SlideShare a Scribd company logo
1 of 36
STUDY ON PILING
( SUMMER INTERNSHIP - 2010 AS A PART OF COURSE CURRICULUM )
MOHAN PRADEEP YADLAPALLI
NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT & RESEARCH
CONTENTS
• PROJECT BACKGROUND
• FOUNDATION
• AREA OF STUDY – PILE FOUNDATION
• SALIENT FEATURES OF THE PILES IN THE SITE
• BORING OF PILE SHAFT BY DMC METHOD
• CONCRETING
• PILE TESTS
• RATE ANALYSIS
• PILE STATUS IN BALLING BUILDING (P.P - 2)
NICMAR HYDERABAD
PROJECT BACKGROUND
Essar Steel Orissa Limited (ESOL) is establishing Steel Pellet Plant in
Paradeep, Orissa to produce 12 MTPA Steel Pellets.
Primary Objective:- Essar is planning to cater the captive demand of pellets
in Essar Plant at Hazira (ESHL) using the pellets produced from the Paradeep
plant using beneficiated slurry of 58-59 %Fe.
Stage 1
Beneficiation plant of 2 x 4 MTPA
Slurry Pipeline of 12 MTPA
Pellet Plant 1 x 6 MTPA
NICMAR HYDERABAD
FOUNDATION
• Foundation is the lowest part of a structure which
provides a base for the superstructure.
• This term includes the portion of the structure
below the ground level as well as the
arrangement of concrete block, piles, raft,
grillage, etc. that are provided to transmit the
loads on the structure including self weight of the
footing itself to the soil below.
NICMAR HYDERABAD
• Foundation – Purpose
• It is used to transmit the load of the structure to
the soil below.
• To distribute the weight of the structure over
large area so as to avoid over-loading of the soil
beneath.
• To load the substratum evenly & thus prevent
unequal settlement.
• To take the structure deep into the ground & thus
increase its stability, preventing overturning.
NICMAR HYDERABAD
NICMAR HYDERABAD
AREA OF STUDY – PILE FOUNDATION
NICMAR HYDERABAD
Pile Foundations – Classification
PILES
Based on
Materials
Based on
method of
Installation
Based
on
Use
Based
on mode
of
Transfer
of load
Steel Piles
Concrete
Piles
Composite
Piles
Driven piles
Driven Cast
In
Situ piles
Bored Cast-
In –
Situ Piles
Friction
Piles
End Bearing
Piles
Tension
Piles
Sheet Piles
Compaction
piles
NICMAR HYDERABAD
NICMAR HYDERABAD
• Salient Features of piles in the site
• Composition of pile : Concrete pile – M35 Grade
• Method of installation : Bored cast in situ
• Based on function : Friction Bearing pile
• Method of Boring : Direct Mud Circulation (DMC)
• Length of the pile : 23m below cut off level
• Diameter of piles : 450mm, 500mm, 600mm
• Total no. of piles : 539
• Sub contractor – Bhagaban Mohapatra Constructions
& Engineers Pvt. Ltd, Bhubaneshwar
NICMAR HYDERABAD
• Boring of Pile by DMC method
• Main accessories are
1. Tripod
2. Winch Machine
3. Bailor
4. Chisel
5. DMC rods
6. Tremie pipes
NICMAR HYDERABAD
Winch operator operating winch machine Tremie pipes
Bailor Chisel
NICMAR HYDERABAD
DMC rods
DMC rods/Tremie pipe stopper
Bentonite mixing tank Concrete hopper
NICMAR HYDERABAD
Process of boring a pile shaft
NICMAR HYDERABAD
• Steps to be taken care while boring a pile
• Ensure that the rigs are placed exactly on the pile
point.
• While lowering the reinforcement care should be
taken to ensure the lap length to be 50D
• Before washing, the density of bentonite to be
checked by using hydrometer
• The density of bentonite slurry should be in
between 1.03 gm/ml to 1.10 gm/ml
NICMAR HYDERABAD
• USE OF BENTONITE IN PILING
• In order to keep the sides of the bore intact bentonite is used for drilling by
suspending it in water to form a viscous material.
• Bentonite suspensions begin to take on the characteristics of a gel
• For these reasons it is a common component of drilling mud used to curtail
drilling fluid invasion and stabilise the bore.
• All bentonites have a capacity to exchange cations.
• Suggestions
• Mixing of bentonite should be done by Agitator rather than manual mixing.
NICMAR HYDERABAD
• Bentonite Properties
S.n
o
Type of Test Method of Test Permissible limits (at
20°C)
1 Density Mud balance or Hydrometer 1.03 g/ml to 1.1 g/ml
2 Viscosity Marsh cone 30 sec to 90 sec
3 pH Value pH paper strips 9.5 to 12
4 10minute Strength Gel Shearometer or vane shear
apparatus
1.4 to 10 N/m2
5 Liquid Limit Casagrande’s Apparatus Less than 300% & not
more than 450%
6 Free Swell Consolidation Apparatus Shall be more than
540%
NICMAR HYDERABAD
• Concreting
NICMAR HYDERABAD
• The volume of the concrete hopper is 0.86Cum.
• For 450mm diameter pile
• Volume of concrete for 1m = 0.159m3
• For 500mm diameter pile
• Volume of concrete for 1m = 0.196m3
• For 600mm diameter pile
• Volume of concrete for 1m = 0.283m3
NICMAR HYDERABAD
• The length of one tremie pipe is 1.6m
• For 600mm diameter volume for 1m = 0.283m3
• Therefore for 1.6m volume of concrete = 0.453m3
• But the volume of concrete in the hopper is 0.86m3
• So at time one tremie pipe can be removed from the
pile shaft of 600mm diameter.
NICMAR HYDERABAD
• For 500mm diameter pile
• Volume of concrete for 1m = 0.196m3
• Therefore for 1.6m volume of concrete = 0.3136m3
• Volume of concrete hopper = 0.86m3
• So at a time two tremie pipes can be removed from
the pile shaft.
NICMAR HYDERABAD
Pile Load Test
NICMAR HYDERABAD
Types of Pile Load Test
LOAD
TEST
DESTRUCTIVE
TEST
NON
DESTRUCTIVE
(NDT)
VERTICAL
LOAD TEST
LATERAL
LOAD TEST
PULL OUT
LOAD TEST
LOW STRAIN HIGH STRAIN
SONIC LOGGINGPILE INTEGRITY
NICMAR HYDERABAD
• Vertical Load Test
NICMAR HYDERABAD
NICMAR HYDERABAD
NICMAR HYDERABAD
• Pull out Test
NICMAR HYDERABAD
• Table for Pull out Test
S.
no
Date Time Increment load
in tons
Cumulative Dial gauge
readings
Average
A B
NICMAR HYDERABAD
• Pile Integrity Test
• Concept
NICMAR HYDERABAD
NICMAR HYDERABAD
Typical PIT plot – For good pile
Typical PIT record for a doubtful pile
NICMAR HYDERABAD
Rate analysis for piles
• Rate analysis for 500mm diameter pile
• Assumptions considered are
Concrete Grade M – 35
Bore diameter 500mm
Bore depth 23m
EPIL’s Scope Concrete &
Reinforcement
are provided
free of cost
NICMAR HYDERABAD
Sub contractors cost – A
S.No Items Units Total Qty Rate per unit
(Given in
WO)
Total cost
1 Shifting of rigs and Boring cost (below cut off level) Metre 23m 800/m 18400
2 Reinforcement cost (Cutting, bending and placing
in bore)
MT 0.4951 7000 3466
3 Pouring Concretie – M35 M 23m 260 5980
4 Static compressive No 1 1160 1160
5 Routine static compressive No 1 1080 1080
6 Lateral load test No 1 350 350
Total Cost 30436
NICMAR HYDERABAD
Material cost - B
S.N
o
Description Quantity Cost Total Cost
1 Concrete – M35
Grade
4.665 Cum Rs
4250/Cum
Rs 19826/-
2 Reinforcement 495.094 Kg Rs
30000/ton
Rs 14852/-
Total Material Cost Rs 34678/-
Total Cost (A+B) Rs 65114/-
Over heads (10%
T.C)
Rs 6511/-
Profit (10% T.C) Rs 6511/-
Grand Total Rs 78136/-
NICMAR HYDERABAD
PILE STATUS
S. NO. PERIOD TOTAL
NO. OF PILES
COMPLETED
NO. OF PILES
REMAINING
1 FEB 539 60 479
2 MAR 479 162 317
3 APR 317 115 202
4 MAY 202 87 115
5 JUNE 115 66 49
NICMAR HYDERABAD
ESSAR
Paradeep
!
NICMAR HYDERABAD

More Related Content

What's hot

BIDEMICS_metric
BIDEMICS_metricBIDEMICS_metric
BIDEMICS_metric
Glynn Shaw
 
500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT
Guo ke
 
Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13
Chris Yarnell
 
APDM - companion flange manufacturing report
APDM - companion flange manufacturing reportAPDM - companion flange manufacturing report
APDM - companion flange manufacturing report
Kerrie Noble
 
iaetsd Thermal energy audit of kiln system in a cement plant
iaetsd Thermal energy audit of kiln system in a cement plantiaetsd Thermal energy audit of kiln system in a cement plant
iaetsd Thermal energy audit of kiln system in a cement plant
Iaetsd Iaetsd
 

What's hot (20)

Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
Complexity of pilgering in nuclear applications
Complexity of pilgering in nuclear applicationsComplexity of pilgering in nuclear applications
Complexity of pilgering in nuclear applications
 
Design and analysis of ball mill inlet chute for roller press circuit in ceme...
Design and analysis of ball mill inlet chute for roller press circuit in ceme...Design and analysis of ball mill inlet chute for roller press circuit in ceme...
Design and analysis of ball mill inlet chute for roller press circuit in ceme...
 
Structures for high speed machines
Structures for high speed machinesStructures for high speed machines
Structures for high speed machines
 
Mineral Processing - Crushing - Plant design, construction, operation and op...
Mineral Processing - Crushing  - Plant design, construction, operation and op...Mineral Processing - Crushing  - Plant design, construction, operation and op...
Mineral Processing - Crushing - Plant design, construction, operation and op...
 
7machinetool
7machinetool7machinetool
7machinetool
 
Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
BIDEMICS_metric
BIDEMICS_metricBIDEMICS_metric
BIDEMICS_metric
 
Block 4 SP 14
Block 4 SP 14Block 4 SP 14
Block 4 SP 14
 
500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT
 
Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13
 
Mr81 231
Mr81 231Mr81 231
Mr81 231
 
Pelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipmentsPelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipments
 
sail bokaro
sail bokarosail bokaro
sail bokaro
 
APDM - companion flange manufacturing report
APDM - companion flange manufacturing reportAPDM - companion flange manufacturing report
APDM - companion flange manufacturing report
 
Gear finishing processes
Gear finishing processesGear finishing processes
Gear finishing processes
 
Block 2 SP 14
Block 2 SP 14Block 2 SP 14
Block 2 SP 14
 
Lapping Machine Process and Application
Lapping Machine Process and ApplicationLapping Machine Process and Application
Lapping Machine Process and Application
 
iaetsd Thermal energy audit of kiln system in a cement plant
iaetsd Thermal energy audit of kiln system in a cement plantiaetsd Thermal energy audit of kiln system in a cement plant
iaetsd Thermal energy audit of kiln system in a cement plant
 
Braoching Operation
Braoching OperationBraoching Operation
Braoching Operation
 

Viewers also liked

A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ Piles
Subham Kundu
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
Winter Sonata
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
Subham Kundu
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
Tong Seng Chua
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
Ahmed Zanaty
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
Minh Bui Si
 

Viewers also liked (20)

DMC Piling
DMC PilingDMC Piling
DMC Piling
 
DMC piling
DMC pilingDMC piling
DMC piling
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
certificate20037782
certificate20037782certificate20037782
certificate20037782
 
Cmh bp profile 2013
Cmh bp profile 2013Cmh bp profile 2013
Cmh bp profile 2013
 
construction procedure of DMC piling
construction procedure of DMC pilingconstruction procedure of DMC piling
construction procedure of DMC piling
 
ARIES CURRENT PROFILE
ARIES CURRENT PROFILEARIES CURRENT PROFILE
ARIES CURRENT PROFILE
 
Mtech Project_2013_ppt
Mtech Project_2013_pptMtech Project_2013_ppt
Mtech Project_2013_ppt
 
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
 
2.foundation
2.foundation2.foundation
2.foundation
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ Piles
 
any
anyany
any
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
Pile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsPile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipments
 
Mat or raft foundation
Mat or raft foundationMat or raft foundation
Mat or raft foundation
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 

Similar to SIP- final - LinkedIn

HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)
Pushon Ghosh
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
muralikrishna317515
 

Similar to SIP- final - LinkedIn (20)

new_presentation7.ppt
new_presentation7.pptnew_presentation7.ppt
new_presentation7.ppt
 
2018 extreme drilling llp
2018 extreme drilling llp2018 extreme drilling llp
2018 extreme drilling llp
 
Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls
 
Final Fully integrated presentation for JSPL SSD products
Final Fully integrated presentation for JSPL SSD productsFinal Fully integrated presentation for JSPL SSD products
Final Fully integrated presentation for JSPL SSD products
 
HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
 
1.Pile foundations 2021 (1).pptx
1.Pile foundations 2021 (1).pptx1.Pile foundations 2021 (1).pptx
1.Pile foundations 2021 (1).pptx
 
Pre- Feasibility study of a low grade iron ore http://mineralprocessingconsul...
Pre- Feasibility study of a low grade iron ore http://mineralprocessingconsul...Pre- Feasibility study of a low grade iron ore http://mineralprocessingconsul...
Pre- Feasibility study of a low grade iron ore http://mineralprocessingconsul...
 
National bearing corporation
National bearing corporationNational bearing corporation
National bearing corporation
 
CONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptxCONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptx
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
Basics to Mining & Mineral Processing
Basics to Mining & Mineral Processing Basics to Mining & Mineral Processing
Basics to Mining & Mineral Processing
 
Fundamentals of manufacturing and Casting Process
Fundamentals of manufacturing and Casting ProcessFundamentals of manufacturing and Casting Process
Fundamentals of manufacturing and Casting Process
 
BM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.pptBM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.ppt
 
Advances in the Grinding of Aerospace Engine Materials
Advances in the Grinding of Aerospace Engine MaterialsAdvances in the Grinding of Aerospace Engine Materials
Advances in the Grinding of Aerospace Engine Materials
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Process Boilers PPT
Process Boilers PPTProcess Boilers PPT
Process Boilers PPT
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
 
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
 
Gulshan rahangdale
Gulshan rahangdaleGulshan rahangdale
Gulshan rahangdale
 

SIP- final - LinkedIn

  • 1. STUDY ON PILING ( SUMMER INTERNSHIP - 2010 AS A PART OF COURSE CURRICULUM ) MOHAN PRADEEP YADLAPALLI NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT & RESEARCH
  • 2. CONTENTS • PROJECT BACKGROUND • FOUNDATION • AREA OF STUDY – PILE FOUNDATION • SALIENT FEATURES OF THE PILES IN THE SITE • BORING OF PILE SHAFT BY DMC METHOD • CONCRETING • PILE TESTS • RATE ANALYSIS • PILE STATUS IN BALLING BUILDING (P.P - 2) NICMAR HYDERABAD
  • 3. PROJECT BACKGROUND Essar Steel Orissa Limited (ESOL) is establishing Steel Pellet Plant in Paradeep, Orissa to produce 12 MTPA Steel Pellets. Primary Objective:- Essar is planning to cater the captive demand of pellets in Essar Plant at Hazira (ESHL) using the pellets produced from the Paradeep plant using beneficiated slurry of 58-59 %Fe. Stage 1 Beneficiation plant of 2 x 4 MTPA Slurry Pipeline of 12 MTPA Pellet Plant 1 x 6 MTPA NICMAR HYDERABAD
  • 4. FOUNDATION • Foundation is the lowest part of a structure which provides a base for the superstructure. • This term includes the portion of the structure below the ground level as well as the arrangement of concrete block, piles, raft, grillage, etc. that are provided to transmit the loads on the structure including self weight of the footing itself to the soil below. NICMAR HYDERABAD
  • 5. • Foundation – Purpose • It is used to transmit the load of the structure to the soil below. • To distribute the weight of the structure over large area so as to avoid over-loading of the soil beneath. • To load the substratum evenly & thus prevent unequal settlement. • To take the structure deep into the ground & thus increase its stability, preventing overturning. NICMAR HYDERABAD
  • 7. AREA OF STUDY – PILE FOUNDATION NICMAR HYDERABAD
  • 8. Pile Foundations – Classification PILES Based on Materials Based on method of Installation Based on Use Based on mode of Transfer of load Steel Piles Concrete Piles Composite Piles Driven piles Driven Cast In Situ piles Bored Cast- In – Situ Piles Friction Piles End Bearing Piles Tension Piles Sheet Piles Compaction piles NICMAR HYDERABAD
  • 10. • Salient Features of piles in the site • Composition of pile : Concrete pile – M35 Grade • Method of installation : Bored cast in situ • Based on function : Friction Bearing pile • Method of Boring : Direct Mud Circulation (DMC) • Length of the pile : 23m below cut off level • Diameter of piles : 450mm, 500mm, 600mm • Total no. of piles : 539 • Sub contractor – Bhagaban Mohapatra Constructions & Engineers Pvt. Ltd, Bhubaneshwar NICMAR HYDERABAD
  • 11. • Boring of Pile by DMC method • Main accessories are 1. Tripod 2. Winch Machine 3. Bailor 4. Chisel 5. DMC rods 6. Tremie pipes NICMAR HYDERABAD
  • 12. Winch operator operating winch machine Tremie pipes Bailor Chisel NICMAR HYDERABAD
  • 13. DMC rods DMC rods/Tremie pipe stopper Bentonite mixing tank Concrete hopper NICMAR HYDERABAD
  • 14. Process of boring a pile shaft NICMAR HYDERABAD
  • 15. • Steps to be taken care while boring a pile • Ensure that the rigs are placed exactly on the pile point. • While lowering the reinforcement care should be taken to ensure the lap length to be 50D • Before washing, the density of bentonite to be checked by using hydrometer • The density of bentonite slurry should be in between 1.03 gm/ml to 1.10 gm/ml NICMAR HYDERABAD
  • 16. • USE OF BENTONITE IN PILING • In order to keep the sides of the bore intact bentonite is used for drilling by suspending it in water to form a viscous material. • Bentonite suspensions begin to take on the characteristics of a gel • For these reasons it is a common component of drilling mud used to curtail drilling fluid invasion and stabilise the bore. • All bentonites have a capacity to exchange cations. • Suggestions • Mixing of bentonite should be done by Agitator rather than manual mixing. NICMAR HYDERABAD
  • 17. • Bentonite Properties S.n o Type of Test Method of Test Permissible limits (at 20°C) 1 Density Mud balance or Hydrometer 1.03 g/ml to 1.1 g/ml 2 Viscosity Marsh cone 30 sec to 90 sec 3 pH Value pH paper strips 9.5 to 12 4 10minute Strength Gel Shearometer or vane shear apparatus 1.4 to 10 N/m2 5 Liquid Limit Casagrande’s Apparatus Less than 300% & not more than 450% 6 Free Swell Consolidation Apparatus Shall be more than 540% NICMAR HYDERABAD
  • 19. • The volume of the concrete hopper is 0.86Cum. • For 450mm diameter pile • Volume of concrete for 1m = 0.159m3 • For 500mm diameter pile • Volume of concrete for 1m = 0.196m3 • For 600mm diameter pile • Volume of concrete for 1m = 0.283m3 NICMAR HYDERABAD
  • 20. • The length of one tremie pipe is 1.6m • For 600mm diameter volume for 1m = 0.283m3 • Therefore for 1.6m volume of concrete = 0.453m3 • But the volume of concrete in the hopper is 0.86m3 • So at time one tremie pipe can be removed from the pile shaft of 600mm diameter. NICMAR HYDERABAD
  • 21. • For 500mm diameter pile • Volume of concrete for 1m = 0.196m3 • Therefore for 1.6m volume of concrete = 0.3136m3 • Volume of concrete hopper = 0.86m3 • So at a time two tremie pipes can be removed from the pile shaft. NICMAR HYDERABAD
  • 23. Types of Pile Load Test LOAD TEST DESTRUCTIVE TEST NON DESTRUCTIVE (NDT) VERTICAL LOAD TEST LATERAL LOAD TEST PULL OUT LOAD TEST LOW STRAIN HIGH STRAIN SONIC LOGGINGPILE INTEGRITY NICMAR HYDERABAD
  • 24. • Vertical Load Test NICMAR HYDERABAD
  • 27. • Pull out Test NICMAR HYDERABAD
  • 28. • Table for Pull out Test S. no Date Time Increment load in tons Cumulative Dial gauge readings Average A B NICMAR HYDERABAD
  • 29. • Pile Integrity Test • Concept NICMAR HYDERABAD
  • 31. Typical PIT plot – For good pile Typical PIT record for a doubtful pile NICMAR HYDERABAD
  • 32. Rate analysis for piles • Rate analysis for 500mm diameter pile • Assumptions considered are Concrete Grade M – 35 Bore diameter 500mm Bore depth 23m EPIL’s Scope Concrete & Reinforcement are provided free of cost NICMAR HYDERABAD
  • 33. Sub contractors cost – A S.No Items Units Total Qty Rate per unit (Given in WO) Total cost 1 Shifting of rigs and Boring cost (below cut off level) Metre 23m 800/m 18400 2 Reinforcement cost (Cutting, bending and placing in bore) MT 0.4951 7000 3466 3 Pouring Concretie – M35 M 23m 260 5980 4 Static compressive No 1 1160 1160 5 Routine static compressive No 1 1080 1080 6 Lateral load test No 1 350 350 Total Cost 30436 NICMAR HYDERABAD
  • 34. Material cost - B S.N o Description Quantity Cost Total Cost 1 Concrete – M35 Grade 4.665 Cum Rs 4250/Cum Rs 19826/- 2 Reinforcement 495.094 Kg Rs 30000/ton Rs 14852/- Total Material Cost Rs 34678/- Total Cost (A+B) Rs 65114/- Over heads (10% T.C) Rs 6511/- Profit (10% T.C) Rs 6511/- Grand Total Rs 78136/- NICMAR HYDERABAD
  • 35. PILE STATUS S. NO. PERIOD TOTAL NO. OF PILES COMPLETED NO. OF PILES REMAINING 1 FEB 539 60 479 2 MAR 479 162 317 3 APR 317 115 202 4 MAY 202 87 115 5 JUNE 115 66 49 NICMAR HYDERABAD

Editor's Notes

  1. Anand George Mohammed Sameer Shrikant Kokate