The document discusses a wheat plant installation project completed by Laker Vent Engineering Limited. It provides details on the scope of the project such as installing over 16,000 meters of pipework within 13 months. It also notes that the peak labor force was 80 personnel and workshop tradesmen peaked at 25. The project cost £4,000,000 and details are provided on the breakdown of labor, plant/equipment, materials, and sub-contract costs. An organizational structure for the LVE project is outlined.
1. European Construction Institute SME of the Year 2003
Wheat Plant Installation
Mechanical & Piping Contract
by
Laker Vent Engineering Limited
2. European Construction Institute SME of the Year 2003
Project Overview
1. Project was bid on a client Bill of Materials which was based upon
12,000m of pipework
2. We actually installed some 16,000M of pipework within 13 months
3. We installed 194 items of free issue equipment
4. Our peak labour force was at 80 personnel skilled tradesmen
5. Workshop Tradesmen peaked at 25 dedicated skilled personnel.
7. European Construction Institute SME of the Year 2003
Wheat Plant 2005-2006
• Project Scope
Supply of Detail Design, Piping Fabrication, Installation of Pipework, Supports
Mechanical Equipment, Testing & Handover
Project cost details
– Project Value £4,000,000
– Labour £2,752,000
– Plant & Equipment £322,000
– Materials £656,000
– Sub-Contract£270,000
LVE Project Structure
– LVE Director/Project Sponsor
– 1 Director of QA & HSE Part Time
– 1 Project Manager
– 1 Site Manager
– 1 Full Time Site Safety Manager
– 1 Site Storemen
– 6 Non Working Supervisors
– 1 Project Document Control
– 1 Full Time QA Clerk
– 1 Full Time Planner
– 1 Full Time Site Receptionist
– 1 Office Based Buyer
– 1 Workshop Manager
– 1 Workshop Storemen1 Workshop Foremen
– All staff & PAYE