SlideShare a Scribd company logo
1 of 12
Project Telstar
Start Up For Satellite Warehouse
13th November 2014
Created by Dave Grayson.
1
Project Management Plan (P.M.P.)
Project Sponsor: Dave Grayson.
 Project Members:
 1. Dave Wilkins-Project Manager.
 2.Chris Fowles-I.T.
 3.Garry Hall-Maintenance & Security.
 4. Transport-Andy Manktelow.
 5. Purchasing- Brian Wade.
 6. MHE- Marcus Dale/Supplier
 7.HR-Amanda Midgley.
 8.H&S-Donna Saville.
 9.Racking- Dave Wilkins/Supplier
2
BACKGROUND
 As the business continues to expand at a significant rate the need for
warehousing space has become business critical during 2014.
 This has lead to a makeshift extension of the warehouse via stillage purchase and
storage on site, 4 hire trailers used as storage and Sims being used as a third
party storage warehouse. This has lead to increased cost totalling £26.5k at the
time of writing for third party storage and £280per week for trailer hire.
 Other additional costs include the need to do increased hours, overtime, shift
work in order to keep the warehouse flowing to cope with both inbound and
outbound peaks.
 The key storage challenge has been that of the accessories we supply to the
main door range which invariably is long product. Despite investing in 2.4m
racking we still find ourselves some 2-300 long locations short and 500 euro’s.
 Therefore we are proposing to lease a satellite warehouse of approximately
15,000 sq. ft. (inc offices)locally to act primarily as a long pallet storage feeder
warehouse. This project will cover the start up of this satellite warehouse.
3
In Scope
 Acquire 4 year lease to commence early Feb 2014.
 Cleanse the main warehouse area floor and then install both cantilever and
2.4m racking to take long pallets.(N.B we can reconfigure, by height, some
of the 2.4m racking to accommodate euro pallets as well though this is not
the main function of this warehouse.)
 Install RF comms for the operational function and link to the main Access
system.
 Assess the office suite for use primarily by the warehouse team but possibly
for other TKC office colleagues?
4
In Scope
 Purchase relevant MHE trucks for the warehouse to be able to load/unload
and put away.
 Create a nominated satellite team & Team Leader to run it.
 Nominate a shunt vehicle and driver for the transport requirements.
 Empty Sims of the current outside storage and absorb back into the main
warehouse or this new warehouse.
 Empty the main warehouse of non or slow moving stock to free up location
space in the main warehouse.
 Full IT sweep and plan for the satellite warehouse.
 Full maintenance and security sweep and plan for the satellite warehouse.
 Create operational KPI’s to measure success.
5
Out of Scope
 Initial function of the warehouse must focus around long pallet storage.
There may be an opportunity, later, to de van trailers that the main
warehouse are unable to do efficiently and then tranship to the main
warehouse as single sku pallets etc. but not as part of this project.
 Major move of office staff into the building at the start. The main function is
to get the warehouse up and running asap after we get the keys!
 Storage of waste/rubbish/excessive pallet stock etc. The satellite warehouse
yards need to be kept clear initially until we have some idea of traffic
movement/frequency etc.
 Bootcamp in the short term!!!!!!
6
Expected Outcome
 To provide a medium term solution to the warehouse space issue.
 Enable the main warehouse to operate more efficiently.
 Provide secondary ops services such as trailer de-van.
 Enable the company to introduce more new ranges into its sales portfolio.
 Provide exceptional delivery service standards to both internal customer,
main warehouse, and they in turn provide same service to the end user.
 To eliminate third party storage costs and bring TKC’s warehousing and
logistics back under its own control.
7
C.D.P.
Jan 5th Jan 12th Jan 19th Jan 26th Feb 2nd Feb 9th Feb 16th Feb 23rd Mar-03 Mar-10 Mar-17 Mar-24 Mar-31
Sign off Lease
Order Racking
Order MHE
Order IT Equip
Project Meeting
Sponsor meeting
Maintenance/Sec
Racking Install
MHE Install
IT Install
H&S Risk Assess
Empty Sims
Emptying Main Whse
Go Live
Operational KPI's
PIR meeting
8
Budget
Racking
MHE
IT
Facilities
Security
Stock Tfr Sims
9
Risks
 There are some key members of the current operational team who will be
taken out of the mainstream operational day, at times, until the project is
complete. Backfill will be required by less experienced staff which could have
an impact on the main warehouse service levels.
 Costs going over budget.
 New ranges in sales demand being introduced into the business or a major
increase in sales demand before this option is up and running.
 With a major racking build alongside probability of maintenance work there
are likely to be a lot of contractors on site. These must be controlled properly
or could pose a H&S risk.
10
GOVERNANCE
 Weekly project meeting-all.
 Weekly review of the CDP-between Project Manager and Project Sponsor.
 Weekly budget review between Project Manager and Project Sponsor
 Weekly update to the Director’s from the Project Sponsor.
 Operational KPI’s post Go Live.
11
Project Sign /Off Closure
 All project team members will be required to sign off that their area is closed
off.
 A final close out meeting will be held to review both success and also any
lessons that can be learnt for future projects. (Post Implementation Review
meeting.)
 Final sign off will then be done by the Project Sponsor/Directors.
12

More Related Content

Viewers also liked

Deuschle discussion 4 ignite slidedesign
Deuschle discussion 4 ignite slidedesignDeuschle discussion 4 ignite slidedesign
Deuschle discussion 4 ignite slidedesignbendeuschle
 
Dossier enseignement supérieur et recherche l’esr au quotidien - master psy...
Dossier enseignement supérieur et recherche   l’esr au quotidien - master psy...Dossier enseignement supérieur et recherche   l’esr au quotidien - master psy...
Dossier enseignement supérieur et recherche l’esr au quotidien - master psy...Réseau Pro Santé
 
Coin culture 1: Mia Wohl
Coin culture 1: Mia WohlCoin culture 1: Mia Wohl
Coin culture 1: Mia Wohlcoinculture
 
Prototipo de empresa
Prototipo de empresaPrototipo de empresa
Prototipo de empresaFabián Rojas
 
The Legend of Miguel de Cervantes
The Legend of Miguel de CervantesThe Legend of Miguel de Cervantes
The Legend of Miguel de CervantesJordan Johnson
 
Foto 1 lenguaje de la imagen
Foto 1 lenguaje de la imagenFoto 1 lenguaje de la imagen
Foto 1 lenguaje de la imagenarancha_ruiz
 
Highlights Prinsjesdag 2011
Highlights Prinsjesdag 2011Highlights Prinsjesdag 2011
Highlights Prinsjesdag 2011Raymond Both
 
Work Placement Opportunities 2
Work Placement Opportunities 2 Work Placement Opportunities 2
Work Placement Opportunities 2 stuartwright
 
การสำรวจอวกาศ
การสำรวจอวกาศการสำรวจอวกาศ
การสำรวจอวกาศRattanathon Phetthom
 
Integrity InfoLetter 1st Quarter 2009
Integrity InfoLetter 1st Quarter 2009Integrity InfoLetter 1st Quarter 2009
Integrity InfoLetter 1st Quarter 2009John Clinton Bradley
 

Viewers also liked (15)

Who Wants to be a millionary?
Who Wants to be a millionary?Who Wants to be a millionary?
Who Wants to be a millionary?
 
éTica renascentista
éTica renascentistaéTica renascentista
éTica renascentista
 
Deuschle discussion 4 ignite slidedesign
Deuschle discussion 4 ignite slidedesignDeuschle discussion 4 ignite slidedesign
Deuschle discussion 4 ignite slidedesign
 
Dossier enseignement supérieur et recherche l’esr au quotidien - master psy...
Dossier enseignement supérieur et recherche   l’esr au quotidien - master psy...Dossier enseignement supérieur et recherche   l’esr au quotidien - master psy...
Dossier enseignement supérieur et recherche l’esr au quotidien - master psy...
 
Coin culture 1: Mia Wohl
Coin culture 1: Mia WohlCoin culture 1: Mia Wohl
Coin culture 1: Mia Wohl
 
tmpIoyC3z.pdf_out
tmpIoyC3z.pdf_outtmpIoyC3z.pdf_out
tmpIoyC3z.pdf_out
 
Prototipo de empresa
Prototipo de empresaPrototipo de empresa
Prototipo de empresa
 
The Legend of Miguel de Cervantes
The Legend of Miguel de CervantesThe Legend of Miguel de Cervantes
The Legend of Miguel de Cervantes
 
Neil Fraser, Scran
Neil Fraser, ScranNeil Fraser, Scran
Neil Fraser, Scran
 
Foto 1 lenguaje de la imagen
Foto 1 lenguaje de la imagenFoto 1 lenguaje de la imagen
Foto 1 lenguaje de la imagen
 
كرت أحمر
كرت أحمركرت أحمر
كرت أحمر
 
Highlights Prinsjesdag 2011
Highlights Prinsjesdag 2011Highlights Prinsjesdag 2011
Highlights Prinsjesdag 2011
 
Work Placement Opportunities 2
Work Placement Opportunities 2 Work Placement Opportunities 2
Work Placement Opportunities 2
 
การสำรวจอวกาศ
การสำรวจอวกาศการสำรวจอวกาศ
การสำรวจอวกาศ
 
Integrity InfoLetter 1st Quarter 2009
Integrity InfoLetter 1st Quarter 2009Integrity InfoLetter 1st Quarter 2009
Integrity InfoLetter 1st Quarter 2009
 

Similar to Project Telstar

Project Tardis (5)
Project Tardis (5)Project Tardis (5)
Project Tardis (5)Dave Grayson
 
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDPREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDSILAS OLUDARE
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1Maricel Molina
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]Leonard Merari Situmeang
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Carige Andrew
 
SreenivasaReddy_Pocha_BOA
SreenivasaReddy_Pocha_BOASreenivasaReddy_Pocha_BOA
SreenivasaReddy_Pocha_BOASrinu Reddy
 
Resume - Kevin Horn 5 Oct 2016
Resume - Kevin Horn 5 Oct 2016Resume - Kevin Horn 5 Oct 2016
Resume - Kevin Horn 5 Oct 2016Kevin Horn
 
paul_jubb cv 16May15
paul_jubb cv  16May15paul_jubb cv  16May15
paul_jubb cv 16May15Paul Jubb
 
End of Internship presentation by John
End of Internship presentation by JohnEnd of Internship presentation by John
End of Internship presentation by JohnAdedigba John
 
Lungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Peter A. Hanna, CPM
 
Fuelfix & Tanks2Go Capability Statement 2015
Fuelfix & Tanks2Go Capability Statement 2015Fuelfix & Tanks2Go Capability Statement 2015
Fuelfix & Tanks2Go Capability Statement 2015Mervin John Radford
 
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docx
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docxRiordan Manufacturing Project Management Plan – Wk 2 Preparation.docx
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docxjoellemurphey
 
Tony schofield profile
Tony schofield profileTony schofield profile
Tony schofield profileskofiled
 

Similar to Project Telstar (20)

Project Tardis (5)
Project Tardis (5)Project Tardis (5)
Project Tardis (5)
 
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDPREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 
Navyug open erp warehouse presentation 2012
Navyug open erp warehouse presentation 2012Navyug open erp warehouse presentation 2012
Navyug open erp warehouse presentation 2012
 
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]
SCM and Logistics : Case Study Presentatiion [MM Trisakti 2015]
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16
 
SreenivasaReddy_Pocha_BOA
SreenivasaReddy_Pocha_BOASreenivasaReddy_Pocha_BOA
SreenivasaReddy_Pocha_BOA
 
Resume - Kevin Horn 5 Oct 2016
Resume - Kevin Horn 5 Oct 2016Resume - Kevin Horn 5 Oct 2016
Resume - Kevin Horn 5 Oct 2016
 
paul_jubb cv 16May15
paul_jubb cv  16May15paul_jubb cv  16May15
paul_jubb cv 16May15
 
End of Internship presentation by John
End of Internship presentation by JohnEnd of Internship presentation by John
End of Internship presentation by John
 
Lungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase P2 Report
Lungelo Mwelase P2 Report
 
Sameer_Resume_L
Sameer_Resume_LSameer_Resume_L
Sameer_Resume_L
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6
 
Fuelfix & Tanks2Go Capability Statement 2015
Fuelfix & Tanks2Go Capability Statement 2015Fuelfix & Tanks2Go Capability Statement 2015
Fuelfix & Tanks2Go Capability Statement 2015
 
Inforln.com ERP LN 10.3 & 10.4 MAUC Hours Differences
Inforln.com ERP LN 10.3 & 10.4 MAUC Hours DifferencesInforln.com ERP LN 10.3 & 10.4 MAUC Hours Differences
Inforln.com ERP LN 10.3 & 10.4 MAUC Hours Differences
 
CV Frank Noort
CV Frank NoortCV Frank Noort
CV Frank Noort
 
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docx
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docxRiordan Manufacturing Project Management Plan – Wk 2 Preparation.docx
Riordan Manufacturing Project Management Plan – Wk 2 Preparation.docx
 
Tony schofield profile
Tony schofield profileTony schofield profile
Tony schofield profile
 

Project Telstar

  • 1. Project Telstar Start Up For Satellite Warehouse 13th November 2014 Created by Dave Grayson. 1
  • 2. Project Management Plan (P.M.P.) Project Sponsor: Dave Grayson.  Project Members:  1. Dave Wilkins-Project Manager.  2.Chris Fowles-I.T.  3.Garry Hall-Maintenance & Security.  4. Transport-Andy Manktelow.  5. Purchasing- Brian Wade.  6. MHE- Marcus Dale/Supplier  7.HR-Amanda Midgley.  8.H&S-Donna Saville.  9.Racking- Dave Wilkins/Supplier 2
  • 3. BACKGROUND  As the business continues to expand at a significant rate the need for warehousing space has become business critical during 2014.  This has lead to a makeshift extension of the warehouse via stillage purchase and storage on site, 4 hire trailers used as storage and Sims being used as a third party storage warehouse. This has lead to increased cost totalling £26.5k at the time of writing for third party storage and £280per week for trailer hire.  Other additional costs include the need to do increased hours, overtime, shift work in order to keep the warehouse flowing to cope with both inbound and outbound peaks.  The key storage challenge has been that of the accessories we supply to the main door range which invariably is long product. Despite investing in 2.4m racking we still find ourselves some 2-300 long locations short and 500 euro’s.  Therefore we are proposing to lease a satellite warehouse of approximately 15,000 sq. ft. (inc offices)locally to act primarily as a long pallet storage feeder warehouse. This project will cover the start up of this satellite warehouse. 3
  • 4. In Scope  Acquire 4 year lease to commence early Feb 2014.  Cleanse the main warehouse area floor and then install both cantilever and 2.4m racking to take long pallets.(N.B we can reconfigure, by height, some of the 2.4m racking to accommodate euro pallets as well though this is not the main function of this warehouse.)  Install RF comms for the operational function and link to the main Access system.  Assess the office suite for use primarily by the warehouse team but possibly for other TKC office colleagues? 4
  • 5. In Scope  Purchase relevant MHE trucks for the warehouse to be able to load/unload and put away.  Create a nominated satellite team & Team Leader to run it.  Nominate a shunt vehicle and driver for the transport requirements.  Empty Sims of the current outside storage and absorb back into the main warehouse or this new warehouse.  Empty the main warehouse of non or slow moving stock to free up location space in the main warehouse.  Full IT sweep and plan for the satellite warehouse.  Full maintenance and security sweep and plan for the satellite warehouse.  Create operational KPI’s to measure success. 5
  • 6. Out of Scope  Initial function of the warehouse must focus around long pallet storage. There may be an opportunity, later, to de van trailers that the main warehouse are unable to do efficiently and then tranship to the main warehouse as single sku pallets etc. but not as part of this project.  Major move of office staff into the building at the start. The main function is to get the warehouse up and running asap after we get the keys!  Storage of waste/rubbish/excessive pallet stock etc. The satellite warehouse yards need to be kept clear initially until we have some idea of traffic movement/frequency etc.  Bootcamp in the short term!!!!!! 6
  • 7. Expected Outcome  To provide a medium term solution to the warehouse space issue.  Enable the main warehouse to operate more efficiently.  Provide secondary ops services such as trailer de-van.  Enable the company to introduce more new ranges into its sales portfolio.  Provide exceptional delivery service standards to both internal customer, main warehouse, and they in turn provide same service to the end user.  To eliminate third party storage costs and bring TKC’s warehousing and logistics back under its own control. 7
  • 8. C.D.P. Jan 5th Jan 12th Jan 19th Jan 26th Feb 2nd Feb 9th Feb 16th Feb 23rd Mar-03 Mar-10 Mar-17 Mar-24 Mar-31 Sign off Lease Order Racking Order MHE Order IT Equip Project Meeting Sponsor meeting Maintenance/Sec Racking Install MHE Install IT Install H&S Risk Assess Empty Sims Emptying Main Whse Go Live Operational KPI's PIR meeting 8
  • 10. Risks  There are some key members of the current operational team who will be taken out of the mainstream operational day, at times, until the project is complete. Backfill will be required by less experienced staff which could have an impact on the main warehouse service levels.  Costs going over budget.  New ranges in sales demand being introduced into the business or a major increase in sales demand before this option is up and running.  With a major racking build alongside probability of maintenance work there are likely to be a lot of contractors on site. These must be controlled properly or could pose a H&S risk. 10
  • 11. GOVERNANCE  Weekly project meeting-all.  Weekly review of the CDP-between Project Manager and Project Sponsor.  Weekly budget review between Project Manager and Project Sponsor  Weekly update to the Director’s from the Project Sponsor.  Operational KPI’s post Go Live. 11
  • 12. Project Sign /Off Closure  All project team members will be required to sign off that their area is closed off.  A final close out meeting will be held to review both success and also any lessons that can be learnt for future projects. (Post Implementation Review meeting.)  Final sign off will then be done by the Project Sponsor/Directors. 12