SlideShare a Scribd company logo
1 of 29
Operator Errors and What 
Can be Done to Minimize 
Global Congress on 
Process Safety 
March 31, 2014
Presenter 
Tom Nolan 
• Graduated from Ohio University with B.S. 
in Chemical Engineering 
• 24 years experience in chemical process 
industry in a variety of roles 
• MAIC and DFSS Six Sigma Black Belt
The Cost of Errors 
Average Dollar Loss per Major Incident by Cause 
0 25 50 75 100 
Sabotage / arson 
Design error 
Natural Hazard 
Process upset 
Unknown 
Operational Error 
Mechanical Failure 
Millions of Dollars 
Source J & H Marsh & McLennan, Inc.
The Cost of Operator Errors 
• ASM estimates total loss due to operator 
error is $8B per year 
• Chemical Safety Topical Committee - average 
of one chemical incident per day - cost of 
over $2 million per incident to comply with 
requirements 
• Errors cause 42% of unscheduled shutdowns 
• 70% of process incidents occur during start-up 
or shutdown
Reasons for Errors 
• Lack of Skill 
• Lack of Knowledge 
• Carelessness 
• System Design 
• Operator set up to make errors by 
inappropriate design – built in errors 
• Errors that are predictable are preventable 
by better design
Focus of this Discussion 
• System Design 
• Alarm Management 
• Operator Graphics 
• Operator set up to make errors by 
inappropriate design – built in errors 
• Errors that are predictable are preventable 
by better design
Alarm Floods 
In a number of industrial incidents, alarm 
floods were identified as a significant 
contributing cause to the incident… 
As found by EEMUA in 1999 and CSB 
Alarm Flood defined by ISA 18.2 as - 
“10 or more annunciated alarms in 
any 10 minute period per operator”
Why do Alarm Floods Occur? 
One reason is not providing dynamic alarm management 
• Alarms need to indicate abnormal situations that 
require operator action 
• Processes do not operate in one state 
• What is normal vs abnormal changes with state 
• Alarms are typically configured for run therefore many 
alarms are triggered upon a Change of State: Run to 
Shutdown 
• Many of the alarms are not applicable or actionable for 
the new state impleading the operators ability to act 
quickly on what is important
What is Impacted by Alarm Floods? 
• Product quality 
• Operability or profitability of the 
process 
• Loss of equipment 
• Loss of containment – 
environmental releases 
• Injury and loss of life in plant or 
community
What Makes Alarm Floods so Dangerous? 
Can be a problem for three reasons: 
• A deluge of alarms can cause critical 
alarms to be missed 
• Floods can be a significant distraction 
when dealing with process upsets 
• Can be an indicator of larger systemic 
safety issues
Impacting Alarm Management Design 
• Alarm rationalization is not a process to 
eliminate alarms - its about quality 
• Good rationalization will add alarms when 
appropriate 
• Typical (Static) rationalization is only for run 
mode 
• Dynamic rationalization considers all plant 
modes
Dynamic Alarm Management 
• Dynamic rationalization does everything 
a static rationalization does plus asks 
“when” for each alarm 
• Requires dynamic software to make 
changes based upon operating mode of 
the plant 
• Eliminates redundant alarms and lowers 
operator loading during transitions 
• Only alarms what is abnormal and 
actionable for the given state
Actual Performance Metrics vs ISA 18.2 
Type 
Avg 
Alarm 
Rate/hr 
Low/Hi 
of Avg 
Rate/hr 
Peak 
Alarm 
Rate/hr 
Low/Hi of 
Peak 
Rate/hr 
% Time 
in 
Flood 
Standing 
Alarms 
>24 hrs 
Before 
Rationalization 
30 Low=6.2 
Hi=61 
638 Low=152 
Hi=2402 
17.2% 9 
ISA 18.2 
Target Metrics 
6 --- <60 --- <1% <5 
After 
Dynamic 
Alarm 
Management 
2 Low=0.09 
Hi=2.5 
25 Low=13 
Hi=42 
0.25% 4
Results After Dynamic Alarm Management
Operator Graphics – The Risk of Changing Focus 
• Distraction of changing focus from process 
graphic to faceplate window 
• Added workload from managing multiple 
open windows 
• Increased probability of errors when 
changing values for un-intended tag with 
multiple faceplates open 
• All of above become multiplied and more 
complex when process is transitioning from 
one state to another
Faceplate Operation
Potential for Errors 
Faceplate Design -can 
introduce additional errors 
• Mode drop down list 
covers SP, PV and OP 
values 
• Operator may select 
wrong Mode if SP, PV 
and OP values are 
hidden from view 
• Mode list offers more 
options than necessary
Direct Entry Operation
Direct Entry Fields 
Values can be entered by: 
• Select point 
• Typing value via keypad 
• Pressing enter 
Key Factors: 
• By maintaining focus of points 
after value change, it improves 
safety for input errors, 
multiple clicking functions and 
is more time efficient 
• Easily recognizable operator 
enterable fields
Evaluation of Methods 
Comparison of Faceplate to Direct Entry 
• Keystroke Level Analysis 
• Operator Loading Analysis 
• Risk Analysis
Keystroke Level Model 
Symbol Time (s) Description 
K 0.28 Keystroke 
P 1.1 Point to object 
BB 0.2 Click on object 
H 0.4 Home hands on keyboard or mouse 
M 1.2+ Mental act or routine thinking
Estimate Execution Time Analysis 
• Evaluates execution 
time by an operator 
comparing faceplates 
to direct entry for 
SP/OP and Mode 
Changes 
• 50 % Reduction
Estimated Operator Loading Analysis 
• Evaluates Mental and 
Physical Load on 
Operator 
• Tasks that require very 
little thought are removed 
– such as (BB), (H) 
• Mental and Physical tasks are weighted 
based on the amount of fatigue they 
cause – assigned a weight of M=2.0 to 
5.0
Risk Analysis 
• Identifies actions where operator 
entry errors can occur
Risk Analysis 
Faceplate operation 
KLM for changing SP/OP Potential Error 
Move to shape (P) Select wrong point 
Click on shape (BB) 
Move to faceplate (P) Point in faceplate is previous point 
Click on SP/OP field (BB) Change wrong parameter 
Move hands to keyboard (H) 
Type in value and press enter (4K) Mistype value and press enter 
Move hands to mouse (H) 
Move to close faceplate (P) 
Click to close faceplate (BB) 
Potential error count 4
Risk Analysis 
Direct Entry operation 
KLM for changing SP/OP 
Potential Error 
Move to SP/OP (P) Select wrong parameter or point 
Click on SP/OP field (BB) 
Move hands to keyboard (H) 
Type in value and press enter (4K) Mistype value and press enter 
Potential error count 2
Direct Entry Vs Faceplate 
Summary of Benefits 
• Execution Time SP/OP Changes - 51.5% less 
• Execution Time for Mode Changes – 50% less 
• Operator Loading – 33 % to 47% less 
• Risk of Errors – 50% less
Conclusion 
• Many industrial errors are a result of 
operators using control systems with flawed 
designs 
• Poor design and performance by alarm management 
distracts operators and/or occludes critical alarms 
• Operator graphics with multiple open faceplates can 
cause a change intended for one controller to be entered 
into the faceplate of another 
• The two mechanisms listed above are predictable and 
therefore preventable through better design available 
today
Questions? 
Comments? 
Contact Prosys 
@prosys.com or 
225-291-9591 x225

More Related Content

What's hot

How to Make Money with Your Operator Graphics
How to Make Money with Your Operator GraphicsHow to Make Money with Your Operator Graphics
How to Make Money with Your Operator GraphicsMary Claire Simoneaux
 
Advanced Control of Multiple Sulfur Units
Advanced Control of Multiple Sulfur Units Advanced Control of Multiple Sulfur Units
Advanced Control of Multiple Sulfur Units Mary Claire Simoneaux
 
2012 02 ureason - oasys-am presentation
2012 02 ureason - oasys-am presentation2012 02 ureason - oasys-am presentation
2012 02 ureason - oasys-am presentationUReasonChannel
 
Predictive maintenance
Predictive maintenancePredictive maintenance
Predictive maintenanceJames Shearer
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02BhaveshShukla15
 
Isa art of alarm rationalization conley 8 26 17
Isa art of alarm rationalization conley 8 26 17Isa art of alarm rationalization conley 8 26 17
Isa art of alarm rationalization conley 8 26 17Randy Conley PE PMP
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Emerson Exchange
 
Plant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringPlant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringElena Maria Vaccher
 
18 Jul 2018 - FMEA and Risk Management in Practice
18 Jul 2018 - FMEA and Risk Management in Practice 18 Jul 2018 - FMEA and Risk Management in Practice
18 Jul 2018 - FMEA and Risk Management in Practice Intland Software GmbH
 
Implement Predictive Maintenance Thanks To TPM
Implement Predictive Maintenance Thanks To TPMImplement Predictive Maintenance Thanks To TPM
Implement Predictive Maintenance Thanks To TPMMobility Work
 
Functional safety by FMEA/FTA
Functional safety by FMEA/FTAFunctional safety by FMEA/FTA
Functional safety by FMEA/FTAmehmor
 
Smart Maintenance engineering
Smart Maintenance engineering Smart Maintenance engineering
Smart Maintenance engineering Michel Mafumba
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniquesEmerson Exchange
 
FAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISFAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISANOOPA NARAYANAN
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Emerson Exchange
 
Predictive Maintenance Solution for Industries - Cyient
Predictive Maintenance Solution for Industries - CyientPredictive Maintenance Solution for Industries - Cyient
Predictive Maintenance Solution for Industries - CyientPercy-Mitchell
 

What's hot (20)

How to Make Money with Your Operator Graphics
How to Make Money with Your Operator GraphicsHow to Make Money with Your Operator Graphics
How to Make Money with Your Operator Graphics
 
Advanced Control of Multiple Sulfur Units
Advanced Control of Multiple Sulfur Units Advanced Control of Multiple Sulfur Units
Advanced Control of Multiple Sulfur Units
 
2012 02 ureason - oasys-am presentation
2012 02 ureason - oasys-am presentation2012 02 ureason - oasys-am presentation
2012 02 ureason - oasys-am presentation
 
Predictive maintenance
Predictive maintenancePredictive maintenance
Predictive maintenance
 
Ep 5512 lecture-03
Ep 5512 lecture-03Ep 5512 lecture-03
Ep 5512 lecture-03
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02
 
Isa art of alarm rationalization conley 8 26 17
Isa art of alarm rationalization conley 8 26 17Isa art of alarm rationalization conley 8 26 17
Isa art of alarm rationalization conley 8 26 17
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2
 
Plant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringPlant Maintenance & Condition Monitoring
Plant Maintenance & Condition Monitoring
 
18 Jul 2018 - FMEA and Risk Management in Practice
18 Jul 2018 - FMEA and Risk Management in Practice 18 Jul 2018 - FMEA and Risk Management in Practice
18 Jul 2018 - FMEA and Risk Management in Practice
 
Implement Predictive Maintenance Thanks To TPM
Implement Predictive Maintenance Thanks To TPMImplement Predictive Maintenance Thanks To TPM
Implement Predictive Maintenance Thanks To TPM
 
How to get the most out of your existing DCS
How to get the most out of your existing DCSHow to get the most out of your existing DCS
How to get the most out of your existing DCS
 
Functional safety by FMEA/FTA
Functional safety by FMEA/FTAFunctional safety by FMEA/FTA
Functional safety by FMEA/FTA
 
Smart Maintenance engineering
Smart Maintenance engineering Smart Maintenance engineering
Smart Maintenance engineering
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniques
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
 
FAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISFAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSIS
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...
 
FMEA Presentation V1.1
FMEA Presentation V1.1FMEA Presentation V1.1
FMEA Presentation V1.1
 
Predictive Maintenance Solution for Industries - Cyient
Predictive Maintenance Solution for Industries - CyientPredictive Maintenance Solution for Industries - Cyient
Predictive Maintenance Solution for Industries - Cyient
 

Viewers also liked

All Work, No Pay: The Impact of Forfeited Time Off
All Work, No Pay: The Impact of Forfeited Time OffAll Work, No Pay: The Impact of Forfeited Time Off
All Work, No Pay: The Impact of Forfeited Time OffU.S. Travel Association
 
financial statement 2004
financial statement  2004financial statement  2004
financial statement 2004traoman
 
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...CoMo: Supporting collaborative groupwork using mobile phones in distant educa...
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...niall
 
What really is the right to an Education? Part 1- 2013
What really is the right to an Education? Part 1- 2013What really is the right to an Education? Part 1- 2013
What really is the right to an Education? Part 1- 2013Great Belize Productions Ltd.
 
Comic explained
Comic explainedComic explained
Comic explainedLynnstyles
 
Malnutrition its impact on attendance among primary school pupils in kirie di...
Malnutrition its impact on attendance among primary school pupils in kirie di...Malnutrition its impact on attendance among primary school pupils in kirie di...
Malnutrition its impact on attendance among primary school pupils in kirie di...Alexander Decker
 
Kartka Wielkanocna
Kartka WielkanocnaKartka Wielkanocna
Kartka Wielkanocnajou
 

Viewers also liked (11)

cv nando
cv nandocv nando
cv nando
 
All Work, No Pay: The Impact of Forfeited Time Off
All Work, No Pay: The Impact of Forfeited Time OffAll Work, No Pay: The Impact of Forfeited Time Off
All Work, No Pay: The Impact of Forfeited Time Off
 
financial statement 2004
financial statement  2004financial statement  2004
financial statement 2004
 
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...CoMo: Supporting collaborative groupwork using mobile phones in distant educa...
CoMo: Supporting collaborative groupwork using mobile phones in distant educa...
 
Nm jun 11, 1949
Nm jun 11, 1949Nm jun 11, 1949
Nm jun 11, 1949
 
Oceanus Vista II
Oceanus Vista IIOceanus Vista II
Oceanus Vista II
 
What really is the right to an Education? Part 1- 2013
What really is the right to an Education? Part 1- 2013What really is the right to an Education? Part 1- 2013
What really is the right to an Education? Part 1- 2013
 
Comic explained
Comic explainedComic explained
Comic explained
 
Malnutrition its impact on attendance among primary school pupils in kirie di...
Malnutrition its impact on attendance among primary school pupils in kirie di...Malnutrition its impact on attendance among primary school pupils in kirie di...
Malnutrition its impact on attendance among primary school pupils in kirie di...
 
Kartka Wielkanocna
Kartka WielkanocnaKartka Wielkanocna
Kartka Wielkanocna
 
368b.6819.file
368b.6819.file368b.6819.file
368b.6819.file
 

Similar to Operator errors and what can be done to minimize

fmea-130116034507-phpapp01.pdf
fmea-130116034507-phpapp01.pdffmea-130116034507-phpapp01.pdf
fmea-130116034507-phpapp01.pdfRajendran C
 
Unit 1 - Session 1.pptx
Unit 1 - Session 1.pptxUnit 1 - Session 1.pptx
Unit 1 - Session 1.pptxAjayLohae
 
Operations Management Solution – Driving Safety and Profitability One Shift a...
Operations Management Solution – Driving Safety and Profitability One Shift a...Operations Management Solution – Driving Safety and Profitability One Shift a...
Operations Management Solution – Driving Safety and Profitability One Shift a...Yokogawa1
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Emerson Exchange
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsYokogawa1
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)Prashant Rasekar
 
S1 the feedback loop
S1 the feedback loopS1 the feedback loop
S1 the feedback loopMohamed Saad
 
Customer Satisfaction and Quality Induction_PPM .pptx
Customer Satisfaction and Quality Induction_PPM .pptxCustomer Satisfaction and Quality Induction_PPM .pptx
Customer Satisfaction and Quality Induction_PPM .pptxMunirahAyub1
 
Reliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During OperationsReliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During OperationsLloyd's Register Energy
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02BhaveshShukla15
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Bhavesh Shukla
 
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...Sergey Mishin
 
Session 01 - Introduction to Industrial Automation
Session 01 - Introduction to Industrial AutomationSession 01 - Introduction to Industrial Automation
Session 01 - Introduction to Industrial AutomationVidyaIA
 
Introduction to Industrial Automation
Introduction to Industrial AutomationIntroduction to Industrial Automation
Introduction to Industrial AutomationPranavAutomation
 

Similar to Operator errors and what can be done to minimize (20)

fmea-130116034507-phpapp01.pdf
fmea-130116034507-phpapp01.pdffmea-130116034507-phpapp01.pdf
fmea-130116034507-phpapp01.pdf
 
Unit 1 - Session 1.pptx
Unit 1 - Session 1.pptxUnit 1 - Session 1.pptx
Unit 1 - Session 1.pptx
 
Engineering
EngineeringEngineering
Engineering
 
Operations Management Solution – Driving Safety and Profitability One Shift a...
Operations Management Solution – Driving Safety and Profitability One Shift a...Operations Management Solution – Driving Safety and Profitability One Shift a...
Operations Management Solution – Driving Safety and Profitability One Shift a...
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2
 
UNIT-I SYLABUS-2.ppt
UNIT-I SYLABUS-2.pptUNIT-I SYLABUS-2.ppt
UNIT-I SYLABUS-2.ppt
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation Projects
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
 
S1 the feedback loop
S1 the feedback loopS1 the feedback loop
S1 the feedback loop
 
Automation21
Automation21Automation21
Automation21
 
Process fmea work_instructions
Process fmea work_instructionsProcess fmea work_instructions
Process fmea work_instructions
 
Customer Satisfaction and Quality Induction_PPM .pptx
Customer Satisfaction and Quality Induction_PPM .pptxCustomer Satisfaction and Quality Induction_PPM .pptx
Customer Satisfaction and Quality Induction_PPM .pptx
 
Reliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During OperationsReliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During Operations
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02
 
Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02Apac 2015 minimizing integrity failure r02
Apac 2015 minimizing integrity failure r02
 
DCS Or PLC
DCS Or PLCDCS Or PLC
DCS Or PLC
 
Control Room of the Future
Control Room of the FutureControl Room of the Future
Control Room of the Future
 
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
 
Session 01 - Introduction to Industrial Automation
Session 01 - Introduction to Industrial AutomationSession 01 - Introduction to Industrial Automation
Session 01 - Introduction to Industrial Automation
 
Introduction to Industrial Automation
Introduction to Industrial AutomationIntroduction to Industrial Automation
Introduction to Industrial Automation
 

Operator errors and what can be done to minimize

  • 1. Operator Errors and What Can be Done to Minimize Global Congress on Process Safety March 31, 2014
  • 2. Presenter Tom Nolan • Graduated from Ohio University with B.S. in Chemical Engineering • 24 years experience in chemical process industry in a variety of roles • MAIC and DFSS Six Sigma Black Belt
  • 3. The Cost of Errors Average Dollar Loss per Major Incident by Cause 0 25 50 75 100 Sabotage / arson Design error Natural Hazard Process upset Unknown Operational Error Mechanical Failure Millions of Dollars Source J & H Marsh & McLennan, Inc.
  • 4. The Cost of Operator Errors • ASM estimates total loss due to operator error is $8B per year • Chemical Safety Topical Committee - average of one chemical incident per day - cost of over $2 million per incident to comply with requirements • Errors cause 42% of unscheduled shutdowns • 70% of process incidents occur during start-up or shutdown
  • 5. Reasons for Errors • Lack of Skill • Lack of Knowledge • Carelessness • System Design • Operator set up to make errors by inappropriate design – built in errors • Errors that are predictable are preventable by better design
  • 6. Focus of this Discussion • System Design • Alarm Management • Operator Graphics • Operator set up to make errors by inappropriate design – built in errors • Errors that are predictable are preventable by better design
  • 7. Alarm Floods In a number of industrial incidents, alarm floods were identified as a significant contributing cause to the incident… As found by EEMUA in 1999 and CSB Alarm Flood defined by ISA 18.2 as - “10 or more annunciated alarms in any 10 minute period per operator”
  • 8. Why do Alarm Floods Occur? One reason is not providing dynamic alarm management • Alarms need to indicate abnormal situations that require operator action • Processes do not operate in one state • What is normal vs abnormal changes with state • Alarms are typically configured for run therefore many alarms are triggered upon a Change of State: Run to Shutdown • Many of the alarms are not applicable or actionable for the new state impleading the operators ability to act quickly on what is important
  • 9. What is Impacted by Alarm Floods? • Product quality • Operability or profitability of the process • Loss of equipment • Loss of containment – environmental releases • Injury and loss of life in plant or community
  • 10. What Makes Alarm Floods so Dangerous? Can be a problem for three reasons: • A deluge of alarms can cause critical alarms to be missed • Floods can be a significant distraction when dealing with process upsets • Can be an indicator of larger systemic safety issues
  • 11. Impacting Alarm Management Design • Alarm rationalization is not a process to eliminate alarms - its about quality • Good rationalization will add alarms when appropriate • Typical (Static) rationalization is only for run mode • Dynamic rationalization considers all plant modes
  • 12. Dynamic Alarm Management • Dynamic rationalization does everything a static rationalization does plus asks “when” for each alarm • Requires dynamic software to make changes based upon operating mode of the plant • Eliminates redundant alarms and lowers operator loading during transitions • Only alarms what is abnormal and actionable for the given state
  • 13. Actual Performance Metrics vs ISA 18.2 Type Avg Alarm Rate/hr Low/Hi of Avg Rate/hr Peak Alarm Rate/hr Low/Hi of Peak Rate/hr % Time in Flood Standing Alarms >24 hrs Before Rationalization 30 Low=6.2 Hi=61 638 Low=152 Hi=2402 17.2% 9 ISA 18.2 Target Metrics 6 --- <60 --- <1% <5 After Dynamic Alarm Management 2 Low=0.09 Hi=2.5 25 Low=13 Hi=42 0.25% 4
  • 14. Results After Dynamic Alarm Management
  • 15. Operator Graphics – The Risk of Changing Focus • Distraction of changing focus from process graphic to faceplate window • Added workload from managing multiple open windows • Increased probability of errors when changing values for un-intended tag with multiple faceplates open • All of above become multiplied and more complex when process is transitioning from one state to another
  • 17. Potential for Errors Faceplate Design -can introduce additional errors • Mode drop down list covers SP, PV and OP values • Operator may select wrong Mode if SP, PV and OP values are hidden from view • Mode list offers more options than necessary
  • 19. Direct Entry Fields Values can be entered by: • Select point • Typing value via keypad • Pressing enter Key Factors: • By maintaining focus of points after value change, it improves safety for input errors, multiple clicking functions and is more time efficient • Easily recognizable operator enterable fields
  • 20. Evaluation of Methods Comparison of Faceplate to Direct Entry • Keystroke Level Analysis • Operator Loading Analysis • Risk Analysis
  • 21. Keystroke Level Model Symbol Time (s) Description K 0.28 Keystroke P 1.1 Point to object BB 0.2 Click on object H 0.4 Home hands on keyboard or mouse M 1.2+ Mental act or routine thinking
  • 22. Estimate Execution Time Analysis • Evaluates execution time by an operator comparing faceplates to direct entry for SP/OP and Mode Changes • 50 % Reduction
  • 23. Estimated Operator Loading Analysis • Evaluates Mental and Physical Load on Operator • Tasks that require very little thought are removed – such as (BB), (H) • Mental and Physical tasks are weighted based on the amount of fatigue they cause – assigned a weight of M=2.0 to 5.0
  • 24. Risk Analysis • Identifies actions where operator entry errors can occur
  • 25. Risk Analysis Faceplate operation KLM for changing SP/OP Potential Error Move to shape (P) Select wrong point Click on shape (BB) Move to faceplate (P) Point in faceplate is previous point Click on SP/OP field (BB) Change wrong parameter Move hands to keyboard (H) Type in value and press enter (4K) Mistype value and press enter Move hands to mouse (H) Move to close faceplate (P) Click to close faceplate (BB) Potential error count 4
  • 26. Risk Analysis Direct Entry operation KLM for changing SP/OP Potential Error Move to SP/OP (P) Select wrong parameter or point Click on SP/OP field (BB) Move hands to keyboard (H) Type in value and press enter (4K) Mistype value and press enter Potential error count 2
  • 27. Direct Entry Vs Faceplate Summary of Benefits • Execution Time SP/OP Changes - 51.5% less • Execution Time for Mode Changes – 50% less • Operator Loading – 33 % to 47% less • Risk of Errors – 50% less
  • 28. Conclusion • Many industrial errors are a result of operators using control systems with flawed designs • Poor design and performance by alarm management distracts operators and/or occludes critical alarms • Operator graphics with multiple open faceplates can cause a change intended for one controller to be entered into the faceplate of another • The two mechanisms listed above are predictable and therefore preventable through better design available today
  • 29. Questions? Comments? Contact Prosys @prosys.com or 225-291-9591 x225

Editor's Notes

  1. ________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
  2. ________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
  3. ________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________