Maspeth Queens Truck Impact
Reduction Project
Master Plan Update
June 2016
Executive Summary
► DOT implemented roadway changes in Maspeth, but
with limited success in rerouting truck traffic
► DOT has developed potential solutions to more
successfully reroute truck traffic
► DOT is conducting public outreach to gain buy-in before
finalizing the Master Plan
► Goals:
► Increase truck usage of Bypass route
► Reroute trucks away from Residential Streets
2
Project Area
3
Project Area
4
This increase
coincides with
general
economic
recovery
Potential Solution:
Improve Public Outreach Short Term
►Outreach to
companies needs to
be wider than just
Maspeth IBZ
Companies located in
Flushing/Metropolitan
/Morgan/Bushwick Aves.
Door knocking exercise/
handing out truck maps
to companies in this area
5
Improvements: Other Short-Term
Maspeth Master Plan Map DRAFT
6
7
Improvement #1
Potential Solution:
Improve Bypass Short Term
►Review signal timings and coordination
►Change stop sign locations along the Bypass
route to prioritize truck movements
Existing Stop Sign Location to be Removed
Proposed Stop Sign Location 8
Maspeth Av.
& Page Pl.
Improvement #1
9
Improvement #2
Potential Solution:
Restripe Rust Street at Maspeth Avenue
10
►Narrow Rust Street to
one lane
Improvement #2
11
Improvement #4
Potential Solution:
Temporary Truck Enforcement Station
►Objective of the Enforcement Station
Provide a safe place for enforcement officials to stop,
inspect trucks and interview drivers
►Trucks at this location will be truck route non-
compliant (if not making a local delivery)
Can be used to stop trucks travelling in both directions
Issued a citation for not following truck route
►Acts as a deterrence for trucks using Flushing
Avenue as a shortcut
12
Improvement #4
Potential Solution:
Temporary Enforcement
►INSERT TEMPORARY SECTION
13
DRAFT
Improvement #4
Potential Solution:
Temporary Enforcement
 Pilot Location: Flushing Avenue Underpass
14
Improvement #10
Viaduct used for Truck Enforcement
Station
15
Improvement #5
Potential Solution:
Add Daylighting
►Northeast corner of
Grand Avenue and
Page Place
16
Improvement #5
Potential Solution:
Add Daylighting
17
►Northwest corner of
Grand Avenue and
57th Drive
Conflict
Area
Improvement #5
Potential Solution:
Add Daylighting
18
►Northwest corner of
Grand Avenue and
57th Drive
Conflict
Area
Improvement #5
19
Improvement #6
Potential Solution: Compliance
►Consistent double parking taking place in highly
active industrial zone
20
Improvement #6
Potential Solution: Street Reconfiguration
21
Improvement #6
►Consistent double parking taking place in highly
active industrial zone
►Existing condition:
Potential Solution: Street Reconfiguration
22
Improvement #6
DRAFT►Study feasibility of reconfiguring 58th Street to
accommodate bypass traffic and local uses
Potential Solution: Street Reconfiguration
23
Improvement #6
DRAFT
24
Improvement #8
Potential Solution:
Improve Bypass Mid-Term
►Study feasibility of extending the one-way streets
of the Maspeth Bypass to LIE / Borden Avenue
►This may reduce number of turning movements
at Borden Avenue / Maurice Avenue and Maurice
Avenue / 55th Drive / 59th Street, allowing for
better traffic flow through this intersection
25
Improvement #8
26
Improvement #9
Potential Solution:
Improve Bypass Mid-Term
►Existing Truck Signage is not effective at various
locations in Maspeth
27
Improvement #9
Potential Solution:
Improve Bypass Mid-Term
►Study Feasibility of designing high visibility custom
truck signage
28
Improvement #9
Typical overhead SBS sign in Manhattan Custom overhead sign at Holland Tunnel
Potential Solution:
Improve Bypass Mid-Term
►Study Feasibility of designing high visibility
custom truck signage
 Location: Flushing Avenue and 53rd Street
29
Improvement #9
Conceptual rendering of custom signage
30
Improvement #10
Potential Solution:
Improve Truck Compliance Mid-Term
31
Improvement #10
►Study Feasibility of Designing ITS Solutions to
Track Truck Traffic
 Digital signs can be activated by a sensor to deter approaching
trucks from turning onto Grand Avenue or Flushing Avenue
Typical laser detector installation
Potential Solution:
Improve Bypass Mid-Term
►Study Feasibility of Designing ITS Solutions to
Track Truck Traffic
 Use smart-city analytics to gather data from cameras,
laser classifiers and overheight detectors.
 Potential location: Flushing Avenue Underpass
32
Improvement #10Typical laser detector installation
33
Improvement #11
Potential Solution:
Vision Zero Improvements at Grand Ave.
DRAFTDRAFT
34
DRAFT
Improvement #11
Grand Avenue Corridor
Potential Solution:
Vision Zero Improvements at Grand Ave.
DRAFTDRAFTDRAFT
35
DRAFT
Improvement #11
Potential Solution:
Vision Zero Improvements at Grand Ave.
DRAFTDRAFTDRAFTDRAFT
36
DRAFT
Improvement #11
Potential Solution:
Vision Zero Improvements at Grand Ave.
DRAFTDRAFTDRAFTDRAFTDRAFTDRAFT
37
DRAFT
Improvement #11
Potential Solution:
Vision Zero Improvements at Grand Ave.
DRAFTDRAFTDRAFTDRAFTDRAFTDRAFT
38
DRAFT
Improvement #11
Paint
39
Improvement #14
Potential Solution:
Permanent Enforcement
40DRAFT
DRAFT
Improvement #14
Potential Solution:
Permanent Enforcement
41DRAFT
DRAFTDRAFTDRAFT
Improvement #14
Potential Solution:
Permanent Enforcement
42DRAFT
DRAFTDRAFT
DRAFT
Improvement #14
DRAFT
Next Steps
►Developing Draft Master Plan
►Incorporate public input into Final Master Plan
43

More Related Content

What's hot

Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber BridgeNaoise
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructurePostTensioningInstitute
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentationguest2d44ee
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_awardSamat Jain
 
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...Yangbo Du
 
Caltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesCaltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesAdina Levin
 
Kwalape Lodge Phase 2 Expansion
Kwalape Lodge Phase 2 ExpansionKwalape Lodge Phase 2 Expansion
Kwalape Lodge Phase 2 ExpansionGrant Hepburn
 
Tiger 2013 Awards
Tiger 2013 AwardsTiger 2013 Awards
Tiger 2013 AwardsRoar Media
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructiongbfengineering
 
NJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets CotterNJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets CotterNew Jersey Future
 
Transportation Milton, presentation by joseph lai - ministry of transporation
Transportation Milton, presentation by  joseph lai - ministry of transporationTransportation Milton, presentation by  joseph lai - ministry of transporation
Transportation Milton, presentation by joseph lai - ministry of transporationMilton Chamber of Commerce
 
City Council Presentation - Boulder Junction Update
City Council Presentation - Boulder Junction UpdateCity Council Presentation - Boulder Junction Update
City Council Presentation - Boulder Junction UpdateCityofBoulder
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_Fphilip dobson
 
Banyan Boulevard Presentation
Banyan Boulevard PresentationBanyan Boulevard Presentation
Banyan Boulevard PresentationAmber Lewis AD
 

What's hot (16)

Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber Bridge
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking Structure
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentation
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
 
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...
Staten Island Bus Hackathon - Redistribution (of Local) and Consolidation (of...
 
Caltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesCaltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanes
 
Kwalape Lodge Phase 2 Expansion
Kwalape Lodge Phase 2 ExpansionKwalape Lodge Phase 2 Expansion
Kwalape Lodge Phase 2 Expansion
 
John Rahaim - Transit Center District Plan
John Rahaim - Transit Center District PlanJohn Rahaim - Transit Center District Plan
John Rahaim - Transit Center District Plan
 
Tiger 2013 Awards
Tiger 2013 AwardsTiger 2013 Awards
Tiger 2013 Awards
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstruction
 
NJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets CotterNJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets Cotter
 
Transportation Milton, presentation by joseph lai - ministry of transporation
Transportation Milton, presentation by  joseph lai - ministry of transporationTransportation Milton, presentation by  joseph lai - ministry of transporation
Transportation Milton, presentation by joseph lai - ministry of transporation
 
City Council Presentation - Boulder Junction Update
City Council Presentation - Boulder Junction UpdateCity Council Presentation - Boulder Junction Update
City Council Presentation - Boulder Junction Update
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_F
 
Banyan Boulevard Presentation
Banyan Boulevard PresentationBanyan Boulevard Presentation
Banyan Boulevard Presentation
 
Chimney Hill Applicant Presentation
Chimney Hill Applicant PresentationChimney Hill Applicant Presentation
Chimney Hill Applicant Presentation
 

Similar to maspeth-bypass-master-plan-jun2016

City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...Harry Black
 
IRJET- Redesign of Existing Private Bus Terminal at Kothamangalam
IRJET- Redesign of Existing Private Bus Terminal at KothamangalamIRJET- Redesign of Existing Private Bus Terminal at Kothamangalam
IRJET- Redesign of Existing Private Bus Terminal at KothamangalamIRJET Journal
 
Planning Report; Assembly Halls, Monaghan
Planning Report; Assembly Halls, MonaghanPlanning Report; Assembly Halls, Monaghan
Planning Report; Assembly Halls, MonaghanPaul Coyle
 
VTA North East County Open Houses Presentation, July 21
VTA North East County Open Houses Presentation, July 21VTA North East County Open Houses Presentation, July 21
VTA North East County Open Houses Presentation, July 21SCVTA
 
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreMammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreDarin Dinsmore
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Maintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsMaintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsJill Reeves
 
VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014SCVTA
 
2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking ManagementTOD India
 
Edinburgh proposed City plan 2030 C&BCC presentation 7 12 21
Edinburgh proposed City plan 2030   C&BCC presentation 7 12 21Edinburgh proposed City plan 2030   C&BCC presentation 7 12 21
Edinburgh proposed City plan 2030 C&BCC presentation 7 12 21CramondandBarntonCom
 
Fy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and UtilitiesFy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and Utilitiesahcitycouncil
 
Glasgow City Centre Transport Strategy presentation
Glasgow City Centre Transport Strategy presentationGlasgow City Centre Transport Strategy presentation
Glasgow City Centre Transport Strategy presentationSTEP_scotland
 

Similar to maspeth-bypass-master-plan-jun2016 (20)

City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
 
Sustainable Urban Mobility Planning
Sustainable Urban Mobility PlanningSustainable Urban Mobility Planning
Sustainable Urban Mobility Planning
 
Project Mobility: Route 3 Express Toll Lanes Study
Project Mobility: Route 3 Express Toll Lanes StudyProject Mobility: Route 3 Express Toll Lanes Study
Project Mobility: Route 3 Express Toll Lanes Study
 
IRJET- Redesign of Existing Private Bus Terminal at Kothamangalam
IRJET- Redesign of Existing Private Bus Terminal at KothamangalamIRJET- Redesign of Existing Private Bus Terminal at Kothamangalam
IRJET- Redesign of Existing Private Bus Terminal at Kothamangalam
 
Simon Latham
Simon LathamSimon Latham
Simon Latham
 
Planning Report; Assembly Halls, Monaghan
Planning Report; Assembly Halls, MonaghanPlanning Report; Assembly Halls, Monaghan
Planning Report; Assembly Halls, Monaghan
 
VTA North East County Open Houses Presentation, July 21
VTA North East County Open Houses Presentation, July 21VTA North East County Open Houses Presentation, July 21
VTA North East County Open Houses Presentation, July 21
 
Woden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTEDWoden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTED
 
West of England Joint Transport Study summary newsletter
West of England Joint Transport Study summary newsletterWest of England Joint Transport Study summary newsletter
West of England Joint Transport Study summary newsletter
 
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreMammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Maintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsMaintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay Projects
 
Level of Service F for Grade A Streets--Cesar Chavez Street
Level of Service F for Grade A Streets--Cesar Chavez Street  Level of Service F for Grade A Streets--Cesar Chavez Street
Level of Service F for Grade A Streets--Cesar Chavez Street
 
VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014
 
2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management
 
Edinburgh proposed City plan 2030 C&BCC presentation 7 12 21
Edinburgh proposed City plan 2030   C&BCC presentation 7 12 21Edinburgh proposed City plan 2030   C&BCC presentation 7 12 21
Edinburgh proposed City plan 2030 C&BCC presentation 7 12 21
 
Fy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and UtilitiesFy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and Utilities
 
Street Survey
Street SurveyStreet Survey
Street Survey
 
2021 Streets Survey
2021 Streets Survey2021 Streets Survey
2021 Streets Survey
 
Glasgow City Centre Transport Strategy presentation
Glasgow City Centre Transport Strategy presentationGlasgow City Centre Transport Strategy presentation
Glasgow City Centre Transport Strategy presentation
 

maspeth-bypass-master-plan-jun2016