43. • New Outpatient Center (OPC2) – LEED
Silver - Complete
• Inpatient Hospital Renovations
‒Neonatal ICU, Pediatric ICU, Inpatient
Rehabilitation, Surgery Recovery Room,
Pharmacy, Central Sterile, other support
areas
• Parking structure entry/exit relocated to MLK
- Complete
• Seismic compliance
Phase I
48. Schedule
Construction to begin in August
Majority of construction is anticipated to be
complete by end of 2019
NICU and OR improvements is anticipated to
extend into early 2022
Other projects is anticipated to occur between
now and 2022
MRI, CT
48
49. Communication & Reporting
49
Project Communication
510-764-3059
Flyers and Project Website
• notifications of change to site conditions as it pertains to the
neighborhood
• http://chonext100.org