Production Schedule
- 1. LaurenRosenfeld,Millie West, AlexPereira &Alex Dwyer
BTECNationalDiploma in Creative Media Production
Production Schedule
Planned date &
time
Whats planned to be
done & where
Who's responsible? Resources needed Changes made & why Date
completed
9.11.16 - 11:00 Initialmeeting LR, MW,AP,AD computer ,google
documents
Target audience changedto15-22
insteadof 18-30
9.11.16
10.11.16 - 11:00 Treatment LR, MW,AP,AD computer ,google
documents
Surnamesadded to characters. 17.11.16
14.11.16 - 10:00 Meeting2 LR, MW,AP,AD computer ,google
documents
14.11.16
14.11.16 - 12:00 Budget LR, MW,AP,AD Computer,google sheets. Added make up artist andbetter/
more professional equipment to be
used.
16.11.16
17.11.16 - 14:00 Script draft 1 LR, MW,AP,AD Computer,Google
documentsand lyrics
sheet
Includedanotherprop. A washing
basket.
28.11.16
- 2. LaurenRosenfeld,Millie West, AlexPereira &Alex Dwyer
BTECNationalDiploma in Creative Media Production
21.11.16 - 9:45 Meeting3 LR, MW,AP,AD Computer ,Google
Documents
Props include: Flowers anda washing
basket.
21.11.16
28.11.16 - 10:00 Meeting4 LR, MW,AP,AD Computer ,Google
Documents
28.11.16
21.11.16 - 3:00 Storyboard LR,, AD Pencil,paper 9.12.16
28.11.16 - 10:00 Script draft 2 LR, MW,AP,AD Computer ,Google
Documents
28.11.16
29.11.16 - 10:00 Script draft 3 LR,MW Computer ,Google
Documents
Scene order hasbeenchanged,asit
wasnot correct.
29.11.16
29.11.16 - 12:00 Locationscout form LR, MW,AP,AD Computer ,Google
Documents
14.12.16
5.12.15- 10:00 Meeting5 LR, MW,AP,AD Computer ,Google
Documents
Change offilming dates,from the 10th
and16th, to the 10th, 12th and13th.
5.12.16
5.12.16- 2:40 Site plan LR, MW,AP,AD Computer ,Google Slides 14.12.16
30.11.16 Risk assessment LR, MW,AP,AD Computer ,Google
Documents
1.12.16
1.12.16 - 3:00 Locationrelease form LR, MW,AP,AD Computer ,Google
Documents
8.12.16
- 3. LaurenRosenfeld,Millie West, AlexPereira &Alex Dwyer
BTECNationalDiploma in Creative Media Production
1.12.16 - 3:00 Talentrelease forms LR, MW,AP,AD Computer ,Google
Documents
5.12.16
2.12.16- 2:40 Shooting schedule LR, MW Computer ,Google
Documents
Added more description of scene.
Date changedof whento film.
5.12.16
6.12.16- 12:00 Call sheets LR Computer ,Google
Documents
Added a newshooting day - 12th
December. Date ofshooting day 3
changedto 13th Decemberinsteadof
16th.
AM/PM addedtotimes.
Date changedof whento film.
12.12.16
6.12.16- 4:00 Notice of filming LR Computer ,Google
Documents
6.12.16
10.12.16 - 10:00 Shooting day 1 LR, MW,AP,AD Video camera,tripod,
steadicam,notice of
filming, script
10.12.16 - 5:00
12.12.16- 10:00 Meeting6 LR, MW,AP,AD Computer ,Google
Documents
12.12.16
12.12.16- 12:00 Shooting day 2 LR, MW,AP,AD Video camera,tripod,
steadicam,notice of
filming, notice of filming,
script
12.12.16
13.12.16- 12:00 Shooting day 3 LR, MW,AP,AD Video camera,tripod, 13.12.16
- 4. LaurenRosenfeld,Millie West, AlexPereira &Alex Dwyer
BTECNationalDiploma in Creative Media Production
steadicam,notice of
filming, notice of filming,
script
19.12.16 - 10:00 Meeting7 LR, MW,AP,AD Computer ,Google
Documents
28.11.16
15.12.16- 10:00 Edit decision list LR, MW,AP Mac,pen,paper,video
camera
16.12.16
19.12.16 - 2:00 Editing LR, MW,AP,AD Mac,headphones,splitter,
storyboard
19.1.17
16.01.17 - 10:00 Meeting8 LR, MW,AP,AD Computer ,Google
Documents
16.01.17
20.01.17- 10:30 Post production
screenshotdescriptions
LR, MW,AP,AD Computer ,Google
Documents
20.01.17