Slab Sequence
- 1. 1. Pickupstart frombuilder.
2. Knowall optionsandbricklocations.
3. Get start fromoffice.
4. Checklotfor any obstructionthatmight
be in driveway(IE,stormdrain,light
pole,valves,ect)
5. Notifybuilder.
6. Schedule tractor. Doeslotneedlot
prep?If so, get PO.
7. Move – OR – order lumber.
8. Schedule formsetter.
9. Notifybuilderaboutformsetting
schedule sobuildercanschedule form
survey.
10. Meetformsetteronsite andgoover
plotplanand plans.
11. Will formbe highform?If so,notify
buildertosee whathe wantsto do
before youset.
12. Setform.
13. Measure Form.
14. Ordersand.
15. Schedule tractor.
16. Notifybuildersohe can schedule
plumber.
17. Findout fromBuilderthe plumber’s
schedule.
18. Ordercablesand steel tobe delivered
accordingto plumber’sschedule.
19. Plumbinginspectionrequired?
20. Doesbuilderhave formsurveyandisit
good?
21. Schedule make-upcrew.
22. Knowbeamdetails –withTrendmaker,
mustknowsubdivisionnumberand
section.
23. Meetmake-upcrewonsite andgo over
plans.Give crewpoly,tape,pocket
formers,catheads,mastic.
24. Move – OR – Order floatlumber.
25. Walkmake-upwithcrewto verifyitis
complete.Use make-upchecklistwhen
walkingwiththe crew.
26. Schedule formsetterforfloat.
27. Doesslabneedto be pumped?If so,get
PO frombuilder.
28. Floatform;mark all doors.
29. Measure floatand checkformfor any
damage.Do notforgetto measure a
detachedgarage.
30. Schedule all pre-pourinspections.
31. Confirmwithoffice all PO’sare in.
32. Schedule concrete andpump(if
needed) withoffice.
33. Schedule pourmonitor.
34. Schedule finishers.
35. Meetpre-pourinspectorsonslabwith
plans. Forcity inspections;Hasbuilder
leftcityapprovedplansandform
survey?
36. Pre pour inspectionspassed:
37. Confirmconcrete andpumpwithoffice.
38. Pre pour inspectionsfailed:
39. Cancel concrete,pump,pourmonitor,
and finishers.
40. Correct issuesandre-schedulepre-pour
inspections.
41. Re-scheduleconcrete,pump,pour
monitor,andfinishers.
42. Meetpour monitorwithplansmorning
of pour.
43. Pourslab. Anchor boltspacingto be:
24” – 30”, 8” – 10” eachcorner and
each side of door.
44. Must vibrate beamsandfloatsduring
pour.
45. Schedule wreckers.
46. Walkfinishonslabat endof day.
47. Afterwrecked,walkslabfor
honeycombs,andmake sure lotis
clean.
48. Turn inpaperworkby10:00 am the next
day.