SlideShare a Scribd company logo
1 of 29
Download to read offline
MECHANICAL ENGINEERING
PORTFOLIO
Matt Sterling
California Polytechnic State University, SLO
Third Year
Table of Contents
• Co-op at Fermi National Accelerator Laboratory Page 1 - 13
 Beam Window Module
 Radioactive Coffin Structural Analysis
 Beryllium Plate Stress Analysis
 Secondary Emissions Monitor: Stand and Assembly
 Shielding Fixture Cart
• Internship with West Gate Sheet Metal Inc. Page 14 - 27
 Gear Box Assembly
 Rotating Satellite Dish Mount
CO-OP WITH FERMILAB
SPRING - SUMMER
2016
1
Beam Window Module: Scope
■ Vacuum window module for Fermilab’s flagship project, the Long
Baseline Neutrino Facility (LBNF)
■ Using metal O-rings to seal for radiation resistance
■ Window needs to be remotely removable due to radiation (bolts are
usually used)
■ Current solution is a wedging system (the module is in a very early
design stage)
2
Beam Window Module: My Work
■ In Siemens NX, took existing 1 meter window
assembly and remade each component to account for
a 1.5 meter window
■ Made several tweaks on dimension as it is in the early
stages of design along with:
– Added an airflow channel
– Added supports to model how it’d be supported
in the target chase (overall assembly)
■ Integrated all parts and assembly into the product
lifecycle management software, Siemens Teamcenter,
allowing engineers around the lab to view and edit the
assembly
3
Radioactive Coffin Structural Analysis: Scope
■ Old Tevatron beam dump needed to be placed in radioactive coffin
■ Work area was an empty pit, concrete blocks were to be placed over it but they could not
support the load
■ Needed to make sure I-beams, which were found on site, could support the loads
4
Radioactive Coffin Structural Analysis: My Work
■ Did several calculations to determine
the max stress and safety factors on the
six different I-beams in three possible
loading situations
– Module, dump, coffin, and
shielding blocks
– Concrete, dump, and shielding
blocks (expected)
– Concrete, module, dump, and
shielding blocks (worst case)
■ Made excel spreadsheet displaying the
calculations for each of the six beams in
three cases
5
Beryllium Plate Stress Analysis: Scope
■ Beryllium plate will be held at vacuum on
one side and atmosphere on the other side
■ Fixed on atmosphere side and simply
supported on vacuum side
■ Head engineer’s hand calculations showed
stresses beyond yield at center
■ Goal was to create more accurate model of
situation on ANSYS to verify safety
6
Beryllium Plate Stress Analysis: My Work
■ Created axisymmetric model in ANSYS
■ Observed a stress riser on a .008” step where
a copper gasket would be supporting the plate
■ Attempted eliminating stress riser by changing
boundary condition, parameterizing the length
of the supporting edge, along with editing
mesh sizes
■ Worked with multiple engineers trying to find
solution
■ Edge’s radius will be physically measured to
determine true stress on corner (Plate has
already been manufactured)
■ Due to the high risk of working with Beryllium,
this project is still in progress among full time
engineers at the lab
7
Secondary Emission Monitor: Scope
■ SEM is a device placed in the beamline that reads beam flux
■ Uses a series of foils, half ground and half with voltage, to
collect freed electrons and, therefore, read particle flux
■ Head engineer has worked on a prototype design that needed
to be assembled, approved, and ultimately installed
■ I was shown a tentative stand/mount design but was told to
change/improve it however I see fit
8
SEM Stand: My Work
■ Original stand design used Unistrut
■ I edited the design and used primarily 80/20, as I believed
it would be easier to adjust lateral position as well as add
new devices in the future
■ Designed entire stand assembly in NX, along with
integrating the actual SEM it would be supporting
■ Created drawings for each part that was to be
manufactured in-house
■ Documented comprehensive installation instructions
according to my design
9
Secondary Emissions Monitor: My Work
■ Procured parts that were missing when I took inventory
■ Assembled SEM in cleanroom using only assembly drawings
■ Documented assembly procedure, including issues that I came across during the
process, in order to optimize future SEM assemblies
■ After baking unit, vacuum was pulled to 6.4 x 10^-10, lower than estimated by hand
calculations
■ Helped head engineer create engineering note for the two vacuum windows (review
was in progress as I left)
10
Secondary Emission Monitor: Pictures
Foil Plane assembled SEM almost finished SEM being pumped down to vacuum
11
Shielding Fixture Cart: Scope/My Work
■ A moveable, liftable, lockable cart needed to be designed to transport 3 shielding base rails
throughout the underground tunnels
■ Drew up a concept using almost entirely 80/20 framing
■ Worked with local distributer to finalize design
■ Analyzed stresses (by hand) on supporting beams to ensure durability
■ After receiving Bill of Materials, adjusted our design to cut costs by 35% by:
– Changing the width of extrusions used
– Eliminating unnecessary components
– Using different distributers for some parts
■ Built entire cart with student technician, now ready for use
12
Shielding Fixture Cart: Pictures
Concept Sketch Bill of Materials Drawing Final Cart
13
INTERNSHIP WITH WESTGATE
SHEET METAL INC
SUMMER 2015
14
Gear Box Assembly
A National Ice Cream producer
engaged West Gate Sheet Metal to
redesign a gear box for their fudge
mixing machines. The original 3
shaft, chain-driven design was not
holding up under the conditions of
mixing not-quite warm fudge,
causing shearing/bending of shafts
and shaft keys.
Key Design Considerations:
■ Must be more robust, especially
when taking torsional load
■ Must be sealed to meet food
industry standards
■ Design improvements must be
cost justified and approved by
the customer
15
The top three gears are the gears
that the head engineer picked out.
Below the gears is the original
middle sprocket
This is a closer view of the
middle sprocket on the right, and
one of the two side sprockets on
the left
Original Housing (both top
and bottom respectively)
16
After getting a rough prototype together, I met with the
customer to discuss the prototype and ensure I understood
his true requirements. He emphasized that it be completely
sealed and durable. While there, I also got to take a look and
get measurements of the actual motor (pictured here) that
would be driving the gearbox.
17
This is an exploded view of the final assembly. Besides the gears, which were made by the head engineer
beforehand, and the hardware (screws, bolts, bearings, etc.), I designed all the parts from scratch on
Solidworks.
18
This is an example detail drawing of the top of the gearbox housing. There was a detail drawing
for every manufactured part including the sides, top, and bottom of the housing, the 3 shafts,
the 3 gears, the inner housing extension, the service hole covers, and the shaft seals. 19
Once the detail drawings and CAD files were finalized, the gear box was ready for production.
Bottom of housing (including
welded legs and gussets)
Top Left: Top of housing (smooth
finish on perimeter to ensure
water-tight O-ring seal)
Top Right (partially covered): Side
shafts with gears attached
Bottom Center: Service window
covers (including O-ring groove)
Sides of housing including front and
back (bent pieces) welded to the
left and right side. Surrounding
O-ring groove not yet machined.
20
Gear box being assembled from
top to bottom
The cube surrounding the main shaft
is the inner-housing extension. This
allowed me to add two more bearings
for extra radial support on the middle
mixer, which would be doing the most
work. 21
Finalized gearbox
Bottom view of final assembly Top view of final assembly
22
Customer was happy and has ordered more!
Rotating Satellite Dish Mount
A customer engaged West Gate Sheet
Metal to design an assembly for a
robotically controlled radio telescope
project. This required a design that
allowed for industrial stepper motors
to rotate the dish antenna in 360
azimuth and 180 altitude directions
in order to track celestial phenomena.
Design Considerations:
■ Must fit the 2 designated motors
■ Must rotate 360 in azimuth
direction
■ Must rotate 180  in altitude
direction
■ For clarification, the full range of
motion would create half of a
sphere
23
I was given two motors (pictured on left), which each rotate about their vertical axis. To
create the range of motion requested, I’d be setting one up vertically to rotate 360
and mounting one horizontally to rotate 180 (visualization of motion on right).
24
I came up with an assembly of 4 parts…
The base stand, in which the
First motor would come from
Below to rotate the top piece
360
The top, which rotates 360
on the base stand. The second
motor could then be mounted
horizontally to allow for the 180
of motion about the horizontal
axis.
The two sides that secure the
actual satellite. These parts surround
the base of the satellite and are
secured by a bolt in each of the four
corners.
25
Example detail drawing of the base stand. I made a detail drawing for each part to be sent
to the shop, along with the CAD files needed.
26
Finalized Satellite Dish Mount
27

More Related Content

What's hot

Geneva mechanism ppt
Geneva mechanism pptGeneva mechanism ppt
Geneva mechanism pptKapil Gaba
 
Special Machines Unit 2: Reciprocating machines
Special Machines Unit 2: Reciprocating machines Special Machines Unit 2: Reciprocating machines
Special Machines Unit 2: Reciprocating machines ARAVIND U
 
Slotter and plannar machine tools
Slotter and plannar machine toolsSlotter and plannar machine tools
Slotter and plannar machine toolsNavroz Navodia
 
Martin Walker GE style CV
Martin Walker GE style CVMartin Walker GE style CV
Martin Walker GE style CVMartin Walker
 
Planer
PlanerPlaner
Planerrmkcet
 
Bringing Atlanta into Plain View
Bringing Atlanta into Plain ViewBringing Atlanta into Plain View
Bringing Atlanta into Plain ViewMcKenney's Inc
 
SAID SAAD ALY CV
SAID SAAD ALY CVSAID SAAD ALY CV
SAID SAAD ALY CVSaid Ali
 

What's hot (8)

Geneva mechanism ppt
Geneva mechanism pptGeneva mechanism ppt
Geneva mechanism ppt
 
Special Machines Unit 2: Reciprocating machines
Special Machines Unit 2: Reciprocating machines Special Machines Unit 2: Reciprocating machines
Special Machines Unit 2: Reciprocating machines
 
Slotter and plannar machine tools
Slotter and plannar machine toolsSlotter and plannar machine tools
Slotter and plannar machine tools
 
Martin Walker GE style CV
Martin Walker GE style CVMartin Walker GE style CV
Martin Walker GE style CV
 
Ijmet 10 01_087
Ijmet 10 01_087Ijmet 10 01_087
Ijmet 10 01_087
 
Planer
PlanerPlaner
Planer
 
Bringing Atlanta into Plain View
Bringing Atlanta into Plain ViewBringing Atlanta into Plain View
Bringing Atlanta into Plain View
 
SAID SAAD ALY CV
SAID SAAD ALY CVSAID SAAD ALY CV
SAID SAAD ALY CV
 

Viewers also liked

Marcio Reinaldo - Plano de Governo 2017 2020
Marcio Reinaldo - Plano de Governo 2017 2020 Marcio Reinaldo - Plano de Governo 2017 2020
Marcio Reinaldo - Plano de Governo 2017 2020 marcioreinaldosetelagoas
 
укр мова фраз.
укр мова фраз.укр мова фраз.
укр мова фраз.innapol
 
Reason Behind Your Child’s Behavior?
Reason Behind Your Child’s Behavior?Reason Behind Your Child’s Behavior?
Reason Behind Your Child’s Behavior?Paras World School
 
свято
святосвято
святоinnapol
 
Hardware y software claudio
Hardware y software claudioHardware y software claudio
Hardware y software claudioclaudiochicago
 
Trabajo práctico nº5 análisis de una página web.pptx0000000
Trabajo práctico nº5 análisis de una página web.pptx0000000Trabajo práctico nº5 análisis de una página web.pptx0000000
Trabajo práctico nº5 análisis de una página web.pptx0000000claudiochicago
 
Trabajo practico n°3 Seguridad en la web
Trabajo practico n°3 Seguridad en la webTrabajo practico n°3 Seguridad en la web
Trabajo practico n°3 Seguridad en la webclaudiochicago
 

Viewers also liked (8)

Marcio Reinaldo - Plano de Governo 2017 2020
Marcio Reinaldo - Plano de Governo 2017 2020 Marcio Reinaldo - Plano de Governo 2017 2020
Marcio Reinaldo - Plano de Governo 2017 2020
 
укр мова фраз.
укр мова фраз.укр мова фраз.
укр мова фраз.
 
Plano de Governo Marcio Reinaldo
Plano de Governo Marcio ReinaldoPlano de Governo Marcio Reinaldo
Plano de Governo Marcio Reinaldo
 
Reason Behind Your Child’s Behavior?
Reason Behind Your Child’s Behavior?Reason Behind Your Child’s Behavior?
Reason Behind Your Child’s Behavior?
 
свято
святосвято
свято
 
Hardware y software claudio
Hardware y software claudioHardware y software claudio
Hardware y software claudio
 
Trabajo práctico nº5 análisis de una página web.pptx0000000
Trabajo práctico nº5 análisis de una página web.pptx0000000Trabajo práctico nº5 análisis de una página web.pptx0000000
Trabajo práctico nº5 análisis de una página web.pptx0000000
 
Trabajo practico n°3 Seguridad en la web
Trabajo practico n°3 Seguridad en la webTrabajo practico n°3 Seguridad en la web
Trabajo practico n°3 Seguridad en la web
 

Similar to Mechanical Engineering Portfolio Showcases Projects

Jerry stoneking work history
Jerry stoneking work historyJerry stoneking work history
Jerry stoneking work historyJerry Stoneking
 
Emgineering Design Portfolio
Emgineering Design PortfolioEmgineering Design Portfolio
Emgineering Design PortfolioTsuyoshi Yokoyama
 
Study and performance analysis of combustion chamber using
Study and performance analysis of combustion chamber usingStudy and performance analysis of combustion chamber using
Study and performance analysis of combustion chamber usingGyanendra Awasthi
 
Portfolio Presentation
Portfolio PresentationPortfolio Presentation
Portfolio Presentationshanged
 
Engineering Projects by Christopher Haman
Engineering Projects by Christopher HamanEngineering Projects by Christopher Haman
Engineering Projects by Christopher HamanChris Haman
 
Engineering Projects by Christopher Haman
Engineering Projects by Christopher HamanEngineering Projects by Christopher Haman
Engineering Projects by Christopher HamanChris Haman
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR PresentationKristopherKerames
 
Solar three wheeler for disabled person
Solar three wheeler for disabled personSolar three wheeler for disabled person
Solar three wheeler for disabled personGokarna Basnet, MRICS
 
Design,analysis and optimization of disc brake
Design,analysis and optimization of disc brakeDesign,analysis and optimization of disc brake
Design,analysis and optimization of disc brakeVenugopalraoSuravara
 
Part 2 Self Supporting tower structures
Part 2 Self Supporting tower structures Part 2 Self Supporting tower structures
Part 2 Self Supporting tower structures Fred Teichman
 
Engineering System Modelling and Simulation Lab
Engineering System Modelling and Simulation LabEngineering System Modelling and Simulation Lab
Engineering System Modelling and Simulation LabVishal Singh
 
Engineering Portfolio - Dave Waknin
Engineering Portfolio - Dave WakninEngineering Portfolio - Dave Waknin
Engineering Portfolio - Dave WakninDave Waknin
 
Design and Development of Oil Skimmer
Design and Development of Oil SkimmerDesign and Development of Oil Skimmer
Design and Development of Oil SkimmerIRJET Journal
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatthew Baum
 
Final Presentation - Senior Design Project
Final Presentation - Senior Design ProjectFinal Presentation - Senior Design Project
Final Presentation - Senior Design ProjectTyler Lemonds
 
Orrbit_Product_Design
Orrbit_Product_DesignOrrbit_Product_Design
Orrbit_Product_DesignKen Orr
 

Similar to Mechanical Engineering Portfolio Showcases Projects (20)

Project List
Project ListProject List
Project List
 
Jerry stoneking work history
Jerry stoneking work historyJerry stoneking work history
Jerry stoneking work history
 
Emgineering Design Portfolio
Emgineering Design PortfolioEmgineering Design Portfolio
Emgineering Design Portfolio
 
Study and performance analysis of combustion chamber using
Study and performance analysis of combustion chamber usingStudy and performance analysis of combustion chamber using
Study and performance analysis of combustion chamber using
 
Portfolio Presentation
Portfolio PresentationPortfolio Presentation
Portfolio Presentation
 
Engineering Projects by Christopher Haman
Engineering Projects by Christopher HamanEngineering Projects by Christopher Haman
Engineering Projects by Christopher Haman
 
Engineering Projects by Christopher Haman
Engineering Projects by Christopher HamanEngineering Projects by Christopher Haman
Engineering Projects by Christopher Haman
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
 
Solar three wheeler for disabled person
Solar three wheeler for disabled personSolar three wheeler for disabled person
Solar three wheeler for disabled person
 
Design,analysis and optimization of disc brake
Design,analysis and optimization of disc brakeDesign,analysis and optimization of disc brake
Design,analysis and optimization of disc brake
 
Part 2 Self Supporting tower structures
Part 2 Self Supporting tower structures Part 2 Self Supporting tower structures
Part 2 Self Supporting tower structures
 
Engineering portfolio
Engineering portfolioEngineering portfolio
Engineering portfolio
 
Engineering System Modelling and Simulation Lab
Engineering System Modelling and Simulation LabEngineering System Modelling and Simulation Lab
Engineering System Modelling and Simulation Lab
 
Portfolio-PDF
Portfolio-PDFPortfolio-PDF
Portfolio-PDF
 
Engineering Portfolio - Dave Waknin
Engineering Portfolio - Dave WakninEngineering Portfolio - Dave Waknin
Engineering Portfolio - Dave Waknin
 
Design and Development of Oil Skimmer
Design and Development of Oil SkimmerDesign and Development of Oil Skimmer
Design and Development of Oil Skimmer
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer Portfolio
 
Final Presentation - Senior Design Project
Final Presentation - Senior Design ProjectFinal Presentation - Senior Design Project
Final Presentation - Senior Design Project
 
6 MONTH INTERNSHIP AT
6 MONTH INTERNSHIP AT6 MONTH INTERNSHIP AT
6 MONTH INTERNSHIP AT
 
Orrbit_Product_Design
Orrbit_Product_DesignOrrbit_Product_Design
Orrbit_Product_Design
 

Mechanical Engineering Portfolio Showcases Projects

  • 1. MECHANICAL ENGINEERING PORTFOLIO Matt Sterling California Polytechnic State University, SLO Third Year
  • 2. Table of Contents • Co-op at Fermi National Accelerator Laboratory Page 1 - 13  Beam Window Module  Radioactive Coffin Structural Analysis  Beryllium Plate Stress Analysis  Secondary Emissions Monitor: Stand and Assembly  Shielding Fixture Cart • Internship with West Gate Sheet Metal Inc. Page 14 - 27  Gear Box Assembly  Rotating Satellite Dish Mount
  • 3. CO-OP WITH FERMILAB SPRING - SUMMER 2016 1
  • 4. Beam Window Module: Scope ■ Vacuum window module for Fermilab’s flagship project, the Long Baseline Neutrino Facility (LBNF) ■ Using metal O-rings to seal for radiation resistance ■ Window needs to be remotely removable due to radiation (bolts are usually used) ■ Current solution is a wedging system (the module is in a very early design stage) 2
  • 5. Beam Window Module: My Work ■ In Siemens NX, took existing 1 meter window assembly and remade each component to account for a 1.5 meter window ■ Made several tweaks on dimension as it is in the early stages of design along with: – Added an airflow channel – Added supports to model how it’d be supported in the target chase (overall assembly) ■ Integrated all parts and assembly into the product lifecycle management software, Siemens Teamcenter, allowing engineers around the lab to view and edit the assembly 3
  • 6. Radioactive Coffin Structural Analysis: Scope ■ Old Tevatron beam dump needed to be placed in radioactive coffin ■ Work area was an empty pit, concrete blocks were to be placed over it but they could not support the load ■ Needed to make sure I-beams, which were found on site, could support the loads 4
  • 7. Radioactive Coffin Structural Analysis: My Work ■ Did several calculations to determine the max stress and safety factors on the six different I-beams in three possible loading situations – Module, dump, coffin, and shielding blocks – Concrete, dump, and shielding blocks (expected) – Concrete, module, dump, and shielding blocks (worst case) ■ Made excel spreadsheet displaying the calculations for each of the six beams in three cases 5
  • 8. Beryllium Plate Stress Analysis: Scope ■ Beryllium plate will be held at vacuum on one side and atmosphere on the other side ■ Fixed on atmosphere side and simply supported on vacuum side ■ Head engineer’s hand calculations showed stresses beyond yield at center ■ Goal was to create more accurate model of situation on ANSYS to verify safety 6
  • 9. Beryllium Plate Stress Analysis: My Work ■ Created axisymmetric model in ANSYS ■ Observed a stress riser on a .008” step where a copper gasket would be supporting the plate ■ Attempted eliminating stress riser by changing boundary condition, parameterizing the length of the supporting edge, along with editing mesh sizes ■ Worked with multiple engineers trying to find solution ■ Edge’s radius will be physically measured to determine true stress on corner (Plate has already been manufactured) ■ Due to the high risk of working with Beryllium, this project is still in progress among full time engineers at the lab 7
  • 10. Secondary Emission Monitor: Scope ■ SEM is a device placed in the beamline that reads beam flux ■ Uses a series of foils, half ground and half with voltage, to collect freed electrons and, therefore, read particle flux ■ Head engineer has worked on a prototype design that needed to be assembled, approved, and ultimately installed ■ I was shown a tentative stand/mount design but was told to change/improve it however I see fit 8
  • 11. SEM Stand: My Work ■ Original stand design used Unistrut ■ I edited the design and used primarily 80/20, as I believed it would be easier to adjust lateral position as well as add new devices in the future ■ Designed entire stand assembly in NX, along with integrating the actual SEM it would be supporting ■ Created drawings for each part that was to be manufactured in-house ■ Documented comprehensive installation instructions according to my design 9
  • 12. Secondary Emissions Monitor: My Work ■ Procured parts that were missing when I took inventory ■ Assembled SEM in cleanroom using only assembly drawings ■ Documented assembly procedure, including issues that I came across during the process, in order to optimize future SEM assemblies ■ After baking unit, vacuum was pulled to 6.4 x 10^-10, lower than estimated by hand calculations ■ Helped head engineer create engineering note for the two vacuum windows (review was in progress as I left) 10
  • 13. Secondary Emission Monitor: Pictures Foil Plane assembled SEM almost finished SEM being pumped down to vacuum 11
  • 14. Shielding Fixture Cart: Scope/My Work ■ A moveable, liftable, lockable cart needed to be designed to transport 3 shielding base rails throughout the underground tunnels ■ Drew up a concept using almost entirely 80/20 framing ■ Worked with local distributer to finalize design ■ Analyzed stresses (by hand) on supporting beams to ensure durability ■ After receiving Bill of Materials, adjusted our design to cut costs by 35% by: – Changing the width of extrusions used – Eliminating unnecessary components – Using different distributers for some parts ■ Built entire cart with student technician, now ready for use 12
  • 15. Shielding Fixture Cart: Pictures Concept Sketch Bill of Materials Drawing Final Cart 13
  • 16. INTERNSHIP WITH WESTGATE SHEET METAL INC SUMMER 2015 14
  • 17. Gear Box Assembly A National Ice Cream producer engaged West Gate Sheet Metal to redesign a gear box for their fudge mixing machines. The original 3 shaft, chain-driven design was not holding up under the conditions of mixing not-quite warm fudge, causing shearing/bending of shafts and shaft keys. Key Design Considerations: ■ Must be more robust, especially when taking torsional load ■ Must be sealed to meet food industry standards ■ Design improvements must be cost justified and approved by the customer 15
  • 18. The top three gears are the gears that the head engineer picked out. Below the gears is the original middle sprocket This is a closer view of the middle sprocket on the right, and one of the two side sprockets on the left Original Housing (both top and bottom respectively) 16
  • 19. After getting a rough prototype together, I met with the customer to discuss the prototype and ensure I understood his true requirements. He emphasized that it be completely sealed and durable. While there, I also got to take a look and get measurements of the actual motor (pictured here) that would be driving the gearbox. 17
  • 20. This is an exploded view of the final assembly. Besides the gears, which were made by the head engineer beforehand, and the hardware (screws, bolts, bearings, etc.), I designed all the parts from scratch on Solidworks. 18
  • 21. This is an example detail drawing of the top of the gearbox housing. There was a detail drawing for every manufactured part including the sides, top, and bottom of the housing, the 3 shafts, the 3 gears, the inner housing extension, the service hole covers, and the shaft seals. 19
  • 22. Once the detail drawings and CAD files were finalized, the gear box was ready for production. Bottom of housing (including welded legs and gussets) Top Left: Top of housing (smooth finish on perimeter to ensure water-tight O-ring seal) Top Right (partially covered): Side shafts with gears attached Bottom Center: Service window covers (including O-ring groove) Sides of housing including front and back (bent pieces) welded to the left and right side. Surrounding O-ring groove not yet machined. 20
  • 23. Gear box being assembled from top to bottom The cube surrounding the main shaft is the inner-housing extension. This allowed me to add two more bearings for extra radial support on the middle mixer, which would be doing the most work. 21
  • 24. Finalized gearbox Bottom view of final assembly Top view of final assembly 22 Customer was happy and has ordered more!
  • 25. Rotating Satellite Dish Mount A customer engaged West Gate Sheet Metal to design an assembly for a robotically controlled radio telescope project. This required a design that allowed for industrial stepper motors to rotate the dish antenna in 360 azimuth and 180 altitude directions in order to track celestial phenomena. Design Considerations: ■ Must fit the 2 designated motors ■ Must rotate 360 in azimuth direction ■ Must rotate 180  in altitude direction ■ For clarification, the full range of motion would create half of a sphere 23
  • 26. I was given two motors (pictured on left), which each rotate about their vertical axis. To create the range of motion requested, I’d be setting one up vertically to rotate 360 and mounting one horizontally to rotate 180 (visualization of motion on right). 24
  • 27. I came up with an assembly of 4 parts… The base stand, in which the First motor would come from Below to rotate the top piece 360 The top, which rotates 360 on the base stand. The second motor could then be mounted horizontally to allow for the 180 of motion about the horizontal axis. The two sides that secure the actual satellite. These parts surround the base of the satellite and are secured by a bolt in each of the four corners. 25
  • 28. Example detail drawing of the base stand. I made a detail drawing for each part to be sent to the shop, along with the CAD files needed. 26