Prepared and presented for guest lecturing at Binus International Program, Jakarta, December 2018.
This presentation discuss about how to minimize project risks by avoiding big bang approach, and by fail early and fail fast.
2. ABOUT ME
Akbar Azwir
MM, PMP, PMI-SP, PSM I, CISSP
• Went to Binus for S1 and S2
• 5 years at Agung Sedayu Group
• 8 years at Bayan Resources Group
• Got my PMP at 2010
• Founded MagnaQM at January 2017
3. CASE STUDY #1 – Palem Games
• Starts developing an android game from 2014
• Soft launch the end of 2015
• Launched at the middle of 2016
• Downloaded by 500 people
• The company shuts down at 2017
4. CASE STUDY #2 – UK NHS NPfIT
National Programme for Information Technology (NPfIT)
NHS Record Service, intended to deliver an electronic health
records system containing patient records across the UK.
5. CASE STUDY #2 – Existing System
• Health records of UK citizens held locally
• Adaptation of electronic health records tended to be slow
• Implementation vary from home grown to government
driven standardized commercial software
6. CASE STUDY #2 – Scope & Estimates
• To create a national EHR system for the entire UK
• To connect 30,000 doctors to 300 hospitals
• "the world's biggest civil information technology
programme”
• Split into 5 cluster with different vendor
GBP 2,3 billion
3 years to complete
8. CASE STUDY #2 – Timeline
2002 2003 2006 2007 2008 2009 2011
Launched
Contracts awarded
to vendors
Accenture depart
and transfer the
contracts to CSC
Testing & deployment 2
years behind schedule.
The head of NPfIT,
Richard Granger,
resigned
Public Accounts
Committee criticized
cost & progress
Officially Dismantled
GAO estimate the cost would be
12,4 billion and would take 10
years to complete
9. CASE STUDY #2 – Post Mortem
• UK lost GBP 12,7 billion trying to complete the project
• Later discovered, the project continues to cost the country millions, with
contracts in some cases not set to expire for 12 more years
References:
https://www.centreforpublicimpact.org/case-study/electronic-health-records-system-uk/
https://www.cl.cam.ac.uk/~rja14/Papers/npfit-mpp-2014-case-history.pdf
https://spectrum.ieee.org/riskfactor/computing/it/lessons-from-the-uk-npfit-debacle-still-being-learned
https://www.nao.org.uk/wp-content/uploads/2006/06/05061173.pdf