1. Work Progress
7th
May – 8th
June
Greenfieldtelephonesupport/additional changes(CJ approved)
Eye ointmentCare plan added
WaitingList amendment
Leg Ulcerrota slotsamended
Quick note functionaddedto DNs unit (Janetrice currentlytesting)
Resolvedwhy missedvisitsdisappearedoffthe face of the earth (inquestion)
Initial Care plan amendment
Overall = 100%
Data migration
Cross checked150 patients(RiO to SystmOne)
Overall = 100%
SystmOne Organisation structure (Reporting/Config)
Set up Strategic reportinggroup
Set up Adult/Childrenparentgroup
I have liaisedwithAlex,Reportingteam & the projectspecialistto give my knowledge on
where we are at withstructure of the system.
Configurationof a strategic Report scheduledjobto run everyday at 02:30 AM
Testingof strategic download pulledintofolderscorrectly
Further strategic report configuration(Delta/full downloads)
Overall = 100%
SpecialistservicesConfig(Podiatry)
1 questionnaire
6 Assessmentscreated& completed,1 outstanding assessment(mayneedAccenture
resource)
34 letterscreated & completed,3 lettersoutstanding
Documentation20/05/15
Overall = 100%
SpecialistservicesConfig(Learningdisability)
1 Template complete
5 Letterscomplete
Documentation20/05/15
Overall = 85%
0-19 Config(ChildHealthy weight)
1 Questionnaire complete
4 letterscomplete
Documentationreceived04/06/15
Overall = 85%