The document discusses the proper design and installation of solar systems. It emphasizes that accurate surveys, good design, proper installation, and regular maintenance are needed for an excellent solar system. The key steps include surveying the location and load, selecting critical components like the solar panel, inverter, and batteries, and safely installing all equipment. Design examples are also provided for solar systems with varying levels of grid support. Proper safety precautions during installation are stressed.
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
Â
Solar Installation and Design: Dos and Don'ts
1. SOLAR INSTALLATION AND DESIGN: THE DOS AND DONâTS
POWER NIGERIA 2017
Engr. Tajudeen Humble Sikiru (PhD)
Electrical Engineering Department, Ahmadu Bello University, Zaria.
Rana World Tech Shop Limited, Kaduna, Nigeria
1
2. 8-Sep-17 2
Accurate Survey data + Good Design + Good Installation + Regular Maintenance = Excellent Solar System
3. ďSurvey: Location and Load parameters
⢠Know your solar installation location
⢠Accurately determine the load size
8-Sep-17 Power Nigeria 2017 3
4. ďSurvey:
⢠Use Google earth to determine roof top space and orientation
⢠Alternatively, physically measure and determine available space
8-Sep-17 Power Nigeria 2017 4
5. 8-Sep-17 5
Solar Design: Critical Component Selection (Solar panel)
i. Solar Panel Selection:
a. Monocrystalline Vs Polycrystalline
b. What does the data sheet means?
c. Beyond the price, what do engineers lookout for?
Power Nigeria 2017
Polycrystalline
Monocrystalline
6. 8-Sep-17 6
i. Solar Panel Selection:
a. What do engineers lookout for?
b. price factor?
Power Nigeria 2017
Solar Design: Critical Component Selection (Solar panel)
Manufacturer A
Manufacturer B
7. 8-Sep-17 7
i. Solar Panel Selection:
a. What do engineers look at for?
b. price factor?
Power Nigeria 2017
Solar Design: Critical Component Selection (Solar panel)
Manufacturer A
Manufacturer B
8. 8-Sep-17 8Power Nigeria 2017
Solar Design: Critical Component Selection (Solar panel)
Manufacturer B
Manufacturer A
9. 8-Sep-17 9
ii. Inverter Selection
a. What is the purpose of technical data sheet?
b. Beyond what the manufacturers claims?
c. Effect of wrong inverter on system performance?
d. Right inverter Vs price?
Solar Design: Critical Component Selection (Inverters and Mppt Charge
controllers)
Power Nigeria 2017
Manufacturer A
Manufacturer B
10. 8-Sep-17 10
What is the purpose of technical data sheet?
Solar Design: Critical Component Selection (Inverters and Mppt Charge
controllers)
Power Nigeria 2017
Manufacturer A
Manufacturer B
11. 8-Sep-17 11
The purpose of technical data sheet?
Solar Design: Critical Component Selection (Inverters and Mppt Charge
controllers)
Power Nigeria 2017
Manufacturer A
Manufacturer B
a. Effect of wrong inverter on system performance?
ďą Premature damage of battery bank
ďą Damage of sensitive equipment
b. Right inverter Vs price?
ďą Application dependent
ďą At least know what you are expecting
12. 8-Sep-17 12
The Effect of Battery Algorithm on
Battery Lifespan?
Solar Design: Critical Component Selection (Inverters and Mppt Charge
controllers)
Power Nigeria 2017
Manufacturer A
Manufacturer B
13. 8-Sep-17 13
ii. Critical Questions Before Battery Selection:
Question 1
Battery type ?:
Maintenance Free Maintenance Required
e.g. Gel, AGM e.g. Flooded
Question 2
Battery use ?:
Low starting current loads High starting current loads
e.g. TV, lighting point, home appliances e.g. Air conditioners, induction machines
Question 3
Expected period of use (autonomy)?
Question 4
Is the number of string less than or equal to 3 per battery bank?
Solar Design: Critical Component Selection (Battery Bank)
Power Nigeria 2017
14. 8-Sep-17 14
Effect of duty cycles on battery life span:
Solar Design: Critical Component Selection (Battery Bank)
Power Nigeria 2017
Manufacturer A
Manufacturer B
15. 8-Sep-17 15
Effect of temperature on battery life span:
Solar Design: Critical Component Selection (Battery Bank)
Power Nigeria 2017
16. 8-Sep-17 16
battery selection based on capacity:
Solar Design: Critical Component Selection (Battery Bank)
Power Nigeria 2017
Manufacturer A
Manufacturer B
17. 8-Sep-17 17
SOLAR DESIGN EXAMPLES
A 3 bedroom flat has the loads indicated in Table 1,
design:
i. A solar solution with 6 hours grid/generator
support
ii. A solar solution with 12 hours grid/generator
support
iii. A solar solution totally off grid
Power Nigeria 2017
18. 8-Sep-17 18
SOLAR DESIGN EXAMPLES
Power Nigeria 2017
s/n Description of load Number Power
consumption
(W)
Hours of use
(h)
Energy
consumption
(kWh)
1 Television/radio/decoder 4 250 5 5
2 Fan 5 75 12 4.5
3 Air conditioner 2 1400 4 11.2
4 Lighting (bulbs) 18 26 12 5.6
5 Washing machining 1 800 3 2.4
6 Water pump 1 1200 2 2.4
Total 6.57 kW 31.1 kWh/day
Diversity factor =0.65 4.27 kW 20.2 kWh/day
6 hours of grid/generator 5.05 kWh/day
12 hours grid/generator 10.1 kWh/day
19. 8-Sep-17 19
SOLAR DESIGN 1 (6 hours of grid/generator support)
Power Nigeria 2017
Location : Abuja
1. 15.15 kWh/day is the minimum power generation from the solar system
2. 50 % Depth Of Discharge (DOD) of battery per day (i.e. Battery bank capacity =30.3 kWh)
3. 1 day autonomy of the battery back up system
Design:
1. Assumed all system loses of 15% (AC and DC cables +inverter)
2. In Abuja, 1 kWp solar system will generate 3.8 kWh per day, hence 4kWp solar system must be installed.
3. 265 W panel was selected , then we need 15 number panels
4. The selected panel has Voc = 37.8V, Isc =9.01 A, we use this information to select charge controller, we could select 150V, 60A or 600 V, 80A or 5kW
grid tied PV inverter
5. We could select 4.6 kW or 5.5 kW battery inverter
6. Expected battery capacity bank =30.3 kWh
7. The selected inverter is 48 V, DC input, we need 24 number of battery @ C10 ( 2 V, 700 Ah). We could select OPZV 750 , OPZV, 2-770.
8. or
9. We could select an alternative battery that would be max. of 2 string.@ C10 (2V, 350 Ah). But we need 48 numbers of batteries.
20. 8-Sep-17 20
SOLAR DESIGN 2 (12 hours of grid/generator support)
Power Nigeria 2017
Location : Abuja
1. 10.1 kWh/day is the minimum power generation from the solar system
2. 50 % Depth Of Discharge (DOD) of battery per day (i.e. Battery bank capacity =20.12kWh)
3. 1 day autonomy of the battery back up system
Design:
1. Assumed all system loses of 15% (AC and DC cables +inverter)
2. In Abuja, 1 kWp solar system will generate 3.8 kWh per day, hence 2.65kWp solar system must be installed.
3. 265 W panel was selected , then we need 10 number panels
4. The selected panel has Voc = 37.8V, Isc =9.01 A, we use this information to select charge controller, we could select 150V, 60A or 2.5 kW grid tied PV
inverter
5. We could select 4.6 kW or 5.5 kW battery inverter
6. Expected battery capacity bank =20.12kWh
7. The selected inverter is 48 V, DC input, we need 24 number of battery @ C10 ( 2 V, 500 Ah). We could select OPZV 520 , OPZV, 2-500.
8. Or
9. We could select an alternative battery that would be max. of 2 string @ C10 (2V, 250 Ah). But we need 48 numbers of batteries.
21. 8-Sep-17 21
SOLAR DESIGN 3 ( totally off grid)
Power Nigeria 2017
Location : Abuja
1. 20.2 kWh/day is the minimum power generation from the solar system
2. 50 % Depth Of Discharge (DOD) of battery per day (i.e. Battery bank capacity = 40.4 kWh)
3. 1 day autonomy of the battery back up system
Design:
1. Assumed all system loses of 15% (AC and DC cables +inverter)
2. In Abuja, 1 kWp solar system will generate 3.8 kWh per day, hence 5.3 kWp solar system must be installed.
3. 265 W panel was selected , then we need 20 number panels
4. The selected panel has Voc = 37.8V, Isc =9.01 A, we use this information to select charge controller, we could select 2 number of 150V, 60A or 1
number of 5.3 kW grid tied PV inverter
5. We could select 4.6 kW or 5.5 kW battery inverter
6. Expected battery capacity bank =40.4kWh
7. The selected inverter is 48 V, DC input, we need 24 number of battery @ C10 ( 2 V, 900 Ah). We could select OPZV 1000 , OPZV, 2-1000.
8. or
9. We could select an alternative battery that would be max. of 2 string @ C10 (2V, 500 Ah). But we need 48 numbers of batteries.
22. ďPersonal Protective Equipment (PPE)
⢠Your Safety is Your Responsibility
⢠Safety is Everyoneâs Responsibility on Site
8-Sep-17 Power Nigeria 2017 22
23. ďMounting System & Panel Installation
⢠What is the roof integrity?
What is the orientation and nature of the roof ?
⢠Does wind speed pose a threat?
⢠Donât walk on the panels, youâll cause
micro cracks
8-Sep-17 Power Nigeria 2017 23
24. ď The danger of bad Solar Panel Installation:
⢠Fire
⢠Death
⢠Electrocution
⢠Law suits
⢠Equipment damage
8-Sep-17 Power Nigeria 2017 24
25. ď Inverter and Mppt Charge Controller Installation
⢠Inverter must be mounted on a solid
Strong wall or metal frame
â˘
⢠DC cables must be separated from AC cables
⢠Communication cables must be separated from power cables
⢠Make your installation neat as must as possible
8-Sep-17 Power Nigeria 2017 25
26. ď Inverter and Mppt Charge Controller Installation
⢠Provide the customer with a
detailed wiring diagram for ease
of maintenance
⢠As built diagram must be accurate
⢠As built diagram must be simple to read
8-Sep-17 Power Nigeria 2017 26
27. ď Battery bank Installation
⢠Never place tools or metal components on Batteries
⢠Ensure that batteries are not mistakenly grounded
⢠Never smoke or handle flames near batteries
⢠Always use the correct cable size
8-Sep-17 Power Nigeria 2017 27
32. SOLAR INSTALLATION AND DESIGN: THE DOS AND DONâTS
THANK YOU FOR LISTENING
POWER NIGERIA 2017
Engr. Tajudeen Humble Sikiru (PhD)
Electrical Engineering Department, Ahmadu Bello University, Zaria.
Rana World Tech Shop Limited, Kaduna, Nigeria
32