2. 2
04.09.2022
Holcim Group Support Course for Cement Applications
Objectives
Understand the importance of cost, time and quality
issues for the construction process
Identify the key success factors for contractors as an
end user of cement and concrete
Understand the influence parameters to optimize
construction processes by cement and concrete
performance
3. 3
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
4. 4
04.09.2022
Holcim Group Support Course for Cement Applications
Source: OECD; HVC Fact Bases; HGRS-CSS
100
1'000
10'000
100'000
0% 20% 40% 60% 80% 100% Current Holcim
bulk ratio [%]
Degree of cement market industrialization (efficiency potential)
Level of wealth
(potential for
growth)
GDP / capita
2004 [US$]
CH
FBNL
Australia
CAN
GER
Italy
Spain Singapore
Venezuela
Bulgaria
Slovakia
Croatia
Hungary
Thailand
Chile
Romania
Bangladesh
Morocco
Malaysia
Vietnam
Indonesia
Mexico
Panama
Libanon
Brazil
Argentina
Colombia
Ecuador
Costa Rica
Philippines
Sri Lanka
Nicaragua
Austria
Czech
Serbia
New Zeal.
South Africa
USA
India
La Reunion
Emerging markets
Developing markets
Transition markets
Mature markets
Market typology: Four market types identified
Focus on working processes and future trends in mature markets
5. 5
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
6. 6
04.09.2022
Holcim Group Support Course for Cement Applications
E.g. building construction: Project cost break down
Estate Con-
struction
Fees Total
20
65
15
12
53
100
Con-
creting
Cement
0.5
Investment 100 Mio
Area 36’000 m2
Concrete 13’000 m3
Cement 4’000 t
Com. area 29’000 m2
Rent 300 CHF/m2 y
Impact of load bearing system cost on total building cost is limited
[Mio. CHF]
Cost of load
bearing
system only
~10 –15%
of total
investment
7. 7
04.09.2022
Holcim Group Support Course for Cement Applications
1. year 2. year 3. year
Planning
Excavation
Construction
Facade
Installation
Interior system
Finish
10 months
Time for load bearing system
On the critical path
Rarely parallel processes possible
Significant potential to minimize total construction
time by accelerating building of load bearing system
E.g. building construction: Project schedule
8. 8
04.09.2022
Holcim Group Support Course for Cement Applications
E.g. building construction:
Value accelerated construction process for owner
Reduce cost:
2 months shorter
building credit
Increase revenue:
2 months earlier /
increase rent
0.6
1.4
2.0
[Mio CHF]
Total value
for owner
2% of total investment
16% of load bearing
system cost
400% of cement cost
Factors for reducing cycle time
Formwork, reinforcement process
Strength development concrete
Demolding formwork
Acceleration construction processes
may lead to significant customer value
Time as key factor for cost savings
8 months
9. 9
04.09.2022
Holcim Group Support Course for Cement Applications
E.g. building construction:
Project organization and specification
Specifications in contracts:
Performance oriented to take advantage of contractor’s know-how,
free choice of working process
Opportunity for RMX and contractors for differentiation
Cement producers needs know-how to support
contractors in different applications and processes
Developer
General
Contractor
Investor
Specifiers
Architect
Civil Eng.
…
Excavation
Contractor
Site manager
…
10. 10
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Foundation applications
Vertical elements: Walls and columns
Horizontal elements: Slabs and beams
Summary
Advanced construction methods
11. 11
04.09.2022
Holcim Group Support Course for Cement Applications
Foundation application types
Mass foundation
Mass concrete, low heat required
High density of reinforcement
Big pours, up to 800 m3 per day by
different RMC suppliers
Sometimes durability required
(sulfates – aggressive soils)
Complicated and high density of
reinforcement concrete workability
Homogeneity (concrete -
reinforcement) to ensure force
transition
Surface quality less important
Final strength important
Ground beam
High quality requirements, but limited time saving potential
12. 12
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Foundation applications
Vertical elements: Walls and columns
Horizontal elements: Slabs and beams
Summary
Advanced construction methods
13. 13
04.09.2022
Holcim Group Support Course for Cement Applications
Walls and columns:
Work flow concreting for load bearing elements
Reinforcement
Placing
Setting
Curing
Final
strength
Early
strength
Formwork
Critical job cycle:
Reuse of formwork for the
following element
Concrete strength:
~4 MPa required for demolding
the next day (~16h)
Cycle time for vertical elements can be significantly influenced
by concrete performance, therefore early strength is decisive
14. 14
04.09.2022
Holcim Group Support Course for Cement Applications
Walls and columns:
Formwork for conventional and fast track projects
Conventional Fast track
Manually lifted panels, slow
Old, often reused wooden
panels
Leaking, impacts surface
quality
Economical unit cost
Wooden or aluminum panels
lifted by crane, fast
Limited life cycle per panel
Good surface quality to save
work for rework
High unit costs
15. 15
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Foundation applications
Vertical elements: Walls and columns
Horizontal elements: Slabs and beams
Summary
Advanced construction methods
16. 16
04.09.2022
Holcim Group Support Course for Cement Applications
Slab and beams:
Work flow concreting for load bearing elements
Reinforcement
Placing
Setting
Curing
Demolding:
3d up to 7d
Final
strength
Early / mid
strength
Formwork
Job cycle:
Access on horizontal element for
ongoing working process
Concrete setting time and strength development has significant
influence on job cycle time and working processes
4 - 6h
Construction material:
Optimization of demolding material
17. 17
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Foundation applications
Vertical elements: Walls and columns
Horizontal elements: Slabs and beams
Summary
Advanced construction methods
18. 18
04.09.2022
Holcim Group Support Course for Cement Applications
Conventional construction methods
Foundation Slab / beam
Wall / column
Strength
development
Early strength
Final strength
Key workflow
requirement
Final strength
Durability
No cracking
Final strength Final strength
Limited deflection
No cracking
Owners long term benefit oppositional to short
cycle time interest of concrete end users
Working
practice
Quality aspects
Benefit
owner
Dem. @ 16h Dem. @ 3 - 7d
19. 19
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
Vertical elements: Jump and slip forms
Pre-cast products for vertical and horizontal elements
SCC applications
Summary
20. 20
04.09.2022
Holcim Group Support Course for Cement Applications
Jump form application process
Working process
Plumb inside formwork
Place the reinforcements
Close outside formwork
Concreting
a) Lifting by crane
Lift external climbing unit
Only 5 to 10 min crane time per lift
Lift the inside shaft formwork
b) Self climbing formwork
Hydraulic compactors lift the formwork
Suitable for lift shafts
No changes of the shape nor wall inclinations
Size limitations
21. 21
04.09.2022
Holcim Group Support Course for Cement Applications
Jump form application benefits
Acceleration of process
Large shiftable units
Quick suspension system
Cost reduction
Large surface area on the
platforms
Work to be carried out safely
and easily behind and in front of
the formwork
Reuse of formwork
No vertical scaffolding
Job cycle time strongly limited
by early strength performance
22. 22
04.09.2022
Holcim Group Support Course for Cement Applications
Slip form application process
Hydraulic jacks elevate the formwork
of the complete structure in a
continuous vertical sliding motion as
concrete placing progresses
Suitable for monolithic structures as
silos, tanks, chimneys, towers, water
towers, lift-shaft cores, tanks
No changes of the shape
Platform size limitations
23. 23
04.09.2022
Holcim Group Support Course for Cement Applications
Slip form application benefits
Acceleration of process
Accelerated, permanent
construction time, no “job
cycles”
Cost reduction
Minimal form and space
requirements
Low personnel expenses
Quality
Monolithically cast
structure free from ties and
cold joints
Time to completion strongly
limited by early strength
performance
24. 24
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
Vertical elements: Jump and slip forms
Pre-cast products for vertical and horizontal elements
SCC applications
Summary
25. 25
04.09.2022
Holcim Group Support Course for Cement Applications
Advantages of pre-cast elements
Smooth and even surface
Early strength concrete on job site not critical
Easy to handle by crane (weight)
~50% faster than conventional wall
construction
Higher unit costs than conventional walls
‘Sandwich’ walls
Pre-cast slabs
Lower cycle time and high surface quality are main advantages
Smooth and even surface
Concrete strength on job site not critical
Easy to handle by crane (weight)
Faster than conventional slab construction
No formworks required
Higher unit costs than conventional slabs
26. 26
04.09.2022
Holcim Group Support Course for Cement Applications
ICF applications
Insulated Concrete Forms (ICF) are
molds that have built-in insulation
The hollow blocks are stacked and
filled with reinforcing bar and concrete
The wall is structurally sound,
insulated, has a vapor barrier and is
ready to accept final exterior and
interior finishes
Suitable for exterior wall systems
(residential and non-residential)
Saves wall formwork and is easy
to handle (home builders)
Need for high slump concrete
>160mm
27. 27
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
Vertical elements: Jump and slip forms
Pre-cast products for vertical and horizontal elements
SCC applications
Summary
28. 28
04.09.2022
Holcim Group Support Course for Cement Applications
CPM: Advantages of SCC applications
Labor intensive placing
To reduce failure rate, often significant
cost for rework
High density of reinforcement and inlays
Fast and simple placement of concrete
Excellent surface quality
Increased material cost
SCC
Standard concrete
Excellent off-form finish is main advantage of SCC for CPM
29. 29
04.09.2022
Holcim Group Support Course for Cement Applications
Jobsite applications
Advantages of SCC applications
SCC placing
Placing wall concrete by only one
worker (reduction labor force)
High surface quality and less
concrete finish and rework
Possibility to pour up to
15 meters in one go
30. 30
04.09.2022
Holcim Group Support Course for Cement Applications
Content
Market typology
Project key success factors
Conventional construction methods
Advanced construction methods
Vertical elements: Jump and slip forms
Pre-cast products for vertical and horizontal elements
SCC applications
Summary
31. 31
04.09.2022
Holcim Group Support Course for Cement Applications
Benefits of advanced construction methods
SCC Pre-cast
Jump / slip form
CPM: Early strength
Concrete: High
slump and flowability
Concrete slump and
flowability
High early strength
Require-
ment
Trend to shorter process cycles leads usually to higher installation
and material cost and allows in return to reduce labor cost
Benefits Faster construction
process
Surface quality
Labor cost
saving
Surface quality
Faster construction
progress