SlideShare a Scribd company logo
1 of 14
An Overview of the Radiological
Environmental Monitoring System
(REMS) for ITER Preliminary Design
Presented by Dijesh Das
C&I Engineer
AMEC Clean Energy
11 February 2014
REMS provides health and radiological monitoring for workers as well as environmental
monitoring for the public, assisting in the protection against ionizing radiation, during the
whole life of ITER starting from construction until operations and decommissioning. The
environmental monitoring programme ensures compliance with the French
Environmental Regulation and allows calculation of doses to the public.
The radiological monitoring for workers includes the following:
• Radiation and Contamination Monitoring
• Sampling
• Alarm handling
• Measuring and limiting individual and accumulative doses to workers within the
Radiological Controlled Areas at ITER
• Beryllium monitoring
• Radiological monitoring for the environment of effluents (gaseous and liquid) release
monitoring & sampling.
In addition, the trigger detectors for the HVAC isolation and connection to the Detriation
system and the tritium detectors in the Port Cells to initiate a cleaning action by the
Detriation System are included.
Overview of Radiological and Environmental Monitoring Systems
(REMS)
Overview of Radiological and Environmental Monitoring Systems
(REMS)
Overview of Radiological and Environmental Monitoring Systems
(REMS)
The REMS comprise of Safety Important Class (SIC) components within some of
the Sub-systems which have a Safety Classification based on the Safety Important
Function that is intended that the component shall provide to protect from an
unsafe event. These are shown below:
Health Physics
• Area Radiological Monitoring (SIC‐2)
• Release Radiological Monitoring (SIC‐1)
• Environmental Monitoring (SR)
• Individual Monitoring (SR)
• Area Beryllium Monitoring (SIC‐2)
• Laboratories
Process Control
• Tritium HVAC/DS (SIC‐1)
• T Port Cell (SR)
ITER System Design & Procurement Arrangement Process
In order to manage the procurement of the systems the ITER project has been sub-divided
into a number of Procurement Packages and distributed to Seven-ITER Parties. There are
currently 30 Plant Breakdown items that form part of a Plant Breakdown Structure (PBS)
where each of the Products are controlled under a Procurement Arrangement (PA) for each
of the parties.
Product Breakdown Structure
ITER System Design & Procurement Arrangement Process
REMS PBS 64 procurement package is a function specification type of PA
ITER ORGANISATION (IO) is responsible of the system development up to the Concept
Design where this is handed over as part of the PA Process to F4E who are responsible of
the preliminary (outsourced to AMEC through framework), & final designs, procurement,
installation and commissioning of the different systems, sub‐systems and equipments
throughout the design lifecycle.
F4E is in charge for the detailed design, procurement, manufacturing, transport, testing and
commissioning of the Radiological and Environmental Monitoring Systems (REMS).
ITER Organisation – ‘Concept Design’ Procurement Arrangement– ‘Detailed Design’
F4E Framework – ‘Preliminary Design’
ITER System Design & Procurement Arrangement Process
Purpose of the Preliminary Design Phase for REMS PA
AMEC are to carry out the Preliminary Design (PD) of the REMS in accordance with Task
Order 1 Lot 2 in line with the PA milestone by achieving PD Baselines which will allow it
to carry on to the next phase of the PA sequence (Final Design). The purpose of the PD
phase is to achieve the following:
 To review the outcome of the CD review meeting together with the issued CHITS – to
identify any outstanding issues and propose solutions to update the proposed CD.
This has been confirmed as completed by F4E.
 To consider whether consolidated System Requirements Document (SRD) from CD is
currently valid and achievable during the PD – this can be done by initially performing
a review of the requirements (for e.g. the applicable list of Codes and Standards and
whether they are current and where necessary shall be requested/recommended to be
updated during the design lifecycle). Note: Do Not Change the SRD Requirements
in the current version, including those that are not fixed. At the end of the PD
phase a new version of the SRD shall be provided for IO and F4E’s review and
approval, together with appropriate justifications for changes.
Delivery of the Preliminary Design Phase for REMS PA
• Develop the REMS PD package with the required design documents and drawings up
to PD maturity for PDR – by preparing the PDR documentation package by updating
the available documents from CD and by compiling new documents relevant for the PD
package. The main documents to be produced as part of the PD package are required
to include the following:
Requirements (SRD, ICD, ISs, CMMs, etc)
Description (DD, RAMI, Load Specs, PFDs, etc)
Operation and Testing (Ops Plan, Maintenance Plan, etc)
Justification (DCM, DR and Recommendations, DJP, etc)
Test and Comissioning (On-site Assembly Plan, etc)
Design Management (Risk Assessment, Work Plan, etc)
Along with detailed specific technical requirements which demonstrate the following:
Classification (Safety, Quality, Seismic and I&C)
Licensing Requirements (Electrical Compliance, etc)
Applicable Code & Standards (Seismic, etc)
System Specific Requirements (See TO1 278RAD/2.1)
Baseline of the Preliminary Design Phase for REMS PA
By the end of the PD phase we should have achieved the following:
• Refined CD to confirm whether the system is feasible, achievable and its robustness
against its production schedule by substantiating it in the PD package.
• Updated DD with detailed schematics and component definition.
• Updated and provided justification documents from CD demonstrating the technical
requirements that have been achieved.
• Manufacturing, Assembly, Qualifications will have been addressed.
• Be able to freeze Interface Specifications (assumptions, ranges and current data) as
the design achieves the right level of maturity during PD.
• Produced a plan for future steps of justification (Test for Mock-ups, verification
planning etc)
• Re-assessed the technical risk of the selected solution and provided a mitigation plan.
• Periodically checked the PD package against the requirements with verification.
Things we will Require to carry out the PD are:
• System Requirements Documents
• Configuration Management Models
• Concept Detailed Design Description
• Concept Drawing/Documents
• ITER/F4E Processes and Quality Management Material
• Working Instruction
Baseline of the Preliminary Design Phase for REMS PA
Preliminary Design Phase for REMS PA
‘An Example of a Baseline Model of the I&C for CODAC
throughout the Design Lifecycle ’
5-Box Model for Preliminary Design Phase for REMS PA
Preliminary Design TO
•Requirements
•Description
•Justification
•Operation and Testing
•Assessments
•Calculations
•Detailed Development
of Drawings and
Documents
•etc
Concept Design
Documents
•CMMs
•SRD
•Concept DD
•Concept ICD
•Concept ISs
•etc
New Material for
Preliminary Design
•PD Requirements
•Current French
Regulation Codes and
Standards
•Current TER /F4E
Processes
•etc
Preliminary Design
CD Updated Documents
•Updated Drawings and
Documents
•Updated Concept DD
•etc
Preliminary Design
New Deliverables
• Recommendations and
Requests for Design
Changes
• PD SRD
• New PD Drawings and
Documents
• Qualification and
Material
•etc
Design Input Design Output
PD Functional
Specification
Lets start the PD of REMS!
AOB

More Related Content

What's hot

Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)SAJJAD KHUDHUR ABBAS
 
HumphriesFarinStandardResume
HumphriesFarinStandardResumeHumphriesFarinStandardResume
HumphriesFarinStandardResumefarin humphries
 
Performance Testing Checklists
Performance Testing ChecklistsPerformance Testing Checklists
Performance Testing ChecklistsJames Venetsanakos
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)SAJJAD KHUDHUR ABBAS
 
Resume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceResume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceDHRUVA MISHRA
 
20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R SargeantRoy Sargeant
 
Episode 32 : Project Execution Part (3)
Episode 32 :  Project Execution Part (3)Episode 32 :  Project Execution Part (3)
Episode 32 : Project Execution Part (3)SAJJAD KHUDHUR ABBAS
 
Facility Upgrade V2
Facility Upgrade V2Facility Upgrade V2
Facility Upgrade V2Rose Buot
 
PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial ControlEmerson Exchange
 
Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Stephanus Roux C Eng , IntPE(uk) , FIET
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation inacatrine
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...Swamy Shettru
 

What's hot (20)

Moc for lcl
Moc for lclMoc for lcl
Moc for lcl
 
Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)
 
Moc for lcl
Moc for lclMoc for lcl
Moc for lcl
 
HumphriesFarinStandardResume
HumphriesFarinStandardResumeHumphriesFarinStandardResume
HumphriesFarinStandardResume
 
MAINTENANCE MANAGEMENT
MAINTENANCE MANAGEMENT MAINTENANCE MANAGEMENT
MAINTENANCE MANAGEMENT
 
019113
019113019113
019113
 
Performance Testing Checklists
Performance Testing ChecklistsPerformance Testing Checklists
Performance Testing Checklists
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
 
Resume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceResume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experience
 
20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant
 
Episode 32 : Project Execution Part (3)
Episode 32 :  Project Execution Part (3)Episode 32 :  Project Execution Part (3)
Episode 32 : Project Execution Part (3)
 
Facility Upgrade V2
Facility Upgrade V2Facility Upgrade V2
Facility Upgrade V2
 
PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial Control
 
Control System - execution plan
Control System - execution planControl System - execution plan
Control System - execution plan
 
Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...
Introduction to DO-178B - Software Considerations in Airborne Systems and Equ...
 
Tab
TabTab
Tab
 
Rbi final report
Rbi final reportRbi final report
Rbi final report
 

Viewers also liked

Raspberry pi jam
Raspberry pi jamRaspberry pi jam
Raspberry pi jamJon Ho
 
Environmental Monitoring With a Raspberry Pi - Daniel Chen
Environmental Monitoring With a Raspberry Pi - Daniel ChenEnvironmental Monitoring With a Raspberry Pi - Daniel Chen
Environmental Monitoring With a Raspberry Pi - Daniel ChenDaniel Chen
 
Pantech embedded systems and IoT projects 2016-17
Pantech   embedded systems and IoT projects 2016-17Pantech   embedded systems and IoT projects 2016-17
Pantech embedded systems and IoT projects 2016-17Senthil Kumar
 
Environmental scanning & Monitoring Techniques
Environmental scanning & Monitoring TechniquesEnvironmental scanning & Monitoring Techniques
Environmental scanning & Monitoring TechniquesRex Mannoor
 

Viewers also liked (6)

Raspberry pi jam
Raspberry pi jamRaspberry pi jam
Raspberry pi jam
 
Environmental Monitoring With a Raspberry Pi - Daniel Chen
Environmental Monitoring With a Raspberry Pi - Daniel ChenEnvironmental Monitoring With a Raspberry Pi - Daniel Chen
Environmental Monitoring With a Raspberry Pi - Daniel Chen
 
Pantech embedded systems and IoT projects 2016-17
Pantech   embedded systems and IoT projects 2016-17Pantech   embedded systems and IoT projects 2016-17
Pantech embedded systems and IoT projects 2016-17
 
ENVIRONMENTAL MONITORING
ENVIRONMENTAL MONITORINGENVIRONMENTAL MONITORING
ENVIRONMENTAL MONITORING
 
Raspberry pi
Raspberry pi Raspberry pi
Raspberry pi
 
Environmental scanning & Monitoring Techniques
Environmental scanning & Monitoring TechniquesEnvironmental scanning & Monitoring Techniques
Environmental scanning & Monitoring Techniques
 

Similar to An Overview of the Radiological Environmental Monitoring System

IWSM2014 COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)
IWSM2014   COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)IWSM2014   COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)
IWSM2014 COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)Nesma
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringJohn Kingsley
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdfharis348605
 
6. System and its Life Cycle.pptx
6. System and its Life Cycle.pptx6. System and its Life Cycle.pptx
6. System and its Life Cycle.pptxAminaButt14
 
WJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWm White
 
Acquisition Cost Estimating
Acquisition Cost EstimatingAcquisition Cost Estimating
Acquisition Cost Estimatingjrunderwood
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyRobert Doig
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差Alex Yin
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelPrakash Poudel
 
Planning for software quality assurance lecture 6
Planning for software quality assurance lecture 6Planning for software quality assurance lecture 6
Planning for software quality assurance lecture 6Abdul Basit
 
ADEPP & Other Software
ADEPP & Other SoftwareADEPP & Other Software
ADEPP & Other SoftwareFabienne Salimi
 
Fireprotectionfirepreventionandfirecontrolregulations
FireprotectionfirepreventionandfirecontrolregulationsFireprotectionfirepreventionandfirecontrolregulations
FireprotectionfirepreventionandfirecontrolregulationsMohamed Tahoun, PMP
 

Similar to An Overview of the Radiological Environmental Monitoring System (20)

Maintainability engineering
Maintainability engineeringMaintainability engineering
Maintainability engineering
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
commissioning c-3
commissioning c-3commissioning c-3
commissioning c-3
 
IWSM2014 COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)
IWSM2014   COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)IWSM2014   COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)
IWSM2014 COSMIC masterclass part 2 - dealing with NFR (Chris Woodward)
 
IWSM2014 COSMIC masterclass part 2 - Dealing with NFR (Chris Woodward)
IWSM2014   COSMIC masterclass part 2 - Dealing with NFR (Chris Woodward)IWSM2014   COSMIC masterclass part 2 - Dealing with NFR (Chris Woodward)
IWSM2014 COSMIC masterclass part 2 - Dealing with NFR (Chris Woodward)
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
6. System and its Life Cycle.pptx
6. System and its Life Cycle.pptx6. System and its Life Cycle.pptx
6. System and its Life Cycle.pptx
 
WJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWJ White Resume_July15_Functional
WJ White Resume_July15_Functional
 
Acquisition Cost Estimating
Acquisition Cost EstimatingAcquisition Cost Estimating
Acquisition Cost Estimating
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差
 
Process Safety Management.pptx
Process Safety Management.pptxProcess Safety Management.pptx
Process Safety Management.pptx
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
 
Planning for software quality assurance lecture 6
Planning for software quality assurance lecture 6Planning for software quality assurance lecture 6
Planning for software quality assurance lecture 6
 
CV
CVCV
CV
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
ADEPP & Other Software
ADEPP & Other SoftwareADEPP & Other Software
ADEPP & Other Software
 
Fireprotectionfirepreventionandfirecontrolregulations
FireprotectionfirepreventionandfirecontrolregulationsFireprotectionfirepreventionandfirecontrolregulations
Fireprotectionfirepreventionandfirecontrolregulations
 

An Overview of the Radiological Environmental Monitoring System

  • 1. An Overview of the Radiological Environmental Monitoring System (REMS) for ITER Preliminary Design Presented by Dijesh Das C&I Engineer AMEC Clean Energy 11 February 2014
  • 2. REMS provides health and radiological monitoring for workers as well as environmental monitoring for the public, assisting in the protection against ionizing radiation, during the whole life of ITER starting from construction until operations and decommissioning. The environmental monitoring programme ensures compliance with the French Environmental Regulation and allows calculation of doses to the public. The radiological monitoring for workers includes the following: • Radiation and Contamination Monitoring • Sampling • Alarm handling • Measuring and limiting individual and accumulative doses to workers within the Radiological Controlled Areas at ITER • Beryllium monitoring • Radiological monitoring for the environment of effluents (gaseous and liquid) release monitoring & sampling. In addition, the trigger detectors for the HVAC isolation and connection to the Detriation system and the tritium detectors in the Port Cells to initiate a cleaning action by the Detriation System are included. Overview of Radiological and Environmental Monitoring Systems (REMS)
  • 3. Overview of Radiological and Environmental Monitoring Systems (REMS)
  • 4. Overview of Radiological and Environmental Monitoring Systems (REMS) The REMS comprise of Safety Important Class (SIC) components within some of the Sub-systems which have a Safety Classification based on the Safety Important Function that is intended that the component shall provide to protect from an unsafe event. These are shown below: Health Physics • Area Radiological Monitoring (SIC‐2) • Release Radiological Monitoring (SIC‐1) • Environmental Monitoring (SR) • Individual Monitoring (SR) • Area Beryllium Monitoring (SIC‐2) • Laboratories Process Control • Tritium HVAC/DS (SIC‐1) • T Port Cell (SR)
  • 5. ITER System Design & Procurement Arrangement Process In order to manage the procurement of the systems the ITER project has been sub-divided into a number of Procurement Packages and distributed to Seven-ITER Parties. There are currently 30 Plant Breakdown items that form part of a Plant Breakdown Structure (PBS) where each of the Products are controlled under a Procurement Arrangement (PA) for each of the parties. Product Breakdown Structure
  • 6. ITER System Design & Procurement Arrangement Process REMS PBS 64 procurement package is a function specification type of PA ITER ORGANISATION (IO) is responsible of the system development up to the Concept Design where this is handed over as part of the PA Process to F4E who are responsible of the preliminary (outsourced to AMEC through framework), & final designs, procurement, installation and commissioning of the different systems, sub‐systems and equipments throughout the design lifecycle. F4E is in charge for the detailed design, procurement, manufacturing, transport, testing and commissioning of the Radiological and Environmental Monitoring Systems (REMS). ITER Organisation – ‘Concept Design’ Procurement Arrangement– ‘Detailed Design’ F4E Framework – ‘Preliminary Design’
  • 7. ITER System Design & Procurement Arrangement Process
  • 8. Purpose of the Preliminary Design Phase for REMS PA AMEC are to carry out the Preliminary Design (PD) of the REMS in accordance with Task Order 1 Lot 2 in line with the PA milestone by achieving PD Baselines which will allow it to carry on to the next phase of the PA sequence (Final Design). The purpose of the PD phase is to achieve the following:  To review the outcome of the CD review meeting together with the issued CHITS – to identify any outstanding issues and propose solutions to update the proposed CD. This has been confirmed as completed by F4E.  To consider whether consolidated System Requirements Document (SRD) from CD is currently valid and achievable during the PD – this can be done by initially performing a review of the requirements (for e.g. the applicable list of Codes and Standards and whether they are current and where necessary shall be requested/recommended to be updated during the design lifecycle). Note: Do Not Change the SRD Requirements in the current version, including those that are not fixed. At the end of the PD phase a new version of the SRD shall be provided for IO and F4E’s review and approval, together with appropriate justifications for changes.
  • 9. Delivery of the Preliminary Design Phase for REMS PA • Develop the REMS PD package with the required design documents and drawings up to PD maturity for PDR – by preparing the PDR documentation package by updating the available documents from CD and by compiling new documents relevant for the PD package. The main documents to be produced as part of the PD package are required to include the following: Requirements (SRD, ICD, ISs, CMMs, etc) Description (DD, RAMI, Load Specs, PFDs, etc) Operation and Testing (Ops Plan, Maintenance Plan, etc) Justification (DCM, DR and Recommendations, DJP, etc) Test and Comissioning (On-site Assembly Plan, etc) Design Management (Risk Assessment, Work Plan, etc) Along with detailed specific technical requirements which demonstrate the following: Classification (Safety, Quality, Seismic and I&C) Licensing Requirements (Electrical Compliance, etc) Applicable Code & Standards (Seismic, etc) System Specific Requirements (See TO1 278RAD/2.1)
  • 10. Baseline of the Preliminary Design Phase for REMS PA By the end of the PD phase we should have achieved the following: • Refined CD to confirm whether the system is feasible, achievable and its robustness against its production schedule by substantiating it in the PD package. • Updated DD with detailed schematics and component definition. • Updated and provided justification documents from CD demonstrating the technical requirements that have been achieved. • Manufacturing, Assembly, Qualifications will have been addressed. • Be able to freeze Interface Specifications (assumptions, ranges and current data) as the design achieves the right level of maturity during PD. • Produced a plan for future steps of justification (Test for Mock-ups, verification planning etc) • Re-assessed the technical risk of the selected solution and provided a mitigation plan. • Periodically checked the PD package against the requirements with verification.
  • 11. Things we will Require to carry out the PD are: • System Requirements Documents • Configuration Management Models • Concept Detailed Design Description • Concept Drawing/Documents • ITER/F4E Processes and Quality Management Material • Working Instruction Baseline of the Preliminary Design Phase for REMS PA
  • 12. Preliminary Design Phase for REMS PA ‘An Example of a Baseline Model of the I&C for CODAC throughout the Design Lifecycle ’
  • 13. 5-Box Model for Preliminary Design Phase for REMS PA Preliminary Design TO •Requirements •Description •Justification •Operation and Testing •Assessments •Calculations •Detailed Development of Drawings and Documents •etc Concept Design Documents •CMMs •SRD •Concept DD •Concept ICD •Concept ISs •etc New Material for Preliminary Design •PD Requirements •Current French Regulation Codes and Standards •Current TER /F4E Processes •etc Preliminary Design CD Updated Documents •Updated Drawings and Documents •Updated Concept DD •etc Preliminary Design New Deliverables • Recommendations and Requests for Design Changes • PD SRD • New PD Drawings and Documents • Qualification and Material •etc Design Input Design Output PD Functional Specification
  • 14. Lets start the PD of REMS! AOB