SlideShare a Scribd company logo
1 of 37
Download to read offline
SDAG

Discretization Methods for Multiphase
Flow Simulation of Ultra-Long
Gas-Condensate Pipelines
       Erich Zakarian & Henning Holm
              Shtokman Development A.G.




       www.bhrgroup.co.uk

       14th International Conference Multiphase Production Technology
                   Cannes, France - 17th - 19th June 2009
SDAG

Contents
• The Shtokman field development
• Profile discretization of gas-condensate pipelines
 • Objective and requirements
 • Method 1 – concept of pipeline profile indicator
 • Method 2 – concept of lumping and redistribution
 • Comparison and simulation

• Conclusions


          14th International Conference Multiphase Production Technology
                        Cannes, France - 17th - 19th June 2009
SDAG
Integrated Development of the Shtokman
Gas-Condensate Field – Phase 1




        14th International Conference Multiphase Production Technology
                      Cannes, France - 17th - 19th June 2009
SDAG
Gas export to shore                              • 70 MSm3/d (2.5 BCFD) – Phase 1
                                                 • 2 x 36” ND trunklines (0.86 m ID)
                                                 • Length 558 km (347 miles)
             Shtokman
                                                 • Dry two-phase flow
             Teriberka                           • CGR = from 2 to 16 Sm3/MSm3


             Murmansk                                                   Paris




                                                                                Cannes

       14th International Conference Multiphase Production Technology
                     Cannes, France - 17th - 19th June 2009
SDAG

          Shtokman pipeline profile
                 200

                 100
 Elevation [m]




                   0

                 -100

                 -200

                 -300

                 -400
                        0       100             200             300             400          500
                                                      Distance [km]

• Detailed pipeline profile from seabed bathymetry survey (2007)
• Free span analysis and seabed intervention taken into account

                                            108,785 points
                            14th International Conference Multiphase Production Technology
                                          Cannes, France - 17th - 19th June 2009
SDAG

Pipeline profile discretization: objective
Given either as-built profile or detailed terrain survey
• In transient multiphase flow simulation, the actual or
expected pipeline geometry must be simplified to achieve
reasonable CPU time
• For long pipelines (> 100 km) laid on rough terrain,
compression of a large set of data points is required
typically from 104-105 points to few 103 points

                       Target
           Simulation time ≥ 24 x CPU time

          14th International Conference Multiphase Production Technology
                        Cannes, France - 17th - 19th June 2009
SDAG

 The Shtokman case

                      Target ≈ 2500 pipes
                      for a total length of 554 km


• Average pipe length will be approximately 200 m

• Avoid small pipe sections to maximize numerical time steps

                              Δt < min (Δx/U)i




            14th International Conference Multiphase Production Technology
                          Cannes, France - 17th - 19th June 2009
SDAG

Pipeline profile discretization: requirements
1. The total pipe length must be conserved
2. The simplified geometry must have the same overall
   shape (large and small scale undulations)
3. The pipe angle distribution of the discretized profile
   must be as close as possible to the original distribution
4. The total climb (cumulative length of uphill pipes) must
   be conserved to predict the same overall liquid content
   in steady-state flow conditions
                                          1
                                                                               3
                                                    2
                                                                               4
 Original profile

              14th International Conference Multiphase Production Technology
                            Cannes, France - 17th - 19th June 2009
SDAG

                     Liquid5.3: liquid holdupvs. pipe inclination velocity
                       OLGAS
                             holdup vs. pipe     inclination and gas superficial
                                      USL=0.003 m/s -  G=180 kg/m3 - o=775 kg/m3 - m G=0.02 cP - m O=2.5 cP
                                        =0.0025 N/m - Wall roughness=30 mm - Inner diameter=0.9906 m
                    0.70

                    0.60
                                                                                                                        USG = 1.00 m/s
Liquid holdup [-]




                                                                                                                        USG = 1.50 m/s
                    0.50
                                                                                                                        USG = 2.00 m/s

                    0.40                                                                                                USG = 2.50 m/s

                                                                                                                        USG = 3.00 m/s
                    0.30                                                                                                USG = 3.50 m/s

                                                                                                                        USG = 4.00 m/s
                    0.20                                                                                                USG = 4.50 m/s


                    0.10

                    0.00
                           -5   -4   -3     -2   -1    0      1    2    3     4     5     6     7     8        9   10
                                                           Pipe inclination [deg]


                                          14th International Conference Multiphase Production Technology
                                                        Cannes, France - 17th - 19th June 2009
SDAG

 Two methods for a single objective
Method 1: concept of pipeline profile indicator
• Select, simplify and complexify relevant sub-profiles
• Use the pipeline profile indicator and the total climb to
  match the original angle distribution
Method 2: concept of lumping elements with similar
  inclination
• Redistribution to match the original large & small
  scale topographies


          14th International Conference Multiphase Production Technology
                        Cannes, France - 17th - 19th June 2009
SDAG




                           Method 1

 Concept of pipeline profile indicator




       14th International Conference Multiphase Production Technology
                     Cannes, France - 17th - 19th June 2009
SDAG

Definition: pipeline profile indicator
                    Holdupi   Holdup0 Li
                    N

                   i 1
           PI                            N
                                                                         1000
                                          Li
                                         i 1

        Holdup i  
                                    Arctan1.9   i  1.66  0.25
                             0.49
                               
        θi = inclination of pipe i with respect to horizontal [%]
        Li = length of pipe i [m]
        N = number of pipes

B. Barrau, “Profile indicator helps predict pipeline holdup, slugging”, Oil & Gas Journal
Vol. 98, Issue 8, p. 58-62, Feb 21, 2000

               14th International Conference Multiphase Production Technology
                             Cannes, France - 17th - 19th June 2009
SDAG
                           OLGAS 5.3: liquid holdup vs. pipe inclination and gas superficial velocity
                    Holdup function vs. OLGAS
                                      USL=0.003 m/s -  G=180 kg/m3 - o=775 kg/m3 - m G=0.02 cP - m O=2.5 cP
                                        =0.0025 N/m - Wall roughness=30 mm - Inner diameter=0.9906 m
                    0.70

                    0.60
                                                                                                                        Holdup function
                                                                                                                        USG = 1.00 m/s
Liquid holdup [-]




                    0.50
                                                                                                                        USG = 1.50 m/s
                                                                                                                        USG = 2.00 m/s
                    0.40
                                                                                                                        USG = 2.50 m/s
                                                                                                                        USG = 3.00 m/s
                    0.30
                                                                                                                        USG = 3.50 m/s
                                                                                                                        USG = 4.00 m/s
                    0.20
                                                                                                                        USG = 4.50 m/s

                    0.10

                    0.00
                           -5   -4   -3   -2    -1    0      1    2     3     4     5     6     7     8        9   10
                                                          Pipe inclination [deg]

                                      14th International Conference Multiphase Production Technology
                                                    Cannes, France - 17th - 19th June 2009
SDAG

Pipeline profile indicator scale
         From Total E&P experience in gas-condensate pipeline
                        design and operation
                Pipeline profile is globally sloping downwards
       PI < 0
                No particular operating problem to be expected
                Pipeline profile is nearly horizontal or over-simplified
    0 < PI < 20
                No particular operating problem to be expected
                 Pipeline profile is relatively flat or slightly hilly
    20 < PI < 40
                 Possible troubles at very low flow rates or during restart
                 Pipeline crosses hilly terrain
    40 < PI < 80
                 Design & Operation needs particular attention
                 Pipeline profile is very hilly or very steep
      80 < PI    Design & Operation needs very careful attention
                 Validity of simulation software to be checked

   Shtokman pipeline profile indicator = 79.7
           14th International Conference Multiphase Production Technology
                         Cannes, France - 17th - 19th June 2009
SDAG

                             Step 1: sub-profile selection
                                                                Pipe inclination                                                                Pipe inclination
                                               10                                                                                10
                                                8                                                                                 8
                          Inclination [deg]




                                                                                                            Inclination [deg]
                                                6                                                                                 6
                                                4                                                                                 4
                                                2                                                                                 2
                                                0                                                                                 0
                                               -2                                                                                -2
                                               -4                                                                                -4
                                               -6                                                                                -6
                                               -8                                                                                -8
                                              -10                                                                               -10
                                              230000   240000   250000    260000    270000    280000                             410000   420000    430000    440000    450000   460000
                                                        Distance from offshore platform [m]                                               Distance from offshore platform [m]




                          180
Pipeline indicattor [-]




                          160
                          140
                          120
                          100
                           80
                           60
                           40
                           20
                            0
                                                0               100000               200000             300000                                400000               500000
                                                                                      Distance from offshore platform [m]


                                                                14th International Conference Multiphase Production Technology
                                                                              Cannes, France - 17th - 19th June 2009
SDAG

Step 2: simplification of the original profile
• Final average pipe length should be about 200 m
  (target ≈ 2500 pipes)
• For example, use the Box Filter from OLGA®
  Geometry Editor




• Or simply select one point every 1 km

         14th International Conference Multiphase Production Technology
                       Cannes, France - 17th - 19th June 2009
SDAG

     Step 2: result
                                                                                Pipeline geometry
                    200                                                                                                                5000
                                Pipe elevation (simplified profile) [m]                                                                4500




                                                                                                                                              Total climb [m]
                    100         Pipe elevation (original profile: 108,785 points) [m]                                                  4000
Elevation [m]




                      0         Total climb (original profile: 108,785 points) [m]                                                     3500
                                Total Climb (simplified profile) [m]                                                                   3000
                    -100                                                                                                               2500
                                                                                                                                       2000
                    -200                                                                                                               1500
                    -300                                                                                                               1000
                                                                                                                                       500
                    -400                                                                                                               0
                           0                   100000                        200000             300000             400000   500000
                                                                             Distance from offshore platform [m]
                                                                                                                                     PI = 79.7
                                                                                  Pipe inclination                                     25.8
                      20
                               Pipe inclination (original profile: 108,785 points) [deg]
                      15
Inclination [deg]




                               Pipe inclination (simplified profile) [deg]
                      10
                       5
                       0
                      -5
                     -10
                     -15
                           0                   100000                        200000             300000             400000   500000
                                                                             Distance from offshore platform [m]




                                             14th International Conference Multiphase Production Technology
                                                           Cannes, France - 17th - 19th June 2009
SDAG
                Step 3: complexification
                 •         Split the simplified profile into smaller pipes
                               5 smaller pipes per simplified pipe  pipe length ≈ 200 m
                 •         Move new points up and down with a random process cum
                                  Pipeline geometry            Inverse of the standard normal
                -305
                                                                                                     4
                                                        Complexified profile
                -310                                                                                 3
                                                        Simplified profile
                -315
                                                                                                    For each sub-profile
                                                                                                     2
Elevation [m]




                -320
                                                                                       • Keep original pipeline
                                                                                            1




                                                                                        NormStd-1
                -325                                                                     indicator within +/-1%
                                                                                            0


                -330                                                                   • Keep original total climb
                                                                                           -1

                                                                                         within +/- 1%
                                                                                           -2
                -335
                                                                                                     -3
                -340
                                                                                                     -4
                       0       2000      4000        6000         8000         10000
                                                                                                          0   0.1   0.2   0.3   0.4       0.5       0.6
                                Distance from offshore platform [m]                                                                   Probability

                                  14th International Conference Multiphase Production Technology
                                                Cannes, France - 17th - 19th June 2009
SDAG

                    Step 3: result
                                                                           Pipeline geometry
                    200                                                                                                         5000
                               Pipe elevation (complexified profile) [m]                                                        4500




                                                                                                                                       Total climb [m]
                    100                                                                                                         4000
Elevation [m]




                               Pipe elevation (original profile: 108,785 points) [m]
                      0        Total climb (complexified profile) [m]                                                           3500
                               Total climb (original profile: 108,785 points) [m]                                               3000
                    -100                                                                                                        2500
                                                                                                                                2000
                    -200                                                                                                        1500
                    -300                                                                                                        1000
                                                                                                                                500
                    -400                                                                                                        0
                           0              100000                      200000               300000             400000   500000
                                                                        Distance from offshore platform [m]

                                                                               Pipe inclination
                      20
                               Pipe inclination (original profile: 108,785 points) [deg]
                      15
Inclination [deg]




                               Pipe inclination (complexified profile) [deg]
                      10
                       5
                       0
                      -5
                     -10
                     -15
                           0              100000                       200000              300000             400000   500000
                                                                        Distance from offshore platform [m]




                                         14th International Conference Multiphase Production Technology
                                                       Cannes, France - 17th - 19th June 2009
SDAG




                           Method 2

  Concept of lumping elements with
         similar inclination



       14th International Conference Multiphase Production Technology
                     Cannes, France - 17th - 19th June 2009
SDAG

Method 2 – “Lumping and redistributing”
1.   Define the criteria (in priority) to determine the pipe length to be used for
     the simplified profile :
     1.   minimum pipe length
     2.   maximum elevation change for a pipe element
     3.   maximum pipe length
2.   Sort all elements in the detailed profile by inclination in ascending order
3.   Lump together the sorted elements to longer pipes, starting with the
     element with the steepest downhill inclination. The length of each pipe
     element is then limited by dominating criteria in 1).
4.   Distribute the pipe elements in the simplified profile to match the large
     scale and small scale topography of the detailed profile.

              14th International Conference Multiphase Production Technology
                            Cannes, France - 17th - 19th June 2009
SDAG

                            Step 1)
                            Define the criteria (in priority) to determine the pipe
                            length to be used for the simplified profile :
                  1.           minimum pipe length (200 m)
                  2.           maximum elevation change for a pipe element (5 m)
                  3.           maximum pipe length (1000 m)

                                                                                                                  25                                                                                 1000
                                                                                                                  20         Elevation change of single pipe                                         900
                                                                                                                  15         Pipe length                                                             800
Pipe elevation change (m)




                                                                                           Elevation change (m)
                                                                                                                  10                                                                                 700




                                                                                                                                                                                                            Pipe length (m)
                                                                                                                   5                                                                                 600
                                Maximum elevation change
                                                                                                                   0                                                                                 500
                                                                                                                   -5                                                                                400
                                                                                                                  -10                                                                                300
                                                                                                                  -15                                                                                200
                                                                                                                  -20                                                                                100
                                                                                                                  -25                                                                                0
                                    Xmin                                        Xmax                                    -8     -6          -4          -2             0              2   4   6   8
                                                             Pipelength (m)
                                                                                                                                                            Pipe inclination (deg)




                                                           14th International Conference Multiphase Production Technology
                                                                         Cannes, France - 17th - 19th June 2009
SDAG
                         Step 2)
                    Sort elements in the detailed profile by inclination in ascending order – divide into
                   0subsections if required

                 -200
Elevation (m)




                 -400

                 -600

                 -800

                -1000

                -1200
                                0               100000                       200000                                   300000        400000       500000        600000
                                                                                                  Distance (m)
                                     -200                                                    5
                                     -300                                                    4
                                     -400                Original profile                    3
                                                                                                  Inclination (deg)

                                     -500                                                    2
                    Elevation (m)




                                     -600
                                     -700
                                                               Inclination
                                                                                             1
                                                                                             0
                                                                                                                         Step 3)
                                     -800                                                    -1                          Lump together the sorted elements to
                                     -900                                                    -2
                                    -1000                                                    -3                          longer pipes, starting with the element
                                    -1100        Lumped, but not redistributed profile       -4
                                    -1200                                                    -5
                                                                                                                         with the steepest downhill inclination.
                                            0                50000                       100000                          The length of each pipe element is then
                                                         Distance (m)
                                                                                                                         limited by dominating criteria in 1).
                                                    14th International Conference Multiphase Production Technology
                                                                  Cannes, France - 17th - 19th June 2009
SDAG

”Inclination classes” versus ”lumping by inclination in ascending order ”


                         600000                                                                                       2000
                                       grouping by inclination classes                                                                 Original profile 20-70 km
                                       Lumping by inclinations in                                                     1800             'lumping by inclination in ascending order'
                         500000        ascending order
                                                                                                                      1600             'Sorted by inclination classes'




                                                                                            Condensate content [m3]
                                                                                                                      1400
Accumulated length (m)




                         400000
                                                                                                                      1200

                         300000                                                                                       1000

                                                                                                                      800
                         200000
                                                                                                                      600

                                                                                                                      400
                         100000
                                                                                                                      200

                             0                                                                                           0
                                  -5   -4    -3    -2    -1     0     1     2   3   4   5                                    30   35    40     45     50      55     60    65        70
                                                        Inclination (deg)
                                                                                                                                         Export flow rate [MSm3/d]



                                              14th International Conference Multiphase Production Technology
                                                            Cannes, France - 17th - 19th June 2009
SDAG
 Step 4)
 Redistribution of elements by “Simulated Annealing” (Travelling salesman problem)
 “minimize distance between detailed profile and simplified profile”
                                                                                              0

                                                                                            -200




                                                                   Elevation (m)
                                                                                            -400

Cost function:                                                                              -600

                                                                                            -800




       F ( y)  i wi  ( yi  yi ) 2
                                                                                      -1000

                                                                                      -1200
                                                                                                   0   100000   200000       300000       400000   500000    600000
                                                                                                                           Distance (m)


                                                                                               0

yi :   values from the simplified profile                                                    -50
                                                                                            -100




                                                                            Elevation (m)
                                                                                            -150
                                                                                            -200


ŷi :   values from the detailed profile                                                     -250
                                                                                            -300
                                                                                            -350
                                                                                            -400
                                                                                                   0   100000   200000        300000      400000   500000    600000

wi :   weight factor                                                                                                       Distance (m)




                                                                         -230

where as “i” denotes:                                                    -240
                                                   Elevation (m)




                                                                         -250
                                                                         -260

1)     Elevation                                                         -270
                                                                         -280
                                                                         -290

2)     “Total Climb”                                                     -300
                                                                                             70000     75000    80000       85000         90000    95000    100000
                                                                                                                         Distance (m)
3)     “Pipeline Indicator” *
                   14th International Conference Multiphase Production Technology
                                 Cannes, France - 17th - 19th June 2009
SDAG

                   Comparison
                                           Original Simplified Method 1                           Method 2
                                            profile   profile   profile                            profile
                Number of pipes            108,784     554      2,766                              2,550
                Pipeline profile indicator   79.7      25.8      80.3                               80.3
                Total climb [m]             4,187     1,235     4,180                              4,187
                Total length [m]           554,505 554,400     554,507                            554,505
                                                     Pipeline geometry
                 -230
                 -240
Elevation [m]




                 -250
                 -260
                 -270
                 -280
                 -290
                 -300                                                                         Original profile
                   70000     75000           80000            85000            90000          Simplified profile
                                                                                                 95000                100000
                                                                                              Discretized profile (method 1)
                                             Distance from offshore platform [m]              Discretized profile (method 2)


                             14th International Conference Multiphase Production Technology
                                           Cannes, France - 17th - 19th June 2009
SDAG

  Angle distributions
                                                                     Pipe angle distribution
                                        80000
Total pipe length per angle group [m]




                                                                                                  Original profile
                                        70000                                                     Discretized profile (Method 2)
                                                                                                  Discretized profile (Method 1)
                                        60000
                                                                                                  Simplified profile
                                        50000

                                        40000

                                        30000

                                        20000

                                        10000

                                              0
                                                        1)




                                                        5)
                                                       5)
                                                          )




                                                          )

                                                          )
                                            (-3 0)


                                              (-1 )




                                                         )

                                                         )

                                                         )
                                                         )

                                                         )
                                                         )




                                                         )

                                                         )
                                                       1)




                                                      20

                                                      90
                                                        0




                                                      ,5

                                                      ,7

                                                      ,9
                                                      ,2

                                                      ,3
                                                      -5




                                                      25




                                                      .2

                                                      .4
                                                     .0




                                                     .2
                                                     .7
                                                    -6

                                                    -2




                                                    ,-




                                                   ,0

                                                   ,0




                                                  (4

                                                  (6

                                                  (8
                                                   0,




                                                   0.




                                                   .5

                                                   .5




                                                  0,

                                                  0,
                                                 ,0




                                                 ,1
                                                 ,0
                                                (-2
                                                 0,

                                                 0,




                                                (1

                                                (2
                                                ,-




                                                .1

                                                .3




                                               (1

                                               (3
                                              (0




                                              (1
                                              .5
                                        (-9




                                            (0

                                            (0
                                             .5




                                           (0
                                         (-0




                                                                         Pipe angle group [deg]

                                                  14th International Conference Multiphase Production Technology
                                                                Cannes, France - 17th - 19th June 2009
SDAG

Steady-state simulation: original vs. discretization
                                                  Condensate content vs. export flow rate
                                        42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor
                            2000
                                                                          Original profile 20-70 km
                            1800
                                                                          Discretized profile 20-70 km (Method 1)
  Condensate content [m3]




                            1600
                                                                          Discretized profile 20-70 km (Method 2)
                            1400

                            1200

                            1000

                             800

                             600

                             400

                             200

                               0
                                   30        35        40        45        50        55        60          65       70
                                                             Export flow rate [MSm3/d]
                                          14th International Conference Multiphase Production Technology
                                                        Cannes, France - 17th - 19th June 2009
SDAG

Steady-state simulation: simplified vs. discretization
                                                         Total condensate content vs. export flow rate
                                                   42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor
                                 10000                                                                                              200
                                                                     Total condensate content (simplified profile)
                                                                     Total condensate content (method 1)
                                  9000                               Total condensate content (method 2)
 Total condensate content [m3]




                                                                     Inlet pressure (simplified profile)                            180
                                  8000                               Inlet pressure (method 1)
                                                                     Inlet pressure (method 2)




                                                                                                                                          Inlet pressure [bara]
                                  7000
                                                                                                                                    160
                                  6000

                                  5000                                                                                              140

                                  4000
                                                                                                                                    120
                                  3000

                                  2000
                                                                                                                                    100
                                  1000

                                     0                                                                                              80
                                         20   25        30      35         40        45        50        55          60   65   70
                                                                     Export flow rate [MSm3/d]

                                              14th International Conference Multiphase Production Technology
                                                            Cannes, France - 17th - 19th June 2009
SDAG
Conclusions
• Simplification of long and rough gas-condensate
pipeline profiles is a key issue for correct design
• Two methods were introduced for the development
of the Shtokman field – Phase 1
• Essential characteristics of the original detailed
pipeline profile are conserved:
 Length + Topography + Angle distribution + Total climb
• The hydrodynamic behavior of the original profile is
conserved through both methods despite significant
data compression
          14th International Conference Multiphase Production Technology
                        Cannes, France - 17th - 19th June 2009
SDAG

 Discretization Methods for Multiphase
  Flow Simulation of Ultra-Long Gas-
         Condensate Pipelines

       Erich Zakarian, Henning Holm
       Shtokman Development A.G., Russia
    erich.zakarian@total.com, hthol@statoilhydro.com


                   Dominique Larrey
    Total E&P, Process Department, France
                dominique.larrey@total.com

        14th International Conference Multiphase Production Technology
                      Cannes, France - 17th - 19th June 2009
SDAG




                        Back-up



       14th International Conference Multiphase Production Technology
                     Cannes, France - 17th - 19th June 2009
SDAG

                                   Why discretization is so important?
                                               Total condensate content vs. export flow rate                                Poor discretization
                                         42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor
                                10000                                                                                       Incorrect design of
                                 9000
                                                                                     Simplified profile
                                                                                                                             receiving facilities
Total condensate content [m3]




                                                                                     Discretized profile (Method 1)
                                 8000
                                                                                     Discretized profile (Method 2)
                                                                                                                            Wrong operating
                                 7000

                                 6000
                                                                                                                             envelope
                                 5000                                                                                       Reduced operating
                                 4000                                                                                        flexibility
                                 3000

                                 2000
                                                                                                                            Higher risk of
                                 1000
                                                                                                                             continuous flaring
                                    0                                                                                       Wrong model tuning
                                        20            30             40             50               60               70
                                                                 Export flow rate [MSm3/d]
                                                                                                                             against field data


                                                           14th International Conference Multiphase Production Technology
                                                                         Cannes, France - 17th - 19th June 2009
SDAG

                                             Seabed profile
                                             200

                                             100
                             Elevation [m]




                                               0

                                             -100

                                             -200

                                             -300
3D Side Scan Sonar imagery




                                             -400
                                                    0       100             200             300             400          500
                                                                                  Distance [km]




                                  Ice scours &                                                                            Pockmarks
                                  depressions               Elongated pockmarks              Ridges & ice scours
                                                        14th International Conference Multiphase Production Technology
                                                                      Cannes, France - 17th - 19th June 2009
SDAG

Total climb
• Total climb = cumulative length of uphill pipes
• Helpful indicator as a first check
• Relevant indicator in addition to the pipeline profile
indicator to match the original angle distribution

  Shtokman original pipeline profile (2007 survey)
              Total climb = 4187 m




          14th International Conference Multiphase Production Technology
                        Cannes, France - 17th - 19th June 2009
SDAG

                           Comparison of the discretization methods
                                                                                       Pipeline geometry
                    200                                                                                                              5000
                                Pipe elevation (discretized profile: first method) [m]
                    100




                                                                                                                                            Total climb [m]
                                Pipe elevation (discretized profile: second method)[m]                                               4000
Elevation [m]




                      0         Total climb (discretized profile: first method) [m]
                                Total climb (discretized profile: second method) [m]                                                 3000
                    -100
                                                                                                                                     2000
                    -200
                    -300                                                                                                             1000

                    -400                                                                                                             0
                           0                   100000                      200000                 300000           400000   500000
                                                                           Distance from offshore platform [m]

                               Pipe inclination (discretized profile: first method) [m]
                                                                                           Pipe inclination
                      10
                       8       Pipe inclination (discretized profile: second method) [m]
                       6
Inclination [deg]




                       4
                       2
                       0
                      -2
                      -4
                      -6
                      -8
                     -10
                           0                   100000                      200000                 300000           400000   500000
                                                                             Distance from offshore platform [m]


                                                   14th International Conference Multiphase Production Technology
                                                                 Cannes, France - 17th - 19th June 2009
SDAG

OLGA® Geometry Editor

                           • Ok for removing noise from as-built
   Box filter              pipeline survey
                           • Not recommended for hilly pipelines




     Angle                 • Requires pre-definition of angle groups
                           • Several tries are necessary
  distribution             • Extremely difficult or even impossible to
 preservation              satisfy the four criteria


        14th International Conference Multiphase Production Technology
                      Cannes, France - 17th - 19th June 2009

More Related Content

What's hot

Directional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdfDirectional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdfssuserd324d9
 
Nodal Analysis introduction to inflow and outflow performance - next
Nodal Analysis   introduction to inflow and outflow performance - nextNodal Analysis   introduction to inflow and outflow performance - next
Nodal Analysis introduction to inflow and outflow performance - nextgusgon
 
Intelligent well completion
Intelligent well completionIntelligent well completion
Intelligent well completionAkshaya Mishra
 
Subsurface safety valves
Subsurface safety valvesSubsurface safety valves
Subsurface safety valvesAkhilesh Maurya
 
Drilling Lab - Mud Filtration
Drilling Lab - Mud FiltrationDrilling Lab - Mud Filtration
Drilling Lab - Mud FiltrationMuhammadSRaniYah
 
Q922+re2+l03 v1
Q922+re2+l03 v1Q922+re2+l03 v1
Q922+re2+l03 v1AFATous
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Q913 rfp w3 lec 12, Separators and Phase envelope calculations
Q913 rfp w3 lec 12, Separators and Phase envelope calculationsQ913 rfp w3 lec 12, Separators and Phase envelope calculations
Q913 rfp w3 lec 12, Separators and Phase envelope calculationsAFATous
 
Module 3 - Basic Equipment
Module 3 - Basic EquipmentModule 3 - Basic Equipment
Module 3 - Basic Equipmentriezqaandika
 
Water coning in oil wells and DWS technology
Water coning in oil wells and DWS technologyWater coning in oil wells and DWS technology
Water coning in oil wells and DWS technologyshubhamsaxena2329
 
Reservoir Rock Properties Laboratory Manual Exp (#3)
 Reservoir Rock Properties Laboratory Manual Exp (#3) Reservoir Rock Properties Laboratory Manual Exp (#3)
Reservoir Rock Properties Laboratory Manual Exp (#3)Muhammed Fuad Al-Barznji
 
METHODOLOGY FOR SLUG CATCHER SIZING
METHODOLOGY FOR SLUG CATCHER SIZINGMETHODOLOGY FOR SLUG CATCHER SIZING
METHODOLOGY FOR SLUG CATCHER SIZINGVijay Sarathy
 
Decline Curve - Bu Boni
Decline Curve - Bu BoniDecline Curve - Bu Boni
Decline Curve - Bu Boniguest0aa706
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingamaborig
 

What's hot (20)

Directional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdfDirectional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdf
 
Nodal Analysis introduction to inflow and outflow performance - next
Nodal Analysis   introduction to inflow and outflow performance - nextNodal Analysis   introduction to inflow and outflow performance - next
Nodal Analysis introduction to inflow and outflow performance - next
 
Intelligent well completion
Intelligent well completionIntelligent well completion
Intelligent well completion
 
Subsurface safety valves
Subsurface safety valvesSubsurface safety valves
Subsurface safety valves
 
Drilling Lab - Mud Filtration
Drilling Lab - Mud FiltrationDrilling Lab - Mud Filtration
Drilling Lab - Mud Filtration
 
Q922+re2+l03 v1
Q922+re2+l03 v1Q922+re2+l03 v1
Q922+re2+l03 v1
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Q913 rfp w3 lec 12, Separators and Phase envelope calculations
Q913 rfp w3 lec 12, Separators and Phase envelope calculationsQ913 rfp w3 lec 12, Separators and Phase envelope calculations
Q913 rfp w3 lec 12, Separators and Phase envelope calculations
 
Determination of porosity By Helium porosimeter
Determination of porosity By Helium porosimeterDetermination of porosity By Helium porosimeter
Determination of porosity By Helium porosimeter
 
Lecture 9 natural gas processes
Lecture 9 natural gas processesLecture 9 natural gas processes
Lecture 9 natural gas processes
 
Module 3 - Basic Equipment
Module 3 - Basic EquipmentModule 3 - Basic Equipment
Module 3 - Basic Equipment
 
psv specifications
psv specificationspsv specifications
psv specifications
 
thermal methods for eor recovery
thermal methods for eor recoverythermal methods for eor recovery
thermal methods for eor recovery
 
Helium Porosimeter
Helium Porosimeter Helium Porosimeter
Helium Porosimeter
 
Water coning in oil wells and DWS technology
Water coning in oil wells and DWS technologyWater coning in oil wells and DWS technology
Water coning in oil wells and DWS technology
 
Reservoir Rock Properties Laboratory Manual Exp (#3)
 Reservoir Rock Properties Laboratory Manual Exp (#3) Reservoir Rock Properties Laboratory Manual Exp (#3)
Reservoir Rock Properties Laboratory Manual Exp (#3)
 
METHODOLOGY FOR SLUG CATCHER SIZING
METHODOLOGY FOR SLUG CATCHER SIZINGMETHODOLOGY FOR SLUG CATCHER SIZING
METHODOLOGY FOR SLUG CATCHER SIZING
 
Decline Curve - Bu Boni
Decline Curve - Bu BoniDecline Curve - Bu Boni
Decline Curve - Bu Boni
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processing
 
Artificial Lift Methods
Artificial Lift MethodsArtificial Lift Methods
Artificial Lift Methods
 

Similar to Pipeline discretization (BHR Multiphase 2009)

Synthesis of pile driving data in South East Asia
Synthesis of pile driving data in South East AsiaSynthesis of pile driving data in South East Asia
Synthesis of pile driving data in South East AsiaCathie Associates
 
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...IRJET Journal
 
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...IRJET Journal
 
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...Fundació CTM Centre Tecnològic
 
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...ESS BILBAO
 
UT: A Review Of New Techniques
UT: A Review Of New TechniquesUT: A Review Of New Techniques
UT: A Review Of New TechniquesOlympus IMS
 
4 - Case studies 12Des09 for-print.ppt
4 - Case studies 12Des09 for-print.ppt4 - Case studies 12Des09 for-print.ppt
4 - Case studies 12Des09 for-print.pptazwararsyad
 
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...Jian Chen
 
IRJET- Intelligent Detection and Elimination of Blockage in Sewage pipes ...
IRJET-  	  Intelligent Detection and Elimination of Blockage in Sewage pipes ...IRJET-  	  Intelligent Detection and Elimination of Blockage in Sewage pipes ...
IRJET- Intelligent Detection and Elimination of Blockage in Sewage pipes ...IRJET Journal
 
High pressure full-bore flow meter
High pressure full-bore flow meterHigh pressure full-bore flow meter
High pressure full-bore flow meterFrank-Michael Jäger
 
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressExperimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressFrank-Michael Jäger
 
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressExperimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressFrank-Michael Jäger
 
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...Fundació CTM Centre Tecnològic
 
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...Jian Chen
 
Iisrt siddharth prabhu (electrical)
Iisrt siddharth prabhu (electrical)Iisrt siddharth prabhu (electrical)
Iisrt siddharth prabhu (electrical)IISRT
 
The future of CTF3
The future of CTF3The future of CTF3
The future of CTF3asafrona
 
UV-VIS SPECTRO final.ppt
UV-VIS SPECTRO final.pptUV-VIS SPECTRO final.ppt
UV-VIS SPECTRO final.pptJgdishrathi
 
tail gas H2S/SO2 analyzer
tail gas H2S/SO2 analyzer tail gas H2S/SO2 analyzer
tail gas H2S/SO2 analyzer Ugo Baggi
 

Similar to Pipeline discretization (BHR Multiphase 2009) (20)

Bhrg 2009 no_backup
Bhrg 2009 no_backupBhrg 2009 no_backup
Bhrg 2009 no_backup
 
Synthesis of pile driving data in South East Asia
Synthesis of pile driving data in South East AsiaSynthesis of pile driving data in South East Asia
Synthesis of pile driving data in South East Asia
 
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...
IRJET- Wave Ultrasonic Testing and how to Improve its Characteristics by Vary...
 
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
 
Santosh_Kr_Yadav_RAIM08
Santosh_Kr_Yadav_RAIM08Santosh_Kr_Yadav_RAIM08
Santosh_Kr_Yadav_RAIM08
 
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...
Ultrasonics inspections and confocal microscopy to evaluate fatigue damage in...
 
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...
ESS-Bilbao Initiative Workshop. PSI experience with high power beam handling,...
 
UT: A Review Of New Techniques
UT: A Review Of New TechniquesUT: A Review Of New Techniques
UT: A Review Of New Techniques
 
4 - Case studies 12Des09 for-print.ppt
4 - Case studies 12Des09 for-print.ppt4 - Case studies 12Des09 for-print.ppt
4 - Case studies 12Des09 for-print.ppt
 
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...
Graded-index Polymer Multimode Waveguides for 100 Gb/s Board-level Data Trans...
 
IRJET- Intelligent Detection and Elimination of Blockage in Sewage pipes ...
IRJET-  	  Intelligent Detection and Elimination of Blockage in Sewage pipes ...IRJET-  	  Intelligent Detection and Elimination of Blockage in Sewage pipes ...
IRJET- Intelligent Detection and Elimination of Blockage in Sewage pipes ...
 
High pressure full-bore flow meter
High pressure full-bore flow meterHigh pressure full-bore flow meter
High pressure full-bore flow meter
 
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressExperimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
 
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stressExperimentalstudy measurement of sonic speed of drilling muds under shear stress
Experimentalstudy measurement of sonic speed of drilling muds under shear stress
 
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...
Ultrasound inspections on glass fiber/phenolicresin and on carbon fiber/epoxy...
 
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...
Restricted Launch Polymer Multimode Waveguides for Board-level Optical Interc...
 
Iisrt siddharth prabhu (electrical)
Iisrt siddharth prabhu (electrical)Iisrt siddharth prabhu (electrical)
Iisrt siddharth prabhu (electrical)
 
The future of CTF3
The future of CTF3The future of CTF3
The future of CTF3
 
UV-VIS SPECTRO final.ppt
UV-VIS SPECTRO final.pptUV-VIS SPECTRO final.ppt
UV-VIS SPECTRO final.ppt
 
tail gas H2S/SO2 analyzer
tail gas H2S/SO2 analyzer tail gas H2S/SO2 analyzer
tail gas H2S/SO2 analyzer
 

Pipeline discretization (BHR Multiphase 2009)

  • 1. SDAG Discretization Methods for Multiphase Flow Simulation of Ultra-Long Gas-Condensate Pipelines Erich Zakarian & Henning Holm Shtokman Development A.G. www.bhrgroup.co.uk 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 2. SDAG Contents • The Shtokman field development • Profile discretization of gas-condensate pipelines • Objective and requirements • Method 1 – concept of pipeline profile indicator • Method 2 – concept of lumping and redistribution • Comparison and simulation • Conclusions 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 3. SDAG Integrated Development of the Shtokman Gas-Condensate Field – Phase 1 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 4. SDAG Gas export to shore • 70 MSm3/d (2.5 BCFD) – Phase 1 • 2 x 36” ND trunklines (0.86 m ID) • Length 558 km (347 miles) Shtokman • Dry two-phase flow Teriberka • CGR = from 2 to 16 Sm3/MSm3 Murmansk Paris Cannes 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 5. SDAG Shtokman pipeline profile 200 100 Elevation [m] 0 -100 -200 -300 -400 0 100 200 300 400 500 Distance [km] • Detailed pipeline profile from seabed bathymetry survey (2007) • Free span analysis and seabed intervention taken into account 108,785 points 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 6. SDAG Pipeline profile discretization: objective Given either as-built profile or detailed terrain survey • In transient multiphase flow simulation, the actual or expected pipeline geometry must be simplified to achieve reasonable CPU time • For long pipelines (> 100 km) laid on rough terrain, compression of a large set of data points is required typically from 104-105 points to few 103 points Target  Simulation time ≥ 24 x CPU time 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 7. SDAG The Shtokman case Target ≈ 2500 pipes for a total length of 554 km • Average pipe length will be approximately 200 m • Avoid small pipe sections to maximize numerical time steps Δt < min (Δx/U)i 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 8. SDAG Pipeline profile discretization: requirements 1. The total pipe length must be conserved 2. The simplified geometry must have the same overall shape (large and small scale undulations) 3. The pipe angle distribution of the discretized profile must be as close as possible to the original distribution 4. The total climb (cumulative length of uphill pipes) must be conserved to predict the same overall liquid content in steady-state flow conditions 1 3 2 4 Original profile 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 9. SDAG Liquid5.3: liquid holdupvs. pipe inclination velocity OLGAS holdup vs. pipe  inclination and gas superficial USL=0.003 m/s -  G=180 kg/m3 - o=775 kg/m3 - m G=0.02 cP - m O=2.5 cP =0.0025 N/m - Wall roughness=30 mm - Inner diameter=0.9906 m 0.70 0.60 USG = 1.00 m/s Liquid holdup [-] USG = 1.50 m/s 0.50 USG = 2.00 m/s 0.40 USG = 2.50 m/s USG = 3.00 m/s 0.30 USG = 3.50 m/s USG = 4.00 m/s 0.20 USG = 4.50 m/s 0.10 0.00 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 Pipe inclination [deg] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 10. SDAG Two methods for a single objective Method 1: concept of pipeline profile indicator • Select, simplify and complexify relevant sub-profiles • Use the pipeline profile indicator and the total climb to match the original angle distribution Method 2: concept of lumping elements with similar inclination • Redistribution to match the original large & small scale topographies 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 11. SDAG Method 1 Concept of pipeline profile indicator 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 12. SDAG Definition: pipeline profile indicator  Holdupi   Holdup0 Li N i 1 PI  N  1000  Li i 1 Holdup i    Arctan1.9   i  1.66  0.25 0.49  θi = inclination of pipe i with respect to horizontal [%] Li = length of pipe i [m] N = number of pipes B. Barrau, “Profile indicator helps predict pipeline holdup, slugging”, Oil & Gas Journal Vol. 98, Issue 8, p. 58-62, Feb 21, 2000 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 13. SDAG OLGAS 5.3: liquid holdup vs. pipe inclination and gas superficial velocity Holdup function vs. OLGAS USL=0.003 m/s -  G=180 kg/m3 - o=775 kg/m3 - m G=0.02 cP - m O=2.5 cP =0.0025 N/m - Wall roughness=30 mm - Inner diameter=0.9906 m 0.70 0.60 Holdup function USG = 1.00 m/s Liquid holdup [-] 0.50 USG = 1.50 m/s USG = 2.00 m/s 0.40 USG = 2.50 m/s USG = 3.00 m/s 0.30 USG = 3.50 m/s USG = 4.00 m/s 0.20 USG = 4.50 m/s 0.10 0.00 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 Pipe inclination [deg] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 14. SDAG Pipeline profile indicator scale From Total E&P experience in gas-condensate pipeline design and operation Pipeline profile is globally sloping downwards PI < 0 No particular operating problem to be expected Pipeline profile is nearly horizontal or over-simplified 0 < PI < 20 No particular operating problem to be expected Pipeline profile is relatively flat or slightly hilly 20 < PI < 40 Possible troubles at very low flow rates or during restart Pipeline crosses hilly terrain 40 < PI < 80 Design & Operation needs particular attention Pipeline profile is very hilly or very steep 80 < PI Design & Operation needs very careful attention Validity of simulation software to be checked Shtokman pipeline profile indicator = 79.7 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 15. SDAG Step 1: sub-profile selection Pipe inclination Pipe inclination 10 10 8 8 Inclination [deg] Inclination [deg] 6 6 4 4 2 2 0 0 -2 -2 -4 -4 -6 -6 -8 -8 -10 -10 230000 240000 250000 260000 270000 280000 410000 420000 430000 440000 450000 460000 Distance from offshore platform [m] Distance from offshore platform [m] 180 Pipeline indicattor [-] 160 140 120 100 80 60 40 20 0 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 16. SDAG Step 2: simplification of the original profile • Final average pipe length should be about 200 m (target ≈ 2500 pipes) • For example, use the Box Filter from OLGA® Geometry Editor • Or simply select one point every 1 km 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 17. SDAG Step 2: result Pipeline geometry 200 5000 Pipe elevation (simplified profile) [m] 4500 Total climb [m] 100 Pipe elevation (original profile: 108,785 points) [m] 4000 Elevation [m] 0 Total climb (original profile: 108,785 points) [m] 3500 Total Climb (simplified profile) [m] 3000 -100 2500 2000 -200 1500 -300 1000 500 -400 0 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] PI = 79.7 Pipe inclination 25.8 20 Pipe inclination (original profile: 108,785 points) [deg] 15 Inclination [deg] Pipe inclination (simplified profile) [deg] 10 5 0 -5 -10 -15 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 18. SDAG Step 3: complexification • Split the simplified profile into smaller pipes 5 smaller pipes per simplified pipe  pipe length ≈ 200 m • Move new points up and down with a random process cum Pipeline geometry Inverse of the standard normal -305 4 Complexified profile -310 3 Simplified profile -315 For each sub-profile 2 Elevation [m] -320 • Keep original pipeline 1 NormStd-1 -325 indicator within +/-1% 0 -330 • Keep original total climb -1 within +/- 1% -2 -335 -3 -340 -4 0 2000 4000 6000 8000 10000 0 0.1 0.2 0.3 0.4 0.5 0.6 Distance from offshore platform [m] Probability 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 19. SDAG Step 3: result Pipeline geometry 200 5000 Pipe elevation (complexified profile) [m] 4500 Total climb [m] 100 4000 Elevation [m] Pipe elevation (original profile: 108,785 points) [m] 0 Total climb (complexified profile) [m] 3500 Total climb (original profile: 108,785 points) [m] 3000 -100 2500 2000 -200 1500 -300 1000 500 -400 0 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] Pipe inclination 20 Pipe inclination (original profile: 108,785 points) [deg] 15 Inclination [deg] Pipe inclination (complexified profile) [deg] 10 5 0 -5 -10 -15 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 20. SDAG Method 2 Concept of lumping elements with similar inclination 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 21. SDAG Method 2 – “Lumping and redistributing” 1. Define the criteria (in priority) to determine the pipe length to be used for the simplified profile : 1. minimum pipe length 2. maximum elevation change for a pipe element 3. maximum pipe length 2. Sort all elements in the detailed profile by inclination in ascending order 3. Lump together the sorted elements to longer pipes, starting with the element with the steepest downhill inclination. The length of each pipe element is then limited by dominating criteria in 1). 4. Distribute the pipe elements in the simplified profile to match the large scale and small scale topography of the detailed profile. 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 22. SDAG Step 1) Define the criteria (in priority) to determine the pipe length to be used for the simplified profile : 1. minimum pipe length (200 m) 2. maximum elevation change for a pipe element (5 m) 3. maximum pipe length (1000 m) 25 1000 20 Elevation change of single pipe 900 15 Pipe length 800 Pipe elevation change (m) Elevation change (m) 10 700 Pipe length (m) 5 600 Maximum elevation change 0 500 -5 400 -10 300 -15 200 -20 100 -25 0 Xmin Xmax -8 -6 -4 -2 0 2 4 6 8 Pipelength (m) Pipe inclination (deg) 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 23. SDAG Step 2) Sort elements in the detailed profile by inclination in ascending order – divide into 0subsections if required -200 Elevation (m) -400 -600 -800 -1000 -1200 0 100000 200000 300000 400000 500000 600000 Distance (m) -200 5 -300 4 -400 Original profile 3 Inclination (deg) -500 2 Elevation (m) -600 -700 Inclination 1 0 Step 3) -800 -1 Lump together the sorted elements to -900 -2 -1000 -3 longer pipes, starting with the element -1100 Lumped, but not redistributed profile -4 -1200 -5 with the steepest downhill inclination. 0 50000 100000 The length of each pipe element is then Distance (m) limited by dominating criteria in 1). 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 24. SDAG ”Inclination classes” versus ”lumping by inclination in ascending order ” 600000 2000 grouping by inclination classes Original profile 20-70 km Lumping by inclinations in 1800 'lumping by inclination in ascending order' 500000 ascending order 1600 'Sorted by inclination classes' Condensate content [m3] 1400 Accumulated length (m) 400000 1200 300000 1000 800 200000 600 400 100000 200 0 0 -5 -4 -3 -2 -1 0 1 2 3 4 5 30 35 40 45 50 55 60 65 70 Inclination (deg) Export flow rate [MSm3/d] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 25. SDAG Step 4) Redistribution of elements by “Simulated Annealing” (Travelling salesman problem) “minimize distance between detailed profile and simplified profile” 0 -200 Elevation (m) -400 Cost function: -600 -800 F ( y)  i wi  ( yi  yi ) 2 -1000 -1200 0 100000 200000 300000 400000 500000 600000 Distance (m) 0 yi : values from the simplified profile -50 -100 Elevation (m) -150 -200 ŷi : values from the detailed profile -250 -300 -350 -400 0 100000 200000 300000 400000 500000 600000 wi : weight factor Distance (m) -230 where as “i” denotes: -240 Elevation (m) -250 -260 1) Elevation -270 -280 -290 2) “Total Climb” -300 70000 75000 80000 85000 90000 95000 100000 Distance (m) 3) “Pipeline Indicator” * 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 26. SDAG Comparison Original Simplified Method 1 Method 2 profile profile profile profile Number of pipes 108,784 554 2,766 2,550 Pipeline profile indicator 79.7 25.8 80.3 80.3 Total climb [m] 4,187 1,235 4,180 4,187 Total length [m] 554,505 554,400 554,507 554,505 Pipeline geometry -230 -240 Elevation [m] -250 -260 -270 -280 -290 -300 Original profile 70000 75000 80000 85000 90000 Simplified profile 95000 100000 Discretized profile (method 1) Distance from offshore platform [m] Discretized profile (method 2) 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 27. SDAG Angle distributions Pipe angle distribution 80000 Total pipe length per angle group [m] Original profile 70000 Discretized profile (Method 2) Discretized profile (Method 1) 60000 Simplified profile 50000 40000 30000 20000 10000 0 1) 5) 5) ) ) ) (-3 0) (-1 ) ) ) ) ) ) ) ) ) 1) 20 90 0 ,5 ,7 ,9 ,2 ,3 -5 25 .2 .4 .0 .2 .7 -6 -2 ,- ,0 ,0 (4 (6 (8 0, 0. .5 .5 0, 0, ,0 ,1 ,0 (-2 0, 0, (1 (2 ,- .1 .3 (1 (3 (0 (1 .5 (-9 (0 (0 .5 (0 (-0 Pipe angle group [deg] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 28. SDAG Steady-state simulation: original vs. discretization Condensate content vs. export flow rate 42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor 2000 Original profile 20-70 km 1800 Discretized profile 20-70 km (Method 1) Condensate content [m3] 1600 Discretized profile 20-70 km (Method 2) 1400 1200 1000 800 600 400 200 0 30 35 40 45 50 55 60 65 70 Export flow rate [MSm3/d] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 29. SDAG Steady-state simulation: simplified vs. discretization Total condensate content vs. export flow rate 42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor 10000 200 Total condensate content (simplified profile) Total condensate content (method 1) 9000 Total condensate content (method 2) Total condensate content [m3] Inlet pressure (simplified profile) 180 8000 Inlet pressure (method 1) Inlet pressure (method 2) Inlet pressure [bara] 7000 160 6000 5000 140 4000 120 3000 2000 100 1000 0 80 20 25 30 35 40 45 50 55 60 65 70 Export flow rate [MSm3/d] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 30. SDAG Conclusions • Simplification of long and rough gas-condensate pipeline profiles is a key issue for correct design • Two methods were introduced for the development of the Shtokman field – Phase 1 • Essential characteristics of the original detailed pipeline profile are conserved: Length + Topography + Angle distribution + Total climb • The hydrodynamic behavior of the original profile is conserved through both methods despite significant data compression 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 31. SDAG Discretization Methods for Multiphase Flow Simulation of Ultra-Long Gas- Condensate Pipelines Erich Zakarian, Henning Holm Shtokman Development A.G., Russia erich.zakarian@total.com, hthol@statoilhydro.com Dominique Larrey Total E&P, Process Department, France dominique.larrey@total.com 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 32. SDAG Back-up 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 33. SDAG Why discretization is so important? Total condensate content vs. export flow rate Poor discretization 42" ND pipeline - Fluid: 50%J0/50%J1 - OLGA steady-state pre-processor 10000  Incorrect design of 9000 Simplified profile receiving facilities Total condensate content [m3] Discretized profile (Method 1) 8000 Discretized profile (Method 2)  Wrong operating 7000 6000 envelope 5000  Reduced operating 4000 flexibility 3000 2000  Higher risk of 1000 continuous flaring 0  Wrong model tuning 20 30 40 50 60 70 Export flow rate [MSm3/d] against field data 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 34. SDAG Seabed profile 200 100 Elevation [m] 0 -100 -200 -300 3D Side Scan Sonar imagery -400 0 100 200 300 400 500 Distance [km] Ice scours & Pockmarks depressions Elongated pockmarks Ridges & ice scours 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 35. SDAG Total climb • Total climb = cumulative length of uphill pipes • Helpful indicator as a first check • Relevant indicator in addition to the pipeline profile indicator to match the original angle distribution Shtokman original pipeline profile (2007 survey) Total climb = 4187 m 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 36. SDAG Comparison of the discretization methods Pipeline geometry 200 5000 Pipe elevation (discretized profile: first method) [m] 100 Total climb [m] Pipe elevation (discretized profile: second method)[m] 4000 Elevation [m] 0 Total climb (discretized profile: first method) [m] Total climb (discretized profile: second method) [m] 3000 -100 2000 -200 -300 1000 -400 0 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] Pipe inclination (discretized profile: first method) [m] Pipe inclination 10 8 Pipe inclination (discretized profile: second method) [m] 6 Inclination [deg] 4 2 0 -2 -4 -6 -8 -10 0 100000 200000 300000 400000 500000 Distance from offshore platform [m] 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009
  • 37. SDAG OLGA® Geometry Editor • Ok for removing noise from as-built Box filter pipeline survey • Not recommended for hilly pipelines Angle • Requires pre-definition of angle groups • Several tries are necessary distribution • Extremely difficult or even impossible to preservation satisfy the four criteria 14th International Conference Multiphase Production Technology Cannes, France - 17th - 19th June 2009