SlideShare a Scribd company logo
1 of 3
Download to read offline
54 ASHRAE Journal ashrae.org July 2005
By Jeff Blaevoet, P.E., Member ASHRAE
When the HVAC design of the Hamil-
ton Landing project was first conceived
in 1998, it consisted of large package
air-cooled rooftop units sitting next to
the historic hangars with a conventional
overhead VAV reheat system.
The developer, however, liked the
underfloor presentation made for the
project and asked the architect to incor-
porate the concept.Along with the usual
benefits of underfloor air, this project
(2787 m2) hangars was also planned to
accommodate a second floor, supported
from the ground floor slab, increasing
the gross square footage of each hangar
to about 58,000 ft2 (5388 m2). Footings
for the second floor columns would have
had features that made it even more
suitable for a raised floor.
The ground floor slabs of the 70 year-
old Hamilton Air Force Base aircraft
hangars had settled into the Bay mud,
bowing down from the edges to the
center of each hangar.
The proposed solution to this was to
pour a topping slab to level the ground
floor, which was budgeted at $3/ft2
($32.29/m2). Each of the seven 30,000 ft2
About the Author
Jeff Blaevoet, P.E., is principal at Guttmann and
Blaevoet Consulting Engineers in San Francisco.
Blaevoet received a 2004 ASHRAE Technology
Award for this project.
Underfloor Air System for
Retrofit Office Complex
Exterior of Hamilton Landing project, which is a retrofit of a 70-year-old Air Force base hangar.
© 2005, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.
org). Reprinted by permission from ASHRAE Journal, (Vol. 47, No. 7, July 2005). This article may not be
copied nor distributed in either paper or digital form without ASHRAE’s permission.
July 2005 ASHRAE Journal 55
had to be poured below the existing slab, requiring cutting of
the slab at 30 ft (9 m) centers. The raised floor eliminated this
cost. The floor covered a multitude of sins, which helped pay
for itself.
Given the character of the 45 ft (14 m) high vaulted ceilings
of the aircraft hangars, suspended ceilings were not a desired
interior treatment, which meant that any ductwork would be
exposed and mounted high up at the structure.This would have
posed a challenge in several respects.
Heating would not be done very efficiently, and ventilation
air would be difficult to throw into each cubicle.Any enclosed
spaces, such as conference rooms, would require duct drops
that would be tricky to support and aesthetically difficult to
design. Given that zoning flexibility is needed, variable-air-
volume (VAV) reheat is required, which is much more dif-
ficult to design exposed with a clean appearance compared
to constant volume (CV)
single zone ducts.
The cost of making ex-
posed ductwork acceptable
in appearance was avoided
by the use of the raised floor.
A similar problem would
have been present for the
power and communications
cabling, with exposed race-
ways and power poles.
Right across a narrow
street from the hangars is a
development of new homes.
Having large air-cooled units
sitting next to the hangars
would have been unsightly
and noisy. Locating all the
mechanical equipment, such
as water-cooled direct expansion (DX) units, boiler and cooling
tower inside the building, enabled the appearance of the historic
buildings to be preserved, site landscaping to flourish and noise
to be controlled. Locating HVAC units on the lightly loaded,
barrel-vaulted roof was not an option from structural, aesthetic
and maintenance perspectives.
It is often difficult to accurately compare the cost of systems
at a conceptual level, and this is especially true when the alter-
nate being considered is relatively new. Even if historical data
is available, unfamiliarity can bump up the estimator’s num-
bers. In this case, the developer had a budget of about $85/ft2
($915/m2), which included a seismic upgrade of the building,
new curtain wall and windows, new roof and all new base-
building systems with the shell and core. The HVAC budget
was $8.50/ft2 ($91.50/m2) and the cost of the raised floor about
$7/ft2 ($75.35/m2). This worked with the previous factors to
stay on the budget planned earlier, but required some faith in
the raised floor system pricing.
Architectural Improvements
Architecturally, the adaptive reuse was designed to disturb
as little of the existing façade as possible to maintain the
historical integrity of the
hangars. Each hanger has
a large, rectangular floor
plate measuring 240 ft by
120 ft (73 m by 37 m).
Attached to each corner
of the building is a 12 ft
by 12 ft (3.7 m by 3.7 m)
tower that rises 38 ft (11.6
m) above grade. These
concrete towers with 11 ft
by 11 ft (3.4 m by 3.4 m)
clear inside were used for
housing four water-cooled
DX VAV air-conditioning
units on the first floor, and
a boiler and cooling tower
on the second floor.
The building envelope
is comprised concrete walls and a builtup roof with an overall
insulation level of R-19.The glazing is a reflective single-pane
glass with a U-value of 0.95 and a solar heat gain coefficient
(SHGC) of 0.37. The facility has an overall glazing ratio of
approximately 40%, with both the north and south elevations
having over 58% glazing.
Conference room in the interior of an office at Hamilton Landing.
56 ASHRAE Journal ashrae.org July 2005
HVAC System Overview
Four 30-ton (106 kW), water-cooled air-conditioning units,
each sized to provide 15,000 cfm (7079 L/s) of supply air,
serve both floors of each quadrant of the former hangars.These
units receive condenser water from a single 200-ton (703 kW)
forced-draft cooling tower, which provides 80°F (27°C) water,
circulated by a 7.5 hp (5.6 kW) pump. A boiler provides heat-
ing hot water for the perimeter hydronic reheat zones. Hot
water is distributed in a variable-flow pumping scheme with
reverse return and a 2 hp (1.5 kW) hot water pump with vari-
able speed drive.
Access flooring using pedestals 18 in. (0.5 m) above the
ground floor slab and 12 in. (0.3 m) above the second floor slab
were used as supply air plenums. This space also is used for
cable distribution (electric/phone/data) throughout the space.
Individuallyadjustable,floormountedsupplyairdiffusersregu-
late the airflow being supplied to the spaces.These diffusers pro-
vide the occupants with control over the airflow to their space.
The air-conditioning units were designed to maintain indoor
temperatures between 70°F and 78°F (21°C and 25°C) and they
supply air to the underfloor plenums at elevated temperatures of
63°F (17°C). At the perimeter of each floor, linear floor grilles
with hot water linear convectors heat the supply air as required.
The perimeter zones are provided with pressure dependent vol-
ume dampers located in the plenum dividers. This eliminated
the need for fan-powered boxes.
The mechanical system was designed to fit within the exist-
ing corner towers at each hangar. Each air-conditioning unit
occupies the first floor of a single tower, and is a tight fit. The
second floor of the northeast tower contains the boiler while the
second level of the southeast tower houses the cooling tower,
also a tight fit, and its associated pumps.
The first level of each tower has louvers for outdoor-air in-
take and serves as an intake air plenum for the air conditioner.
Second floor louvers provide intake air for the forced-draft
cooling tower, which discharges through the roof, and for
toilet exhaust.
The mechanical equipment is, therefore, entirely integrated
into the original building design, being very unobtrusive. Return
air is transferred through sidewall openings from the towers to
the interior space on each level.
Energy Efficiency
The building design is 29.6% below the 1998 CaliforniaTitle-
24 Energy Standards, and the facility qualified for more than
$55,000 in owner utility incentives.The project site weather cli-
mate has summer conditions (ASHRAE 0.5%) of 87°F (31°C)
DB and 63°F (17°C) WB and winter conditions (ASHRAE
0.2%) of 30°F (–1°C) DB. The typically mild conditions allow
the facility to use many hours of “free cooling” through the use
of an airside economizer.The low wet-bulb temperature ensures
that water cooled equipment can be efficiently applied.
The use of an underfloor system meant that many more econo-
mizer hours were possible with a 63°F to 65°F (17°C to 18°C)
supply air temperature compared to a typical system with 55°F
(13°C) supply air temperature. Utilizing water-cooled equip-
ment allowed the nominal cooling efficiency to be increased
from about 1.1 kW/ton (0.3 kW/kW) for air-cooled equipment,
to 0.7 kW/ton (0.2 kW/kW).
The underfloor air distribution system results in low external
static pressures (0.05 to 0.08 in. w.c. [12.5 to 20 Pa]) reducing
the amount of fan power consumed. Variable frequency drives
(VFDs) were installed on all the supply fans.TheVFDs are used
to maintain a constant static pressure in the supply plenum as
the tenants open and close individual diffusers, or VAV zones
modulate. Motorized dampers were provided behind the existing
building louvers, which are now used for relieving air from the
space when the units are in economizer mode, thus avoiding the
energy use of return or relief fans. The underfloor air system
supplying air at a temperature closer to that of room tempera-
ture results in less concern about operable windows conflicting
with air conditioning. All fans and pumps were specified with
premium efficiency motors.
Conclusion
Many different types of tenant improvements have been
successfully accommodated at Hamilton Landing, including
a YMCA, branch library, full service kitchen and deli, as well
as a multitude of office uses.
This project demonstrates that underfloor air can be a cost-
effective solution for retrofits and speculative office buildings.
The flexibility, comfort, indoor air quality, and energy efficiency
of underfloor air are very affordable, if not lower cost than
conventional overhead systems when executed well.
Underfloor air has been growing in its acceptance in the
United States and many new products, including fan-powered
VAV reheat boxes, and floor diffusers are now available. De-
sign guides, such as the Underfloor Air Distribution (UFAD)
Design Guide published by ASHRAE, have been written, and
more data is available now for cost comparisons, and technical
considerations such as leakage, which will help designers and
decision makers.
Interior photograph of the Hamilton Landing project.

More Related Content

What's hot

Centralized ac system
Centralized ac systemCentralized ac system
Centralized ac systemFebin Siby
 
Chilled water systems
Chilled water systemsChilled water systems
Chilled water systemsJason Abston
 
Complete hvac ppt by kk 354647.pptx 1234
Complete hvac ppt by kk 354647.pptx 1234Complete hvac ppt by kk 354647.pptx 1234
Complete hvac ppt by kk 354647.pptx 1234KRISHAN KUMAR
 
Training manual boiler general arrangement_mongduong ii
Training manual boiler general arrangement_mongduong iiTraining manual boiler general arrangement_mongduong ii
Training manual boiler general arrangement_mongduong iiHOANG VAN DUC
 
Air refrigeration system used in aircraft
Air refrigeration system used in aircraftAir refrigeration system used in aircraft
Air refrigeration system used in aircraftNissan Patel
 
Cooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesCooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesHusain Baqer
 
Hvac made easy selection tips for chiller compressors
Hvac made easy   selection tips for chiller compressorsHvac made easy   selection tips for chiller compressors
Hvac made easy selection tips for chiller compressorsMazhar Sheikh
 
Industrial gas turbine (air cooling & sealing sys) 5th
Industrial gas turbine (air cooling & sealing sys)   5thIndustrial gas turbine (air cooling & sealing sys)   5th
Industrial gas turbine (air cooling & sealing sys) 5thNguyen Phuong Dong
 
Air conditioning for large multistory buildings
Air conditioning for large multistory buildingsAir conditioning for large multistory buildings
Air conditioning for large multistory buildingspnazila
 
Centralised Air Conditioning
Centralised Air ConditioningCentralised Air Conditioning
Centralised Air ConditioningKapil Sinha
 
Hvac presentation
Hvac presentationHvac presentation
Hvac presentationcswisher
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemesMazhar Sheikh
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaJitendra Jha
 
Renewable energy sources
Renewable energy sources Renewable energy sources
Renewable energy sources Surendra Patait
 
turbine engine intake
 turbine engine intake turbine engine intake
turbine engine intakeradhebharvad
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]Amardeep Jadeja
 
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...Komandur Sunder Raj, P.E.
 

What's hot (20)

Centralized ac system
Centralized ac systemCentralized ac system
Centralized ac system
 
Chilled water systems
Chilled water systemsChilled water systems
Chilled water systems
 
Complete hvac ppt by kk 354647.pptx 1234
Complete hvac ppt by kk 354647.pptx 1234Complete hvac ppt by kk 354647.pptx 1234
Complete hvac ppt by kk 354647.pptx 1234
 
Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)
 
Training manual boiler general arrangement_mongduong ii
Training manual boiler general arrangement_mongduong iiTraining manual boiler general arrangement_mongduong ii
Training manual boiler general arrangement_mongduong ii
 
Air refrigeration system used in aircraft
Air refrigeration system used in aircraftAir refrigeration system used in aircraft
Air refrigeration system used in aircraft
 
Cooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesCooling Systems - Chiller Technologies
Cooling Systems - Chiller Technologies
 
Hvac made easy selection tips for chiller compressors
Hvac made easy   selection tips for chiller compressorsHvac made easy   selection tips for chiller compressors
Hvac made easy selection tips for chiller compressors
 
Industrial gas turbine (air cooling & sealing sys) 5th
Industrial gas turbine (air cooling & sealing sys)   5thIndustrial gas turbine (air cooling & sealing sys)   5th
Industrial gas turbine (air cooling & sealing sys) 5th
 
Air conditioning for large multistory buildings
Air conditioning for large multistory buildingsAir conditioning for large multistory buildings
Air conditioning for large multistory buildings
 
Centralised Air Conditioning
Centralised Air ConditioningCentralised Air Conditioning
Centralised Air Conditioning
 
Hvac presentation
Hvac presentationHvac presentation
Hvac presentation
 
BOILER INSTRUMENTATION
BOILER INSTRUMENTATIONBOILER INSTRUMENTATION
BOILER INSTRUMENTATION
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemes
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra Jha
 
Renewable energy sources
Renewable energy sources Renewable energy sources
Renewable energy sources
 
turbine engine intake
 turbine engine intake turbine engine intake
turbine engine intake
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
 

Viewers also liked

The underfloor air alternative
The underfloor air alternativeThe underfloor air alternative
The underfloor air alternativeJeff Blaevoet
 
046-057_Monterey Bay
046-057_Monterey Bay046-057_Monterey Bay
046-057_Monterey BayJeff Blaevoet
 
ASHRAE Providing Care for MOB JB
ASHRAE Providing Care for MOB JBASHRAE Providing Care for MOB JB
ASHRAE Providing Care for MOB JBJeff Blaevoet
 
GB Library Sets Example - Valley Hi Library
GB Library Sets Example - Valley Hi LibraryGB Library Sets Example - Valley Hi Library
GB Library Sets Example - Valley Hi LibraryJeff Blaevoet
 
8 Tips for Scaling Mobile Users in China by Edith Yeung
8 Tips for Scaling Mobile Users in China by Edith Yeung8 Tips for Scaling Mobile Users in China by Edith Yeung
8 Tips for Scaling Mobile Users in China by Edith YeungEdith Yeung
 

Viewers also liked (8)

The underfloor air alternative
The underfloor air alternativeThe underfloor air alternative
The underfloor air alternative
 
046-057_Monterey Bay
046-057_Monterey Bay046-057_Monterey Bay
046-057_Monterey Bay
 
JB EEACS Article
JB EEACS ArticleJB EEACS Article
JB EEACS Article
 
November2005
November2005November2005
November2005
 
ASHRAE Providing Care for MOB JB
ASHRAE Providing Care for MOB JBASHRAE Providing Care for MOB JB
ASHRAE Providing Care for MOB JB
 
GB Library Sets Example - Valley Hi Library
GB Library Sets Example - Valley Hi LibraryGB Library Sets Example - Valley Hi Library
GB Library Sets Example - Valley Hi Library
 
JB Kaiser article
JB Kaiser articleJB Kaiser article
JB Kaiser article
 
8 Tips for Scaling Mobile Users in China by Edith Yeung
8 Tips for Scaling Mobile Users in China by Edith Yeung8 Tips for Scaling Mobile Users in China by Edith Yeung
8 Tips for Scaling Mobile Users in China by Edith Yeung
 

Similar to ASHRAEJuly05-HamiltonLanding

Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towersAbdelrahim Ramadan
 
Air Conditioning case study
Air Conditioning case studyAir Conditioning case study
Air Conditioning case studySona Rawat
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar
 
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdf
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdflecture 3 - COMPRESSED AIR ENERGY STORAGE.pdf
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdfDinaSaad22
 
Guidelines hvac India
Guidelines hvac IndiaGuidelines hvac India
Guidelines hvac IndiaRohil Kumar
 
Final report on spent solution in hydro
Final report on spent solution in hydroFinal report on spent solution in hydro
Final report on spent solution in hydroprateekj765
 
Lecture 8 heating ventilation & air-conditioning
Lecture 8   heating ventilation & air-conditioningLecture 8   heating ventilation & air-conditioning
Lecture 8 heating ventilation & air-conditioningBekark
 
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdf
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdfPRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdf
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdfDanielNgwenya
 
LECTURE 6 ZONING IN HVAC.ppt
LECTURE  6 ZONING IN HVAC.pptLECTURE  6 ZONING IN HVAC.ppt
LECTURE 6 ZONING IN HVAC.pptBhaskarBhatia2
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between SystemsVictor Ashkenazy
 
Mechanical systems
Mechanical systemsMechanical systems
Mechanical systemsSunil Surya
 
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...riteshs229
 
Design options for hvac distribution systems
Design options for hvac distribution systemsDesign options for hvac distribution systems
Design options for hvac distribution systemsJASON KEMBOI
 
mini-cooling-tower
mini-cooling-towermini-cooling-tower
mini-cooling-towerKani Vel
 

Similar to ASHRAEJuly05-HamiltonLanding (20)

Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towers
 
Radiant cooling
Radiant coolingRadiant cooling
Radiant cooling
 
Cooling towers tech article v1r04
Cooling towers tech article v1r04Cooling towers tech article v1r04
Cooling towers tech article v1r04
 
final project.docx
final project.docxfinal project.docx
final project.docx
 
Air Conditioning case study
Air Conditioning case studyAir Conditioning case study
Air Conditioning case study
 
Radiant Ceiling Cooling
Radiant Ceiling CoolingRadiant Ceiling Cooling
Radiant Ceiling Cooling
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'
 
final project1.docx
final project1.docxfinal project1.docx
final project1.docx
 
Energy Efficiency in Offices
Energy Efficiency in OfficesEnergy Efficiency in Offices
Energy Efficiency in Offices
 
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdf
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdflecture 3 - COMPRESSED AIR ENERGY STORAGE.pdf
lecture 3 - COMPRESSED AIR ENERGY STORAGE.pdf
 
Guidelines hvac India
Guidelines hvac IndiaGuidelines hvac India
Guidelines hvac India
 
Final report on spent solution in hydro
Final report on spent solution in hydroFinal report on spent solution in hydro
Final report on spent solution in hydro
 
Lecture 8 heating ventilation & air-conditioning
Lecture 8   heating ventilation & air-conditioningLecture 8   heating ventilation & air-conditioning
Lecture 8 heating ventilation & air-conditioning
 
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdf
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdfPRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdf
PRESENTATION ON HVAC COOLING TOWERS AND CHILLERS.pdf
 
LECTURE 6 ZONING IN HVAC.ppt
LECTURE  6 ZONING IN HVAC.pptLECTURE  6 ZONING IN HVAC.ppt
LECTURE 6 ZONING IN HVAC.ppt
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between Systems
 
Mechanical systems
Mechanical systemsMechanical systems
Mechanical systems
 
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...
Air conditioner using peltier module final report [ rahul lakshkar, ashay, ri...
 
Design options for hvac distribution systems
Design options for hvac distribution systemsDesign options for hvac distribution systems
Design options for hvac distribution systems
 
mini-cooling-tower
mini-cooling-towermini-cooling-tower
mini-cooling-tower
 

ASHRAEJuly05-HamiltonLanding

  • 1. 54 ASHRAE Journal ashrae.org July 2005 By Jeff Blaevoet, P.E., Member ASHRAE When the HVAC design of the Hamil- ton Landing project was first conceived in 1998, it consisted of large package air-cooled rooftop units sitting next to the historic hangars with a conventional overhead VAV reheat system. The developer, however, liked the underfloor presentation made for the project and asked the architect to incor- porate the concept.Along with the usual benefits of underfloor air, this project (2787 m2) hangars was also planned to accommodate a second floor, supported from the ground floor slab, increasing the gross square footage of each hangar to about 58,000 ft2 (5388 m2). Footings for the second floor columns would have had features that made it even more suitable for a raised floor. The ground floor slabs of the 70 year- old Hamilton Air Force Base aircraft hangars had settled into the Bay mud, bowing down from the edges to the center of each hangar. The proposed solution to this was to pour a topping slab to level the ground floor, which was budgeted at $3/ft2 ($32.29/m2). Each of the seven 30,000 ft2 About the Author Jeff Blaevoet, P.E., is principal at Guttmann and Blaevoet Consulting Engineers in San Francisco. Blaevoet received a 2004 ASHRAE Technology Award for this project. Underfloor Air System for Retrofit Office Complex Exterior of Hamilton Landing project, which is a retrofit of a 70-year-old Air Force base hangar. © 2005, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae. org). Reprinted by permission from ASHRAE Journal, (Vol. 47, No. 7, July 2005). This article may not be copied nor distributed in either paper or digital form without ASHRAE’s permission.
  • 2. July 2005 ASHRAE Journal 55 had to be poured below the existing slab, requiring cutting of the slab at 30 ft (9 m) centers. The raised floor eliminated this cost. The floor covered a multitude of sins, which helped pay for itself. Given the character of the 45 ft (14 m) high vaulted ceilings of the aircraft hangars, suspended ceilings were not a desired interior treatment, which meant that any ductwork would be exposed and mounted high up at the structure.This would have posed a challenge in several respects. Heating would not be done very efficiently, and ventilation air would be difficult to throw into each cubicle.Any enclosed spaces, such as conference rooms, would require duct drops that would be tricky to support and aesthetically difficult to design. Given that zoning flexibility is needed, variable-air- volume (VAV) reheat is required, which is much more dif- ficult to design exposed with a clean appearance compared to constant volume (CV) single zone ducts. The cost of making ex- posed ductwork acceptable in appearance was avoided by the use of the raised floor. A similar problem would have been present for the power and communications cabling, with exposed race- ways and power poles. Right across a narrow street from the hangars is a development of new homes. Having large air-cooled units sitting next to the hangars would have been unsightly and noisy. Locating all the mechanical equipment, such as water-cooled direct expansion (DX) units, boiler and cooling tower inside the building, enabled the appearance of the historic buildings to be preserved, site landscaping to flourish and noise to be controlled. Locating HVAC units on the lightly loaded, barrel-vaulted roof was not an option from structural, aesthetic and maintenance perspectives. It is often difficult to accurately compare the cost of systems at a conceptual level, and this is especially true when the alter- nate being considered is relatively new. Even if historical data is available, unfamiliarity can bump up the estimator’s num- bers. In this case, the developer had a budget of about $85/ft2 ($915/m2), which included a seismic upgrade of the building, new curtain wall and windows, new roof and all new base- building systems with the shell and core. The HVAC budget was $8.50/ft2 ($91.50/m2) and the cost of the raised floor about $7/ft2 ($75.35/m2). This worked with the previous factors to stay on the budget planned earlier, but required some faith in the raised floor system pricing. Architectural Improvements Architecturally, the adaptive reuse was designed to disturb as little of the existing façade as possible to maintain the historical integrity of the hangars. Each hanger has a large, rectangular floor plate measuring 240 ft by 120 ft (73 m by 37 m). Attached to each corner of the building is a 12 ft by 12 ft (3.7 m by 3.7 m) tower that rises 38 ft (11.6 m) above grade. These concrete towers with 11 ft by 11 ft (3.4 m by 3.4 m) clear inside were used for housing four water-cooled DX VAV air-conditioning units on the first floor, and a boiler and cooling tower on the second floor. The building envelope is comprised concrete walls and a builtup roof with an overall insulation level of R-19.The glazing is a reflective single-pane glass with a U-value of 0.95 and a solar heat gain coefficient (SHGC) of 0.37. The facility has an overall glazing ratio of approximately 40%, with both the north and south elevations having over 58% glazing. Conference room in the interior of an office at Hamilton Landing.
  • 3. 56 ASHRAE Journal ashrae.org July 2005 HVAC System Overview Four 30-ton (106 kW), water-cooled air-conditioning units, each sized to provide 15,000 cfm (7079 L/s) of supply air, serve both floors of each quadrant of the former hangars.These units receive condenser water from a single 200-ton (703 kW) forced-draft cooling tower, which provides 80°F (27°C) water, circulated by a 7.5 hp (5.6 kW) pump. A boiler provides heat- ing hot water for the perimeter hydronic reheat zones. Hot water is distributed in a variable-flow pumping scheme with reverse return and a 2 hp (1.5 kW) hot water pump with vari- able speed drive. Access flooring using pedestals 18 in. (0.5 m) above the ground floor slab and 12 in. (0.3 m) above the second floor slab were used as supply air plenums. This space also is used for cable distribution (electric/phone/data) throughout the space. Individuallyadjustable,floormountedsupplyairdiffusersregu- late the airflow being supplied to the spaces.These diffusers pro- vide the occupants with control over the airflow to their space. The air-conditioning units were designed to maintain indoor temperatures between 70°F and 78°F (21°C and 25°C) and they supply air to the underfloor plenums at elevated temperatures of 63°F (17°C). At the perimeter of each floor, linear floor grilles with hot water linear convectors heat the supply air as required. The perimeter zones are provided with pressure dependent vol- ume dampers located in the plenum dividers. This eliminated the need for fan-powered boxes. The mechanical system was designed to fit within the exist- ing corner towers at each hangar. Each air-conditioning unit occupies the first floor of a single tower, and is a tight fit. The second floor of the northeast tower contains the boiler while the second level of the southeast tower houses the cooling tower, also a tight fit, and its associated pumps. The first level of each tower has louvers for outdoor-air in- take and serves as an intake air plenum for the air conditioner. Second floor louvers provide intake air for the forced-draft cooling tower, which discharges through the roof, and for toilet exhaust. The mechanical equipment is, therefore, entirely integrated into the original building design, being very unobtrusive. Return air is transferred through sidewall openings from the towers to the interior space on each level. Energy Efficiency The building design is 29.6% below the 1998 CaliforniaTitle- 24 Energy Standards, and the facility qualified for more than $55,000 in owner utility incentives.The project site weather cli- mate has summer conditions (ASHRAE 0.5%) of 87°F (31°C) DB and 63°F (17°C) WB and winter conditions (ASHRAE 0.2%) of 30°F (–1°C) DB. The typically mild conditions allow the facility to use many hours of “free cooling” through the use of an airside economizer.The low wet-bulb temperature ensures that water cooled equipment can be efficiently applied. The use of an underfloor system meant that many more econo- mizer hours were possible with a 63°F to 65°F (17°C to 18°C) supply air temperature compared to a typical system with 55°F (13°C) supply air temperature. Utilizing water-cooled equip- ment allowed the nominal cooling efficiency to be increased from about 1.1 kW/ton (0.3 kW/kW) for air-cooled equipment, to 0.7 kW/ton (0.2 kW/kW). The underfloor air distribution system results in low external static pressures (0.05 to 0.08 in. w.c. [12.5 to 20 Pa]) reducing the amount of fan power consumed. Variable frequency drives (VFDs) were installed on all the supply fans.TheVFDs are used to maintain a constant static pressure in the supply plenum as the tenants open and close individual diffusers, or VAV zones modulate. Motorized dampers were provided behind the existing building louvers, which are now used for relieving air from the space when the units are in economizer mode, thus avoiding the energy use of return or relief fans. The underfloor air system supplying air at a temperature closer to that of room tempera- ture results in less concern about operable windows conflicting with air conditioning. All fans and pumps were specified with premium efficiency motors. Conclusion Many different types of tenant improvements have been successfully accommodated at Hamilton Landing, including a YMCA, branch library, full service kitchen and deli, as well as a multitude of office uses. This project demonstrates that underfloor air can be a cost- effective solution for retrofits and speculative office buildings. The flexibility, comfort, indoor air quality, and energy efficiency of underfloor air are very affordable, if not lower cost than conventional overhead systems when executed well. Underfloor air has been growing in its acceptance in the United States and many new products, including fan-powered VAV reheat boxes, and floor diffusers are now available. De- sign guides, such as the Underfloor Air Distribution (UFAD) Design Guide published by ASHRAE, have been written, and more data is available now for cost comparisons, and technical considerations such as leakage, which will help designers and decision makers. Interior photograph of the Hamilton Landing project.