supplies
• Variable Frequency Drives
• Battery Chargers
• Large Motors During Startup
• Electronic Dimming Systems
• Lighting Ballasts (esp. Electronic)
• Arc Welders, and Other Arc Devices
• Medical Equipment, e.g. MRIs and X-Ray
Machines
• Office Equipment and Computers
• Wiring
Typical problems Disturbance Type Possible Causes
Overheated neutral
Intermittent lock-ups
Frequency deviations
Steady-state Shared neutrals
Improper or inadequate wiring
High source impedance
SCR/Rectifiers and notching
Harmonics
Typical problems Disturbance Type Possible Causes
Overheated neutral
Intermittent lock-ups
Frequency deviations
Steady-state Shared neutrals
Improper or inadequate wiring
High source impedance
SCR/Rectifiers and notching
Harmonics
Interruption
Garbled data
Random increase in harmonics levels
Utility faults
Inrush currents
Inadequate wiring
Typical problems Disturbance Type Possible Causes
Overheated neutral
Intermittent lock-ups
Frequency deviations
Steady-state Shared neutrals
Improper or inadequate wiring
High source impedance
SCR/Rectifiers and notching
Harmonics
Interruption
Garbled data
Random increase in harmonics levels
Utility faults
Inrush currents
Inadequate wiring
Intermittent lock-ups
Lights flicker
Garbled data
Sags/Swell Source voltage variations
Inrush/surge currents
Inadequate wiring
Typical problems Disturbance Type Possible Causes
Overheated neutral
Intermittent lock-ups
Frequency deviations
Steady-state Shared neutrals
Improper or inadequate wiring
High source impedance
SCR/Rectifiers and notching
Harmonics
Interruption
Garbled data
Random increase in harmonics levels
Utility faults
Inrush currents
Inadequate wiring
Intermittent lock-ups
Lights flicker
Garbled data
Sags/Swell Source voltage variations
Inrush/surge currents
Inadequate wiring
Component failure
Dielectric breakdown
Lock-ups
Garbled data
Wavy CRTs
Impulses
EMI/RFI
Lightning
Load switching
Capacitor switching
Static discharge
Hand-held radios
Loose wiring/arcing
Typical problems Disturbance Type Possible Causes
Overheated neutral
Intermittent lock-ups
Frequency deviations
Steady-state Shared neutrals
Improper or inadequate wiring
High source impedance
SCR/Rectifiers and notching
Harmonics
Interruption
Garbled data
Random increase in harmonics levels
Utility faults
Inrush currents
Inadequate wiring
Intermittent lock-ups
Lights flicker
Garbled data
Sags/Swell Source voltage variations
Inrush/surge currents
Inadequate wiring
Component failure
Dielectric breakdown
Lock-ups
Garbled data
Wavy CRTs
Impulses
EMI/RFI
Lightning
Load switching
Capacitor switching
Static discharge
Hand-held radios
Loose wiring/arcing
Overheated transformers and motors
Voltage and current distortions
Garbled data
Lock-ups
Harmonics Electronic loads
SCR/rectifier
Source: EPRI, 1994
Spikes, 7%
Sags, 56%
Outages,
6%
Swells,
31%
Sags (Dips)
Associated with system faults
Switching of heavy loads
Starting of large motors
Swells
System fault conditions
Switching on a large capacitor bank
Switching off a large load
Textile Industry
Plastics Industry
Glass Industry
Process Industry
Semiconductors
$1k $10k $100k $1M $10M
Losses per Voltage Sag Event
Source: EPRI “The Economics of Custom Power”, IEEE T&D Show 2003
Momentary Outages
create problems when
computers and clocks
reset, equipment stalls,
and work stops.
High Speed Waveform Capture Is the Most Important PQ
Troubleshooting Tool
Continuous PQ Monitoring Detects, Records, and Leads
to the Prevention of PQ Problems
• Power Quality monitoring provides a continuous
“Health Check” of a facility’s power system … for
example:
o Harmonic interaction between loads and
power conditioning equipment spotted
o High Inrush currents from equipment
startup detected
o Transients from load switching are seen
• It provides data to see, diagnose and avert
looming problems – “like squeaky brakes on a
car”
o Trends can be detected
o JIT equipment maintenance programs
can be established
• It acts like a “Black Box” on an airplane to tell
you what, when, and where a Power Quality
event occurred … to prevent it from reoccurring
PQ Monitors must detect and
record the 7 types of PQ
problems
◦ Transients
◦ Interruptions
◦ Sag/Under Voltage
◦ Swell/Over Voltage
◦ Waveform Distortion
◦ Voltage Fluctuations
◦ Frequency Variations
These include Flicker and
Compliance to ITI(CBEMA), IEEE
and ISO Standards
Plus they must …
• Be easy to use
• Be Suitable for continuously
monitoring indoors and outdoors
• Interface with standard PQ analysis
Software…PQDif format
• Be fast enough to capture high
speed events that produce
equipment problems
• Have enough storage to save the
waveforms you need
• Have PQ analysis tools that
produce usable, actionable
recommendations
Source: AGA Brazil
Meter: EPM9650
Period: Jan 2005 – Dec
2005
Continuous Monitoring of the Station for PQ Problems
Equipment Interrupting
Voltage Sags as Recorded
Damage Inducing Voltage
Surges as Recorded
ITI Acceptable Power
Disturbance Envelope
GE Multilin provides the necessary tools for a successful PQ
disturbance analysis and allows users to take remedial actions
Accurate Measurement to
determine actual state
Examinations
Remedial actionsRemedy
Feels the pulse of the
power system network
Symptoms
High resolution recordings
for longer durations
GE Communicator
software
Diagnosis
If You Can’t Measure it You Can’t Manage
it
If You Can Measure it You Can Manage
it

More Related Content

Similar to Power Quality and Harmonics

Introduction to Power Quality
Introduction to Power QualityIntroduction to Power Quality
Introduction to Power QualitySteve Johnson
 
General: Power Quality Presentation
General: Power Quality PresentationGeneral: Power Quality Presentation
General: Power Quality PresentationStaco Energy
 
Power Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyPower Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyKetan Bhavsar
 
Over voltage protection pert. 6
Over voltage protection pert. 6Over voltage protection pert. 6
Over voltage protection pert. 6Novia Putri
 
Overview of power quality problems ppt
Overview of power quality problems pptOverview of power quality problems ppt
Overview of power quality problems pptMitesh Karmur
 
Power Quality Basics_Complex Compatibility_Aclara
Power Quality Basics_Complex Compatibility_AclaraPower Quality Basics_Complex Compatibility_Aclara
Power Quality Basics_Complex Compatibility_AclaraAclara
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationRekaNext Capital
 
Power quality disturbances
Power quality disturbancesPower quality disturbances
Power quality disturbancesManasKumarPatro
 
Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1 Dilip kumar
 

Similar to Power Quality and Harmonics (20)

UST Power Quality Basics
UST Power Quality BasicsUST Power Quality Basics
UST Power Quality Basics
 
Introduction to Power Quality
Introduction to Power QualityIntroduction to Power Quality
Introduction to Power Quality
 
General: Power Quality Presentation
General: Power Quality PresentationGeneral: Power Quality Presentation
General: Power Quality Presentation
 
Introduction to Power Quality Problems
Introduction to Power Quality ProblemsIntroduction to Power Quality Problems
Introduction to Power Quality Problems
 
Understanding power quality and its importantce
Understanding power quality and its importantceUnderstanding power quality and its importantce
Understanding power quality and its importantce
 
power_ quality
power_ qualitypower_ quality
power_ quality
 
Power quality
Power  qualityPower  quality
Power quality
 
Power Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyPower Quality Issues _Literature Survey
Power Quality Issues _Literature Survey
 
UNDERSTANDING POWER QUALITY AND ITS IMPORTANCE
UNDERSTANDING POWER QUALITY AND ITS IMPORTANCEUNDERSTANDING POWER QUALITY AND ITS IMPORTANCE
UNDERSTANDING POWER QUALITY AND ITS IMPORTANCE
 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
 
OM PRAKASH.pptx
OM PRAKASH.pptxOM PRAKASH.pptx
OM PRAKASH.pptx
 
Over voltage protection pert. 6
Over voltage protection pert. 6Over voltage protection pert. 6
Over voltage protection pert. 6
 
Power Quality
Power QualityPower Quality
Power Quality
 
Overview of power quality problems ppt
Overview of power quality problems pptOverview of power quality problems ppt
Overview of power quality problems ppt
 
Ups fundamentals dmrc
Ups fundamentals dmrcUps fundamentals dmrc
Ups fundamentals dmrc
 
Power Quality Basics_Complex Compatibility_Aclara
Power Quality Basics_Complex Compatibility_AclaraPower Quality Basics_Complex Compatibility_Aclara
Power Quality Basics_Complex Compatibility_Aclara
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for Instrumentation
 
Power quality disturbances
Power quality disturbancesPower quality disturbances
Power quality disturbances
 
Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1
 
An Overview of Power Quality
An Overview of Power QualityAn Overview of Power Quality
An Overview of Power Quality
 

More from Mohsin Mulla

Eiae unit 4 jointing of cables1
Eiae unit  4 jointing of cables1Eiae unit  4 jointing of cables1
Eiae unit 4 jointing of cables1Mohsin Mulla
 
Flow measurement in industries
Flow measurement in industriesFlow measurement in industries
Flow measurement in industriesMohsin Mulla
 
Under ground cables
Under ground cablesUnder ground cables
Under ground cablesMohsin Mulla
 
Electrical wiring plan for house
Electrical wiring plan for houseElectrical wiring plan for house
Electrical wiring plan for houseMohsin Mulla
 
Basics of Electrical wiring
Basics of Electrical wiring Basics of Electrical wiring
Basics of Electrical wiring Mohsin Mulla
 
Basics of Electric circuit theory
Basics of Electric circuit theoryBasics of Electric circuit theory
Basics of Electric circuit theoryMohsin Mulla
 
Electric network theorems
Electric network theoremsElectric network theorems
Electric network theoremsMohsin Mulla
 

More from Mohsin Mulla (7)

Eiae unit 4 jointing of cables1
Eiae unit  4 jointing of cables1Eiae unit  4 jointing of cables1
Eiae unit 4 jointing of cables1
 
Flow measurement in industries
Flow measurement in industriesFlow measurement in industries
Flow measurement in industries
 
Under ground cables
Under ground cablesUnder ground cables
Under ground cables
 
Electrical wiring plan for house
Electrical wiring plan for houseElectrical wiring plan for house
Electrical wiring plan for house
 
Basics of Electrical wiring
Basics of Electrical wiring Basics of Electrical wiring
Basics of Electrical wiring
 
Basics of Electric circuit theory
Basics of Electric circuit theoryBasics of Electric circuit theory
Basics of Electric circuit theory
 
Electric network theorems
Electric network theoremsElectric network theorems
Electric network theorems
 

Recently uploaded

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Power Quality and Harmonics

  • 1. Prof. Mohsin A Mulla Assistant Professor, EE SITCOE Yadrav
  • 2. ◦ Effects of power quality ◦ Power Quality definitions revisited ◦ What is needed for PQ monitoring ? ◦ GE Multilin’s solution  PQMII  EPM9000 series ◦ Summary Monitor and Analyze Power Disturbances, Disruptions & Harmonics
  • 3. Power Quality issues cause business problems such as: ◦ Lost productivity, idle people and equipment ◦ Lost orders, good will, customers and profits ◦ Lost transactions and orders not being processed ◦ Revenue and accounting problems ◦ Customer and/or management dissatisfaction ◦ Overtime required to make up for lost work time According to Electric Light and Power Magazine, 30 to 40 Percent of All Business Downtime Is Related to Power Quality Problems.
  • 4.
  • 5. ◦ The sensitivity of today’s electronic equipment makes it susceptible to power disturbances ◦ For some devices, a momentary disturbance can cause  scrambled data  interrupted communications  a frozen mouse  system crashes and equipment failure
  • 6. ◦ Berkeley Lab Study Estimates $80 Billion Annual Cost of Power Interruptions … Research News, Berkeley Lab, February 2, 2005 ◦ $50 billon per year in the USA is lost as a results of power quality breakdowns …. Bank of America Report ◦ A manufacturing company lost more than $3 million one day last summer in Silicon Valley when the “lights went out.” … New York Times January 2000 ◦ “A voltage sag in a paper mill can waste a whole day of production - $250,000 loss” … Business Week, June 17,, 1996 ◦ Half of all computer problems and one-third of all data loss can be traced back to the power line … Contingency Planning Research, LAN Times
  • 7. ◦ Lost production ◦ Scrap ◦ Costs to restart ◦ Labor costs ◦ Equipment damage and repair ◦ Other costs • High Cost Facilities o Semiconductor plants o Pharmaceuticals o Data centers • Medium Cost Facilities o Automotive manufacturing o Glass plants o Plastics & Chemicals o Textiles
  • 8. IEEE Categories Std 1159-1995 Short Duration Variations Typical Duration Instantaneous Sag 0.5 – 30 cycles Momentary Sag 30 cycles – 3 sec Temporary Sag 3 sec – 1 min
  • 9. IEEE Categories Std 1159-1995 Short Duration Variations Typical Duration Instantaneous Sag 0.5 – 30 cycles Momentary Sag 30 cycles – 3 sec. Temporary Sag 3 sec – 1 min. Instantaneous Swell 0.5 – 30 cycles Momentary Swell 30 cycles – 3 sec. Temporary Swell 3 sec – 1 min.
  • 10. IEEE Categories Std 1159-1995 Short Duration Variations Typical Duration Instantaneous Sag 0.5 – 30 cycles Momentary Sag 30 cycles – 3 sec. Temporary Sag 3 sec – 1 min. Instantaneous Swell 0.5 – 30 cycles Momentary Swell 30 cycles – 3 sec. Temporary Swell 3 sec – 1 min. Momentary Interruptions 0.5 – 30 cycles Temporary Interruptions 30 cycles – 3 sec.
  • 11. IEEE Categories Std 1159-1995 Long Duration Variations Typical Duration Sustained interruptions > 1 min Under voltages > 1 min Over voltages > 1 min
  • 12. IEEE Categories Std 1159-1995 Long Duration Variations Typical Duration Sustained interruptions > 1 min Under voltages > 1 min Over voltages > 1 min Voltage imbalance Steady state Waveform Distortion
  • 13. IEEE Categories Std 1159-1995 Long Duration Variations Typical Duration Sustained interruptions > 1 min Under voltages > 1 min Over voltages > 1 min Voltage imbalance Steady state Waveform Distortion DC offset Steady state Harmonics Steady state Inter harmonics Steady state For Electric Utilities Control of Voltage and Prevention of Outages is Power Quality
  • 14. Utility Sources ◦ Lightning ◦ PF Correction Equipment ◦ Faults ◦ Switching Internal Sources • Individual Loads –Lighting, Elevators, Coolers, HVAC • Uninterruptible Power Supplies • Variable Frequency Drives • Battery Chargers • Large Motors During Startup • Electronic Dimming Systems • Lighting Ballasts (esp. Electronic) • Arc Welders, and Other Arc Devices • Medical Equipment, e.g. MRIs and X-Ray Machines • Office Equipment and Computers • Wiring
  • 15. Typical problems Disturbance Type Possible Causes Overheated neutral Intermittent lock-ups Frequency deviations Steady-state Shared neutrals Improper or inadequate wiring High source impedance SCR/Rectifiers and notching Harmonics
  • 16. Typical problems Disturbance Type Possible Causes Overheated neutral Intermittent lock-ups Frequency deviations Steady-state Shared neutrals Improper or inadequate wiring High source impedance SCR/Rectifiers and notching Harmonics Interruption Garbled data Random increase in harmonics levels Utility faults Inrush currents Inadequate wiring
  • 17. Typical problems Disturbance Type Possible Causes Overheated neutral Intermittent lock-ups Frequency deviations Steady-state Shared neutrals Improper or inadequate wiring High source impedance SCR/Rectifiers and notching Harmonics Interruption Garbled data Random increase in harmonics levels Utility faults Inrush currents Inadequate wiring Intermittent lock-ups Lights flicker Garbled data Sags/Swell Source voltage variations Inrush/surge currents Inadequate wiring
  • 18. Typical problems Disturbance Type Possible Causes Overheated neutral Intermittent lock-ups Frequency deviations Steady-state Shared neutrals Improper or inadequate wiring High source impedance SCR/Rectifiers and notching Harmonics Interruption Garbled data Random increase in harmonics levels Utility faults Inrush currents Inadequate wiring Intermittent lock-ups Lights flicker Garbled data Sags/Swell Source voltage variations Inrush/surge currents Inadequate wiring Component failure Dielectric breakdown Lock-ups Garbled data Wavy CRTs Impulses EMI/RFI Lightning Load switching Capacitor switching Static discharge Hand-held radios Loose wiring/arcing
  • 19. Typical problems Disturbance Type Possible Causes Overheated neutral Intermittent lock-ups Frequency deviations Steady-state Shared neutrals Improper or inadequate wiring High source impedance SCR/Rectifiers and notching Harmonics Interruption Garbled data Random increase in harmonics levels Utility faults Inrush currents Inadequate wiring Intermittent lock-ups Lights flicker Garbled data Sags/Swell Source voltage variations Inrush/surge currents Inadequate wiring Component failure Dielectric breakdown Lock-ups Garbled data Wavy CRTs Impulses EMI/RFI Lightning Load switching Capacitor switching Static discharge Hand-held radios Loose wiring/arcing Overheated transformers and motors Voltage and current distortions Garbled data Lock-ups Harmonics Electronic loads SCR/rectifier
  • 20. Source: EPRI, 1994 Spikes, 7% Sags, 56% Outages, 6% Swells, 31% Sags (Dips) Associated with system faults Switching of heavy loads Starting of large motors Swells System fault conditions Switching on a large capacitor bank Switching off a large load
  • 21. Textile Industry Plastics Industry Glass Industry Process Industry Semiconductors $1k $10k $100k $1M $10M Losses per Voltage Sag Event Source: EPRI “The Economics of Custom Power”, IEEE T&D Show 2003
  • 22. Momentary Outages create problems when computers and clocks reset, equipment stalls, and work stops.
  • 23. High Speed Waveform Capture Is the Most Important PQ Troubleshooting Tool
  • 24. Continuous PQ Monitoring Detects, Records, and Leads to the Prevention of PQ Problems • Power Quality monitoring provides a continuous “Health Check” of a facility’s power system … for example: o Harmonic interaction between loads and power conditioning equipment spotted o High Inrush currents from equipment startup detected o Transients from load switching are seen • It provides data to see, diagnose and avert looming problems – “like squeaky brakes on a car” o Trends can be detected o JIT equipment maintenance programs can be established • It acts like a “Black Box” on an airplane to tell you what, when, and where a Power Quality event occurred … to prevent it from reoccurring
  • 25. PQ Monitors must detect and record the 7 types of PQ problems ◦ Transients ◦ Interruptions ◦ Sag/Under Voltage ◦ Swell/Over Voltage ◦ Waveform Distortion ◦ Voltage Fluctuations ◦ Frequency Variations These include Flicker and Compliance to ITI(CBEMA), IEEE and ISO Standards Plus they must … • Be easy to use • Be Suitable for continuously monitoring indoors and outdoors • Interface with standard PQ analysis Software…PQDif format • Be fast enough to capture high speed events that produce equipment problems • Have enough storage to save the waveforms you need • Have PQ analysis tools that produce usable, actionable recommendations
  • 26. Source: AGA Brazil Meter: EPM9650 Period: Jan 2005 – Dec 2005 Continuous Monitoring of the Station for PQ Problems
  • 27. Equipment Interrupting Voltage Sags as Recorded Damage Inducing Voltage Surges as Recorded ITI Acceptable Power Disturbance Envelope
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33. GE Multilin provides the necessary tools for a successful PQ disturbance analysis and allows users to take remedial actions Accurate Measurement to determine actual state Examinations Remedial actionsRemedy Feels the pulse of the power system network Symptoms High resolution recordings for longer durations GE Communicator software Diagnosis
  • 34. If You Can’t Measure it You Can’t Manage it If You Can Measure it You Can Manage it