Lean/Six Sigma Green Belt
MTF FY19: Improve Command Check-In Process
1st Medical Bn
Project Belt: LCDR John McAfee
Champion: LT Jeremy Jackson / LT Amber Lenfert
Command Black Belt: LCDR Nick Saltzman
Black Belt Mentor: Mr. Michael Teegardin
18 July 2019
PIO - #26704
Pre-Event Tollgate
PIO - #26704
Task Start Complete
Project Charter 18 July 2019
Communication Plan 22 July 2019 22 July 2019
SIPOC 22 July 2019 22 July 2019
Voice of the Customer 22 July 2019 22 July 2019
Data Collection Plan 23 July 2019 23 July 2019
Preliminary Analysis 23 July 2019 23 July 2019
Project Team
Core Team
Project Lead
Project Sponsor /
Champion
Command Black Belt Financial SME
LCDR John McAfee
LT Jeremy Jackson &
LT Amber Lenfert
LCDR Nick Saltzman N/A
Team Members
PS1 Rui Li HM1 Wilfred Flores HM1 Marlon Yulo HM2 Jose Gonzalez
JM2 William Hohmann HM2 Matthew Rol PS2 Dongye Xu HM3 Alexandra Martin
PIO - #26704
Project Charter
PIO - #26704
Communication Plan
Purpose Audience Media Discussion Topics Responsible Person
Frequency of
Communication
Location Notes / Status
MEETING AGENDA
Project Team Share Drive
Database
E-mail
Project Status
Next Team Meeting
Action Item Status
Other Project Information
Project Belt Weekly / As Needed Office
Telephone
E-Mail
TOLLGATES
Green Belt
Project Team
Discussion Tollgate Development
Pre-Event
Event
Post Event, Validate
Project Belt
Team
Weekly / As Needed Office
Telephone
E-Mail
CHAMPION MEETING
Champion
Green Belt
Sponsor
Process Owner
Meeting Project Charter Brief
Tollgate Briefs
Project Status
Project Belt As Needed Office
Telephone
E-Mail
TEAM MEETING
Staff Meeting Charter
SIPOC, Current State Map
Ishikawa, VOC, VSM
Project Team Weekly / As Needed Office
Telephone
EVALUATION MEETING
Staff Meeting Review BUMED Regulations
Review MTF Data
Review VOC, Develop VSA
Project Team Weekly / As Needed Office
Telephone
E-Mail
REPORTING MEETING
Staff Meeting
PowerPoint
Team Reviews
Project Status Reviews
Project Team Monthly / As Needed Office
Telephone
E-Mail
DECISION MAKING MEETING
Staff Meeting Team Reviews
Project Status Reviews
Ishikawa
VOC
Project Team Weekly / As Needed Office
Telephone
E-Mail
PROBLEM SOLVING MEETING
Staff Meeting Brainstorming
Ishikawa
VSA, VOC
Project Team Weekly / As Needed Office
Telephone
E-Mail
PLANNING MEETING
Staff Meeting Brainstorming Project Team Weekly / As Needed Office
E-Mail
PIO - #26704
SIPOC
Suppliers
• Individual Issue Facility
(IIF)
• Headquarters & Services
(H&S) Sections
• Citibank GTCC
• MLG G6
• PSD Memphis
• Field Medical Training
Battalion-West
Inputs
• Check-In Sheet
• Operational Taskers from
1st MLG
• TEEP
• Orders
• Training (i.e. GTCC on
MarineNet)
• In-Brief Appointments
with CO/XO/CMC
• Travel Claim
Process Outputs
Products
• New GTCC issued
• SACO materials
• IIF gear issue
• Security Clearance
Reports
• Morning Report
• Billet Identification Code
Report
• Physical Readiness
Report
Records
• Deployment Folder
• DRC Record
Customers
• CGIP Inspectors
• Adjacent Units
• 1st MLG
• Deploying Unit
• Surgical Companies
• New Check-In
• New Check-In’s Family
New Check-In
Receives Check-In
Sheet from
S-1/Admin
New Check-In
obtains signatures
from POC at each
section
New Check-In
make
approximately 40
stops
New Check-In
returns completed
sheet to
S-1/Admin
CTP CTC
PIO - #26704
Voice of the Customer (VOC)
Voice of the Customer Why it is Important Critical Customer Requirement
New Check-In Complaints of outdated check-in sheet Timeliness and organization
1st Medical Battalion
No accurate contact information from
the prospective gain prior to check-in
Need to provide forms and documents to
the prospective gain prior to check-in
Sections, especially S-1
Capitalize on a captive audience during
Command Indoctrination to complete
check-in requirements
Timeliness and organization
1st Medical Bn
Commanding General’s Inspection
Program (CGIP)
Requirement for accurate and complete
process
PIO - #26704
Data Collection Plan
Metric Data Type Operational Definition Sampling Notes Source & Location Collection Method
Who will Collect the
Data
Number of
check-ins within
14 business days
Continuous
(variable)
Active Duty Navy personnel
assigned to 1st Med Bn
Sample size of 30
Green check-in
logbook and cabinet
Physical counting
HM2 Hohmann,
HM3 Martin
Number of
check-ins didn’t
complete sheet
Continuous
(variable)
Active Duty Navy personnel
assigned to 1st Med Bn
Sample size of 30
Green check-in
logbook and cabinet
Physical counting
HM2 Hohmann,
HM3 Martin
Distance
traveled to
complete sheet
Attribute
(discrete)
Distance to travel in order to
complete check-in sheet
N/A
MCB Camp
Pendleton
Google Maps HM2 Gonzalez
Time to
complete check-
in sheet
Attribute
(discrete)
Time to complete check-in
sheet
N/A
MCB Camp
Pendleton
Walk the process New Check-In
How will the Data be Used? The data will be used to improve the check-in process?
How will the Data be displayed? Graphical
What is the plan for starting Data Collection?
The members listed in the final column in the chart above will initiate their specific data
collection per the plan outlined above.
1 Time & distance
2 Completed / Not Completed
3
PIO - #26704
Baseline Data Sample
PIO - #26704
28252219161310741
25
20
15
10
5
0
-5
Observation
IndividualValue
_
X=8.63
UCL=21.47
LCL=-4.21
1
I Chart of Pre Days
Baseline Circle Diagram
PIO - #26704
Handoffs: 35
Flow Clock Time: 871 min/14.52 hours
Manual Touch Time: 615 min/10.25 hours
Distance: 71,725 ft/13.58 miles
1. S-1: Page 2, Etc
2. S-1: Eval Manager, Etc
3. S-1: Family Care Plan
4. S-1: NFAAS
5. S-1: Family Care Plan
6. S-1: Mailroom
7. S-1: MOL
8. S-6
9. Surg Co C: FMF
10. Career Counselor11. DRC
12. SACO
13. Admin Chief Brief
14. MCMH: Motorcycle Safety15. S-2
16. S-4
17. Legal
18. Surg Co C: Watchbill
19. S3T: BCA & Training
20. MCMH: Medical & Dental
21. Armory22. PMU: Safety
23. MFLC
24. IIF
25. DMO
26. S3T: CBRN
27. PMU: Voting Officer
28. Surg Co B/Supply
29. Bldg. 13150: EFMP
30. JRC: Vehicle Registration
31. NMCRS
32. Bldg. 1146: Base Library
33. Bldg. 1523: PMO
34. Bldg. 98: Housing
Baseline Data Analysis
• Referencing the run chart, there appears no accountability for the check-in process
to be completed in the required 14 business days.
– 10 of 30 new check-ins turned in a check-in sheet but did not complete it within the
allotted 14 business days;
– 1 of 30 new check-ins did not complete the check-process
• Referring to the circle chart, The current process has grown over the years, falling
victim to "Its-Always-Been-Done-This-Way.“
– NO formal Marine Corps Orders, etc. to support why several stops in the current process
are required
– One requirement is mandatory at Navy commands; 1st Medical Bn is a Marine Corps
command, and therefore not held to Navy requirements
• Stops are missing from each of the separate Officer and Enlisted check-in sheets
• Listing names instead of locations appears to play a negative role in version control,
as some names were listed differently on the 2 sheets, or missing completely
• The number of stops appear to be inefficient; several of the stops can be addressed
during command indoctrination.
• Based on the 29 data points the average check-In occurs in 8.63 days
• 51.7% of the time a Check-In takes more than 7 days
• 79.3% of the time a Check-In takes more than 5 days
PIO - #26704
Investigate Existing Solution
PIO - #26704Screenshot captured 14-Aug
Event Tollgate
Task Start Complete
Define Current State 24 July 2019 24 July 2019
Root Cause Analysis 24 July 2019 24 July 2019
Define Future State 24 July 2019 24 July 2019
PIO - #26704
Current State Process Map / Value Stream Map
Start
New AD Enlisted
Reports
Check-In Pkg
Provided
Member In Brief PRT/SACO/S2/S6
Marine Centered
Medical Home
S1
DTS
GOV CC
Mail ROOM
11F
S3T-CBRN
(Gas Mask)
FMF
B Co / C Co
Legal
S-4
Watchbill
Coordinator
for Enlisted
DRC
Days/Hours
Chaplain
CLR-15
Armory Supply
DMO
Safety
Voting Officer
ADJ Provost Marshal
Vehicle
Registration
Base Housing
Navy-Marine
Corps Relief
Society
Base Library
Member Returns
Completed Check-In
Sheet to S1
Dental
End
No
EFMP
MFLC
Yes
PIO - #26704
GEMBA
# Observation Area/Activity Observed
Findings / Data Collected or
Reviewed /Concerns for Further
Analysis
1 Unable to find the Chaplain’s office
No guidance or directions are
provided to get to the Chaplain’s
office
Bn doesn’t provide directions or
have an RP available.
2 Unorganized Check-In Process Check-in sheet doesn’t flow
The check-in sheet needs to be
organized to decrease
inefficiencies and error.
3 New Check-In’s Sponsor Unavailable
Lack of guidance and assistance from
the sponsor
Sponsors should be more readily
available to assist the new check-
in with the process
PIO - #26704
Check-In Long & Incomplete
New Check-In Family Issue
Availability of POCs
Sponsor Availability & Motivation
Member Lack of Motivation
Out-Dated Check-In Sheet
Check-In Sheet Provided by
Multiple People
Sponsorship Program
14 Business Days
Too Generous
Lack of POV
Lack of Map/
Welcome Aboard Pack
PC/Network
Availability
Root Cause Analysis – Ishikawa Diagram
PIO - #26704
Root Cause Analysis – Affinity Diagram
Outdated Check-
In Sheet
Not Primary S-1
POC
Updates from
POCs not
provided
periodically
Version Control
of Master Copy
Different sheet
for Os & Es
Lack of
Motivation from
New Check in
Take advantage
of allotted time
to complete
No
consequences
for passing 14
business days
Lack of
Computer/
Network
LRC only allows
access to
MarineNet
courses
Technical
barriers to NKO
courses
Ineffective
sponsorship
Different levels
of motivation
Not engaged
Lack of training
Lack of
availability
Command events
/holidays
Lack of POCs
OPTEMPO
What are the barriers to not completing check-in sheet within 14 business days?
PIO - #26704
7 Forms of Waste (MUDA)
Observed Type Location Team Voting
Transport
Inventory
Motion
Waiting POC unavailable during process 3 of 3
Over-Production
Over-Processing Non-value added stops in process 1 of 3
Defects Requiring Rework or Scrap
Specific steps completed out of order or
multiple stops to single POC
2 of 3
PIO - #26704
Future State Process Map / Value Stream Map
PIO - #26704
Start
MBR Receives
Check-InSheet from
S1
MBR
CompletesCritical
Req s atCommand
MBR Completes
Req s at22 Area
MCMH
MBR Completes1st
DeckReq s
MBR Completes22
AreaReqs
MBR Completes
MCBCamp
PendletonReq s
MBR Returns
CompletedCheck-In
SheettoS1
End
Artifacts
PIO - #26704
Artifacts
PIO - #26704
Post Event Tollgate
Task Start Complete
Implementation Plan 14 August 2019 9 September 2019
Control Plan
CPIMS Documentation
Benefits Workbook
PIO - #26704
Implementation Plan
Problem Identified Action Needed Created Date
Completed
Date
Improvement Metrics Person Responsible
What is the waste?
How is the waste
Eliminated?
Inefficient steps on
command check-in
sheet
Outline necessary stops for
command check-in to follow
methodical & efficient flow
14 Aug 2019 30 Aug 2019
Decrease in
time/distance
HM2 Gonzalez,
HM2 Hohmann,
HM2 Martin
Multiple unnecessary
or non-mandatory
stops. Removed.
Lack of uniformity
between officer
and enlisted
command check-in
sheet
Combine the Officer and
Enlisted command check-in
sheets
14 Aug 2019 30 Aug 2019
Improvement in
completion of check-in
process
HM2 Gonzalez,
HM2 Hohmann,
HM2 Martin
Missed stops on the
two different
formats; version
control with new
updates
Sponsor unavailable
to escort their new
check-in
Reiterate to sponsors that
they must escort their new
check-in throughout the
check-in process
14 Aug 2019 30 Aug 2019 Metric is Intangible LT Lenfert
Sponsor is there to
assist new check-in to
find unfamiliar
locations
PIO - #26704
Control Plan
Name of
Measure
Measure
Definition
Measure
Calculation
Data
Source
Goal
Measure
Frequency
Sample
Size
When to
Act
Who
Decides to
Act
Who
Acts
Reaction
to Out of
Control
Display
Method
Command
Check-In
Process
Completion
Check-In sheets
will be returned
within 10
business days.
Number of
check-in sheets
returned to S-1
within 10
business days.
S-1
collection
of check-in
sheets
100%
complete
and
within 10
business
days.
Weekly
10% of
weekly
check-in
sheets
completed
Mondays,
puling the
previous
week’s
completed
check-in
sheets
Process
Owner
S-1 staff
New check-
in’s chain of
command is
notified
1st – E-mail sent
to section head
or company
commander
2nd – Metrics
presented during
XO’s staff
meeting
PIO - #26704
Post Intervention Data Sample
PIO - #26704
Date Issued Date Complete Delta
10/8/2019 10/18/2019 6
10/10/2019 10/15/2019 3
10/10/2019 10/17/2019 4
10/10/2019 10/17/2019 5
10/10/2019 10/18/2019 6
10/12/2019 10/18/2019 4
10/12/2019 10/18/2019 5
Post Intervention Data Analysis
PIO - #26704
0
5
10
15
20
25
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Days
Check In Sheet
Check In (Individuals)
Post Intervention Circle Diagram
PIO - #26704
Handoffs: 28
Flow Clock Time: 778 min/13 hours
Manual Touch Time: 600 min/10 hours
Distance: 44,880 ft/8.5 miles
1. S-1: Page 2, Etc
2. S-1: Update MOL
3. SACO: Urinalysis
4. FPC
5. CFL: Weigh-In
6. S2: ISOPREP
7. S6: SAAR
8. Command Deck
9. Medical
10. Dental11. S1: DTS
12. Indoc Coord.13. CCC
14. S1: Mail Clerk15. S1: NFAAS, etc.
16. S1: Evals17. S1: ESO
18. DRC19. S3T
20. WBC21. MFLC
22. Armory
23. IIF
24. Safety25. Supply
26. Supply27. Credentialing
28. Main Side Library
29. JRC: Vehicle registration
30. Family Housing Office
Project Benefits
Tangible
• Efficiency in the process
• Immediate staff utilization
• Better accountability of staff
• Decrease in manpower idle time
due to a prolonged check-in
process
Intangible
• Potential spin-off from this
project is a LSS or “Just Do It”
project on the Command Check-
Out Process
• A replication of this project may
apply to adjacent units and
should be shared with those units
seeking to streamline their
command check-in process
PIO - #26704

More Related Content

Similar to Lean/Six Sigma Green Belt: Improve Command Check-In Process

MS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionMS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionSelf employed
 
Temp management measure & analyze tollgate presentation final
Temp management measure & analyze tollgate presentation finalTemp management measure & analyze tollgate presentation final
Temp management measure & analyze tollgate presentation finalAshley Lucci-Vaughn
 
Tollgate Int Med Cycle Time 151120
Tollgate Int Med Cycle Time 151120Tollgate Int Med Cycle Time 151120
Tollgate Int Med Cycle Time 151120Adam Reed, PMP
 
Bct 2018 a1 briefing
Bct 2018 a1 briefingBct 2018 a1 briefing
Bct 2018 a1 briefingemilydladd
 
20140311 - Catel 01_ Effective lean deployment to FDA approval
20140311 - Catel 01_ Effective lean deployment to FDA approval20140311 - Catel 01_ Effective lean deployment to FDA approval
20140311 - Catel 01_ Effective lean deployment to FDA approvalCyrille Catel
 
PPT on returns
PPT on returnsPPT on returns
PPT on returnsNiharPaul1
 
2015 CDA Dagupan Annual Accomplishment Report
2015  CDA Dagupan Annual Accomplishment Report2015  CDA Dagupan Annual Accomplishment Report
2015 CDA Dagupan Annual Accomplishment Reportjo bitonio
 
Perfect Service Delivery
Perfect Service DeliveryPerfect Service Delivery
Perfect Service DeliveryAmy S. Friend
 
GPC Face to Face Training Slides.pptx2023
GPC Face to Face Training Slides.pptx2023GPC Face to Face Training Slides.pptx2023
GPC Face to Face Training Slides.pptx2023GheorgheBadea2
 
VaARNG Cooperative Agreement Process
VaARNG Cooperative Agreement ProcessVaARNG Cooperative Agreement Process
VaARNG Cooperative Agreement ProcessJames Foster
 
Land Development Improvement Process
Land Development Improvement ProcessLand Development Improvement Process
Land Development Improvement ProcessFairfax County
 
3 by 4 and No More - Strategic Customer Engagement
3 by 4 and No More - Strategic Customer Engagement3 by 4 and No More - Strategic Customer Engagement
3 by 4 and No More - Strategic Customer EngagementCOL Vernon Myers
 
Charles Einarson Greenbelt Presentation
Charles Einarson Greenbelt PresentationCharles Einarson Greenbelt Presentation
Charles Einarson Greenbelt PresentationCharles Einarson
 
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%GoLeanSixSigma.com
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionJohn W. McAfee, MHA, PMP, FACHE
 
Kulis Out Brief
Kulis Out BriefKulis Out Brief
Kulis Out Briefwilleetee
 
Inbound MIPR Process
Inbound MIPR ProcessInbound MIPR Process
Inbound MIPR ProcessJames Foster
 

Similar to Lean/Six Sigma Green Belt: Improve Command Check-In Process (20)

MS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionMS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 million
 
Temp management measure & analyze tollgate presentation final
Temp management measure & analyze tollgate presentation finalTemp management measure & analyze tollgate presentation final
Temp management measure & analyze tollgate presentation final
 
Tollgate Int Med Cycle Time 151120
Tollgate Int Med Cycle Time 151120Tollgate Int Med Cycle Time 151120
Tollgate Int Med Cycle Time 151120
 
Bct 2018 a1 briefing
Bct 2018 a1 briefingBct 2018 a1 briefing
Bct 2018 a1 briefing
 
Program Weekly Meeting
Program Weekly MeetingProgram Weekly Meeting
Program Weekly Meeting
 
20140311 - Catel 01_ Effective lean deployment to FDA approval
20140311 - Catel 01_ Effective lean deployment to FDA approval20140311 - Catel 01_ Effective lean deployment to FDA approval
20140311 - Catel 01_ Effective lean deployment to FDA approval
 
PPT on returns
PPT on returnsPPT on returns
PPT on returns
 
2015 CDA Dagupan Annual Accomplishment Report
2015  CDA Dagupan Annual Accomplishment Report2015  CDA Dagupan Annual Accomplishment Report
2015 CDA Dagupan Annual Accomplishment Report
 
Perfect Service Delivery
Perfect Service DeliveryPerfect Service Delivery
Perfect Service Delivery
 
GPC Face to Face Training Slides.pptx2023
GPC Face to Face Training Slides.pptx2023GPC Face to Face Training Slides.pptx2023
GPC Face to Face Training Slides.pptx2023
 
VaARNG Cooperative Agreement Process
VaARNG Cooperative Agreement ProcessVaARNG Cooperative Agreement Process
VaARNG Cooperative Agreement Process
 
Land Development Improvement Process
Land Development Improvement ProcessLand Development Improvement Process
Land Development Improvement Process
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
3 by 4 and No More - Strategic Customer Engagement
3 by 4 and No More - Strategic Customer Engagement3 by 4 and No More - Strategic Customer Engagement
3 by 4 and No More - Strategic Customer Engagement
 
Charles Einarson Greenbelt Presentation
Charles Einarson Greenbelt PresentationCharles Einarson Greenbelt Presentation
Charles Einarson Greenbelt Presentation
 
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%
SUCCESS STORY: How Lean Six Sigma Reduced Travel Expense Approval Time by 94%
 
IRS Employee Plans
IRS Employee PlansIRS Employee Plans
IRS Employee Plans
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate Reduction
 
Kulis Out Brief
Kulis Out BriefKulis Out Brief
Kulis Out Brief
 
Inbound MIPR Process
Inbound MIPR ProcessInbound MIPR Process
Inbound MIPR Process
 

Recently uploaded

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCNAP Global Network
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourCall Girls in Nagpur High Profile
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...SUHANI PANDEY
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisChristina Parmionova
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hourCall Girls in Nagpur High Profile
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...SUHANI PANDEY
 
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Patna Escorts Just Dail 8250092165 service available anytime 24 hour
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
 

Lean/Six Sigma Green Belt: Improve Command Check-In Process

  • 1. Lean/Six Sigma Green Belt MTF FY19: Improve Command Check-In Process 1st Medical Bn Project Belt: LCDR John McAfee Champion: LT Jeremy Jackson / LT Amber Lenfert Command Black Belt: LCDR Nick Saltzman Black Belt Mentor: Mr. Michael Teegardin 18 July 2019 PIO - #26704
  • 2. Pre-Event Tollgate PIO - #26704 Task Start Complete Project Charter 18 July 2019 Communication Plan 22 July 2019 22 July 2019 SIPOC 22 July 2019 22 July 2019 Voice of the Customer 22 July 2019 22 July 2019 Data Collection Plan 23 July 2019 23 July 2019 Preliminary Analysis 23 July 2019 23 July 2019
  • 3. Project Team Core Team Project Lead Project Sponsor / Champion Command Black Belt Financial SME LCDR John McAfee LT Jeremy Jackson & LT Amber Lenfert LCDR Nick Saltzman N/A Team Members PS1 Rui Li HM1 Wilfred Flores HM1 Marlon Yulo HM2 Jose Gonzalez JM2 William Hohmann HM2 Matthew Rol PS2 Dongye Xu HM3 Alexandra Martin PIO - #26704
  • 5. Communication Plan Purpose Audience Media Discussion Topics Responsible Person Frequency of Communication Location Notes / Status MEETING AGENDA Project Team Share Drive Database E-mail Project Status Next Team Meeting Action Item Status Other Project Information Project Belt Weekly / As Needed Office Telephone E-Mail TOLLGATES Green Belt Project Team Discussion Tollgate Development Pre-Event Event Post Event, Validate Project Belt Team Weekly / As Needed Office Telephone E-Mail CHAMPION MEETING Champion Green Belt Sponsor Process Owner Meeting Project Charter Brief Tollgate Briefs Project Status Project Belt As Needed Office Telephone E-Mail TEAM MEETING Staff Meeting Charter SIPOC, Current State Map Ishikawa, VOC, VSM Project Team Weekly / As Needed Office Telephone EVALUATION MEETING Staff Meeting Review BUMED Regulations Review MTF Data Review VOC, Develop VSA Project Team Weekly / As Needed Office Telephone E-Mail REPORTING MEETING Staff Meeting PowerPoint Team Reviews Project Status Reviews Project Team Monthly / As Needed Office Telephone E-Mail DECISION MAKING MEETING Staff Meeting Team Reviews Project Status Reviews Ishikawa VOC Project Team Weekly / As Needed Office Telephone E-Mail PROBLEM SOLVING MEETING Staff Meeting Brainstorming Ishikawa VSA, VOC Project Team Weekly / As Needed Office Telephone E-Mail PLANNING MEETING Staff Meeting Brainstorming Project Team Weekly / As Needed Office E-Mail PIO - #26704
  • 6. SIPOC Suppliers • Individual Issue Facility (IIF) • Headquarters & Services (H&S) Sections • Citibank GTCC • MLG G6 • PSD Memphis • Field Medical Training Battalion-West Inputs • Check-In Sheet • Operational Taskers from 1st MLG • TEEP • Orders • Training (i.e. GTCC on MarineNet) • In-Brief Appointments with CO/XO/CMC • Travel Claim Process Outputs Products • New GTCC issued • SACO materials • IIF gear issue • Security Clearance Reports • Morning Report • Billet Identification Code Report • Physical Readiness Report Records • Deployment Folder • DRC Record Customers • CGIP Inspectors • Adjacent Units • 1st MLG • Deploying Unit • Surgical Companies • New Check-In • New Check-In’s Family New Check-In Receives Check-In Sheet from S-1/Admin New Check-In obtains signatures from POC at each section New Check-In make approximately 40 stops New Check-In returns completed sheet to S-1/Admin CTP CTC PIO - #26704
  • 7. Voice of the Customer (VOC) Voice of the Customer Why it is Important Critical Customer Requirement New Check-In Complaints of outdated check-in sheet Timeliness and organization 1st Medical Battalion No accurate contact information from the prospective gain prior to check-in Need to provide forms and documents to the prospective gain prior to check-in Sections, especially S-1 Capitalize on a captive audience during Command Indoctrination to complete check-in requirements Timeliness and organization 1st Medical Bn Commanding General’s Inspection Program (CGIP) Requirement for accurate and complete process PIO - #26704
  • 8. Data Collection Plan Metric Data Type Operational Definition Sampling Notes Source & Location Collection Method Who will Collect the Data Number of check-ins within 14 business days Continuous (variable) Active Duty Navy personnel assigned to 1st Med Bn Sample size of 30 Green check-in logbook and cabinet Physical counting HM2 Hohmann, HM3 Martin Number of check-ins didn’t complete sheet Continuous (variable) Active Duty Navy personnel assigned to 1st Med Bn Sample size of 30 Green check-in logbook and cabinet Physical counting HM2 Hohmann, HM3 Martin Distance traveled to complete sheet Attribute (discrete) Distance to travel in order to complete check-in sheet N/A MCB Camp Pendleton Google Maps HM2 Gonzalez Time to complete check- in sheet Attribute (discrete) Time to complete check-in sheet N/A MCB Camp Pendleton Walk the process New Check-In How will the Data be Used? The data will be used to improve the check-in process? How will the Data be displayed? Graphical What is the plan for starting Data Collection? The members listed in the final column in the chart above will initiate their specific data collection per the plan outlined above. 1 Time & distance 2 Completed / Not Completed 3 PIO - #26704
  • 9. Baseline Data Sample PIO - #26704 28252219161310741 25 20 15 10 5 0 -5 Observation IndividualValue _ X=8.63 UCL=21.47 LCL=-4.21 1 I Chart of Pre Days
  • 10. Baseline Circle Diagram PIO - #26704 Handoffs: 35 Flow Clock Time: 871 min/14.52 hours Manual Touch Time: 615 min/10.25 hours Distance: 71,725 ft/13.58 miles 1. S-1: Page 2, Etc 2. S-1: Eval Manager, Etc 3. S-1: Family Care Plan 4. S-1: NFAAS 5. S-1: Family Care Plan 6. S-1: Mailroom 7. S-1: MOL 8. S-6 9. Surg Co C: FMF 10. Career Counselor11. DRC 12. SACO 13. Admin Chief Brief 14. MCMH: Motorcycle Safety15. S-2 16. S-4 17. Legal 18. Surg Co C: Watchbill 19. S3T: BCA & Training 20. MCMH: Medical & Dental 21. Armory22. PMU: Safety 23. MFLC 24. IIF 25. DMO 26. S3T: CBRN 27. PMU: Voting Officer 28. Surg Co B/Supply 29. Bldg. 13150: EFMP 30. JRC: Vehicle Registration 31. NMCRS 32. Bldg. 1146: Base Library 33. Bldg. 1523: PMO 34. Bldg. 98: Housing
  • 11. Baseline Data Analysis • Referencing the run chart, there appears no accountability for the check-in process to be completed in the required 14 business days. – 10 of 30 new check-ins turned in a check-in sheet but did not complete it within the allotted 14 business days; – 1 of 30 new check-ins did not complete the check-process • Referring to the circle chart, The current process has grown over the years, falling victim to "Its-Always-Been-Done-This-Way.“ – NO formal Marine Corps Orders, etc. to support why several stops in the current process are required – One requirement is mandatory at Navy commands; 1st Medical Bn is a Marine Corps command, and therefore not held to Navy requirements • Stops are missing from each of the separate Officer and Enlisted check-in sheets • Listing names instead of locations appears to play a negative role in version control, as some names were listed differently on the 2 sheets, or missing completely • The number of stops appear to be inefficient; several of the stops can be addressed during command indoctrination. • Based on the 29 data points the average check-In occurs in 8.63 days • 51.7% of the time a Check-In takes more than 7 days • 79.3% of the time a Check-In takes more than 5 days PIO - #26704
  • 12. Investigate Existing Solution PIO - #26704Screenshot captured 14-Aug
  • 13. Event Tollgate Task Start Complete Define Current State 24 July 2019 24 July 2019 Root Cause Analysis 24 July 2019 24 July 2019 Define Future State 24 July 2019 24 July 2019 PIO - #26704
  • 14. Current State Process Map / Value Stream Map Start New AD Enlisted Reports Check-In Pkg Provided Member In Brief PRT/SACO/S2/S6 Marine Centered Medical Home S1 DTS GOV CC Mail ROOM 11F S3T-CBRN (Gas Mask) FMF B Co / C Co Legal S-4 Watchbill Coordinator for Enlisted DRC Days/Hours Chaplain CLR-15 Armory Supply DMO Safety Voting Officer ADJ Provost Marshal Vehicle Registration Base Housing Navy-Marine Corps Relief Society Base Library Member Returns Completed Check-In Sheet to S1 Dental End No EFMP MFLC Yes PIO - #26704
  • 15. GEMBA # Observation Area/Activity Observed Findings / Data Collected or Reviewed /Concerns for Further Analysis 1 Unable to find the Chaplain’s office No guidance or directions are provided to get to the Chaplain’s office Bn doesn’t provide directions or have an RP available. 2 Unorganized Check-In Process Check-in sheet doesn’t flow The check-in sheet needs to be organized to decrease inefficiencies and error. 3 New Check-In’s Sponsor Unavailable Lack of guidance and assistance from the sponsor Sponsors should be more readily available to assist the new check- in with the process PIO - #26704
  • 16. Check-In Long & Incomplete New Check-In Family Issue Availability of POCs Sponsor Availability & Motivation Member Lack of Motivation Out-Dated Check-In Sheet Check-In Sheet Provided by Multiple People Sponsorship Program 14 Business Days Too Generous Lack of POV Lack of Map/ Welcome Aboard Pack PC/Network Availability Root Cause Analysis – Ishikawa Diagram PIO - #26704
  • 17. Root Cause Analysis – Affinity Diagram Outdated Check- In Sheet Not Primary S-1 POC Updates from POCs not provided periodically Version Control of Master Copy Different sheet for Os & Es Lack of Motivation from New Check in Take advantage of allotted time to complete No consequences for passing 14 business days Lack of Computer/ Network LRC only allows access to MarineNet courses Technical barriers to NKO courses Ineffective sponsorship Different levels of motivation Not engaged Lack of training Lack of availability Command events /holidays Lack of POCs OPTEMPO What are the barriers to not completing check-in sheet within 14 business days? PIO - #26704
  • 18. 7 Forms of Waste (MUDA) Observed Type Location Team Voting Transport Inventory Motion Waiting POC unavailable during process 3 of 3 Over-Production Over-Processing Non-value added stops in process 1 of 3 Defects Requiring Rework or Scrap Specific steps completed out of order or multiple stops to single POC 2 of 3 PIO - #26704
  • 19. Future State Process Map / Value Stream Map PIO - #26704 Start MBR Receives Check-InSheet from S1 MBR CompletesCritical Req s atCommand MBR Completes Req s at22 Area MCMH MBR Completes1st DeckReq s MBR Completes22 AreaReqs MBR Completes MCBCamp PendletonReq s MBR Returns CompletedCheck-In SheettoS1 End
  • 22. Post Event Tollgate Task Start Complete Implementation Plan 14 August 2019 9 September 2019 Control Plan CPIMS Documentation Benefits Workbook PIO - #26704
  • 23. Implementation Plan Problem Identified Action Needed Created Date Completed Date Improvement Metrics Person Responsible What is the waste? How is the waste Eliminated? Inefficient steps on command check-in sheet Outline necessary stops for command check-in to follow methodical & efficient flow 14 Aug 2019 30 Aug 2019 Decrease in time/distance HM2 Gonzalez, HM2 Hohmann, HM2 Martin Multiple unnecessary or non-mandatory stops. Removed. Lack of uniformity between officer and enlisted command check-in sheet Combine the Officer and Enlisted command check-in sheets 14 Aug 2019 30 Aug 2019 Improvement in completion of check-in process HM2 Gonzalez, HM2 Hohmann, HM2 Martin Missed stops on the two different formats; version control with new updates Sponsor unavailable to escort their new check-in Reiterate to sponsors that they must escort their new check-in throughout the check-in process 14 Aug 2019 30 Aug 2019 Metric is Intangible LT Lenfert Sponsor is there to assist new check-in to find unfamiliar locations PIO - #26704
  • 24. Control Plan Name of Measure Measure Definition Measure Calculation Data Source Goal Measure Frequency Sample Size When to Act Who Decides to Act Who Acts Reaction to Out of Control Display Method Command Check-In Process Completion Check-In sheets will be returned within 10 business days. Number of check-in sheets returned to S-1 within 10 business days. S-1 collection of check-in sheets 100% complete and within 10 business days. Weekly 10% of weekly check-in sheets completed Mondays, puling the previous week’s completed check-in sheets Process Owner S-1 staff New check- in’s chain of command is notified 1st – E-mail sent to section head or company commander 2nd – Metrics presented during XO’s staff meeting PIO - #26704
  • 25. Post Intervention Data Sample PIO - #26704 Date Issued Date Complete Delta 10/8/2019 10/18/2019 6 10/10/2019 10/15/2019 3 10/10/2019 10/17/2019 4 10/10/2019 10/17/2019 5 10/10/2019 10/18/2019 6 10/12/2019 10/18/2019 4 10/12/2019 10/18/2019 5
  • 26. Post Intervention Data Analysis PIO - #26704 0 5 10 15 20 25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Days Check In Sheet Check In (Individuals)
  • 27. Post Intervention Circle Diagram PIO - #26704 Handoffs: 28 Flow Clock Time: 778 min/13 hours Manual Touch Time: 600 min/10 hours Distance: 44,880 ft/8.5 miles 1. S-1: Page 2, Etc 2. S-1: Update MOL 3. SACO: Urinalysis 4. FPC 5. CFL: Weigh-In 6. S2: ISOPREP 7. S6: SAAR 8. Command Deck 9. Medical 10. Dental11. S1: DTS 12. Indoc Coord.13. CCC 14. S1: Mail Clerk15. S1: NFAAS, etc. 16. S1: Evals17. S1: ESO 18. DRC19. S3T 20. WBC21. MFLC 22. Armory 23. IIF 24. Safety25. Supply 26. Supply27. Credentialing 28. Main Side Library 29. JRC: Vehicle registration 30. Family Housing Office
  • 28. Project Benefits Tangible • Efficiency in the process • Immediate staff utilization • Better accountability of staff • Decrease in manpower idle time due to a prolonged check-in process Intangible • Potential spin-off from this project is a LSS or “Just Do It” project on the Command Check- Out Process • A replication of this project may apply to adjacent units and should be shared with those units seeking to streamline their command check-in process PIO - #26704

Editor's Notes

  1. Insert PIO #in Footer – Click Insert Tab, Click Header & Footer, Enter the rest of the PIO# number in the footer section
  2. Insert Start and Complete Dates for Each Deliverable of the Pre-Event Phase
  3. Voice of the Customer What do they say when you ask about how they feel about your processes outputs? Why it is Important Figure out why they think this is important. Keep asking why and follow each path they present. Each one will lead to a specific measure. Critical Customer Requirement A simple and measurable metric that you can focus on for process improvement. If you can't figure out how to measure it, find a different measure.
  4. You may not have 3 questions that support your Data collection. The questions asked will be answered by the data collected and ties back to your metrics.
  5. From HM2 Hohmann’s data pull… Since 15 June 2019, 19 of 30 new check-ins turned in a completed check-in sheet within the allotted 14 business days; 10 of 30 new check-ins turned in a check-in sheet but did not complete it within the allotted 14 business days; 1 of 30 new check-ins did not complete the check-process (no completed check-in sheet was found in the archive file)
  6. 19 of 30 new check-ins turned in a completed check-in sheet within the allotted 14 business days; 10 of 30 new check-ins turned in a check-in sheet but did not complete it within the allotted 14 business days; 1 of 30 new check-ins did not complete the check-process (no completed check-in sheet was found in the archive file)
  7. Query CPIMS for existing project. Capture screenshot and paste as image. Include date when image was captured.
  8. Insert Start and Complete Dates for Each Deliverable of the Event Phase
  9. Start/Stop Identified Loops Closed/Connection Points VA / NVA / NVAE Gemba Data Box Identify Constraints
  10. Insert Ishikawa from iGrafx or Visio
  11. Replace the ‘x’ with goal of project. For example: If your project focused on on-time delivery of medications then you would replace the ‘x’ with on-time delivery of medications? The blue boxes would be the category name followed with all the barriers for that particular category. Right click and format shape color to red if it is one of the barriers that your project will eliminate or improve.
  12. Start/Stop Identified Loops Closed/Connection Points VA / NVA / NVAE Data Box Identify Constraints
  13. Insert pertinent documents for this tollgate, such as Sustainment Audit, Pre/Post Pictures, Waste Identification/Elimination Document, Improved Metrics, Sustainment Plans, etc.