SlideShare a Scribd company logo
1 of 2
Download to read offline
Sources: US Census Bureau, ORDOT bid lettings, ORDOT Bid Express, Oregon Statewide Transportation Improvement Program FY 2018-2021
WWW.STARAMERICAP.COM • 390 N Broadway, Jericho, NY, 11753 • (516) 882-4100
Oregon Department of Transportation:
FY2017 – 3Q2018 Summary & Analysis
According to the U.S. Census Bureau's July 2017 population estimate, Oregon is the 27th most populous state in the United
States. Since the 2010 Census, Oregon’s population has grown 7.97%, which ranks 27th among all states. According to
Oregon Department of Transportation (ORDOT), the total proposed transportation budget for 2018-2021 is more than $2.8
Billion.
The table on the left below highlights the 2017 – 3Q 2018 bidding activity on ORDOT projects. The largest project awarded
during the period was a $29M project won by Knife River Corporation. Additionally, there were a total of 8 projects larger
than $10M and 3 projects larger than $20M awarded during this period. A total of 6 different contractors won jobs over
$10M. The total value of contracts let during the period was $523 Million, the top five contractors won 49% of all work let
during the period. Wildish Standard Paving Co. was the most active during this period submitting a total of 51 bids, with 12
low bids for a win percentage of 15.7% and total value of $31M. Oregon Mainline Paving was the most successful
contractor, winning the most projects (12) for a total value of $105M.
The table on the right below highlights the average margin of victory by letting period between first and second place bidders
on these projects, with the most competitive period being January 2018 with an average margin of victory of 3.14% and the
most active period being March 2018 with 10 projects awarded. July 2017 was the least active month with only 1 project
being let.
The table to the right highlights the total planned
expenditures for ORDOT for the 4-year period of
2018-2022. These planned expenditure were
detailed in the FY 2018-2021 Oregon Statewide
Transportation Improvement Program. A total
of $2.81 Billion have been made available by
ORDOT for the 2018-2021 period. The largest
contributor to the budgets was the National
Highway Performance Program. The NHPP
contributes $1.22 Billion which accounts for 43%
of the total $2.81 Billion budget. The other major
contributor to the budget were STP Block Grants,
$845 million (30%) and Advance Construction
$325 million (11%).
Top 20 Contractors by Low Bid ORDOT Contract Value
Jan 2017 – Sep 2018
Bidder
Total 1st
Place Bids Total Bids Win %
Winning
Bid Value
1 OREGON MAINLINE PAVING LLC 12 26 46.2% 105,937,199
2 KNIFE RIVER CORPORATION 4 14 28.6% 48,636,856
3 HAMILTON CONSTRUCTION CO 4 18 22.2% 42,926,590
4 WILDISH STANDARD PAVING CO 8 51 15.7% 31,038,457
5 LEGACY CONTRACTING INC 4 9 44.4% 25,847,654
6 HIGH DESERT AGGREGATE & PAVING INC 4 10 40.0% 21,120,874
7 LTM INC DBA KNIFE RIVER MATERIALS 4 7 57.1% 19,806,344
8 WILDISH CONSTRUCTION CO 5 7 71.4% 19,709,119
9 STELLAR J CORPORATION 2 10 20.0% 18,013,058
10 ROY HOUCK CONSTRUCTION LLC 2 5 40.0% 17,012,875
11 ROCKY MOUNTAIN CONSTRUCTION LLC 3 5 60.0% 16,859,057
12 CARTER & COMPANY INC 7 24 29.2% 13,768,505
13 HP CIVIL INC 6 26 23.1% 11,971,386
14 BABB CONSTRUCTION CO 5 12 41.7% 10,195,024
15 EMERY & SONS CONSTRUCTION GROUP 1 2 50.0% 9,158,979
16 FREYSSINET INC 1 1 100.0% 8,486,118
17 ALEX HODGE CONSTRUCTION INC 4 7 57.1% 8,419,770
18 FD THOMAS INC 1 2 50.0% 7,785,635
19 LADUKE CONSTRUCTION LLC 3 20 15.0% 7,279,637
20 BROWN CONTRACTING INC 3 8 37.5% 6,791,039
Margin of Victory ORDOT Bid Results
Jan 2017 – Sep 2018
# of Projects w/
Multiple Bidders
Average Win
Margin
January 4 8.18%
February 2 4.84%
March 9 10.77%
April 7 15.21%
May 6 17.39%
June 6 7.93%
July 1 10.12%
August 5 8.28%
September 8 8.08%
October 6 5.45%
November 8 7.80%
December 5 8.59%
January 5 3.14%
February 7 17.51%
March 10 12.94%
April 8 5.49%
May 7 10.92%
June 7 14.07%
July 5 19.28%
August 3 16.40%
September 3 13.14%
Annual Weighted Average 10.85%
Total Proposed Commitment ($ 000’s)
Highway Fund Program 2018 2019 2020 2021 Total
National Highway Performance Program 332,178 322,489 374,767 197,005 1,226,439
Surface Transportation Program Block Grant 178,061 171,950 176,765 318,895 845,671
Advance Construct 4,560 2,398 2,398 2,398 325,370
Highway Safety Improvement Program 41,103 36,029 41,487 42,287 160,906
Congestion Management & Air Quality 35,197 17,182 20,779 15,540 88,698
National Highway Freight Program 3,771 4,195 4,195 4,195 65,962
Transportation Alternatives Program 10,138 6,405 4,538 15,140 36,222
Other Federal Funds 16,962 16,333 16,333 16,333 29,397
Metropolitan PL Funds 19,492 5,121 2,392 2,392 16,357
Railway - Highway Grade Crossing Program 169,404 59,582 48,377 48,007 11,753
Total Highway Fund Program 810,866 641,685 692,031 662,193 2,806,775
Oregon DOT Total Proposed Commitments 2018-2021
Why We Are Different Star America Global Reach
Focused Strictly on Infrastructure
• Management has years of experience in the Infrastructure
Industry
• Solely focused on advising public and private clients in the
Infrastructure/Construction sector
Broad Range of Advisory Services
• M&A, Project Financing, Strategic Consulting, Restructuring,
Executive Placement, and Financial Analysis
• All Industry Sub-Sectors
Experience in All Major Infrastructure Markets
• Star America has worked in all infrastructure markets,
including Civil Construction, Vertical Building, Public-Private
Partnerships, Industrial
Business Development
Mergers & Acquisitions PPP Financial Advisory
Management Consulting
Capital Raising Strategic & Financial Analysis
Star is well qualified to assist clients in developing their
business plans in the U.S. Given the depth of experience of its
partners and operating professionals, the company offers
access to thought leadership of C-Level executives.
We have a strong track record in both domestic and cross-
border M&A advisory roles. We operate both negotiated
processes and auctions, assist in deal structuring, and provide
impartial advice about the merits of transactions in our industry
of focus.
Star provides financial advisory services to companies and
consortia seeking to participate in alternative procurement
processes. We advise on debt capital raising in the bank and
bond markets, and help structure competitive bids for our
clients.
We work with clients to formulate and pursue strategic and
tactical goals. Star provides true business solutions, including
identifying potential management hires, developing and
implementing marketing plans, and increasing operational
efficiencies.
We maintain contacts at banks, hedge funds, equipment
finance companies, and other financial firms. These are
sources of capital for clients desiring funds for expansionary
capital expenditures or general operating cash flow needs.
Industry analytics form the core of a successful financing or
business development strategy. With our significant industry
knowledge, we assess companies’ current and projected
financial and competitive positions to provide actionable
recommendations. We have the capacity to provide
comprehensive financial analysis as well as contractor
prequalification solutions, allowing contractors to properly vet
lower tiers and improve overall capital strength.
Star America Capital Advisors, LLC
Services Overview
Service Offerings
Disclaimer:
This material is for informational purposes only. It should not be relied on for any other purposes. The goal of this report is to help market
participants critically asses each state's expected infrastructure budgets and competitive environment.
WWW.STARAMERICAP.COM • 390 N Broadway, Jericho, NY, 11753 • (516) 882-4100

More Related Content

Similar to Oregon Transportation Report

Driving growth and differential performance among Class I railroads
Driving growth and differential performance among Class I railroadsDriving growth and differential performance among Class I railroads
Driving growth and differential performance among Class I railroadsDeloitte United States
 
Natural Gas Vehicle Infrastructure business models
Natural Gas Vehicle Infrastructure business modelsNatural Gas Vehicle Infrastructure business models
Natural Gas Vehicle Infrastructure business modelspiersfrench
 
Trc investor presentation final
Trc investor presentation finalTrc investor presentation final
Trc investor presentation finaltrcsolutions
 
Budget Critique Portland
Budget Critique PortlandBudget Critique Portland
Budget Critique PortlandEric Schlimgen
 
A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”OnTrackNorthAmerica
 
Public Construction Overviews - 2Q 2018
Public Construction Overviews - 2Q 2018Public Construction Overviews - 2Q 2018
Public Construction Overviews - 2Q 2018Jonathan Hunt
 
Trc investor presentation 05 13 final
Trc investor presentation 05 13 finalTrc investor presentation 05 13 final
Trc investor presentation 05 13 finaltrcsolutions
 
2017 0724 rate_case_exchange_final
2017 0724 rate_case_exchange_final2017 0724 rate_case_exchange_final
2017 0724 rate_case_exchange_finalInfraREIT
 
ENR 2016 CM at Risk PLANT #89
ENR 2016 CM at Risk PLANT #89ENR 2016 CM at Risk PLANT #89
ENR 2016 CM at Risk PLANT #89Chris Rivielle
 
TPC KeyBanc EC&U Conference Presentation
TPC KeyBanc EC&U Conference PresentationTPC KeyBanc EC&U Conference Presentation
TPC KeyBanc EC&U Conference Presentationtutorperinicorp
 
2014 ARTBA Annual Report
2014 ARTBA Annual Report2014 ARTBA Annual Report
2014 ARTBA Annual Reportartba
 
Public Private Patnership
Public Private Patnership Public Private Patnership
Public Private Patnership Sagar Srivastava
 
Revised road webinar article Oct 17
Revised road webinar article Oct 17Revised road webinar article Oct 17
Revised road webinar article Oct 17Mekhala Leelasagar
 
8(A), Gsa Presentation(2)
8(A), Gsa Presentation(2)8(A), Gsa Presentation(2)
8(A), Gsa Presentation(2)dcheon1
 
Accelerating Housing Delivery in London; is planning reform working
Accelerating Housing Delivery in London; is planning reform workingAccelerating Housing Delivery in London; is planning reform working
Accelerating Housing Delivery in London; is planning reform workingGL Hearn, part of Capita Real Estate
 
MPG Q2 2021 Software Technology Public Market Update
MPG Q2 2021 Software  Technology Public Market UpdateMPG Q2 2021 Software  Technology Public Market Update
MPG Q2 2021 Software Technology Public Market UpdateMadison Park Group
 
Spotlight on PU megaprojects Final_web_single
Spotlight on PU megaprojects Final_web_singleSpotlight on PU megaprojects Final_web_single
Spotlight on PU megaprojects Final_web_singleChristopher Matthews
 

Similar to Oregon Transportation Report (20)

Driving growth and differential performance among Class I railroads
Driving growth and differential performance among Class I railroadsDriving growth and differential performance among Class I railroads
Driving growth and differential performance among Class I railroads
 
Natural Gas Vehicle Infrastructure business models
Natural Gas Vehicle Infrastructure business modelsNatural Gas Vehicle Infrastructure business models
Natural Gas Vehicle Infrastructure business models
 
Trc investor presentation final
Trc investor presentation finalTrc investor presentation final
Trc investor presentation final
 
Budget Critique Portland
Budget Critique PortlandBudget Critique Portland
Budget Critique Portland
 
A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”
 
Public Construction Overviews - 2Q 2018
Public Construction Overviews - 2Q 2018Public Construction Overviews - 2Q 2018
Public Construction Overviews - 2Q 2018
 
Trc investor presentation 05 13 final
Trc investor presentation 05 13 finalTrc investor presentation 05 13 final
Trc investor presentation 05 13 final
 
DGHG Fact Sheet Q3 2011
DGHG Fact Sheet Q3 2011DGHG Fact Sheet Q3 2011
DGHG Fact Sheet Q3 2011
 
2017 0724 rate_case_exchange_final
2017 0724 rate_case_exchange_final2017 0724 rate_case_exchange_final
2017 0724 rate_case_exchange_final
 
ENR 2016 CM at Risk PLANT #89
ENR 2016 CM at Risk PLANT #89ENR 2016 CM at Risk PLANT #89
ENR 2016 CM at Risk PLANT #89
 
Evercore Investor Presentation
Evercore Investor PresentationEvercore Investor Presentation
Evercore Investor Presentation
 
TPC KeyBanc EC&U Conference Presentation
TPC KeyBanc EC&U Conference PresentationTPC KeyBanc EC&U Conference Presentation
TPC KeyBanc EC&U Conference Presentation
 
2014 ARTBA Annual Report
2014 ARTBA Annual Report2014 ARTBA Annual Report
2014 ARTBA Annual Report
 
Public Private Patnership
Public Private Patnership Public Private Patnership
Public Private Patnership
 
Revised road webinar article Oct 17
Revised road webinar article Oct 17Revised road webinar article Oct 17
Revised road webinar article Oct 17
 
new-road-old-pain
new-road-old-painnew-road-old-pain
new-road-old-pain
 
8(A), Gsa Presentation(2)
8(A), Gsa Presentation(2)8(A), Gsa Presentation(2)
8(A), Gsa Presentation(2)
 
Accelerating Housing Delivery in London; is planning reform working
Accelerating Housing Delivery in London; is planning reform workingAccelerating Housing Delivery in London; is planning reform working
Accelerating Housing Delivery in London; is planning reform working
 
MPG Q2 2021 Software Technology Public Market Update
MPG Q2 2021 Software  Technology Public Market UpdateMPG Q2 2021 Software  Technology Public Market Update
MPG Q2 2021 Software Technology Public Market Update
 
Spotlight on PU megaprojects Final_web_single
Spotlight on PU megaprojects Final_web_singleSpotlight on PU megaprojects Final_web_single
Spotlight on PU megaprojects Final_web_single
 

More from Jonathan Hunt

International Contractor Overviews Q3 2017
International Contractor Overviews Q3 2017International Contractor Overviews Q3 2017
International Contractor Overviews Q3 2017Jonathan Hunt
 
Public Construction Company Overviews Q3 2017
Public Construction Company Overviews Q3 2017Public Construction Company Overviews Q3 2017
Public Construction Company Overviews Q3 2017Jonathan Hunt
 
Public Private Partnerships - State of the Market and the Future of P3's
Public Private Partnerships - State of the Market and the Future of P3'sPublic Private Partnerships - State of the Market and the Future of P3's
Public Private Partnerships - State of the Market and the Future of P3'sJonathan Hunt
 
International Contractor Overviews Q2 2017
International Contractor Overviews Q2 2017International Contractor Overviews Q2 2017
International Contractor Overviews Q2 2017Jonathan Hunt
 
Public Construction Company Overviews 1H 2017
Public Construction Company Overviews 1H 2017Public Construction Company Overviews 1H 2017
Public Construction Company Overviews 1H 2017Jonathan Hunt
 
Public Construction Company Overviews Q1 2017
Public Construction Company Overviews Q1 2017Public Construction Company Overviews Q1 2017
Public Construction Company Overviews Q1 2017Jonathan Hunt
 
International Contractor Overviews Vol. 1
International Contractor Overviews Vol. 1International Contractor Overviews Vol. 1
International Contractor Overviews Vol. 1Jonathan Hunt
 
Public Construction Company Overviews
Public Construction Company OverviewsPublic Construction Company Overviews
Public Construction Company OverviewsJonathan Hunt
 
Public Construction Company Overviews
Public Construction Company OverviewsPublic Construction Company Overviews
Public Construction Company OverviewsJonathan Hunt
 

More from Jonathan Hunt (9)

International Contractor Overviews Q3 2017
International Contractor Overviews Q3 2017International Contractor Overviews Q3 2017
International Contractor Overviews Q3 2017
 
Public Construction Company Overviews Q3 2017
Public Construction Company Overviews Q3 2017Public Construction Company Overviews Q3 2017
Public Construction Company Overviews Q3 2017
 
Public Private Partnerships - State of the Market and the Future of P3's
Public Private Partnerships - State of the Market and the Future of P3'sPublic Private Partnerships - State of the Market and the Future of P3's
Public Private Partnerships - State of the Market and the Future of P3's
 
International Contractor Overviews Q2 2017
International Contractor Overviews Q2 2017International Contractor Overviews Q2 2017
International Contractor Overviews Q2 2017
 
Public Construction Company Overviews 1H 2017
Public Construction Company Overviews 1H 2017Public Construction Company Overviews 1H 2017
Public Construction Company Overviews 1H 2017
 
Public Construction Company Overviews Q1 2017
Public Construction Company Overviews Q1 2017Public Construction Company Overviews Q1 2017
Public Construction Company Overviews Q1 2017
 
International Contractor Overviews Vol. 1
International Contractor Overviews Vol. 1International Contractor Overviews Vol. 1
International Contractor Overviews Vol. 1
 
Public Construction Company Overviews
Public Construction Company OverviewsPublic Construction Company Overviews
Public Construction Company Overviews
 
Public Construction Company Overviews
Public Construction Company OverviewsPublic Construction Company Overviews
Public Construction Company Overviews
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Oregon Transportation Report

  • 1. Sources: US Census Bureau, ORDOT bid lettings, ORDOT Bid Express, Oregon Statewide Transportation Improvement Program FY 2018-2021 WWW.STARAMERICAP.COM • 390 N Broadway, Jericho, NY, 11753 • (516) 882-4100 Oregon Department of Transportation: FY2017 – 3Q2018 Summary & Analysis According to the U.S. Census Bureau's July 2017 population estimate, Oregon is the 27th most populous state in the United States. Since the 2010 Census, Oregon’s population has grown 7.97%, which ranks 27th among all states. According to Oregon Department of Transportation (ORDOT), the total proposed transportation budget for 2018-2021 is more than $2.8 Billion. The table on the left below highlights the 2017 – 3Q 2018 bidding activity on ORDOT projects. The largest project awarded during the period was a $29M project won by Knife River Corporation. Additionally, there were a total of 8 projects larger than $10M and 3 projects larger than $20M awarded during this period. A total of 6 different contractors won jobs over $10M. The total value of contracts let during the period was $523 Million, the top five contractors won 49% of all work let during the period. Wildish Standard Paving Co. was the most active during this period submitting a total of 51 bids, with 12 low bids for a win percentage of 15.7% and total value of $31M. Oregon Mainline Paving was the most successful contractor, winning the most projects (12) for a total value of $105M. The table on the right below highlights the average margin of victory by letting period between first and second place bidders on these projects, with the most competitive period being January 2018 with an average margin of victory of 3.14% and the most active period being March 2018 with 10 projects awarded. July 2017 was the least active month with only 1 project being let. The table to the right highlights the total planned expenditures for ORDOT for the 4-year period of 2018-2022. These planned expenditure were detailed in the FY 2018-2021 Oregon Statewide Transportation Improvement Program. A total of $2.81 Billion have been made available by ORDOT for the 2018-2021 period. The largest contributor to the budgets was the National Highway Performance Program. The NHPP contributes $1.22 Billion which accounts for 43% of the total $2.81 Billion budget. The other major contributor to the budget were STP Block Grants, $845 million (30%) and Advance Construction $325 million (11%). Top 20 Contractors by Low Bid ORDOT Contract Value Jan 2017 – Sep 2018 Bidder Total 1st Place Bids Total Bids Win % Winning Bid Value 1 OREGON MAINLINE PAVING LLC 12 26 46.2% 105,937,199 2 KNIFE RIVER CORPORATION 4 14 28.6% 48,636,856 3 HAMILTON CONSTRUCTION CO 4 18 22.2% 42,926,590 4 WILDISH STANDARD PAVING CO 8 51 15.7% 31,038,457 5 LEGACY CONTRACTING INC 4 9 44.4% 25,847,654 6 HIGH DESERT AGGREGATE & PAVING INC 4 10 40.0% 21,120,874 7 LTM INC DBA KNIFE RIVER MATERIALS 4 7 57.1% 19,806,344 8 WILDISH CONSTRUCTION CO 5 7 71.4% 19,709,119 9 STELLAR J CORPORATION 2 10 20.0% 18,013,058 10 ROY HOUCK CONSTRUCTION LLC 2 5 40.0% 17,012,875 11 ROCKY MOUNTAIN CONSTRUCTION LLC 3 5 60.0% 16,859,057 12 CARTER & COMPANY INC 7 24 29.2% 13,768,505 13 HP CIVIL INC 6 26 23.1% 11,971,386 14 BABB CONSTRUCTION CO 5 12 41.7% 10,195,024 15 EMERY & SONS CONSTRUCTION GROUP 1 2 50.0% 9,158,979 16 FREYSSINET INC 1 1 100.0% 8,486,118 17 ALEX HODGE CONSTRUCTION INC 4 7 57.1% 8,419,770 18 FD THOMAS INC 1 2 50.0% 7,785,635 19 LADUKE CONSTRUCTION LLC 3 20 15.0% 7,279,637 20 BROWN CONTRACTING INC 3 8 37.5% 6,791,039 Margin of Victory ORDOT Bid Results Jan 2017 – Sep 2018 # of Projects w/ Multiple Bidders Average Win Margin January 4 8.18% February 2 4.84% March 9 10.77% April 7 15.21% May 6 17.39% June 6 7.93% July 1 10.12% August 5 8.28% September 8 8.08% October 6 5.45% November 8 7.80% December 5 8.59% January 5 3.14% February 7 17.51% March 10 12.94% April 8 5.49% May 7 10.92% June 7 14.07% July 5 19.28% August 3 16.40% September 3 13.14% Annual Weighted Average 10.85% Total Proposed Commitment ($ 000’s) Highway Fund Program 2018 2019 2020 2021 Total National Highway Performance Program 332,178 322,489 374,767 197,005 1,226,439 Surface Transportation Program Block Grant 178,061 171,950 176,765 318,895 845,671 Advance Construct 4,560 2,398 2,398 2,398 325,370 Highway Safety Improvement Program 41,103 36,029 41,487 42,287 160,906 Congestion Management & Air Quality 35,197 17,182 20,779 15,540 88,698 National Highway Freight Program 3,771 4,195 4,195 4,195 65,962 Transportation Alternatives Program 10,138 6,405 4,538 15,140 36,222 Other Federal Funds 16,962 16,333 16,333 16,333 29,397 Metropolitan PL Funds 19,492 5,121 2,392 2,392 16,357 Railway - Highway Grade Crossing Program 169,404 59,582 48,377 48,007 11,753 Total Highway Fund Program 810,866 641,685 692,031 662,193 2,806,775 Oregon DOT Total Proposed Commitments 2018-2021
  • 2. Why We Are Different Star America Global Reach Focused Strictly on Infrastructure • Management has years of experience in the Infrastructure Industry • Solely focused on advising public and private clients in the Infrastructure/Construction sector Broad Range of Advisory Services • M&A, Project Financing, Strategic Consulting, Restructuring, Executive Placement, and Financial Analysis • All Industry Sub-Sectors Experience in All Major Infrastructure Markets • Star America has worked in all infrastructure markets, including Civil Construction, Vertical Building, Public-Private Partnerships, Industrial Business Development Mergers & Acquisitions PPP Financial Advisory Management Consulting Capital Raising Strategic & Financial Analysis Star is well qualified to assist clients in developing their business plans in the U.S. Given the depth of experience of its partners and operating professionals, the company offers access to thought leadership of C-Level executives. We have a strong track record in both domestic and cross- border M&A advisory roles. We operate both negotiated processes and auctions, assist in deal structuring, and provide impartial advice about the merits of transactions in our industry of focus. Star provides financial advisory services to companies and consortia seeking to participate in alternative procurement processes. We advise on debt capital raising in the bank and bond markets, and help structure competitive bids for our clients. We work with clients to formulate and pursue strategic and tactical goals. Star provides true business solutions, including identifying potential management hires, developing and implementing marketing plans, and increasing operational efficiencies. We maintain contacts at banks, hedge funds, equipment finance companies, and other financial firms. These are sources of capital for clients desiring funds for expansionary capital expenditures or general operating cash flow needs. Industry analytics form the core of a successful financing or business development strategy. With our significant industry knowledge, we assess companies’ current and projected financial and competitive positions to provide actionable recommendations. We have the capacity to provide comprehensive financial analysis as well as contractor prequalification solutions, allowing contractors to properly vet lower tiers and improve overall capital strength. Star America Capital Advisors, LLC Services Overview Service Offerings Disclaimer: This material is for informational purposes only. It should not be relied on for any other purposes. The goal of this report is to help market participants critically asses each state's expected infrastructure budgets and competitive environment. WWW.STARAMERICAP.COM • 390 N Broadway, Jericho, NY, 11753 • (516) 882-4100