SlideShare a Scribd company logo
1 of 59
Download to read offline
Frontier Energy Services, LLC
Concept to Construction: Design and Build Management
Energy Pipeline Management Summit
July 16 – 17, 2018 Dallas, Texas
2
Overview
• Project Development
• Best Practices
• Critical Project Concepts
3
Overview
• Project Development
• Best Practices
• Critical Project Concepts
4
Oversight and Management
Key Project Development Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
5
Oversight and Management
6
Oversight and Management
7
Concept
Key Project Development Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
8
Concept
Why?
• Starts as an Idea / Why do it?
• Meets a Need?
• Fit with Current Business Environment?
• Fit with Corporate Strategy?
• Competition?
• Exit Strategy Required?
9
Feasibility
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
10
Feasibility
Feasibility /
FEED Stage
11
Feasibility
Two (2) Contracting Tactics:
• Internally
o With SME Support
• 3rd Party Consulting Firm
12
Feasibility
If Using a 3rd Party for Feasibility and /
or FEED:
• Preclude 3rd Party from Bidding Next
Phase
• Set Firm Completion Date
• Bid Lump Sum
13
Feasibility
The Key Deliverables for Feasibility Study:
• Route Selection (desk top), Including Options
• Hydraulics for Pipe Sizing & Facility Placement
• Level 4 Cost Estimates – CAPEX and OPEX
• Technical Basis / EBOD – Pipelines & Facilities
• Market Analysis (may be internal)
• Level 2 Schedule
• Risks & Key Issues, i.e. Environmental,
Species, Logistics, Housing, Crossings, etc.
14
Feasibility
Pipe Size vs Pump Station Spacing
Assessment
DIA # PS TIC % Diff
8 5 41,525,000$ -22%
10 2 42,080,000$ -21%
12 1 38,117,000$ -28%
14 1 44,443,000$ -16%
16 1 47,693,000$ -10%
18 1 52,949,000$ 0%
Economic Comparison
Pipe Diameter 10
Pipeline Length 237,600
TIC per foot 134.68$
Total Pipeline Cost 32,000,000$
# Pump Stations 2
HP per Pump Station 1,200
Total HP 2,400
Cost per HP 2,100.00$
Total Pump Station Costs 5,040,000$
TIC: 42,080,000$
Pipeline Costs:
Pump Station Costs:
15
Feasibility
Project Structure
Project Execution / Financing:
• Develop Yourself
•Internal / External Financing
•Debt / Equity
• Partner to Reduce CAPEX or Gain a
Strategic Advantage
• Combinations
16
Feasibility
FEED Phase - If Required
If Project is Feasible; Move to FEED
If FEED is Not Required – Move to
Detail Engineering & Design.
FEED on a Lump Sum Basis.
17
FEED
The principle deliverables for FEED:
• Basis of Design (BOD)
• PFD’s & P&ID’s; Electrical 1-lines; Area
Classifications (Facilities); Calculations;
Control Philosophy; etc.
• Project Specifications
• Environmental Assessment & Mitigations
18
FEED
• Vendor Quotes for Major Equipment
• Long Lead Items & RFQ’s
• Class III Cost Estimate - CAPEX & OPEX
• Level II Schedule
• Risk Assessment / Key Issues
19
Feasibility & FEED – Key Steps
Behind the Scenes
• Execution Planning:
• Organization
• Cost and Schedule
• Procurement
• Management of Change
• Reporting
• Independent Project Reviews
20
Feasibility & FEED – Key Steps
• Alignment Across all Stakeholders
• Do the Work to Support the Next
Decision. Be Decision Driven.
• Key Objectives for the Project:
Prioritize & Communicate
Keys to Success
21
Engineering and Design
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
22
Engineering and Design
Engineering &
Detail Design
23
Engineering and Design
To Be Successful -
Engineering & Procurement
must be Construction-
Driven
What Does that Mean?
24
Engineering and Design
What Construction-Driven does
not mean:
• Construction Calls the Shots -
What Construction Wants,
Construction Gets
25
Engineering and Design
What Construction-Driven does
mean:
• Construction’s Schedule Drives
Engineering & Procurement
Schedule.
• Drawings, Equipment & Materials
Ready When Required (ROS
Dates).
26
Engineering and Design
Engineering Management
• Manage Interfaces & Division of
Responsibilities on Company
Design Team and Contractor(s)
• Drive Engineering Schedule &
Deliverables to Meet
Construction’s Schedule.
27
Procurement
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
28
Procurement
Procurement Management
• Three Key Areas:
• Purchasing
• Materials Management
• Contract Management
29
Procurement
Purchasing
• Procurement of Long Lead
Items
• Ship of Equipment and
Materials to Support
Construction’s Schedule
30
Procurement
Materials Management
• Identify Most Efficient
Laydown Yard Location(s)
• Determine Best Methodology
for Pipe Transport & Interim
Storage
31
Procurement
Contract Management
• Assure Major Areas of Risk
are Prudently Allocated
• Develop Technical &
Commercial Bid Evaluation
Process
32
Construction Management
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
33
Construction Management
• Start at Conceptual Stage - Input for
Organization, Schedule & CAPEX
Cost
• Provides ROS dates for Equipment
and Material.
• Move Sense of Urgency from
Backend of the Project to Front End.
Construction Management
34
Commissioning and Start Up
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
35
Commissioning and Start Up
Commissioning &
Start Up
Activities
36
Commissioning and Start Up
Commissioning - Integrated Team Effort:
• Project Team
• Construction
• Engineering
• Major Equipment Vendors
• Operations Team
• Operations Manager
• Commissioning Manager
37
Commissioning and Start Up
Four Basic Steps:
1. Pre-Commissioning – Construction
Led
2. Mechanical Completion –
Construction Led
3. Turnover & Commissioning –
Operations Led
4. Start Up – Operations Led
38
Operations
Key Project Phases:
• Concept
• Feasibility
• FEED
• Engineering & Design
• Procurement
• Construction & Construction Management
• Commissioning & Start Up
• Operations
39
Operations
• Early Participation:
• Operational Risks
• Operations Assurance
• OPEX Organization & Cost
Estimates
• Scheduling for Commissioning &
Start-Up
Operations
40
Overview
• Oversight and Management
• Best Practices
• Critical Project Concepts
41
What is a Best Practice?
Best Practices
* Definition per Wikipedia
 A best practice is a method or technique
that has been generally accepted as
superior to any alternatives because it
produces results that are superior to those
achieved by other means or because it has
become a standard way of doing things,
e.g., a standard way of complying with legal
or ethical requirements.
42
Where We Get Best Practices?
•Internal
•Partners / Competitors
•Colleagues
•Workshops / Seminars
•Industry Websites
• Project Management Institute (PMI)
• Construction Industry Institute (CII)
Best Practices
43
*CII Best Practices Guide–Improving Project Performance includes:
Best Practices
* CII Implementation Resource 166-3, Version 3.1 / www.construction.institute.org
They offer
excellent
ideas and
thoughts,
but are
not
designed
for cut &
paste.
• Quality Management
• Benchmarking &
Metrics
• Change
Management
• Dispute Prevention &
Resolution
• Zero Accidents
Techniques
• Front End Planning
• Alignment
• Constructability
• Materials
Management
• Planning for Start Up
• Team Building
• Partnering
• Lessons Learned
44
Overview
• Oversight and Management
• Best Practices
• Critical Project Concepts
45
1. Management of Change
2. Contracting & Strategies
3. Transitions
4. Lessons Learned
5. Written Plans
Critical Project Concepts
46
Management of Change
• Concept, Feasibility, FEED, early
Engineering (until Design is
Frozen):
• Changes Encouraged to Capture
Cost & Schedule Saving
Opportunities.
MOC by Phase
47
Management of Change
• After Design Freeze:
• NO Discretionary Changes.
• Robust Hurdles Put in Place.
MOC by Phase
48
Management of Change
After Engineering/Design freeze:
• Changes Considered Only If:
• Not Safe
• Does Not Meet Regs or Specs
• Does Not Work (HAZOP Re-
validated?)
MOC Objectives by Phase
49
Management of Change
MOC Covers at a Minimum Approved:
• BOD
• PEP
• Project Specifications
• PFD’s & P&ID’s
• IFC / AFC Drawings
• Baseline Schedule
• Budget
MOC Coverage Areas
Contracting & Strategies
50
Standardized Documents Available:
• Feasibility / FEED Agreements
• Major Contract Outline Agreements
• EPC
• Engineering / Survey
• Procurement
• Construction
• Land Acquisition
• Inspection (Personnel, NDT, Vendor, etc.)
• Others
Contracting & Strategies
51
Advantages:
• Reduces Bid Cycle Time by Using
Documents 95% Complete
• Reduces Legal & Procurement
Resources
• Ability to Move Fast & Maintaining a
Competitive Position
52
Contracting & Strategies
FEED Phase
• Use FEED Competitions to
Optimize Design
• Issue as Lump Sum
53
Contracting & Strategies
EPC
• EPC Can Create Efficiencies & Synergies
Between Project Phases
• Fixed Pricing (i.e. Lump Sum or Fixed
Unit Prices) is Preferred for EPC
Contracts
• Long Lead Items - Purchased by
Company and Assigned to EPC
Contractor
54
Typical Transitions:
• Bidding & Award to Start Work
• Detail Design to Construction
• Fabrication to Installation
• Structural to Piping
• Construction to Operations
Transitions
55
Management of Transitions is Often
Overlooked (Fighting Today’s “Fire“):
• Disruptions From Poor Timing
(Transitions Too Early or Late)
While One Phase is Underway, Plan
the Next Transition
Transitions
56
Prepare a Transition Plan:
• Identify Activities to Mitigate
Impacts of Transitions
• Structured Approach to Time
the Transition
• Get Organizations & Systems
Ready Before Needed
Transitions
57
Application Plan:
• Select Top 10
• Develop a Plan for Each
• Actions
• Deliverables
• Responsibilities
• Timing
Lessons Learned
58
Why Written Plans:
• Forces You to Think Through
What You are Doing and How
• Great Tool for Communicating
Across All Levels
• Eliminates Ambiguities &
Misunderstandings
Written Plans
59
Wrap Up
Questions
Answers
and

More Related Content

What's hot

K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511REDceo.net
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP PreparationVladimir Vujovic
 
eCIO PPT Plan of Action for a Systems Integrations (SAP) Project
eCIO PPT Plan of Action for a Systems Integrations (SAP) ProjecteCIO PPT Plan of Action for a Systems Integrations (SAP) Project
eCIO PPT Plan of Action for a Systems Integrations (SAP) ProjectDavid Niles
 
Project management plan
Project management planProject management plan
Project management planGerges Fadel
 
Building Construction, Project Planning and Project Management (Level 100 Pro...
Building Construction, Project Planning and Project Management (Level 100 Pro...Building Construction, Project Planning and Project Management (Level 100 Pro...
Building Construction, Project Planning and Project Management (Level 100 Pro...Akhona Siyabulela Stuurman
 
American Electric Power Ercot kickoff
American Electric Power Ercot kickoffAmerican Electric Power Ercot kickoff
American Electric Power Ercot kickoffJohn Napier
 
PMI-ACP Domain VII - Continuous Improvement v1.0
PMI-ACP Domain VII - Continuous Improvement v1.0PMI-ACP Domain VII - Continuous Improvement v1.0
PMI-ACP Domain VII - Continuous Improvement v1.0PhuocNT (Fresher.VN)
 
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVES
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVESeCIO PPT 2000 SPI CC REWARDS AND INCENTIVES
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVESDavid Niles
 
A g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier pptA g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier pptp6academy
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope ManagementSAJJAD KHUDHUR ABBAS
 
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsDeveloping Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsWater Design-Build Council
 
Develop project charter
Develop project charterDevelop project charter
Develop project charterShereef Sabri
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
Leading Lean Six Sigma
Leading Lean Six SigmaLeading Lean Six Sigma
Leading Lean Six Sigmajackkahler
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 

What's hot (20)

K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4
 
resume-.PDF (2)
resume-.PDF (2)resume-.PDF (2)
resume-.PDF (2)
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
 
eCIO PPT Plan of Action for a Systems Integrations (SAP) Project
eCIO PPT Plan of Action for a Systems Integrations (SAP) ProjecteCIO PPT Plan of Action for a Systems Integrations (SAP) Project
eCIO PPT Plan of Action for a Systems Integrations (SAP) Project
 
Making of Stakeholders Delight
Making of Stakeholders Delight Making of Stakeholders Delight
Making of Stakeholders Delight
 
Project management plan
Project management planProject management plan
Project management plan
 
Building Construction, Project Planning and Project Management (Level 100 Pro...
Building Construction, Project Planning and Project Management (Level 100 Pro...Building Construction, Project Planning and Project Management (Level 100 Pro...
Building Construction, Project Planning and Project Management (Level 100 Pro...
 
American Electric Power Ercot kickoff
American Electric Power Ercot kickoffAmerican Electric Power Ercot kickoff
American Electric Power Ercot kickoff
 
PMI-ACP Domain VII - Continuous Improvement v1.0
PMI-ACP Domain VII - Continuous Improvement v1.0PMI-ACP Domain VII - Continuous Improvement v1.0
PMI-ACP Domain VII - Continuous Improvement v1.0
 
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVES
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVESeCIO PPT 2000 SPI CC REWARDS AND INCENTIVES
eCIO PPT 2000 SPI CC REWARDS AND INCENTIVES
 
A g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier pptA g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier ppt
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope Management
 
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsDeveloping Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
 
Develop project charter
Develop project charterDevelop project charter
Develop project charter
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
Leading Lean Six Sigma
Leading Lean Six SigmaLeading Lean Six Sigma
Leading Lean Six Sigma
 
PMO and project server 2013
PMO and project server 2013PMO and project server 2013
PMO and project server 2013
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 

Similar to Concept to Construction: Design and Build Management-Greg Lamberson, Frontier Energy Services, LLC

Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTSAJJAD KHUDHUR ABBAS
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...mike benedetto
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in projectMukesh Doshi
 
1017191EE 200 Electrical Engineering Design Project.docx
1017191EE 200 Electrical Engineering Design Project.docx1017191EE 200 Electrical Engineering Design Project.docx
1017191EE 200 Electrical Engineering Design Project.docxaulasnilda
 
Cordoba Corp: Best Practices for Security Camera Implementation
Cordoba Corp: Best  Practices for Security Camera ImplementationCordoba Corp: Best  Practices for Security Camera Implementation
Cordoba Corp: Best Practices for Security Camera ImplementationCordoba Corp
 
asug-alm-Nov 2020 - SAP Solution Manager and ALM - Your One Stop E2E Solut...
asug-alm-Nov 2020 - SAP Solution  Manager and ALM -  Your One Stop  E2E Solut...asug-alm-Nov 2020 - SAP Solution  Manager and ALM -  Your One Stop  E2E Solut...
asug-alm-Nov 2020 - SAP Solution Manager and ALM - Your One Stop E2E Solut...hemangjadhav1
 
Project Management
Project ManagementProject Management
Project ManagementXubitech
 
Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...Triumvirate Environmental
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016Aconex
 
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...Black & Veatch
 

Similar to Concept to Construction: Design and Build Management-Greg Lamberson, Frontier Energy Services, LLC (20)

Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
RFPs and RFQs: Selecting the Design-Builder
RFPs and RFQs: Selecting the Design-BuilderRFPs and RFQs: Selecting the Design-Builder
RFPs and RFQs: Selecting the Design-Builder
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
TOGAF®9.1 in Pictures
TOGAF®9.1 in PicturesTOGAF®9.1 in Pictures
TOGAF®9.1 in Pictures
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
 
1017191EE 200 Electrical Engineering Design Project.docx
1017191EE 200 Electrical Engineering Design Project.docx1017191EE 200 Electrical Engineering Design Project.docx
1017191EE 200 Electrical Engineering Design Project.docx
 
Cordoba Corp: Best Practices for Security Camera Implementation
Cordoba Corp: Best  Practices for Security Camera ImplementationCordoba Corp: Best  Practices for Security Camera Implementation
Cordoba Corp: Best Practices for Security Camera Implementation
 
asug-alm-Nov 2020 - SAP Solution Manager and ALM - Your One Stop E2E Solut...
asug-alm-Nov 2020 - SAP Solution  Manager and ALM -  Your One Stop  E2E Solut...asug-alm-Nov 2020 - SAP Solution  Manager and ALM -  Your One Stop  E2E Solut...
asug-alm-Nov 2020 - SAP Solution Manager and ALM - Your One Stop E2E Solut...
 
Project Management
Project ManagementProject Management
Project Management
 
Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
 
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
 

More from Energy Network marcus evans

Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, EastmanTransforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, EastmanEnergy Network marcus evans
 
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross EnergyPipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross EnergyEnergy Network marcus evans
 
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.Energy Network marcus evans
 
The Future of the Refining Industry - Joseph Israel, News Release
The Future of the Refining Industry -  Joseph Israel, News ReleaseThe Future of the Refining Industry -  Joseph Israel, News Release
The Future of the Refining Industry - Joseph Israel, News ReleaseEnergy Network marcus evans
 
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc. Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc. Energy Network marcus evans
 
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...Energy Network marcus evans
 
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...Energy Network marcus evans
 
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...Energy Network marcus evans
 
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...Energy Network marcus evans
 
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...Energy Network marcus evans
 
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...Energy Network marcus evans
 
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...Energy Network marcus evans
 
“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power CompanyEnergy Network marcus evans
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Energy Network marcus evans
 
The one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters mostThe one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters mostEnergy Network marcus evans
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Energy Network marcus evans
 
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar EnergyEnsuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar EnergyEnergy Network marcus evans
 
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...Energy Network marcus evans
 

More from Energy Network marcus evans (20)

Managing Project Transitions
Managing Project TransitionsManaging Project Transitions
Managing Project Transitions
 
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, EastmanTransforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
 
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross EnergyPipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
 
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
 
The Future of the Refining Industry - Joseph Israel, News Release
The Future of the Refining Industry -  Joseph Israel, News ReleaseThe Future of the Refining Industry -  Joseph Israel, News Release
The Future of the Refining Industry - Joseph Israel, News Release
 
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc. Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
 
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
 
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
 
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
 
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
 
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
 
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
 
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
 
“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Grow Your Business
Grow Your Business Grow Your Business
Grow Your Business
 
The one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters mostThe one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters most
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
 
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar EnergyEnsuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
 
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
 

Recently uploaded

Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 

Recently uploaded (20)

Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 

Concept to Construction: Design and Build Management-Greg Lamberson, Frontier Energy Services, LLC

  • 1. Frontier Energy Services, LLC Concept to Construction: Design and Build Management Energy Pipeline Management Summit July 16 – 17, 2018 Dallas, Texas
  • 2. 2 Overview • Project Development • Best Practices • Critical Project Concepts
  • 3. 3 Overview • Project Development • Best Practices • Critical Project Concepts
  • 4. 4 Oversight and Management Key Project Development Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 7. 7 Concept Key Project Development Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 8. 8 Concept Why? • Starts as an Idea / Why do it? • Meets a Need? • Fit with Current Business Environment? • Fit with Corporate Strategy? • Competition? • Exit Strategy Required?
  • 9. 9 Feasibility Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 11. 11 Feasibility Two (2) Contracting Tactics: • Internally o With SME Support • 3rd Party Consulting Firm
  • 12. 12 Feasibility If Using a 3rd Party for Feasibility and / or FEED: • Preclude 3rd Party from Bidding Next Phase • Set Firm Completion Date • Bid Lump Sum
  • 13. 13 Feasibility The Key Deliverables for Feasibility Study: • Route Selection (desk top), Including Options • Hydraulics for Pipe Sizing & Facility Placement • Level 4 Cost Estimates – CAPEX and OPEX • Technical Basis / EBOD – Pipelines & Facilities • Market Analysis (may be internal) • Level 2 Schedule • Risks & Key Issues, i.e. Environmental, Species, Logistics, Housing, Crossings, etc.
  • 14. 14 Feasibility Pipe Size vs Pump Station Spacing Assessment DIA # PS TIC % Diff 8 5 41,525,000$ -22% 10 2 42,080,000$ -21% 12 1 38,117,000$ -28% 14 1 44,443,000$ -16% 16 1 47,693,000$ -10% 18 1 52,949,000$ 0% Economic Comparison Pipe Diameter 10 Pipeline Length 237,600 TIC per foot 134.68$ Total Pipeline Cost 32,000,000$ # Pump Stations 2 HP per Pump Station 1,200 Total HP 2,400 Cost per HP 2,100.00$ Total Pump Station Costs 5,040,000$ TIC: 42,080,000$ Pipeline Costs: Pump Station Costs:
  • 15. 15 Feasibility Project Structure Project Execution / Financing: • Develop Yourself •Internal / External Financing •Debt / Equity • Partner to Reduce CAPEX or Gain a Strategic Advantage • Combinations
  • 16. 16 Feasibility FEED Phase - If Required If Project is Feasible; Move to FEED If FEED is Not Required – Move to Detail Engineering & Design. FEED on a Lump Sum Basis.
  • 17. 17 FEED The principle deliverables for FEED: • Basis of Design (BOD) • PFD’s & P&ID’s; Electrical 1-lines; Area Classifications (Facilities); Calculations; Control Philosophy; etc. • Project Specifications • Environmental Assessment & Mitigations
  • 18. 18 FEED • Vendor Quotes for Major Equipment • Long Lead Items & RFQ’s • Class III Cost Estimate - CAPEX & OPEX • Level II Schedule • Risk Assessment / Key Issues
  • 19. 19 Feasibility & FEED – Key Steps Behind the Scenes • Execution Planning: • Organization • Cost and Schedule • Procurement • Management of Change • Reporting • Independent Project Reviews
  • 20. 20 Feasibility & FEED – Key Steps • Alignment Across all Stakeholders • Do the Work to Support the Next Decision. Be Decision Driven. • Key Objectives for the Project: Prioritize & Communicate Keys to Success
  • 21. 21 Engineering and Design Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 23. 23 Engineering and Design To Be Successful - Engineering & Procurement must be Construction- Driven What Does that Mean?
  • 24. 24 Engineering and Design What Construction-Driven does not mean: • Construction Calls the Shots - What Construction Wants, Construction Gets
  • 25. 25 Engineering and Design What Construction-Driven does mean: • Construction’s Schedule Drives Engineering & Procurement Schedule. • Drawings, Equipment & Materials Ready When Required (ROS Dates).
  • 26. 26 Engineering and Design Engineering Management • Manage Interfaces & Division of Responsibilities on Company Design Team and Contractor(s) • Drive Engineering Schedule & Deliverables to Meet Construction’s Schedule.
  • 27. 27 Procurement Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 28. 28 Procurement Procurement Management • Three Key Areas: • Purchasing • Materials Management • Contract Management
  • 29. 29 Procurement Purchasing • Procurement of Long Lead Items • Ship of Equipment and Materials to Support Construction’s Schedule
  • 30. 30 Procurement Materials Management • Identify Most Efficient Laydown Yard Location(s) • Determine Best Methodology for Pipe Transport & Interim Storage
  • 31. 31 Procurement Contract Management • Assure Major Areas of Risk are Prudently Allocated • Develop Technical & Commercial Bid Evaluation Process
  • 32. 32 Construction Management Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 33. 33 Construction Management • Start at Conceptual Stage - Input for Organization, Schedule & CAPEX Cost • Provides ROS dates for Equipment and Material. • Move Sense of Urgency from Backend of the Project to Front End. Construction Management
  • 34. 34 Commissioning and Start Up Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 35. 35 Commissioning and Start Up Commissioning & Start Up Activities
  • 36. 36 Commissioning and Start Up Commissioning - Integrated Team Effort: • Project Team • Construction • Engineering • Major Equipment Vendors • Operations Team • Operations Manager • Commissioning Manager
  • 37. 37 Commissioning and Start Up Four Basic Steps: 1. Pre-Commissioning – Construction Led 2. Mechanical Completion – Construction Led 3. Turnover & Commissioning – Operations Led 4. Start Up – Operations Led
  • 38. 38 Operations Key Project Phases: • Concept • Feasibility • FEED • Engineering & Design • Procurement • Construction & Construction Management • Commissioning & Start Up • Operations
  • 39. 39 Operations • Early Participation: • Operational Risks • Operations Assurance • OPEX Organization & Cost Estimates • Scheduling for Commissioning & Start-Up Operations
  • 40. 40 Overview • Oversight and Management • Best Practices • Critical Project Concepts
  • 41. 41 What is a Best Practice? Best Practices * Definition per Wikipedia  A best practice is a method or technique that has been generally accepted as superior to any alternatives because it produces results that are superior to those achieved by other means or because it has become a standard way of doing things, e.g., a standard way of complying with legal or ethical requirements.
  • 42. 42 Where We Get Best Practices? •Internal •Partners / Competitors •Colleagues •Workshops / Seminars •Industry Websites • Project Management Institute (PMI) • Construction Industry Institute (CII) Best Practices
  • 43. 43 *CII Best Practices Guide–Improving Project Performance includes: Best Practices * CII Implementation Resource 166-3, Version 3.1 / www.construction.institute.org They offer excellent ideas and thoughts, but are not designed for cut & paste. • Quality Management • Benchmarking & Metrics • Change Management • Dispute Prevention & Resolution • Zero Accidents Techniques • Front End Planning • Alignment • Constructability • Materials Management • Planning for Start Up • Team Building • Partnering • Lessons Learned
  • 44. 44 Overview • Oversight and Management • Best Practices • Critical Project Concepts
  • 45. 45 1. Management of Change 2. Contracting & Strategies 3. Transitions 4. Lessons Learned 5. Written Plans Critical Project Concepts
  • 46. 46 Management of Change • Concept, Feasibility, FEED, early Engineering (until Design is Frozen): • Changes Encouraged to Capture Cost & Schedule Saving Opportunities. MOC by Phase
  • 47. 47 Management of Change • After Design Freeze: • NO Discretionary Changes. • Robust Hurdles Put in Place. MOC by Phase
  • 48. 48 Management of Change After Engineering/Design freeze: • Changes Considered Only If: • Not Safe • Does Not Meet Regs or Specs • Does Not Work (HAZOP Re- validated?) MOC Objectives by Phase
  • 49. 49 Management of Change MOC Covers at a Minimum Approved: • BOD • PEP • Project Specifications • PFD’s & P&ID’s • IFC / AFC Drawings • Baseline Schedule • Budget MOC Coverage Areas
  • 50. Contracting & Strategies 50 Standardized Documents Available: • Feasibility / FEED Agreements • Major Contract Outline Agreements • EPC • Engineering / Survey • Procurement • Construction • Land Acquisition • Inspection (Personnel, NDT, Vendor, etc.) • Others
  • 51. Contracting & Strategies 51 Advantages: • Reduces Bid Cycle Time by Using Documents 95% Complete • Reduces Legal & Procurement Resources • Ability to Move Fast & Maintaining a Competitive Position
  • 52. 52 Contracting & Strategies FEED Phase • Use FEED Competitions to Optimize Design • Issue as Lump Sum
  • 53. 53 Contracting & Strategies EPC • EPC Can Create Efficiencies & Synergies Between Project Phases • Fixed Pricing (i.e. Lump Sum or Fixed Unit Prices) is Preferred for EPC Contracts • Long Lead Items - Purchased by Company and Assigned to EPC Contractor
  • 54. 54 Typical Transitions: • Bidding & Award to Start Work • Detail Design to Construction • Fabrication to Installation • Structural to Piping • Construction to Operations Transitions
  • 55. 55 Management of Transitions is Often Overlooked (Fighting Today’s “Fire“): • Disruptions From Poor Timing (Transitions Too Early or Late) While One Phase is Underway, Plan the Next Transition Transitions
  • 56. 56 Prepare a Transition Plan: • Identify Activities to Mitigate Impacts of Transitions • Structured Approach to Time the Transition • Get Organizations & Systems Ready Before Needed Transitions
  • 57. 57 Application Plan: • Select Top 10 • Develop a Plan for Each • Actions • Deliverables • Responsibilities • Timing Lessons Learned
  • 58. 58 Why Written Plans: • Forces You to Think Through What You are Doing and How • Great Tool for Communicating Across All Levels • Eliminates Ambiguities & Misunderstandings Written Plans