SlideShare a Scribd company logo
1 of 1
Download to read offline
Iterative back to/from:
Define Scope
Develop Schedule
Estimate Costs
Jump in
from:
Create WBS
Also jump to: Plan
Procurement Management
Iterative back to:
Estimate Costs
Plan Risk Management
Control Risks
Plan Procurement Management
Could be performed multiple times throughout project
Develop Project
Management Plan
(PM Plan)
Direct and
Manage
Project Work
Perform Integrated
Change Control
Monitor and
Control Project
Work
Scope Change
Request
Control Quality
(Correctness)
Validate Scope
(Completeness)
Close
Phase
Close
Project
Close
Procurements
LEGEND
Initiating Planning Executing Monitoring/Controlling Closing
Integration
Scope
Plan Scope
Management
Collect
Requirements
Time
Cost
Quality
Human
Resource
Communications
Risk
Procurement
StakeholderIdentify
Stakeholders
Define Scope Create WBS
Plan Schedule
Management
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
Control
Schedule
Estimate Costs
Determine
Budget
Control Costs
Plan Quality
Management
Perform Quality
Assurance
Plan Human
Resource
Management
Acquire Project
Team
Develop Project
Team
Manage Project
Team
Plan
Communications
Management
Manage
Communications
Control
Communications
Plan Risk
Management
Identify Risks Perform
Qualitative
Risk Analysis
Plan Risk
Responses
Perform
Quantitative
Risk Analysis
Control Risks
Plan Procurement
Management
Conduct
Procurements
Control
Procurements
Plan Stakeholder
Management
Manage
Stakeholder
Engagement
Control
Stakeholder
Engagement
Control Scope
Spending for
Planning or Execution
Iterative
Back to PM Plan
Iterative
Back to PM Plan
Iterative
Back to PM Plan
Plan Cost
Management
Iterative
Back to PM Plan
Iterative
Back to PM Plan
Updates
Iterative
Back to PM Plan
May be Simultaneous
Can happen often due to
project phases or changes
Seller’s completion of work AND Buyers completion of payment
Buyer cancellation due to non-performance OR Mutual agreement to end contract
Project Triggers
(Reasons Project
is needed)
Develop Project
Charter
Start/Finish
Integration
Scope
Time
Cost
Start/Finish
Quality
Human
Resource
Communications
Risk
Stakeholder
Procurement
When work is to be done
Change HOW the
work is being done
Change the WORK
that is being done
Early in the project life
Delivery of some
product components
Delivery of some
product components
Scope Baseline
Work Performance Data
Usually simultaneous
Early in the project life
Early in the project life
Begins early in the project life and continues throughout
Iterative Jump or Flowchart JumpExternal InputKnowledge Area

More Related Content

Viewers also liked

Brochure coaching 2013 10
Brochure coaching 2013 10Brochure coaching 2013 10
Brochure coaching 2013 10Carsten Jensen
 
Proposal rise written ok (2)
Proposal rise written ok (2)Proposal rise written ok (2)
Proposal rise written ok (2)valrivera
 
Lysosomal storage disease 2
Lysosomal storage disease 2Lysosomal storage disease 2
Lysosomal storage disease 2valrivera
 
Estrategias de Marketing
Estrategias de MarketingEstrategias de Marketing
Estrategias de MarketingPatrucha
 
Environmental impacts risk-securing techniques
Environmental impacts risk-securing techniquesEnvironmental impacts risk-securing techniques
Environmental impacts risk-securing techniquesHabib ur Rehman Solangi
 
Itec640 work breakdown structure
Itec640   work breakdown structureItec640   work breakdown structure
Itec640 work breakdown structurescotyh
 
C26 pollution
C26 pollutionC26 pollution
C26 pollutionChemrcwss
 
план роботи на канікулах
план роботи на канікулахплан роботи на канікулах
план роботи на канікулахalic_o
 
Inflammatory bowel disease & the liver
Inflammatory bowel disease & the liver Inflammatory bowel disease & the liver
Inflammatory bowel disease & the liver Samir Haffar
 
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use Thisproject management
 

Viewers also liked (16)

Wind Energy
Wind EnergyWind Energy
Wind Energy
 
Brochure coaching 2013 10
Brochure coaching 2013 10Brochure coaching 2013 10
Brochure coaching 2013 10
 
Prezi tecnicas y metdologia pdf
Prezi tecnicas y metdologia pdfPrezi tecnicas y metdologia pdf
Prezi tecnicas y metdologia pdf
 
Proposal rise written ok (2)
Proposal rise written ok (2)Proposal rise written ok (2)
Proposal rise written ok (2)
 
wasim resume
wasim resumewasim resume
wasim resume
 
Cv
CvCv
Cv
 
Textstil broderi
Textstil broderiTextstil broderi
Textstil broderi
 
Lysosomal storage disease 2
Lysosomal storage disease 2Lysosomal storage disease 2
Lysosomal storage disease 2
 
Estrategias de Marketing
Estrategias de MarketingEstrategias de Marketing
Estrategias de Marketing
 
Environmental impacts risk-securing techniques
Environmental impacts risk-securing techniquesEnvironmental impacts risk-securing techniques
Environmental impacts risk-securing techniques
 
Géneros literarios
Géneros literariosGéneros literarios
Géneros literarios
 
Itec640 work breakdown structure
Itec640   work breakdown structureItec640   work breakdown structure
Itec640 work breakdown structure
 
C26 pollution
C26 pollutionC26 pollution
C26 pollution
 
план роботи на канікулах
план роботи на канікулахплан роботи на канікулах
план роботи на канікулах
 
Inflammatory bowel disease & the liver
Inflammatory bowel disease & the liver Inflammatory bowel disease & the liver
Inflammatory bowel disease & the liver
 
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use This
 

Similar to PMPFlowChart

Pmp doc data_as per pmp - copy
Pmp doc data_as per pmp - copyPmp doc data_as per pmp - copy
Pmp doc data_as per pmp - copysandeep sonkusale
 
Mastering ITTO DataFlow PMP - PMBOK Version 5
Mastering ITTO DataFlow PMP - PMBOK Version 5Mastering ITTO DataFlow PMP - PMBOK Version 5
Mastering ITTO DataFlow PMP - PMBOK Version 5sandeep sonkusale
 
PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areassandeep sonkusale
 
PM Knowledge Areas
PM Knowledge AreasPM Knowledge Areas
PM Knowledge AreasDerya Milner
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagramriosabel
 
Project Management: Knowledge Areas
Project Management: Knowledge Areas Project Management: Knowledge Areas
Project Management: Knowledge Areas Gregory Mangos
 
Project management
Project managementProject management
Project managementNitin KR
 
Project management presentation
Project management presentationProject management presentation
Project management presentationPACF
 
Project management
Project managementProject management
Project managementAnshu Suri
 
Kayani presentation
Kayani presentationKayani presentation
Kayani presentationWAUM INTL
 
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docx
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docxInitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docx
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docxdirkrplav
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project ManagementTrue Corporation
 
Learnsmart Certificate of completions for PMP
Learnsmart Certificate of completions for PMPLearnsmart Certificate of completions for PMP
Learnsmart Certificate of completions for PMPcbegemann
 
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)Mike Cottmeyer
 
The agile pmp teaching an old dog new tricks
The agile pmp teaching an old dog new tricksThe agile pmp teaching an old dog new tricks
The agile pmp teaching an old dog new tricksLong Thay
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
 
Project management 101
Project management 101 Project management 101
Project management 101 Expoco
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOKGeoDiga
 
Definition presentation
Definition presentationDefinition presentation
Definition presentationPrem Kumar
 

Similar to PMPFlowChart (20)

Pmp doc data_as per pmp - copy
Pmp doc data_as per pmp - copyPmp doc data_as per pmp - copy
Pmp doc data_as per pmp - copy
 
Mastering ITTO DataFlow PMP - PMBOK Version 5
Mastering ITTO DataFlow PMP - PMBOK Version 5Mastering ITTO DataFlow PMP - PMBOK Version 5
Mastering ITTO DataFlow PMP - PMBOK Version 5
 
PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areas
 
PM Knowledge Areas
PM Knowledge AreasPM Knowledge Areas
PM Knowledge Areas
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagram
 
Project Management: Knowledge Areas
Project Management: Knowledge Areas Project Management: Knowledge Areas
Project Management: Knowledge Areas
 
Project management
Project managementProject management
Project management
 
Project management presentation
Project management presentationProject management presentation
Project management presentation
 
Project management
Project managementProject management
Project management
 
Kayani presentation
Kayani presentationKayani presentation
Kayani presentation
 
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docx
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docxInitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docx
InitiatingHold Project Kickoff MeetingPrepare Stakeholder Regist.docx
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
Learnsmart Certificate of completions for PMP
Learnsmart Certificate of completions for PMPLearnsmart Certificate of completions for PMP
Learnsmart Certificate of completions for PMP
 
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)
The Agile PMP: Teaching An Old Dog New Tricks (90 minutes)
 
The agile pmp teaching an old dog new tricks
The agile pmp teaching an old dog new tricksThe agile pmp teaching an old dog new tricks
The agile pmp teaching an old dog new tricks
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
Project management 101
Project management 101 Project management 101
Project management 101
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOK
 
Definition presentation
Definition presentationDefinition presentation
Definition presentation
 

PMPFlowChart

  • 1. Iterative back to/from: Define Scope Develop Schedule Estimate Costs Jump in from: Create WBS Also jump to: Plan Procurement Management Iterative back to: Estimate Costs Plan Risk Management Control Risks Plan Procurement Management Could be performed multiple times throughout project Develop Project Management Plan (PM Plan) Direct and Manage Project Work Perform Integrated Change Control Monitor and Control Project Work Scope Change Request Control Quality (Correctness) Validate Scope (Completeness) Close Phase Close Project Close Procurements LEGEND Initiating Planning Executing Monitoring/Controlling Closing Integration Scope Plan Scope Management Collect Requirements Time Cost Quality Human Resource Communications Risk Procurement StakeholderIdentify Stakeholders Define Scope Create WBS Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule Estimate Costs Determine Budget Control Costs Plan Quality Management Perform Quality Assurance Plan Human Resource Management Acquire Project Team Develop Project Team Manage Project Team Plan Communications Management Manage Communications Control Communications Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Plan Risk Responses Perform Quantitative Risk Analysis Control Risks Plan Procurement Management Conduct Procurements Control Procurements Plan Stakeholder Management Manage Stakeholder Engagement Control Stakeholder Engagement Control Scope Spending for Planning or Execution Iterative Back to PM Plan Iterative Back to PM Plan Iterative Back to PM Plan Plan Cost Management Iterative Back to PM Plan Iterative Back to PM Plan Updates Iterative Back to PM Plan May be Simultaneous Can happen often due to project phases or changes Seller’s completion of work AND Buyers completion of payment Buyer cancellation due to non-performance OR Mutual agreement to end contract Project Triggers (Reasons Project is needed) Develop Project Charter Start/Finish Integration Scope Time Cost Start/Finish Quality Human Resource Communications Risk Stakeholder Procurement When work is to be done Change HOW the work is being done Change the WORK that is being done Early in the project life Delivery of some product components Delivery of some product components Scope Baseline Work Performance Data Usually simultaneous Early in the project life Early in the project life Begins early in the project life and continues throughout Iterative Jump or Flowchart JumpExternal InputKnowledge Area