SlideShare a Scribd company logo
1 of 3
Download to read offline
Gustavo Brandt – Project Management Profile 
 
1 | P a g e  
 
The table below provides a summary of Gustavo Brandt’s Project Management career while working at Honeywell Process Solutions (1996 – 2004) and Suncor Energy Inc. (2004 – 2016).  
 
Role  Projects 
 
Projects 
Involvement 
Initiating 
 
Planning 
 
Executing 
 
Monitoring & Controlling  Closing 
Senior 
Automation 
Engineer 
(2015 – 2016) 
 Opex Projects (system 
enhancements/upgrades/replacem
ent) ‐ management 
 Contracts and Business Cases 
Development/Review 
100%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
Lead Process 
Control Engineer 
(2010 – 2015) 
 Alarm Management System 
 Failure Analysis Reduction 
100%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
E,I&C Reliability 
Engineer Lead 
(2010) 
 Opex Projects (system 
enhancements/upgrades/replacem
ent) ‐ management 
 Capex Projects (Tailings Recovery 
Operations) – management & 
execution 
 Contracts and Business Cases 
Development/Review 
50%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
I&C Reliability 
Engineer 
(2009) 
 Opex Projects (system 
enhancements/upgrades/replacem
ent) 
50%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
Gustavo Brandt – Project Management Profile 
 
2 | P a g e  
 
 Contracts and Business Cases 
Development/Review 
resources. Development of project 
charter and stakeholder register. 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
management of change 
completion, lessons learned 
advisor) 
Staff Engineer 
(2007 – 2008) 
 
 Opex Projects (system 
enhancements/upgrades/replacem
ent) 
 Contracts and Business Cases 
Development/Review 
50%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
Senior Control 
Systems Specialist 
(2004 – 2007) 
 
 
 Opex Projects (system 
enhancements/upgrades/replacem
ent) 
 Contracts and Business Cases 
Development/Review 
25%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Participated in processes to 
stablish the total scope, defined 
and refined the objectives, 
provided input for the course of 
action required to attain the 
project objectives. Supported the 
development project management 
plan and the project documents 
used for the project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
Jr Lead Project 
Engineer 
(2004) 
 
 
 Termozulia  100%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
Performed processes to stablish 
the total scope, defined and 
refined the objectives, developed 
the course of action required to 
attain the project objectives. 
Supported the development of the 
project management plan and the 
project documents used for the 
project. 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements). 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor) 
Gustavo Brandt – Project Management Profile 
 
3 | P a g e  
 
Senior Engineer 
(2000 – 2004) 
 
 Corocoro 
 Petrozuata 
 PDAY/PTAY‐1/PTAY‐2 
 Solids Handling Expansion 
 PPGPL 
 Ameriven Downstream 
 System Upgrade of TDC‐3000 at 
Palito Refinery 
100%  Performed processes to define a 
new project or a new phase by the 
authorization to start it. Defined 
the initial scope and initial 
resources. Development of project 
charter and stakeholder register. 
 
Performed processes to stablish 
the total scope, defined and 
refined the objectives, developed 
the course of action required to 
attain the project objectives. 
Supported the development of the 
project management plan and the 
project documents used for the 
project. 
 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. 
Coordinating people and 
resources, managing stakeholder 
expectations, integrating and 
performing activities of the project 
as per the project management 
plan. Planning updates and 
rebaselining associated to activity 
durations, changes in resources 
productivity and availability, and 
risks. 
Involved in tracking, reviewing, 
and coordinating the progress and 
performance of the project(s). 
Identified areas where changes to 
the plan were required, initiating 
the corresponding changes 
(internal and external 
requirements).  
 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor). 
 
Junior Engineer 
(1996 – 1999) 
 
 Bold 3 
 Y2K 
 AMAY 
 TAEJ 
 Effluentes 
 Limoncocha 
 COPLA 
 Fertilizantes 
 Guaicaipuro 
 GLP 
 Bajo Grande 
100%   
 
Performed processes to complete 
the work defined in the project 
management plan to satisfy the 
project specifications. Involved in 
discussions for planning updates 
and rebaselining. Involved in 
discussions toward changes of 
expected activity durations and 
productivity. 
 
Performed processes to conclude 
all activities to formally complete 
the project (final documentation, 
as‐built documentation, 
management of change 
completion, lessons learned 
advisor). 
 
 
In addition to the table above, the following major documentation was created, reviewed, commented, and/or approved while the Project Management task: 
1. Project Charters 
2. Project Management Plans 
a. Work Breakdown Structure (WBS) 
b. Schedule (Microsoft Project / Oracle Primavera) 
c. Budget 
3. Risk Register 
4. Change Log 
 
Gustavo Brandt – PMP, PEng, MSc 
https://ca.linkedin.com/in/gusbrandt 
 
 
 
 

More Related Content

What's hot

Project control wps office
Project control wps officeProject control wps office
Project control wps officekaransingh1064
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Approaches to project control
Approaches to project controlApproaches to project control
Approaches to project controlNITISH SADOTRA
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And ControllingTom Milner
 
Project controls function
Project controls functionProject controls function
Project controls functionHatem Hegazi
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planningjosephb987
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project HR plan presentation
Project HR plan presentationProject HR plan presentation
Project HR plan presentationmominandhammad
 
Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Dr. Joy Kenneth Sala Biasong
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control Systemjunejalok
 

What's hot (20)

Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project control wps office
Project control wps officeProject control wps office
Project control wps office
 
Project control
Project controlProject control
Project control
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Construction management
Construction managementConstruction management
Construction management
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Approaches to project control
Approaches to project controlApproaches to project control
Approaches to project control
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Project controls function
Project controls functionProject controls function
Project controls function
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
 
Project management tools
Project management toolsProject management tools
Project management tools
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project HR plan presentation
Project HR plan presentationProject HR plan presentation
Project HR plan presentation
 
095 Project Cycle Management
095 Project Cycle Management095 Project Cycle Management
095 Project Cycle Management
 
Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control System
 
Dynamic Schedule Management
Dynamic Schedule ManagementDynamic Schedule Management
Dynamic Schedule Management
 
Project management
Project managementProject management
Project management
 
STOworx Petronas Presentation
STOworx Petronas PresentationSTOworx Petronas Presentation
STOworx Petronas Presentation
 

Similar to Gustavo Brandt - Project Management Profile

Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)Innovate Vancouver
 
Jose de Jesus Resume July 2016 Rev 01
Jose de Jesus Resume July 2016 Rev 01Jose de Jesus Resume July 2016 Rev 01
Jose de Jesus Resume July 2016 Rev 01Jose Antonio de Jesus
 
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docxRunning head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docxcowinhelen
 
A Software For Project Management Process
A Software For Project Management ProcessA Software For Project Management Process
A Software For Project Management ProcessRenee Lewis
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Loren Schwappach
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
AssignmentsAssignment 1Example for the charts and or graphs.pp.docx
AssignmentsAssignment 1Example for the charts and or graphs.pp.docxAssignmentsAssignment 1Example for the charts and or graphs.pp.docx
AssignmentsAssignment 1Example for the charts and or graphs.pp.docxssuser562afc1
 

Similar to Gustavo Brandt - Project Management Profile (20)

Project Management
Project ManagementProject Management
Project Management
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
RINAL_PATEL
RINAL_PATELRINAL_PATEL
RINAL_PATEL
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
 
EDG Resume 06.2016
EDG Resume 06.2016EDG Resume 06.2016
EDG Resume 06.2016
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)Business scorecard   multiple workstreams - Travis Barker, MPA GCPM (2018)
Business scorecard multiple workstreams - Travis Barker, MPA GCPM (2018)
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Jose de Jesus Resume July 2016 Rev 01
Jose de Jesus Resume July 2016 Rev 01Jose de Jesus Resume July 2016 Rev 01
Jose de Jesus Resume July 2016 Rev 01
 
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docxRunning head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
 
A Software For Project Management Process
A Software For Project Management ProcessA Software For Project Management Process
A Software For Project Management Process
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
AssignmentsAssignment 1Example for the charts and or graphs.pp.docx
AssignmentsAssignment 1Example for the charts and or graphs.pp.docxAssignmentsAssignment 1Example for the charts and or graphs.pp.docx
AssignmentsAssignment 1Example for the charts and or graphs.pp.docx
 

Gustavo Brandt - Project Management Profile

  • 1. Gustavo Brandt – Project Management Profile    1 | P a g e     The table below provides a summary of Gustavo Brandt’s Project Management career while working at Honeywell Process Solutions (1996 – 2004) and Suncor Energy Inc. (2004 – 2016).     Role  Projects    Projects  Involvement  Initiating    Planning    Executing    Monitoring & Controlling  Closing  Senior  Automation  Engineer  (2015 – 2016)   Opex Projects (system  enhancements/upgrades/replacem ent) ‐ management   Contracts and Business Cases  Development/Review  100%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor)  Lead Process  Control Engineer  (2010 – 2015)   Alarm Management System   Failure Analysis Reduction  100%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor)  E,I&C Reliability  Engineer Lead  (2010)   Opex Projects (system  enhancements/upgrades/replacem ent) ‐ management   Capex Projects (Tailings Recovery  Operations) – management &  execution   Contracts and Business Cases  Development/Review  50%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor)  I&C Reliability  Engineer  (2009)   Opex Projects (system  enhancements/upgrades/replacem ent)  50%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation, 
  • 2. Gustavo Brandt – Project Management Profile    2 | P a g e      Contracts and Business Cases  Development/Review  resources. Development of project  charter and stakeholder register.  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  management of change  completion, lessons learned  advisor)  Staff Engineer  (2007 – 2008)     Opex Projects (system  enhancements/upgrades/replacem ent)   Contracts and Business Cases  Development/Review  50%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor)  Senior Control  Systems Specialist  (2004 – 2007)       Opex Projects (system  enhancements/upgrades/replacem ent)   Contracts and Business Cases  Development/Review  25%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Participated in processes to  stablish the total scope, defined  and refined the objectives,  provided input for the course of  action required to attain the  project objectives. Supported the  development project management  plan and the project documents  used for the project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor)  Jr Lead Project  Engineer  (2004)       Termozulia  100%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.  Performed processes to stablish  the total scope, defined and  refined the objectives, developed  the course of action required to  attain the project objectives.  Supported the development of the  project management plan and the  project documents used for the  project.  Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).  Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor) 
  • 3. Gustavo Brandt – Project Management Profile    3 | P a g e     Senior Engineer  (2000 – 2004)     Corocoro   Petrozuata   PDAY/PTAY‐1/PTAY‐2   Solids Handling Expansion   PPGPL   Ameriven Downstream   System Upgrade of TDC‐3000 at  Palito Refinery  100%  Performed processes to define a  new project or a new phase by the  authorization to start it. Defined  the initial scope and initial  resources. Development of project  charter and stakeholder register.    Performed processes to stablish  the total scope, defined and  refined the objectives, developed  the course of action required to  attain the project objectives.  Supported the development of the  project management plan and the  project documents used for the  project.    Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications.  Coordinating people and  resources, managing stakeholder  expectations, integrating and  performing activities of the project  as per the project management  plan. Planning updates and  rebaselining associated to activity  durations, changes in resources  productivity and availability, and  risks.  Involved in tracking, reviewing,  and coordinating the progress and  performance of the project(s).  Identified areas where changes to  the plan were required, initiating  the corresponding changes  (internal and external  requirements).     Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor).    Junior Engineer  (1996 – 1999)     Bold 3   Y2K   AMAY   TAEJ   Effluentes   Limoncocha   COPLA   Fertilizantes   Guaicaipuro   GLP   Bajo Grande  100%      Performed processes to complete  the work defined in the project  management plan to satisfy the  project specifications. Involved in  discussions for planning updates  and rebaselining. Involved in  discussions toward changes of  expected activity durations and  productivity.    Performed processes to conclude  all activities to formally complete  the project (final documentation,  as‐built documentation,  management of change  completion, lessons learned  advisor).      In addition to the table above, the following major documentation was created, reviewed, commented, and/or approved while the Project Management task:  1. Project Charters  2. Project Management Plans  a. Work Breakdown Structure (WBS)  b. Schedule (Microsoft Project / Oracle Primavera)  c. Budget  3. Risk Register  4. Change Log    Gustavo Brandt – PMP, PEng, MSc  https://ca.linkedin.com/in/gusbrandt