   Wheat Plant Installation
 Mechanical & Piping Contract
              by

Laker Vent Engineering Limited
European Construction Institute SME of the Year 2003




                       Project Overview

1. Project was bid on a client Bill of Materials which was based upon
   12,000m of pipework
2. We actually installed some 16,000M of pipework within 13 months
3. We installed 194 items of free issue equipment
4. Our peak labour force was at 80 personnel skilled tradesmen
5. Workshop Tradesmen peaked at 25 dedicated skilled personnel.
European Construction Institute SME of the Year 2003




Ground floor Wheat Plant
European Construction Institute SME of the Year 2003




Second floor Hydro-cyclone Area
          Wheat Plant
European Construction Institute SME of the Year 2003




Second Floor Hydro-Cyclone
           Area
European Construction Institute SME of the Year 2003




Ground floor Pipe-rack
    Wheat Plant
European Construction Institute SME of the Year 2003




                                     Wheat Plant 2005-2006
•   Project Scope
     Supply of Detail Design, Piping Fabrication, Installation of Pipework, Supports
     Mechanical Equipment, Testing & Handover

     Project cost details
     – Project Value £4,000,000
     – Labour £2,752,000
     – Plant & Equipment £322,000
     – Materials £656,000
     – Sub-Contract£270,000

    LVE   Project Structure
     –    LVE Director/Project Sponsor
     –    1 Director of QA & HSE Part Time
     –    1 Project Manager
     –    1 Site Manager
     –    1 Full Time Site Safety Manager
     –    1 Site Storemen
     –    6 Non Working Supervisors
     –    1 Project Document Control
     –    1 Full Time QA Clerk
     –    1 Full Time Planner
     –    1 Full Time Site Receptionist
     –    1 Office Based Buyer
     –    1 Workshop Manager
     –    1 Workshop Storemen1 Workshop Foremen
     –    All staff & PAYE

More Related Content

Viewers also liked (17)

Latefa qalab zreya elim
Latefa qalab  zreya elimLatefa qalab  zreya elim
Latefa qalab zreya elim
 
Cob 20090519 2
Cob 20090519 2Cob 20090519 2
Cob 20090519 2
 
Presentatie 2009
Presentatie 2009Presentatie 2009
Presentatie 2009
 
Eikon Overview
Eikon OverviewEikon Overview
Eikon Overview
 
Para voce
Para vocePara voce
Para voce
 
1С и 1-йСоветник
1С и 1-йСоветник1С и 1-йСоветник
1С и 1-йСоветник
 
Problema
ProblemaProblema
Problema
 
Educaciòn y currìculo
Educaciòn y currìculoEducaciòn y currìculo
Educaciòn y currìculo
 
Ardyan Adiguna 081289779565 - pdf
Ardyan Adiguna 081289779565 - pdfArdyan Adiguna 081289779565 - pdf
Ardyan Adiguna 081289779565 - pdf
 
Fundamentos da Matemática para Estatística - Matrizes
Fundamentos da Matemática para Estatística - MatrizesFundamentos da Matemática para Estatística - Matrizes
Fundamentos da Matemática para Estatística - Matrizes
 
Petxacucha E-SPORTS
Petxacucha E-SPORTSPetxacucha E-SPORTS
Petxacucha E-SPORTS
 
La Prehistoria para Educación Infantil
La Prehistoria para Educación InfantilLa Prehistoria para Educación Infantil
La Prehistoria para Educación Infantil
 
Caso chads
Caso chadsCaso chads
Caso chads
 
El arte en la prehistoria.pptx
El arte en la prehistoria.pptxEl arte en la prehistoria.pptx
El arte en la prehistoria.pptx
 
La prehistoria para web
La prehistoria para webLa prehistoria para web
La prehistoria para web
 
Chad's Creative Concept
Chad's Creative ConceptChad's Creative Concept
Chad's Creative Concept
 
Proyecto: La Prehistoria
Proyecto: La PrehistoriaProyecto: La Prehistoria
Proyecto: La Prehistoria
 

Similar to Installation Trafford Park Wheat Plant

Similar to Installation Trafford Park Wheat Plant (20)

Greenergy Facility Presentation
Greenergy Facility PresentationGreenergy Facility Presentation
Greenergy Facility Presentation
 
Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
Resume
ResumeResume
Resume
 
CV
CVCV
CV
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2
 
Terry CV June 2015
Terry CV June 2015Terry CV June 2015
Terry CV June 2015
 
mohammad fathi cv2017
mohammad fathi cv2017mohammad fathi cv2017
mohammad fathi cv2017
 
Projects Annex
Projects AnnexProjects Annex
Projects Annex
 
mohammad fathi cv2017
mohammad fathi cv2017mohammad fathi cv2017
mohammad fathi cv2017
 
Mohamed Ahmed (2008)
Mohamed Ahmed  (2008)Mohamed Ahmed  (2008)
Mohamed Ahmed (2008)
 
- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)
 
Sulfuric Acid Plant - DOSTEL, Turkey
Sulfuric Acid Plant - DOSTEL, TurkeySulfuric Acid Plant - DOSTEL, Turkey
Sulfuric Acid Plant - DOSTEL, Turkey
 
Report
ReportReport
Report
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 
Mohamed kamal cv2018
Mohamed kamal cv2018Mohamed kamal cv2018
Mohamed kamal cv2018
 
Execution of Copper Rod Plant
Execution of  Copper Rod PlantExecution of  Copper Rod Plant
Execution of Copper Rod Plant
 
Civil eng.m.sayed c.v & cover letter last
Civil eng.m.sayed c.v & cover letter lastCivil eng.m.sayed c.v & cover letter last
Civil eng.m.sayed c.v & cover letter last
 
Hydrogen Peroxide Plants
Hydrogen Peroxide PlantsHydrogen Peroxide Plants
Hydrogen Peroxide Plants
 
Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16
 
E n e r g o Cement Plant - Projects
E n e r g o Cement Plant - ProjectsE n e r g o Cement Plant - Projects
E n e r g o Cement Plant - Projects
 

Installation Trafford Park Wheat Plant

  • 1. European Construction Institute SME of the Year 2003 Wheat Plant Installation Mechanical & Piping Contract by Laker Vent Engineering Limited
  • 2. European Construction Institute SME of the Year 2003 Project Overview 1. Project was bid on a client Bill of Materials which was based upon 12,000m of pipework 2. We actually installed some 16,000M of pipework within 13 months 3. We installed 194 items of free issue equipment 4. Our peak labour force was at 80 personnel skilled tradesmen 5. Workshop Tradesmen peaked at 25 dedicated skilled personnel.
  • 3. European Construction Institute SME of the Year 2003 Ground floor Wheat Plant
  • 4. European Construction Institute SME of the Year 2003 Second floor Hydro-cyclone Area Wheat Plant
  • 5. European Construction Institute SME of the Year 2003 Second Floor Hydro-Cyclone Area
  • 6. European Construction Institute SME of the Year 2003 Ground floor Pipe-rack Wheat Plant
  • 7. European Construction Institute SME of the Year 2003 Wheat Plant 2005-2006 • Project Scope Supply of Detail Design, Piping Fabrication, Installation of Pipework, Supports Mechanical Equipment, Testing & Handover Project cost details – Project Value £4,000,000 – Labour £2,752,000 – Plant & Equipment £322,000 – Materials £656,000 – Sub-Contract£270,000 LVE Project Structure – LVE Director/Project Sponsor – 1 Director of QA & HSE Part Time – 1 Project Manager – 1 Site Manager – 1 Full Time Site Safety Manager – 1 Site Storemen – 6 Non Working Supervisors – 1 Project Document Control – 1 Full Time QA Clerk – 1 Full Time Planner – 1 Full Time Site Receptionist – 1 Office Based Buyer – 1 Workshop Manager – 1 Workshop Storemen1 Workshop Foremen – All staff & PAYE