SlideShare a Scribd company logo
1 of 22
Download to read offline
Paralleling Existing Rights-of-Way for
Congested Areas
Jack Halpern
Power Sector Leader-Environmental Services
19th Annual Transmission Summit 2016
March 31, 2016
Preference Approach for Siting in Congested
Areas
1. Upgrade or double
circuit an existing line
2. Parallel an existing
line
3. Parallel roads,
railroads and pipelines
4. Green field solutions
Paralleling Situations
• Entirely on existing ROW
• Existing ROW /
overhanging adjacent
land
• Adjacent existing ROW /
overhang existing ROW
• Entirely adjacent land
abutting existing ROW
Parallel Existing Transmission- Issues
• Voltages
• Crossing Restrictions
• Substations
• Adjacent Lands
Development
• Accessibility Issues
• ROW Acquisition Issues
Parallel Transmission Lines- Negatives
• Induced voltage in a transmission line due to its
proximity to another transmission line can occur
• Reduced reliability - Tornados, aircraft, fires,
sabotage, wind gust, and wet snow
• Possible increase in impacts to agricultural
operations.
• New double-circuited structures may be taller
• Transmission lines in close proximity and parallel
to a distribution line can contribute to stray
voltage issues.
Parallel Transmission Lines- Positives
• Reduced right of way costs
• Reduced environmental impacts
• Simplified permitting
• Reduced opposition by adjacent landowners
• Existing access roads
Parallel Existing Roads- Issues
• Interstate highways, primary roads & local roads
• Overhead and underground
• Bridges, tunnels and cut/fills
• Adjacent Lands Development
o Bill boards
o Cell Towers
• Accessibility Issues
• ROW Acquisition Issues
• Construction issues
Some State Actions
• Minnesota. Stat. §216E.03, subdivision 7: The commission
must make specific findings that it has considered locating
a route for a high-voltage transmission line on an existing
high-voltage transmission route and the use of parallel
existing highway right-of-way and, to the extent those are
not used for the route, the commission must state the
reasons
• Maine’s Energy Infrastructure Interagency Review Panel
(IRP) is accepting letters of intent for the possible use of
state-owned I-95 and I-295 as corridors for electric
transmission, according to an Oct. 9 2012 statement from
Gov. Paul LePage
Fargo-St. Cloud 345 kV project
• Pennsylvania, Virginia, and Illinois:
o Longitudinal occupation of limited access
highways not permitted
o Perpendicular crossings and some very limited
conditions for longitudinal occupancy are
sanctioned under very specific criteria
Some State Actions
Utilities have right by law to occupy highway ROW. Public utilities
considered for permission to longitudinally occupy limited access
highway ROW when demonstrated extreme cases need exist, shown
best public interest and safety criteria can be met:
Accommodation not adversely affect the design, construction, operation,
maintenance, or stability of the limited access highways
A utility demonstrate alternate locations not available or cannot be
implemented at reasonable cost
Not interfere with or impair the present use or future expansion of limited
access highways
The public utility facility shall be placed underground;
The public utility facility shall present no hazard to life, health or property, if it
fails to function properly, is severed, or otherwise damaged; and
After the public utility facility is installed, it will be virtually maintenance free.
Some State Actions – New Jersey
Parallel Railroads - Issues
• Mainlines, secondary lines
• Unused or recently abandoned right-of-way
• Signaling and train control facilities
• Sidings, branches and yards
• Fiber optic lines
• Bridges, tunnels, cuts/fills
• Adjacent Lands Development
• Accessibility Issues
• ROW Acquisition Issues
• Construction issues
Parallel Railroads – Negatives
• Some RR ROWs have long distances between road
crossings and additional access roads would be needed
• Railroad corridors that pass through wetlands are
generally berms that too narrow to support transmission
structures, resulting in additional impacts to wetlands.
• Communication signals used by railroads can be affected
by electromagnetic fields
• Electrical induction in rails can interfere with proper
operation grade crossing control equipment/track-
connected signal equipment.
• Foundation vibrations
Parallel Pipelines - Issues
• Mainlines, secondary lines
• Valves, cleanouts and compressor stations
• Ownership issues
• Adjacent Lands Development
• Accessibility Issues
• Electric cathodic protection
• ROW Size/Acquisition Issues
• Construction issues
Parallel Pipelines - Negatives
• Pipeline ROWs often run cross-country with little
or no visual or agricultural effects
• Transmission lines constructed cross-country can
interfere with farm operations and produce a
negative visual impact
• For reasons of safety gas pipelines often require
transmission line ROW to parallel the pipeline
ROW with no or very minimal overlap-minimizes
any potential benefits of corridor sharing
• Separation Distance-Severity Ranking of HVAC
Interference
o Distance less than 100 feet- High
o 100 to 500 feet- Medium
o 500 to 1,000 feet- Low
o 1,000 to 2,500 feet- Very Low
• Collocation Length- Relative Severity
o Length greater than 5,000 feet- High
o 1,000 to 5,000 feet- Medium
o Less than 1,000 feet- Low
INGAA – Criteria for Pipelines Co-Existing
with Electric Power Lines *
*October 2015
CONCLUSIONS ON PARALLELING LINEAR
FEATURES
• THERE IS NO STANDARD CONCLUSION
• INDEPENDENT OF SITING MODEL USED
• EACH PARALLEL CASE MUST BE REVIEWED
SEPARATELY AS TO ITS OVER- ALL IMPACT ON:
o Human Environment
o Natural Environment
o Reliability of the Grid
o Engineering Variances
o Project Costs
Jack Halpern
Power Sector Leader-Environmental Services
Stantec Consulting Services
jack.halpern@stantec.com
561.212.2282
Any Questions?
Contact Information

More Related Content

What's hot

Georgia Traffic Mega Projects December 2019
Georgia Traffic Mega Projects December 2019Georgia Traffic Mega Projects December 2019
Georgia Traffic Mega Projects December 2019Steven Simms
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsFairfax County
 
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backupSelf-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backupmshiels
 
Melbourne metro tunnel project
Melbourne metro tunnel projectMelbourne metro tunnel project
Melbourne metro tunnel projectJumpingJaq
 
Agreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe DevelopmentAgreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe DevelopmentCity of College Station
 

What's hot (7)

Georgia Traffic Mega Projects December 2019
Georgia Traffic Mega Projects December 2019Georgia Traffic Mega Projects December 2019
Georgia Traffic Mega Projects December 2019
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to Tysons
 
2015 March 16 ASCE TTG - I-405 Improvement Project
2015 March 16   ASCE TTG - I-405 Improvement Project 2015 March 16   ASCE TTG - I-405 Improvement Project
2015 March 16 ASCE TTG - I-405 Improvement Project
 
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backupSelf-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
 
INTRODUCTION
INTRODUCTION INTRODUCTION
INTRODUCTION
 
Melbourne metro tunnel project
Melbourne metro tunnel projectMelbourne metro tunnel project
Melbourne metro tunnel project
 
Agreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe DevelopmentAgreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe Development
 

Viewers also liked

Unofficial ATS Transcript 2016
Unofficial ATS Transcript 2016Unofficial ATS Transcript 2016
Unofficial ATS Transcript 2016Megan Kidwell
 
wedding-brochure 2015
wedding-brochure 2015wedding-brochure 2015
wedding-brochure 2015Hayley Rawle
 
Act 2016-2017-assinado
Act 2016-2017-assinadoAct 2016-2017-assinado
Act 2016-2017-assinadoJose Carlos
 
Clausulas econômicas - Correios
Clausulas econômicas - CorreiosClausulas econômicas - Correios
Clausulas econômicas - CorreiosJose Carlos
 
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Tracking
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Trackingtop 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Tracking
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand TrackingDominic Artzrouni
 
Pirx - solutions for your business
Pirx - solutions for your businessPirx - solutions for your business
Pirx - solutions for your businessTomek Jelski
 
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011hugomedina36
 
2016-2017 Mentorship Program details
2016-2017 Mentorship Program details2016-2017 Mentorship Program details
2016-2017 Mentorship Program detailsStaci Trekles
 
Importancia del estudio del derecho adjetivo procesal laboral
Importancia del estudio del derecho adjetivo procesal laboralImportancia del estudio del derecho adjetivo procesal laboral
Importancia del estudio del derecho adjetivo procesal laboralNesmaryPalluotto
 
CV - Rufino B.Cada
CV - Rufino B.CadaCV - Rufino B.Cada
CV - Rufino B.Cadaruffy cada
 
Personas juridicas del dip
Personas juridicas del dipPersonas juridicas del dip
Personas juridicas del dipNesmaryPalluotto
 
Spring Japan Generic Brochure - July 2016
Spring Japan Generic Brochure - July 2016Spring Japan Generic Brochure - July 2016
Spring Japan Generic Brochure - July 2016Koshiro Iwaya
 
Jonny doin safe io t- lt_spice failsafe
Jonny doin safe io t- lt_spice failsafeJonny doin safe io t- lt_spice failsafe
Jonny doin safe io t- lt_spice failsafeJonny Doin
 

Viewers also liked (20)

Informe climático no. 300
Informe climático no. 300Informe climático no. 300
Informe climático no. 300
 
Unofficial ATS Transcript 2016
Unofficial ATS Transcript 2016Unofficial ATS Transcript 2016
Unofficial ATS Transcript 2016
 
MY CV
MY CVMY CV
MY CV
 
wedding-brochure 2015
wedding-brochure 2015wedding-brochure 2015
wedding-brochure 2015
 
Licda. Yanny Bermudez
Licda. Yanny BermudezLicda. Yanny Bermudez
Licda. Yanny Bermudez
 
Act 2016-2017-assinado
Act 2016-2017-assinadoAct 2016-2017-assinado
Act 2016-2017-assinado
 
Clausulas econômicas - Correios
Clausulas econômicas - CorreiosClausulas econômicas - Correios
Clausulas econômicas - Correios
 
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Tracking
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Trackingtop 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Tracking
top 10 brands in HOUSE OF CARDS season 4 - by Concave Brand Tracking
 
Pirx - solutions for your business
Pirx - solutions for your businessPirx - solutions for your business
Pirx - solutions for your business
 
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011
PROGRAMA EDUCACIÓN FÍSICA PRIMARIA 2011
 
2016-2017 Mentorship Program details
2016-2017 Mentorship Program details2016-2017 Mentorship Program details
2016-2017 Mentorship Program details
 
Importancia del estudio del derecho adjetivo procesal laboral
Importancia del estudio del derecho adjetivo procesal laboralImportancia del estudio del derecho adjetivo procesal laboral
Importancia del estudio del derecho adjetivo procesal laboral
 
Derecho humano
Derecho humanoDerecho humano
Derecho humano
 
Passive Voice
Passive VoicePassive Voice
Passive Voice
 
CV - Rufino B.Cada
CV - Rufino B.CadaCV - Rufino B.Cada
CV - Rufino B.Cada
 
Where does it hurt?
Where does it hurt?Where does it hurt?
Where does it hurt?
 
Personas juridicas del dip
Personas juridicas del dipPersonas juridicas del dip
Personas juridicas del dip
 
Spring Japan Generic Brochure - July 2016
Spring Japan Generic Brochure - July 2016Spring Japan Generic Brochure - July 2016
Spring Japan Generic Brochure - July 2016
 
Irfan_Ahmed_CV
Irfan_Ahmed_CVIrfan_Ahmed_CV
Irfan_Ahmed_CV
 
Jonny doin safe io t- lt_spice failsafe
Jonny doin safe io t- lt_spice failsafeJonny doin safe io t- lt_spice failsafe
Jonny doin safe io t- lt_spice failsafe
 

Similar to Transmission Summit 2016- Halpern

3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cablesssuser30d0c22
 
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...Fairfax County
 
Application of power electronics in hvdc copy
Application of power electronics in hvdc   copyApplication of power electronics in hvdc   copy
Application of power electronics in hvdc copySARAVANAN A
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)Abhishek Choksi
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioningPreet_patel
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesahmed usama
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Avirup Ghosh
 
underground cable in transmission grid
underground cable in transmission gridunderground cable in transmission grid
underground cable in transmission gridEngr. naeem
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesahmed usama
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And CommisioningSuraj Naik
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165michaeljmack
 
Transmission and distribution system of electricity
Transmission and distribution system of electricity Transmission and distribution system of electricity
Transmission and distribution system of electricity anjali s
 
LUNCH NISAC Presentation
LUNCH NISAC PresentationLUNCH NISAC Presentation
LUNCH NISAC PresentationMark Ehlen
 

Similar to Transmission Summit 2016- Halpern (20)

3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables
 
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
 
Pdu 2021 s2
Pdu 2021 s2Pdu 2021 s2
Pdu 2021 s2
 
Application of power electronics in hvdc copy
Application of power electronics in hvdc   copyApplication of power electronics in hvdc   copy
Application of power electronics in hvdc copy
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
underground cable in transmission grid
underground cable in transmission gridunderground cable in transmission grid
underground cable in transmission grid
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
 
PLS 2019: EV infrastructure requirements
PLS 2019: EV infrastructure requirementsPLS 2019: EV infrastructure requirements
PLS 2019: EV infrastructure requirements
 
AC Interference Analysis and Mitigation
AC Interference Analysis and MitigationAC Interference Analysis and Mitigation
AC Interference Analysis and Mitigation
 
Transmission and distribution system of electricity
Transmission and distribution system of electricity Transmission and distribution system of electricity
Transmission and distribution system of electricity
 
UNIT 1 CLASS1.pdf
UNIT 1 CLASS1.pdfUNIT 1 CLASS1.pdf
UNIT 1 CLASS1.pdf
 
LUNCH NISAC Presentation
LUNCH NISAC PresentationLUNCH NISAC Presentation
LUNCH NISAC Presentation
 
transmission line installation
transmission line installationtransmission line installation
transmission line installation
 
Electric09
Electric09Electric09
Electric09
 

Transmission Summit 2016- Halpern

  • 1. Paralleling Existing Rights-of-Way for Congested Areas Jack Halpern Power Sector Leader-Environmental Services 19th Annual Transmission Summit 2016 March 31, 2016
  • 2. Preference Approach for Siting in Congested Areas 1. Upgrade or double circuit an existing line 2. Parallel an existing line 3. Parallel roads, railroads and pipelines 4. Green field solutions
  • 3. Paralleling Situations • Entirely on existing ROW • Existing ROW / overhanging adjacent land • Adjacent existing ROW / overhang existing ROW • Entirely adjacent land abutting existing ROW
  • 4. Parallel Existing Transmission- Issues • Voltages • Crossing Restrictions • Substations • Adjacent Lands Development • Accessibility Issues • ROW Acquisition Issues
  • 5. Parallel Transmission Lines- Negatives • Induced voltage in a transmission line due to its proximity to another transmission line can occur • Reduced reliability - Tornados, aircraft, fires, sabotage, wind gust, and wet snow • Possible increase in impacts to agricultural operations. • New double-circuited structures may be taller • Transmission lines in close proximity and parallel to a distribution line can contribute to stray voltage issues.
  • 6.
  • 7. Parallel Transmission Lines- Positives • Reduced right of way costs • Reduced environmental impacts • Simplified permitting • Reduced opposition by adjacent landowners • Existing access roads
  • 8. Parallel Existing Roads- Issues • Interstate highways, primary roads & local roads • Overhead and underground • Bridges, tunnels and cut/fills • Adjacent Lands Development o Bill boards o Cell Towers • Accessibility Issues • ROW Acquisition Issues • Construction issues
  • 9. Some State Actions • Minnesota. Stat. §216E.03, subdivision 7: The commission must make specific findings that it has considered locating a route for a high-voltage transmission line on an existing high-voltage transmission route and the use of parallel existing highway right-of-way and, to the extent those are not used for the route, the commission must state the reasons • Maine’s Energy Infrastructure Interagency Review Panel (IRP) is accepting letters of intent for the possible use of state-owned I-95 and I-295 as corridors for electric transmission, according to an Oct. 9 2012 statement from Gov. Paul LePage
  • 10. Fargo-St. Cloud 345 kV project
  • 11. • Pennsylvania, Virginia, and Illinois: o Longitudinal occupation of limited access highways not permitted o Perpendicular crossings and some very limited conditions for longitudinal occupancy are sanctioned under very specific criteria Some State Actions
  • 12. Utilities have right by law to occupy highway ROW. Public utilities considered for permission to longitudinally occupy limited access highway ROW when demonstrated extreme cases need exist, shown best public interest and safety criteria can be met: Accommodation not adversely affect the design, construction, operation, maintenance, or stability of the limited access highways A utility demonstrate alternate locations not available or cannot be implemented at reasonable cost Not interfere with or impair the present use or future expansion of limited access highways The public utility facility shall be placed underground; The public utility facility shall present no hazard to life, health or property, if it fails to function properly, is severed, or otherwise damaged; and After the public utility facility is installed, it will be virtually maintenance free. Some State Actions – New Jersey
  • 13. Parallel Railroads - Issues • Mainlines, secondary lines • Unused or recently abandoned right-of-way • Signaling and train control facilities • Sidings, branches and yards • Fiber optic lines • Bridges, tunnels, cuts/fills • Adjacent Lands Development • Accessibility Issues • ROW Acquisition Issues • Construction issues
  • 14.
  • 15. Parallel Railroads – Negatives • Some RR ROWs have long distances between road crossings and additional access roads would be needed • Railroad corridors that pass through wetlands are generally berms that too narrow to support transmission structures, resulting in additional impacts to wetlands. • Communication signals used by railroads can be affected by electromagnetic fields • Electrical induction in rails can interfere with proper operation grade crossing control equipment/track- connected signal equipment. • Foundation vibrations
  • 16.
  • 17. Parallel Pipelines - Issues • Mainlines, secondary lines • Valves, cleanouts and compressor stations • Ownership issues • Adjacent Lands Development • Accessibility Issues • Electric cathodic protection • ROW Size/Acquisition Issues • Construction issues
  • 18.
  • 19. Parallel Pipelines - Negatives • Pipeline ROWs often run cross-country with little or no visual or agricultural effects • Transmission lines constructed cross-country can interfere with farm operations and produce a negative visual impact • For reasons of safety gas pipelines often require transmission line ROW to parallel the pipeline ROW with no or very minimal overlap-minimizes any potential benefits of corridor sharing
  • 20. • Separation Distance-Severity Ranking of HVAC Interference o Distance less than 100 feet- High o 100 to 500 feet- Medium o 500 to 1,000 feet- Low o 1,000 to 2,500 feet- Very Low • Collocation Length- Relative Severity o Length greater than 5,000 feet- High o 1,000 to 5,000 feet- Medium o Less than 1,000 feet- Low INGAA – Criteria for Pipelines Co-Existing with Electric Power Lines * *October 2015
  • 21. CONCLUSIONS ON PARALLELING LINEAR FEATURES • THERE IS NO STANDARD CONCLUSION • INDEPENDENT OF SITING MODEL USED • EACH PARALLEL CASE MUST BE REVIEWED SEPARATELY AS TO ITS OVER- ALL IMPACT ON: o Human Environment o Natural Environment o Reliability of the Grid o Engineering Variances o Project Costs
  • 22. Jack Halpern Power Sector Leader-Environmental Services Stantec Consulting Services jack.halpern@stantec.com 561.212.2282 Any Questions? Contact Information