SlideShare a Scribd company logo
1 of 8
Download to read offline
CPMGT/302
PROCUREMENT AND RISK
MANAGEMENT
The Latest Version A+ Study Guide
**********************************************
CPMGT 302 Entire Course Link
https://uopcourses.com/category/cpmgt-302/
**********************************************
CPMGT 302 Week 1 Risk Management Small Group
Discussion
Discuss the role of risk management in the project planning process in small groups
by completing the related "Risk Management Discussion" learning activity.
Submit a response of 250 to 350 words in length summarizing your small group's
discussion of the role of risk management in the project planning.
A discussion summary is not a paper when you can assign sections out to team
members. A discussion summary is brief but first requires that you have a team
discussion. Everyone must participate equally and early in the week to earn full credit.
CPMGT 302 Week 1 Risk Identification Worksheet and Paper
Complete the University of Phoenix Material: Risk Identification Scenarios worksheet.
Insert the values which correspond to the probability of those risks, and the impact of the
risk events
For each risk scenario - write a 50 to 100 word description on how you would document
and mitigate the risks you identified.
Format the worksheet by including in-text citation and a reference page consistent with
APA guidelines.
Submit the completed University of Phoenix Material: Risk Identification Scenarios
Worksheet
Risk Identification Scenarios
Review each of the following scenarios and identify the risk events, the probability of those
risks, and the impact of the risk events. Some scenarios may have more risks than others.
Scenario One
A retail firm has a project that is focused on expansion into third-world countries to sell
pharmaceutical products. The project timeline is, as always, aggressive. The scope is well
documented and understood by the project team and key members of the firm. The firm is
financially sound, with project funds secure; however, the stakeholders expect that the project
will pay for itself within 2 years of deployment.
Risk event
Probability of risk event
(1=high; 3=medium; 5=low)
Impact of risk event
(1=high; 3=medium; 5=low)
Scenario Two
A construction company has been awarded the contract to build a pipeline in Alaska. The
project timeline is of the highest priority because work can only be completed during summer
months due to adverse weather conditions. One of the suppliers of a key component has
longer lead time than is required to complete the pipeline, but may be able to deliver if the
construction company will pay fees to expedite. There are other suppliers, but these suppliers
are not on the construction company’s approved suppler list and it would take time to get them
approved. There is a huge penalty in the contract if the project is not completed on time.
Risk event
Probability of risk event
(1=high; 3=medium; 5=low)
Impact of risk event
(1=high; 3=medium; 5=low)
Scenario Three
A telecommunications company has just assigned you to be project manager for a product
improvement project. The scope statement of the project simply says, “Make this product better.”
The engineering team believes that they know how to make the product better and have ignored
ideas from the sales team. The project funds are secure, as the company believes that improving
this product will give them strategic advantages.
Risk event
Probability of risk event
(1=high; 3=medium; 5=low)
Impact of risk event
(1=high; 3=medium; 5=low)
CPMGT 302 Week 2 Risk Management Breakdown Structure
Paper
Select an organization you are familiar with as the basis of the paper.
Read the following scenario for the selected organization:
Risk involves uncertainty, the lack of knowledge of future events, and the measures of
profitability and consequences of not achieving the project goal. Your organization has
decided that to be successful in the global economy it must expand its supply base into
China or another country approved by your instructor. This has become a strategic project
for the organization.
Resource: Figure 11-4 in A Guide to the Project Management Body of Knowledge
(PMBOK®
Guide)
Write a 1,400- to 2,100-word paper in which you address the following risk management
items for this supplier global expansion project:
 Describe the objectives and goals, tools and techniques, and organizational roles
and responsibilities for effective risk management for the project.
 Describe various information sources that may be used by the project team for risk
identification.
 Identify and describe the risk management documentation that will be required for
the project. Examples include RMP and risk management log or register.
 Explain the role of risk management in the project planning process.
Create a risk breakdown structure, which outlines the organization's risk categories. See
Figure 11-4 in the PMBOK®
Guide. Consider the following categories:
 Project risks
o Business
o Contract relationships with customers and suppliers
o Management
o Political
 Organizational risks
 Project management risks
o Cost estimates
o Schedule estimates
o Communication
 Technical risks
 Production risks
o Manufacturing concerns
o Logistics
 Support risks
o Maintainabilit
o Warranty
 External risks
o Procurement
 Material availability
 Lead times
 Quality
 Market
Format your paper consistent with APA guidelines.
Performing Risk Analysis Discussion
CPMGT 302 Week 2 Performing Risk Analysis Discussion
Review the Week 1 Activity Performing Risk Analysis (PMBOK®
Guide Fifth Edition)
course individually.
Discuss the Project Risk Management course with your Learning Team:
 What qualitative risk analysis techniques did you learn about in the course?
o Describe a real-world project management example of when you would
use one or more of the qualitative risk analysis techniques your team
identified.
Agree collectively on a response to the discussion question.
Submit a Learning Team response of 250 to 350 words in length.
CPMGT 302 Week 3 Risk Management Paper
Agree on using one of the organizations individual team members used in Week 2.
Your organization has determined that more resources are required to complete the
project's risk management process for the expansion into China or another country
approved by your instructor. Your team has been asked to perform a risk analysis,
develop risk responses, and determine how the project will monitor and control risks.
Resource: Risk Breakdown Structure from Part I and University of Phoenix Material:
Risk Project Log
Write a 1,050- to 1,400-word paper in which you do the following:
 Identify the risks associated with the supplier expansion. Document those risks in
the Risk Project Log template.
 Perform a qualitative risk analysis using risk probability and impact analysis.
 Perform quantitative risk analysis.
 Determine and document the criteria used to determine which risks will have a risk
response plan.
 Outline the timing--when and how often--of the risk management process in the
project life cycle, including risk monitoring and controlling processes. Consider the
following:
o Risk reassessment
o Risk audits
o Status meetings
Format your paper and presentation consistent with APA guidelines.
CPMGT 302 Week 3 Risk Response and Control Discussion
Review the Week 2 Risk Response and Control (PMBOK®
Guide Fifth Edition) course
individually.
Discuss the Risk Response and Control course with your Learning Team:
 What strategies for handling negative risk did you learn about in the course?
o Describe a real-world project management example of when you would
use one or more of the strategies to handle negative risk your team
identified.
 What strategies for handling positive risk did you learn about in the course?
o Describe a real-world project management example of when you would
use one or more of the strategies to handle positive risk your team
identified.
Agree collectively on a response to the discussion question.
Submit a Learning Team response of 250 to 350 words in length.
CPMGT 302 Week 4 Planning Project Procurement
Management Discussion
Review the Week 3 Planning Project Procurement Management (PMBOK®
Guide Fifth
Edition) course individually.
Discuss the Planning Project Procurement Management course with your Learning
Team:
 What common tools and techniques for planning project procurement did you
learn about in the course?
 What factors need to be considered in a make-or-buy analysis?
o Describe a real-world project management example of when you would
use one or more of the tools and techniques for planning project
procurement your team identified.
Agree collectively on a response to the discussion question.
Submit a Learning Team response of 250 to 350 words in length.
CPMGT 302 Week 4 Procurement Planning Paper
Write a 1,050- to 1,400-word paper in which you do the following:
 Describe the project procurement planning process. See Section 12.1 in
the PMBOK®
Guide.
 Identify the most valuable output of the plan procurement process and explain
why you believe it is most valuable.
 Explain the various contract types and describe who--buyer or seller--has the
most at risk for each contract type.
 Describe a source selection criterion that would be applicable to any project and
identify three criteria that would apply to most projects. See Section 12.1.3.5 in
thePMBOK®
Guide.
 Analyze the ethical concerns that should be considered when identifying source
selection criteria.
 Explain the role of risk management in the procurement planning process.
Format your paper consistent with APA guidelines.
CPMGT 302 Week 5 Contracting Process Paper
Write a 1,400- to 1,750-word paper in which you explain the process for conducting and
closing procurements. Include the following:
 Outline and explain high-level process steps for conducting project procurements.
 Outline and explain contract administration policies and procedures.
 Describe tools and techniques for the contract administration process, including
the following:
o Contract change control process
o Procurement performance reviews
o Inspections and audits
o Performance reporting
o Payment process (n/30, n/60, and so forth)
o Records management system (RMS)
 Describe conflict resolution techniques used while managing contractual
relationships.
 Outline steps to be taken to close out project procurements.
 Explain the importance of closing project procurements and accounts.
 Examine external influences on the procurement and risk management process.
 Analyze the relationship between the risk response plan and the external
influences.
Format your paper consistent with APA guidelines.

More Related Content

What's hot

Risk 6 questions - 170
Risk 6 questions - 170Risk 6 questions - 170
Risk 6 questions - 170Mohamed Saeed
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & templateAllie Gentry
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
BUS 519 Education Organization -- snaptutorial.com
BUS 519   Education Organization -- snaptutorial.comBUS 519   Education Organization -- snaptutorial.com
BUS 519 Education Organization -- snaptutorial.comDavisMurphyB97
 
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Safak EBESEK
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk ManagementMinhas Kamal
 
Integrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskIntegrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskHKA
 
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examRanga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examrrangraj
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
Bus 519 Enhance teaching / snaptutorial.com
Bus 519  Enhance teaching / snaptutorial.comBus 519  Enhance teaching / snaptutorial.com
Bus 519 Enhance teaching / snaptutorial.comHarrisGeorg50
 
Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides SlideTeam
 

What's hot (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
PM Professional Development
PM Professional DevelopmentPM Professional Development
PM Professional Development
 
Risk 6 questions - 170
Risk 6 questions - 170Risk 6 questions - 170
Risk 6 questions - 170
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
 
BUS 519 Education Organization -- snaptutorial.com
BUS 519   Education Organization -- snaptutorial.comBUS 519   Education Organization -- snaptutorial.com
BUS 519 Education Organization -- snaptutorial.com
 
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMI-RMP a test mod 00
PMI-RMP a test  mod 00PMI-RMP a test  mod 00
PMI-RMP a test mod 00
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk Management
 
Integrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskIntegrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost Risk
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examRanga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
What is risk?
What is risk?What is risk?
What is risk?
 
Bus 519 Enhance teaching / snaptutorial.com
Bus 519  Enhance teaching / snaptutorial.comBus 519  Enhance teaching / snaptutorial.com
Bus 519 Enhance teaching / snaptutorial.com
 
Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides
 
Project Risk management
Project Risk managementProject Risk management
Project Risk management
 

Similar to Cpmgt 302 cpmgt302

MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxAASTHA76
 
D.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docxD.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docxtheodorelove43763
 
Risk Project LogCPMGT302 Version 81University of Phoenix .docx
Risk Project LogCPMGT302 Version 81University of Phoenix .docxRisk Project LogCPMGT302 Version 81University of Phoenix .docx
Risk Project LogCPMGT302 Version 81University of Phoenix .docxjoellemurphey
 
Project planning - Unit III AssessmentQ.1Differentiate betwe.docx
Project planning - Unit III AssessmentQ.1Differentiate betwe.docxProject planning - Unit III AssessmentQ.1Differentiate betwe.docx
Project planning - Unit III AssessmentQ.1Differentiate betwe.docxwkyra78
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Anakinzs
 
CMGT 433 Entire Course NEW
CMGT 433 Entire Course NEWCMGT 433 Entire Course NEW
CMGT 433 Entire Course NEWshyamuopuop
 
Cmgt 433 Entire Course NEW
Cmgt 433 Entire Course NEWCmgt 433 Entire Course NEW
Cmgt 433 Entire Course NEWshyamuop
 
Cmgt410
Cmgt410Cmgt410
Cmgt4107Fase1
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docxSheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docxlesleyryder69361
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxbraycarissa250
 
Cmgt 410 Entire Course
Cmgt 410 Entire CourseCmgt 410 Entire Course
Cmgt 410 Entire CourseCMGT410
 
Cmgt410
Cmgt410Cmgt410
Cmgt410joituy
 
Cmgt410 Entire Course
Cmgt410 Entire CourseCmgt410 Entire Course
Cmgt410 Entire CourseCMGT410
 
1 Assignment Objectives Introduction to Project Risk Managemen.docx
1 Assignment Objectives Introduction to Project Risk Managemen.docx1 Assignment Objectives Introduction to Project Risk Managemen.docx
1 Assignment Objectives Introduction to Project Risk Managemen.docxhoney725342
 

Similar to Cpmgt 302 cpmgt302 (20)

Pmstudy exam 2
Pmstudy exam 2Pmstudy exam 2
Pmstudy exam 2
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
D.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docxD.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docx
 
Risk Project LogCPMGT302 Version 81University of Phoenix .docx
Risk Project LogCPMGT302 Version 81University of Phoenix .docxRisk Project LogCPMGT302 Version 81University of Phoenix .docx
Risk Project LogCPMGT302 Version 81University of Phoenix .docx
 
Project planning - Unit III AssessmentQ.1Differentiate betwe.docx
Project planning - Unit III AssessmentQ.1Differentiate betwe.docxProject planning - Unit III AssessmentQ.1Differentiate betwe.docx
Project planning - Unit III AssessmentQ.1Differentiate betwe.docx
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
Presentation on Project Risk Management
Presentation on Project Risk ManagementPresentation on Project Risk Management
Presentation on Project Risk Management
 
Cmgt410
Cmgt410Cmgt410
Cmgt410
 
Cpmgt 305 cpmgt305
Cpmgt 305 cpmgt305Cpmgt 305 cpmgt305
Cpmgt 305 cpmgt305
 
CMGT 433 Entire Course NEW
CMGT 433 Entire Course NEWCMGT 433 Entire Course NEW
CMGT 433 Entire Course NEW
 
Cmgt 433 Entire Course NEW
Cmgt 433 Entire Course NEWCmgt 433 Entire Course NEW
Cmgt 433 Entire Course NEW
 
Cmgt410
Cmgt410Cmgt410
Cmgt410
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docxSheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
 
Cmgt 410 Entire Course
Cmgt 410 Entire CourseCmgt 410 Entire Course
Cmgt 410 Entire Course
 
Cmgt410
Cmgt410Cmgt410
Cmgt410
 
Cmgt410 Entire Course
Cmgt410 Entire CourseCmgt410 Entire Course
Cmgt410 Entire Course
 
1 Assignment Objectives Introduction to Project Risk Managemen.docx
1 Assignment Objectives Introduction to Project Risk Managemen.docx1 Assignment Objectives Introduction to Project Risk Managemen.docx
1 Assignment Objectives Introduction to Project Risk Managemen.docx
 

More from GOODCourseHelp (20)

Soc 110 soc110
Soc 110 soc110Soc 110 soc110
Soc 110 soc110
 
Soc 110 soc110
Soc 110 soc110Soc 110 soc110
Soc 110 soc110
 
Psy 203 psy203
Psy 203 psy203Psy 203 psy203
Psy 203 psy203
 
Psy 103 psy103 UOP
Psy 103 psy103 UOPPsy 103 psy103 UOP
Psy 103 psy103 UOP
 
Prg 211 prg211
Prg 211 prg211Prg 211 prg211
Prg 211 prg211
 
Pos 433 pos433
Pos 433 pos433Pos 433 pos433
Pos 433 pos433
 
Mkt 421 mkt421
Mkt 421 mkt421Mkt 421 mkt421
Mkt 421 mkt421
 
Mgt 312 mgt312
Mgt 312 mgt312Mgt 312 mgt312
Mgt 312 mgt312
 
Law 421 law421
Law 421 law421Law 421 law421
Law 421 law421
 
It 242 it242
It 242 it242It 242 it242
It 242 it242
 
It 241 it241
It 241 it241It 241 it241
It 241 it241
 
It 240 it240
It 240 it240It 240 it240
It 240 it240
 
It 237 it237
It 237 it237It 237 it237
It 237 it237
 
It 236 it236
It 236 it236It 236 it236
It 236 it236
 
It 200 it200
It 200 it200It 200 it200
It 200 it200
 
Hum 186 hum186
Hum 186 hum186Hum 186 hum186
Hum 186 hum186
 
Hum 115 hum115
Hum 115 hum115Hum 115 hum115
Hum 115 hum115
 
Hrm 498 hrm498
Hrm 498 hrm498Hrm 498 hrm498
Hrm 498 hrm498
 
Web 240 web240
Web 240 web240Web 240 web240
Web 240 web240
 
Sci220 sci 220
Sci220 sci 220Sci220 sci 220
Sci220 sci 220
 

Recently uploaded

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonJericReyAuditor
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 

Recently uploaded (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lesson
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 

Cpmgt 302 cpmgt302

  • 1. CPMGT/302 PROCUREMENT AND RISK MANAGEMENT The Latest Version A+ Study Guide ********************************************** CPMGT 302 Entire Course Link https://uopcourses.com/category/cpmgt-302/ ********************************************** CPMGT 302 Week 1 Risk Management Small Group Discussion Discuss the role of risk management in the project planning process in small groups by completing the related "Risk Management Discussion" learning activity. Submit a response of 250 to 350 words in length summarizing your small group's discussion of the role of risk management in the project planning. A discussion summary is not a paper when you can assign sections out to team members. A discussion summary is brief but first requires that you have a team discussion. Everyone must participate equally and early in the week to earn full credit. CPMGT 302 Week 1 Risk Identification Worksheet and Paper Complete the University of Phoenix Material: Risk Identification Scenarios worksheet. Insert the values which correspond to the probability of those risks, and the impact of the risk events
  • 2. For each risk scenario - write a 50 to 100 word description on how you would document and mitigate the risks you identified. Format the worksheet by including in-text citation and a reference page consistent with APA guidelines. Submit the completed University of Phoenix Material: Risk Identification Scenarios Worksheet Risk Identification Scenarios Review each of the following scenarios and identify the risk events, the probability of those risks, and the impact of the risk events. Some scenarios may have more risks than others. Scenario One A retail firm has a project that is focused on expansion into third-world countries to sell pharmaceutical products. The project timeline is, as always, aggressive. The scope is well documented and understood by the project team and key members of the firm. The firm is financially sound, with project funds secure; however, the stakeholders expect that the project will pay for itself within 2 years of deployment. Risk event Probability of risk event (1=high; 3=medium; 5=low) Impact of risk event (1=high; 3=medium; 5=low) Scenario Two A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are not on the construction company’s approved suppler list and it would take time to get them approved. There is a huge penalty in the contract if the project is not completed on time. Risk event Probability of risk event (1=high; 3=medium; 5=low) Impact of risk event (1=high; 3=medium; 5=low)
  • 3. Scenario Three A telecommunications company has just assigned you to be project manager for a product improvement project. The scope statement of the project simply says, “Make this product better.” The engineering team believes that they know how to make the product better and have ignored ideas from the sales team. The project funds are secure, as the company believes that improving this product will give them strategic advantages. Risk event Probability of risk event (1=high; 3=medium; 5=low) Impact of risk event (1=high; 3=medium; 5=low) CPMGT 302 Week 2 Risk Management Breakdown Structure Paper Select an organization you are familiar with as the basis of the paper. Read the following scenario for the selected organization: Risk involves uncertainty, the lack of knowledge of future events, and the measures of profitability and consequences of not achieving the project goal. Your organization has decided that to be successful in the global economy it must expand its supply base into China or another country approved by your instructor. This has become a strategic project for the organization. Resource: Figure 11-4 in A Guide to the Project Management Body of Knowledge (PMBOK® Guide) Write a 1,400- to 2,100-word paper in which you address the following risk management items for this supplier global expansion project:
  • 4.  Describe the objectives and goals, tools and techniques, and organizational roles and responsibilities for effective risk management for the project.  Describe various information sources that may be used by the project team for risk identification.  Identify and describe the risk management documentation that will be required for the project. Examples include RMP and risk management log or register.  Explain the role of risk management in the project planning process. Create a risk breakdown structure, which outlines the organization's risk categories. See Figure 11-4 in the PMBOK® Guide. Consider the following categories:  Project risks o Business o Contract relationships with customers and suppliers o Management o Political  Organizational risks  Project management risks o Cost estimates o Schedule estimates o Communication  Technical risks  Production risks o Manufacturing concerns o Logistics  Support risks o Maintainabilit o Warranty  External risks o Procurement  Material availability  Lead times  Quality  Market
  • 5. Format your paper consistent with APA guidelines. Performing Risk Analysis Discussion CPMGT 302 Week 2 Performing Risk Analysis Discussion Review the Week 1 Activity Performing Risk Analysis (PMBOK® Guide Fifth Edition) course individually. Discuss the Project Risk Management course with your Learning Team:  What qualitative risk analysis techniques did you learn about in the course? o Describe a real-world project management example of when you would use one or more of the qualitative risk analysis techniques your team identified. Agree collectively on a response to the discussion question. Submit a Learning Team response of 250 to 350 words in length. CPMGT 302 Week 3 Risk Management Paper Agree on using one of the organizations individual team members used in Week 2. Your organization has determined that more resources are required to complete the project's risk management process for the expansion into China or another country approved by your instructor. Your team has been asked to perform a risk analysis, develop risk responses, and determine how the project will monitor and control risks. Resource: Risk Breakdown Structure from Part I and University of Phoenix Material: Risk Project Log Write a 1,050- to 1,400-word paper in which you do the following:  Identify the risks associated with the supplier expansion. Document those risks in the Risk Project Log template.  Perform a qualitative risk analysis using risk probability and impact analysis.  Perform quantitative risk analysis.
  • 6.  Determine and document the criteria used to determine which risks will have a risk response plan.  Outline the timing--when and how often--of the risk management process in the project life cycle, including risk monitoring and controlling processes. Consider the following: o Risk reassessment o Risk audits o Status meetings Format your paper and presentation consistent with APA guidelines. CPMGT 302 Week 3 Risk Response and Control Discussion Review the Week 2 Risk Response and Control (PMBOK® Guide Fifth Edition) course individually. Discuss the Risk Response and Control course with your Learning Team:  What strategies for handling negative risk did you learn about in the course? o Describe a real-world project management example of when you would use one or more of the strategies to handle negative risk your team identified.  What strategies for handling positive risk did you learn about in the course? o Describe a real-world project management example of when you would use one or more of the strategies to handle positive risk your team identified. Agree collectively on a response to the discussion question. Submit a Learning Team response of 250 to 350 words in length. CPMGT 302 Week 4 Planning Project Procurement Management Discussion Review the Week 3 Planning Project Procurement Management (PMBOK® Guide Fifth Edition) course individually. Discuss the Planning Project Procurement Management course with your Learning Team:
  • 7.  What common tools and techniques for planning project procurement did you learn about in the course?  What factors need to be considered in a make-or-buy analysis? o Describe a real-world project management example of when you would use one or more of the tools and techniques for planning project procurement your team identified. Agree collectively on a response to the discussion question. Submit a Learning Team response of 250 to 350 words in length. CPMGT 302 Week 4 Procurement Planning Paper Write a 1,050- to 1,400-word paper in which you do the following:  Describe the project procurement planning process. See Section 12.1 in the PMBOK® Guide.  Identify the most valuable output of the plan procurement process and explain why you believe it is most valuable.  Explain the various contract types and describe who--buyer or seller--has the most at risk for each contract type.  Describe a source selection criterion that would be applicable to any project and identify three criteria that would apply to most projects. See Section 12.1.3.5 in thePMBOK® Guide.  Analyze the ethical concerns that should be considered when identifying source selection criteria.  Explain the role of risk management in the procurement planning process. Format your paper consistent with APA guidelines. CPMGT 302 Week 5 Contracting Process Paper Write a 1,400- to 1,750-word paper in which you explain the process for conducting and closing procurements. Include the following:  Outline and explain high-level process steps for conducting project procurements.  Outline and explain contract administration policies and procedures.
  • 8.  Describe tools and techniques for the contract administration process, including the following: o Contract change control process o Procurement performance reviews o Inspections and audits o Performance reporting o Payment process (n/30, n/60, and so forth) o Records management system (RMS)  Describe conflict resolution techniques used while managing contractual relationships.  Outline steps to be taken to close out project procurements.  Explain the importance of closing project procurements and accounts.  Examine external influences on the procurement and risk management process.  Analyze the relationship between the risk response plan and the external influences. Format your paper consistent with APA guidelines.