SlideShare a Scribd company logo
1 of 18
Tariff
Determination
for Hydro Power
Plant
Krishnakumar R V
M.E Power Engineering & Management
Anna University, Chennai
General Concepts
(i) Additional capitalization
Additional capitalisation means the capital expenditure
incurred or projected to be incurred, after the date of
commercial operation of the project and admitted by the
Commission.
(ii) Auxiliary energy consumption
The quantum of energy consumed by auxiliary equipment
of the generating station, and transformer losses within
the generating station, expressed as a percentage of the
sum of gross energy generated at the generator terminals
of all the units of the generating station.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
2
General Concepts
Contd.,
(iii) Capital cost
Capital Cost for a Project includes the expenditure
incurred or projected to be incurred, including interest
during construction and financing charges, any gain or
loss on account of foreign exchange risk variation during
construction on the loan.
(iv) Date of Commercial Operation’ or ‘COD’
The date declared by the Generating company after
demonstrating peaking capability corresponding to
Installed capacity of the Generating station through a
successful trial run, after notice to the beneficiaries.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
3
General Concepts
Contd.,
(v) Debt-Equity Ratio
Debt–Equity ratio as on the date of commercial operation
shall be considered as 70:30 for determination of tariff.
However, if the Equity employed is more than 30%, the
amount of Equity for determination of tariff would be
limited to 30%. Also, if the actual equity employed by the
developer is less than 30%, the actual Debt and Equity
would considered for determination of tariff.
(vi) Declared capacity
The capability to deliver ex-bus electricity in MW declared
by such generating station in relation to any time-block of
the day or whole of the day, duly taking into account the
availability of fuel or water, and subject to further
qualification in the relevant regulation.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
4
General Concepts
Contd.,
(vii) Design energy
Design energy means the quantum of energy which can be
generated in a 90% dependable year with 95% installed
capacity of the Hydro generating station.
(viii) Operation and Maintenance expenses
The expenditure incurred on operation and maintenance of
the project, or part thereof, and includes the expenditure on
manpower, repairs, spares, consumables, insurance and
overheads.
(xii) Plant availability factor (PAF)
The average of the daily declared capacities (DCs) for all the
days during that period expressed as a percentage of the
installed capacity in MW reduced by the normative auxiliary
energy consumption.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
5
General Concepts
Contd.,
(viii) Normative Annual Plant Availability Factor (NAPAF)
Normative annual plant availability factor (NAPAF) for Hydro
generating stations is determined by the Commission as per the
following criteria:
(a) Storage and Pondage type plants with head variation between
Full Reservoir Level (FRL) and Minimum Draw Down Level
(MDDL) of up to 8%, and where plant availability is not affected
by silt : 90%
(b) Storage and Pondage type plants with head variation between
FRL and MDDL of more than 8%, where plant availability is not
affected by silt : (Average head / Rated head) + 0.02
(c) Pondage type plants where plant availability is significantly
affected by silt: 85%.
(d) Run-of-river type plants: NAPAF to be determined plant-wise,
based on 10-day design energy data, moderated by past experience
where available/relevant.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
6
General Concepts
Contd.,
(xiii) Capacity Index (CI)
Capacity Index (CI) = {Declared Capacity (MW) /
Maximum Available Capacity (MW)} x 100
Where, Declared Capacity (DC) is the power that is
expected to be generated next day based on availability of
water & machine; and Maximum Available Capacity
(MAC) is the maximum power that a station can generate
with all units running, under the prevailing water levels
and flows over the peaking hours next day.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
7
Components of Fixed Charge
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
8
Interest on Working Capital
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
9
Capacity Charge
Capacity Charge (Rs) = AFC x 0.5 x NDM / NDY x (PAFM / NAPAF)
• AFC (Rs) = Annual fixed cost as specified by the Commission for the year
• NAPAF = Normative Plant availability factor, in percentage
• NDM = Number of days in the month
• NDY = Number of days in the year
• PAFM = Plant availability factor achieved during the month, in
Percentage
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
10
Capacity Charge
Contd.,
PAFM = 10000 X ∑ DCi / {N x IC x (100 – Aux)}%
• AUX = Normative auxiliary energy consumption in
percentage
• DCi = Declared capacity (in ex-bus MW) for the ith day of the
month which the station can deliver for at least three (3)
hours
• IC = Installed capacity (in MW) of the complete generating
station
• N = Number of days in the month
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
11
Energy charges
• The Energy charge are payable by each beneficiary for the total energy
scheduled to be supplied to the beneficiary
Total Energy charge payable to the generating company for a month:
(Energy charge rate in Rs./kWh) x {Scheduled energy for the month in
kWh} x (100 – FEHS) / 100
Energy charge rate = AFC x 0.5 x 10 / {DE x (100 – AUX) x (100 –
FEHS)}
Where,
• DE (MWh) = Annual design energy specified for the Hydro generating
station
• FEHS (%) = Free energy for the home State
• CERC has capped the Energy charge rate at Rs 0.80/Unit
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
12
Tariff determination for a 500
MW Hydro Power Plant
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
13
Calculations
Return on equity
1. Capital cost/MW= Rs. 6 Cr
2. Capital cost for 500 MW = 500 x 6= Rs. 3,000 Cr.
3. Normative Debt/Equity Ratio= 70:30
4. Equity = 30/100 X 3000 = Rs. 900 Cr.
5. Debt =70/100 X 3000 = Rs. 2, 100 Cr.
RoE = 15.5% of Equity
= 15.5/100 x 900 = Rs. 139.50 Cr.
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
14
Calculations
(2) Interest on Loan
10% of Debt=10 /100 x 2100 =Rs. 210 Cr.
(3) Interest on Working capital
10% of Working capital (Rs. 300 Cr.)
10/100 x 300 = Rs. 30 Cr.
(4) Depreciation
5.28% of Capital cost= 5.28/100 x 3000= Rs. 158.40 Cr.
• (5) O & M Cost
• Normative O&M Cost: 2% of Project Cost
• 2% x 3000 = Rs. 60 Cr
• Hence, Total Fixed cost = (1) + (2) + (3) + (4) + (5)
• = Rs. (139.50+210+30+158.40+60) = Rs. 597.90 Cr. = Rs. 597.90 x 107
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
15
Calculations
Contd.,
Annual Energy generation
Gross Energy generated in the Year
500 MW = 500 x 365 x 24 x 90 x 1000/ 106
= 3942 Million Units (MUs)
= 3942 x 106 Units
Auxiliary consumption: 1%
Net Annual Energy generation:
=Gross energy x (1 – Aux consumption)
= 3942 x 106 x (1 - 1%)
= 3902.58 x 106 Units
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
16
Calculations
Contd.,
Fixed cost per unit
Fixed Cost/Unit = (Total Fixed Cost) / (Net Annual
Energy generation)
= (597.90 x 107) / (3902.58 x 106)
= Rs 1.53 / kWh
Nominal Tariff:
Nominal Tariff = (Fixed Cost / Unit) + (Variable cost
/Unit)
= Rs (1.53 + 0)/Unit
= Rs. 1.53/Unit
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
17
THANK YOU
8/1/2017
DeptOfPowerEngg&Mgmt,AnnaUniversity,
Chennai
18

More Related Content

What's hot

Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Ryan Triadhitama
 
Hydroelectric powerplant
Hydroelectric  powerplantHydroelectric  powerplant
Hydroelectric powerplantAbhi1900
 
PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANTNilanjana Sen
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantNishkam Dhiman
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Power System Operation
 
Small hydro power in india
Small hydro power in indiaSmall hydro power in india
Small hydro power in indiaAshish Verma
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTvikaspanch
 
Hydro POWER PLANT
Hydro POWER PLANTHydro POWER PLANT
Hydro POWER PLANTsoprajap
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scadaHemendra Kumar Rajput
 
Hydroelectric power plant
Hydroelectric power plant Hydroelectric power plant
Hydroelectric power plant Ravindra Kolhe
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case studyWaseem Hashmat
 
UKAI HYDRO POWER PLANT VISIT
UKAI HYDRO POWER PLANT VISITUKAI HYDRO POWER PLANT VISIT
UKAI HYDRO POWER PLANT VISITSAURAV DAYAL SING
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?Power System Operation
 
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)shyamies11
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc systemAazim Rasool
 

What's hot (20)

Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Hydroelectric powerplant
Hydroelectric  powerplantHydroelectric  powerplant
Hydroelectric powerplant
 
PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANT
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
 
Small hydro power in india
Small hydro power in indiaSmall hydro power in india
Small hydro power in india
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANT
 
Hydro POWER PLANT
Hydro POWER PLANTHydro POWER PLANT
Hydro POWER PLANT
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scada
 
Hydroelectric power plant
Hydroelectric power plant Hydroelectric power plant
Hydroelectric power plant
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case study
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Demand Side Management
Demand Side ManagementDemand Side Management
Demand Side Management
 
UKAI HYDRO POWER PLANT VISIT
UKAI HYDRO POWER PLANT VISITUKAI HYDRO POWER PLANT VISIT
UKAI HYDRO POWER PLANT VISIT
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?
 
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
 
9 system-sizing
9 system-sizing9 system-sizing
9 system-sizing
 
Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in India
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc system
 

Similar to Tariff determination for hydro power plant

T Divya CV
T Divya CVT Divya CV
T Divya CVDIVYA T
 
Economics of Power Generation(4) h.pdf
Economics of Power Generation(4)       h.pdfEconomics of Power Generation(4)       h.pdf
Economics of Power Generation(4) h.pdfMahamad Jawhar
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNISTS.Vijaya Bhaskar
 
Capacity planning
Capacity planningCapacity planning
Capacity planningRatan479
 
Lecture 16_Unit 6. Economic Analysis of Power Plants
Lecture 16_Unit 6. Economic Analysis of Power PlantsLecture 16_Unit 6. Economic Analysis of Power Plants
Lecture 16_Unit 6. Economic Analysis of Power PlantsRushikesh Sonar
 
Introduction to Sciemus Wind
Introduction to Sciemus WindIntroduction to Sciemus Wind
Introduction to Sciemus WindSciemus
 
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...
Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...IRJET Journal
 
Maintenance and Projects 16+ Yrs in Automotive Industry
Maintenance and Projects 16+ Yrs in Automotive IndustryMaintenance and Projects 16+ Yrs in Automotive Industry
Maintenance and Projects 16+ Yrs in Automotive IndustryNishant Patil
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential BuildingIRJET Journal
 
Energy Benchmarking For cement Industry Final Copy.pdf
Energy Benchmarking For cement Industry Final Copy.pdfEnergy Benchmarking For cement Industry Final Copy.pdf
Energy Benchmarking For cement Industry Final Copy.pdfMan_Ebook
 
Meghalaya Wind Energy
Meghalaya Wind Energy Meghalaya Wind Energy
Meghalaya Wind Energy Siraj Ahmed
 
Enhancing the Electric Grid Reliability through Data Analytics
Enhancing the Electric Grid Reliability through Data Analytics Enhancing the Electric Grid Reliability through Data Analytics
Enhancing the Electric Grid Reliability through Data Analytics Mrinalini Sharma
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologiesLeonardo ENERGY
 

Similar to Tariff determination for hydro power plant (20)

CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption
 
T Divya CV
T Divya CVT Divya CV
T Divya CV
 
Economics of Power Generation(4) h.pdf
Economics of Power Generation(4)       h.pdfEconomics of Power Generation(4)       h.pdf
Economics of Power Generation(4) h.pdf
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
 
Activity based costing
Activity based costingActivity based costing
Activity based costing
 
Availability Based Tariff and UI charges
Availability Based Tariff and UI chargesAvailability Based Tariff and UI charges
Availability Based Tariff and UI charges
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Lecture 16_Unit 6. Economic Analysis of Power Plants
Lecture 16_Unit 6. Economic Analysis of Power PlantsLecture 16_Unit 6. Economic Analysis of Power Plants
Lecture 16_Unit 6. Economic Analysis of Power Plants
 
Introduction to Sciemus Wind
Introduction to Sciemus WindIntroduction to Sciemus Wind
Introduction to Sciemus Wind
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...
Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...
 
Maintenance and Projects 16+ Yrs in Automotive Industry
Maintenance and Projects 16+ Yrs in Automotive IndustryMaintenance and Projects 16+ Yrs in Automotive Industry
Maintenance and Projects 16+ Yrs in Automotive Industry
 
Chain Drive Power Generation in Roadways by Using Vehicles
Chain Drive Power Generation in Roadways by Using VehiclesChain Drive Power Generation in Roadways by Using Vehicles
Chain Drive Power Generation in Roadways by Using Vehicles
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
 
Electric vehicles
Electric vehiclesElectric vehicles
Electric vehicles
 
Energy Benchmarking For cement Industry Final Copy.pdf
Energy Benchmarking For cement Industry Final Copy.pdfEnergy Benchmarking For cement Industry Final Copy.pdf
Energy Benchmarking For cement Industry Final Copy.pdf
 
Meghalaya Wind Energy
Meghalaya Wind Energy Meghalaya Wind Energy
Meghalaya Wind Energy
 
Enhancing the Electric Grid Reliability through Data Analytics
Enhancing the Electric Grid Reliability through Data Analytics Enhancing the Electric Grid Reliability through Data Analytics
Enhancing the Electric Grid Reliability through Data Analytics
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Tariff determination for hydro power plant

  • 1. Tariff Determination for Hydro Power Plant Krishnakumar R V M.E Power Engineering & Management Anna University, Chennai
  • 2. General Concepts (i) Additional capitalization Additional capitalisation means the capital expenditure incurred or projected to be incurred, after the date of commercial operation of the project and admitted by the Commission. (ii) Auxiliary energy consumption The quantum of energy consumed by auxiliary equipment of the generating station, and transformer losses within the generating station, expressed as a percentage of the sum of gross energy generated at the generator terminals of all the units of the generating station. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 2
  • 3. General Concepts Contd., (iii) Capital cost Capital Cost for a Project includes the expenditure incurred or projected to be incurred, including interest during construction and financing charges, any gain or loss on account of foreign exchange risk variation during construction on the loan. (iv) Date of Commercial Operation’ or ‘COD’ The date declared by the Generating company after demonstrating peaking capability corresponding to Installed capacity of the Generating station through a successful trial run, after notice to the beneficiaries. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 3
  • 4. General Concepts Contd., (v) Debt-Equity Ratio Debt–Equity ratio as on the date of commercial operation shall be considered as 70:30 for determination of tariff. However, if the Equity employed is more than 30%, the amount of Equity for determination of tariff would be limited to 30%. Also, if the actual equity employed by the developer is less than 30%, the actual Debt and Equity would considered for determination of tariff. (vi) Declared capacity The capability to deliver ex-bus electricity in MW declared by such generating station in relation to any time-block of the day or whole of the day, duly taking into account the availability of fuel or water, and subject to further qualification in the relevant regulation. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 4
  • 5. General Concepts Contd., (vii) Design energy Design energy means the quantum of energy which can be generated in a 90% dependable year with 95% installed capacity of the Hydro generating station. (viii) Operation and Maintenance expenses The expenditure incurred on operation and maintenance of the project, or part thereof, and includes the expenditure on manpower, repairs, spares, consumables, insurance and overheads. (xii) Plant availability factor (PAF) The average of the daily declared capacities (DCs) for all the days during that period expressed as a percentage of the installed capacity in MW reduced by the normative auxiliary energy consumption. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 5
  • 6. General Concepts Contd., (viii) Normative Annual Plant Availability Factor (NAPAF) Normative annual plant availability factor (NAPAF) for Hydro generating stations is determined by the Commission as per the following criteria: (a) Storage and Pondage type plants with head variation between Full Reservoir Level (FRL) and Minimum Draw Down Level (MDDL) of up to 8%, and where plant availability is not affected by silt : 90% (b) Storage and Pondage type plants with head variation between FRL and MDDL of more than 8%, where plant availability is not affected by silt : (Average head / Rated head) + 0.02 (c) Pondage type plants where plant availability is significantly affected by silt: 85%. (d) Run-of-river type plants: NAPAF to be determined plant-wise, based on 10-day design energy data, moderated by past experience where available/relevant. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 6
  • 7. General Concepts Contd., (xiii) Capacity Index (CI) Capacity Index (CI) = {Declared Capacity (MW) / Maximum Available Capacity (MW)} x 100 Where, Declared Capacity (DC) is the power that is expected to be generated next day based on availability of water & machine; and Maximum Available Capacity (MAC) is the maximum power that a station can generate with all units running, under the prevailing water levels and flows over the peaking hours next day. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 7
  • 8. Components of Fixed Charge 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 8
  • 9. Interest on Working Capital 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 9
  • 10. Capacity Charge Capacity Charge (Rs) = AFC x 0.5 x NDM / NDY x (PAFM / NAPAF) • AFC (Rs) = Annual fixed cost as specified by the Commission for the year • NAPAF = Normative Plant availability factor, in percentage • NDM = Number of days in the month • NDY = Number of days in the year • PAFM = Plant availability factor achieved during the month, in Percentage 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 10
  • 11. Capacity Charge Contd., PAFM = 10000 X ∑ DCi / {N x IC x (100 – Aux)}% • AUX = Normative auxiliary energy consumption in percentage • DCi = Declared capacity (in ex-bus MW) for the ith day of the month which the station can deliver for at least three (3) hours • IC = Installed capacity (in MW) of the complete generating station • N = Number of days in the month 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 11
  • 12. Energy charges • The Energy charge are payable by each beneficiary for the total energy scheduled to be supplied to the beneficiary Total Energy charge payable to the generating company for a month: (Energy charge rate in Rs./kWh) x {Scheduled energy for the month in kWh} x (100 – FEHS) / 100 Energy charge rate = AFC x 0.5 x 10 / {DE x (100 – AUX) x (100 – FEHS)} Where, • DE (MWh) = Annual design energy specified for the Hydro generating station • FEHS (%) = Free energy for the home State • CERC has capped the Energy charge rate at Rs 0.80/Unit 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 12
  • 13. Tariff determination for a 500 MW Hydro Power Plant 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 13
  • 14. Calculations Return on equity 1. Capital cost/MW= Rs. 6 Cr 2. Capital cost for 500 MW = 500 x 6= Rs. 3,000 Cr. 3. Normative Debt/Equity Ratio= 70:30 4. Equity = 30/100 X 3000 = Rs. 900 Cr. 5. Debt =70/100 X 3000 = Rs. 2, 100 Cr. RoE = 15.5% of Equity = 15.5/100 x 900 = Rs. 139.50 Cr. 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 14
  • 15. Calculations (2) Interest on Loan 10% of Debt=10 /100 x 2100 =Rs. 210 Cr. (3) Interest on Working capital 10% of Working capital (Rs. 300 Cr.) 10/100 x 300 = Rs. 30 Cr. (4) Depreciation 5.28% of Capital cost= 5.28/100 x 3000= Rs. 158.40 Cr. • (5) O & M Cost • Normative O&M Cost: 2% of Project Cost • 2% x 3000 = Rs. 60 Cr • Hence, Total Fixed cost = (1) + (2) + (3) + (4) + (5) • = Rs. (139.50+210+30+158.40+60) = Rs. 597.90 Cr. = Rs. 597.90 x 107 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 15
  • 16. Calculations Contd., Annual Energy generation Gross Energy generated in the Year 500 MW = 500 x 365 x 24 x 90 x 1000/ 106 = 3942 Million Units (MUs) = 3942 x 106 Units Auxiliary consumption: 1% Net Annual Energy generation: =Gross energy x (1 – Aux consumption) = 3942 x 106 x (1 - 1%) = 3902.58 x 106 Units 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 16
  • 17. Calculations Contd., Fixed cost per unit Fixed Cost/Unit = (Total Fixed Cost) / (Net Annual Energy generation) = (597.90 x 107) / (3902.58 x 106) = Rs 1.53 / kWh Nominal Tariff: Nominal Tariff = (Fixed Cost / Unit) + (Variable cost /Unit) = Rs (1.53 + 0)/Unit = Rs. 1.53/Unit 8/1/2017 DeptOfPowerEngg&Mgmt,AnnaUniversity, Chennai 17