SlideShare a Scribd company logo
1 of 15
PORTLAND WATER
BUREAU
CONSTRUCTION MANAGEMENT INTERN
1st CECOP INTERNSHIP
BRANDEN RICHARD CONFER
PRESENTATION OVERVIEW
 HISTORY OF PORTLANT WATER
BUREAU
 HOURS, SCHEDULES, AND WAGES
 SERVICE GROUPS FOR PWB
 PROJECT INVOLVEMENT OVERVIEW
 BIG PROJECTS
 USEFUL CLASSES
 TAKE AWAYS
FROM FOREST TO FAUCET, WE DELIVER THE BEST DRINKING WATER IN THE WORLD.
BRIEF HISTORY OF PWB
 PWB WAS ESTABLISHED IN 1851.
 IN 1895, BULL RUN COMPLETED CONSTRUCTION OF CONDUIT
1 WHICH ALLOWED FLOW TO MT. TABOR.
 CREDIT WAS DUE IN 1905 TO PWB FOR THE DECREASE IN
DEATHS SINCE BULL RUN BECAME OPERATIONAL.
 1927 WATER METERS WERE INSTALLED IN THE PORTLAND
AREA TO ALL WATER SERVICES.
 1930-1940 CHLORINE WAS FIRST INTRODUCE TO PREP WATER
FOR TREATMENT AND ALLOWED FOR CLEANER WATER FOR
PUBLIC USE.
 BY 1962 BOTH DAM 1 AND 2 WERE CONSTRUCTED AT BULL
RUN.
 DURING THE 2000’S, TECHNOLOGY INCREASED ALLOWING
FOR EFFICIENCY AND REUSABLE UTILITIES WHICH
DECREASED WATER USAGE BY 80%.
 IN 1995, PWB INSTALLED A 50 MILLION GALLON TANK AT
POWELL BUTTE TO HELP DISTRIBUTE WATER TO CONSUMERS.
HOURS
 I CHOSE MY OWN
WORKING HOURS.
 I WORKED 7:00AM TO
4:30PM.
 30 MIN LUNCH.
 FLEXIBLE.
SCHEDUELS
WAGES
 THEY OFFERED A FLEX
SCHEDULE.
 9 HR WORK DAYS MON-
THRU.
 WORK 8 HR EVERY
OTHER FRIDAY.
 EVERY OTHER FRIDAY
OFF.
 HAD THE OPTION FOR
MY FLEX DAYS.
 MENTORS AND
COWORKERS WORKED
WELL WITH MY
PERSONAL SCHEDULE.
 40 HOUR WORK
WEEKS.
 19$ AN HOUR.
 PAYED HOLIDAYS.
 NO BENEFITS.
 SICK DAYS AFTER
90 DAYS.
ENGINEERING CM SERVICES GROUP
Teresa Elliott
Chief Engineer
Stan VandeBergh
Principal
Engineer
Walter Lewandowski
Senior Engineer
Rick Lapp
Sr Eng Associate
Jim Scanlon
CAD Tech III
Roy Martinez
Inspection
Manager
Branden Confer
CM Intern
Kate Barrrett
Senior Inspector
Ted Roos
Senior Inspector
Clay Luper
Senior Inspector
Project Involvement
 Road 10/
Watershed
 Interstate
Renovation
Project
 Hydrogravitram
 Fulton Pump
Station
 Mt. Tabor
 Lusted Hill
Road 10 Activates
 Erosion and traffic controls
 Saw Cutting
 Grinding (Change in spec..)
 Overlaying
 North and South side widening
 Culvert replacements
 Reconditioning and paving
 Retaining wall
Road 10 Cont.…
 Pre Bid Meeting
 To give the bidders an opportunity to ask questions and get answers about the project.
 Pre Con meeting
 Contractor ask specific questions and submits submittals to the CM before project.
 Contract Weekly Meetings
 Up coming schedule and communication on project details.
 Submittals
 Items /materials needed for project. Kept record of each sub and response.
 RFI’s
 Request for information between CM and Contractor.
 Chlorine Safety Certified
 Chlorine station located close to project.
 Inspections
 Inspected/ site walks to insure safety and progress for project.
INTERSTATE RENOVATION PROJECT
Activities
 Administration
 Reconciling of documentation
for project.
 Inspections
 Daily reports, safety, and
progress, punch lists.
 Electrical As-builds
 Worked in Auto Cad and Micro
Station to build the electrical
As-build for IRP.
FULTON PUMP STATION ACTIVITIES
 INSPECTIONS
 Inspected the sight to insure safety and progress.
 PROJECT MEETINGS
 A collective meeting where we confer upcoming schedules and discuss potential
problems.
 PERMITS
 Permit revision.
 RFI
 Request for Information.
 Submittals
Hydrogravitram Involvement
Built by Shab Levy 1983
 Masonry
 Metal Work
 Cleaning
 Planning
 Organizing
 Scheduling
https://www.facebook.com/branden.confer.1/videos/1335081266506917/
Side Activities
 Wood Fair
 CM/GC
 Micro Station
 Operations/GIS
 Culvert Inspections
 Surveying
 Air Compressor
Woodend Culvert
& Largest Culvert.
Combusted Pipe
at Mt. Tabor.
Surveying at
Watershed
Helpful Courses
Engineering Planning
Surveying
Technical writing
Fluid Mechanics
AutoCAD
Take Away’s
 Understanding of job titles and roles within PWB.
 Being clear and verbal.
 Don’t wait, just do.
 Follow up.
 Be a team player.
QUESTIONS???

More Related Content

Viewers also liked

english proficiency assessments of primary and secondary teachers and student...
english proficiency assessments of primary and secondary teachers and student...english proficiency assessments of primary and secondary teachers and student...
english proficiency assessments of primary and secondary teachers and student...Md Ashraf Siddique
 
18 dicas para Detonar no Youtube
18 dicas para Detonar no Youtube18 dicas para Detonar no Youtube
18 dicas para Detonar no YoutubeWilson Souza
 
Interactive E-Learning System. Usages, perception et attentes des étudiants à...
Interactive E-Learning System. Usages, perception et attentes desétudiants à...Interactive E-Learning System. Usages, perception et attentes desétudiants à...
Interactive E-Learning System. Usages, perception et attentes des étudiants à...Maxime GIGNON
 
Localbook Corporate Presentation
Localbook Corporate PresentationLocalbook Corporate Presentation
Localbook Corporate PresentationUmesh Dahare
 
Lire et critiquer un article en pratique médicale
Lire et critiquer un article  en pratique médicaleLire et critiquer un article  en pratique médicale
Lire et critiquer un article en pratique médicaleMaxime GIGNON
 
Évaluation du ressenti des étudiants entrant en deuxième cycle des études méd...
Évaluation du ressenti des étudiants entrant en deuxième cycle desétudes méd...Évaluation du ressenti des étudiants entrant en deuxième cycle desétudes méd...
Évaluation du ressenti des étudiants entrant en deuxième cycle des études méd...Maxime GIGNON
 
March 2016 Competency development for advanced nursing
March 2016 Competency development for advanced nursingMarch 2016 Competency development for advanced nursing
March 2016 Competency development for advanced nursingLinda Nazarko
 

Viewers also liked (10)

english proficiency assessments of primary and secondary teachers and student...
english proficiency assessments of primary and secondary teachers and student...english proficiency assessments of primary and secondary teachers and student...
english proficiency assessments of primary and secondary teachers and student...
 
18 dicas para Detonar no Youtube
18 dicas para Detonar no Youtube18 dicas para Detonar no Youtube
18 dicas para Detonar no Youtube
 
Interactive E-Learning System. Usages, perception et attentes des étudiants à...
Interactive E-Learning System. Usages, perception et attentes desétudiants à...Interactive E-Learning System. Usages, perception et attentes desétudiants à...
Interactive E-Learning System. Usages, perception et attentes des étudiants à...
 
Anegone
AnegoneAnegone
Anegone
 
Page0022
Page0022Page0022
Page0022
 
Localbook Corporate Presentation
Localbook Corporate PresentationLocalbook Corporate Presentation
Localbook Corporate Presentation
 
Campeonato baiano de tkd
Campeonato baiano de tkdCampeonato baiano de tkd
Campeonato baiano de tkd
 
Lire et critiquer un article en pratique médicale
Lire et critiquer un article  en pratique médicaleLire et critiquer un article  en pratique médicale
Lire et critiquer un article en pratique médicale
 
Évaluation du ressenti des étudiants entrant en deuxième cycle des études méd...
Évaluation du ressenti des étudiants entrant en deuxième cycle desétudes méd...Évaluation du ressenti des étudiants entrant en deuxième cycle desétudes méd...
Évaluation du ressenti des étudiants entrant en deuxième cycle des études méd...
 
March 2016 Competency development for advanced nursing
March 2016 Competency development for advanced nursingMarch 2016 Competency development for advanced nursing
March 2016 Competency development for advanced nursing
 

Similar to PORTLAND WATER BUREAU 0 [Autosaved]

Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PA
Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PAHarry E. Coal Waste Pile Reclamation Project in Swoyersville, PA
Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PAMichael Hewitt, GISP
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statementNECB
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description detailsAonghus Murray
 
Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-19501066heritage
 
Phillip james hawley august 2015
Phillip james hawley august 2015Phillip james hawley august 2015
Phillip james hawley august 2015Phillip Hawley
 
Flood Alleviation Scheme Banbury
Flood Alleviation Scheme BanburyFlood Alleviation Scheme Banbury
Flood Alleviation Scheme BanburyCPCLLP69
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfAmmar475682
 
Finch MSF EA Consultation July 7, 2014 - MSF specific
Finch MSF EA Consultation July 7, 2014 - MSF specificFinch MSF EA Consultation July 7, 2014 - MSF specific
Finch MSF EA Consultation July 7, 2014 - MSF specificCrosstown TO
 
Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Stephen Bolduc
 
Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Steve OConnor
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSepehr Aghamehdi
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationFairfax County
 
KDK RES 2016 Sunoco
KDK RES 2016 SunocoKDK RES 2016 Sunoco
KDK RES 2016 SunocoKarl Keller
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21Fairfax County
 
190916 alliesandmorrison paul_appleton_citymakers_catalytic
190916 alliesandmorrison paul_appleton_citymakers_catalytic190916 alliesandmorrison paul_appleton_citymakers_catalytic
190916 alliesandmorrison paul_appleton_citymakers_catalyticAlliesMorrison
 
Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27loyalj
 

Similar to PORTLAND WATER BUREAU 0 [Autosaved] (20)

Resume 2013
Resume 2013Resume 2013
Resume 2013
 
Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PA
Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PAHarry E. Coal Waste Pile Reclamation Project in Swoyersville, PA
Harry E. Coal Waste Pile Reclamation Project in Swoyersville, PA
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950
 
Phillip james hawley august 2015
Phillip james hawley august 2015Phillip james hawley august 2015
Phillip james hawley august 2015
 
Flood Alleviation Scheme Banbury
Flood Alleviation Scheme BanburyFlood Alleviation Scheme Banbury
Flood Alleviation Scheme Banbury
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
 
Finch MSF EA Consultation July 7, 2014 - MSF specific
Finch MSF EA Consultation July 7, 2014 - MSF specificFinch MSF EA Consultation July 7, 2014 - MSF specific
Finch MSF EA Consultation July 7, 2014 - MSF specific
 
Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010
 
NA
NANA
NA
 
srjCV_Auditor1
srjCV_Auditor1srjCV_Auditor1
srjCV_Auditor1
 
Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - Rotherham
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream Restoration
 
KDK RES 2016 Sunoco
KDK RES 2016 SunocoKDK RES 2016 Sunoco
KDK RES 2016 Sunoco
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
 
190916 alliesandmorrison paul_appleton_citymakers_catalytic
190916 alliesandmorrison paul_appleton_citymakers_catalytic190916 alliesandmorrison paul_appleton_citymakers_catalytic
190916 alliesandmorrison paul_appleton_citymakers_catalytic
 
Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27
 

PORTLAND WATER BUREAU 0 [Autosaved]

  • 1. PORTLAND WATER BUREAU CONSTRUCTION MANAGEMENT INTERN 1st CECOP INTERNSHIP BRANDEN RICHARD CONFER
  • 2. PRESENTATION OVERVIEW  HISTORY OF PORTLANT WATER BUREAU  HOURS, SCHEDULES, AND WAGES  SERVICE GROUPS FOR PWB  PROJECT INVOLVEMENT OVERVIEW  BIG PROJECTS  USEFUL CLASSES  TAKE AWAYS FROM FOREST TO FAUCET, WE DELIVER THE BEST DRINKING WATER IN THE WORLD.
  • 3. BRIEF HISTORY OF PWB  PWB WAS ESTABLISHED IN 1851.  IN 1895, BULL RUN COMPLETED CONSTRUCTION OF CONDUIT 1 WHICH ALLOWED FLOW TO MT. TABOR.  CREDIT WAS DUE IN 1905 TO PWB FOR THE DECREASE IN DEATHS SINCE BULL RUN BECAME OPERATIONAL.  1927 WATER METERS WERE INSTALLED IN THE PORTLAND AREA TO ALL WATER SERVICES.  1930-1940 CHLORINE WAS FIRST INTRODUCE TO PREP WATER FOR TREATMENT AND ALLOWED FOR CLEANER WATER FOR PUBLIC USE.  BY 1962 BOTH DAM 1 AND 2 WERE CONSTRUCTED AT BULL RUN.  DURING THE 2000’S, TECHNOLOGY INCREASED ALLOWING FOR EFFICIENCY AND REUSABLE UTILITIES WHICH DECREASED WATER USAGE BY 80%.  IN 1995, PWB INSTALLED A 50 MILLION GALLON TANK AT POWELL BUTTE TO HELP DISTRIBUTE WATER TO CONSUMERS.
  • 4. HOURS  I CHOSE MY OWN WORKING HOURS.  I WORKED 7:00AM TO 4:30PM.  30 MIN LUNCH.  FLEXIBLE. SCHEDUELS WAGES  THEY OFFERED A FLEX SCHEDULE.  9 HR WORK DAYS MON- THRU.  WORK 8 HR EVERY OTHER FRIDAY.  EVERY OTHER FRIDAY OFF.  HAD THE OPTION FOR MY FLEX DAYS.  MENTORS AND COWORKERS WORKED WELL WITH MY PERSONAL SCHEDULE.  40 HOUR WORK WEEKS.  19$ AN HOUR.  PAYED HOLIDAYS.  NO BENEFITS.  SICK DAYS AFTER 90 DAYS.
  • 5. ENGINEERING CM SERVICES GROUP Teresa Elliott Chief Engineer Stan VandeBergh Principal Engineer Walter Lewandowski Senior Engineer Rick Lapp Sr Eng Associate Jim Scanlon CAD Tech III Roy Martinez Inspection Manager Branden Confer CM Intern Kate Barrrett Senior Inspector Ted Roos Senior Inspector Clay Luper Senior Inspector
  • 6. Project Involvement  Road 10/ Watershed  Interstate Renovation Project  Hydrogravitram  Fulton Pump Station  Mt. Tabor  Lusted Hill
  • 7. Road 10 Activates  Erosion and traffic controls  Saw Cutting  Grinding (Change in spec..)  Overlaying  North and South side widening  Culvert replacements  Reconditioning and paving  Retaining wall
  • 8. Road 10 Cont.…  Pre Bid Meeting  To give the bidders an opportunity to ask questions and get answers about the project.  Pre Con meeting  Contractor ask specific questions and submits submittals to the CM before project.  Contract Weekly Meetings  Up coming schedule and communication on project details.  Submittals  Items /materials needed for project. Kept record of each sub and response.  RFI’s  Request for information between CM and Contractor.  Chlorine Safety Certified  Chlorine station located close to project.  Inspections  Inspected/ site walks to insure safety and progress for project.
  • 9. INTERSTATE RENOVATION PROJECT Activities  Administration  Reconciling of documentation for project.  Inspections  Daily reports, safety, and progress, punch lists.  Electrical As-builds  Worked in Auto Cad and Micro Station to build the electrical As-build for IRP.
  • 10. FULTON PUMP STATION ACTIVITIES  INSPECTIONS  Inspected the sight to insure safety and progress.  PROJECT MEETINGS  A collective meeting where we confer upcoming schedules and discuss potential problems.  PERMITS  Permit revision.  RFI  Request for Information.  Submittals
  • 11. Hydrogravitram Involvement Built by Shab Levy 1983  Masonry  Metal Work  Cleaning  Planning  Organizing  Scheduling https://www.facebook.com/branden.confer.1/videos/1335081266506917/
  • 12. Side Activities  Wood Fair  CM/GC  Micro Station  Operations/GIS  Culvert Inspections  Surveying  Air Compressor Woodend Culvert & Largest Culvert. Combusted Pipe at Mt. Tabor. Surveying at Watershed
  • 14. Take Away’s  Understanding of job titles and roles within PWB.  Being clear and verbal.  Don’t wait, just do.  Follow up.  Be a team player.